SlideShare una empresa de Scribd logo
1 de 12
Descargar para leer sin conexión
PM World Today – June 2011 (Vol. XIII, Issue VI)


                PM WORLD TODAY – FEATURED PAPER – JUNE 2011

       Project Selection in Large Engineering Construction
                             Programs

                                                   By Bob Prieto

One of the most important steps in implementation of a program management
approach is the selection of the projects which will comprise the program. This
selection process, done appropriately, is neither intuitively obvious nor simple. Done
poorly, the program may achieve less than optimum results or be exposed to risks
which may degrade its value over time. Project selection must flow from strategy
which in turn is defined by an organization’s strategic business objectives. Key
performance indicators which are established to assure strategic business objectives
are met, must cascade down through strategy assessment into overall project
portfolio assessment and ultimately into individual projects.




© 2011 Bob Prieto
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 1
PM World Today – June 2011 (Vol. XIII, Issue VI)


The selection of the portfolio of projects that will comprise the program must:

             optimize multiple strategic business objectives
             address sequencing required for optimization
             address interdependencies between projects
             reflect real world resource constraints
             enhance program (and organizational) flexibility and resiliency

Programs which experience weak project selection may have failed to:

        maintain focus on strategic business objectives allowing biases to enter the
         process
        establish a sufficiently strong methodology for project portfolio evaluation,
         often only considering one primary strategic business objective without
         attention to other such objectives
        appropriately cascade metrics down to the assessment of project portfolio
         performance
        inadequately reflect uncertainty and risks in portfolio evaluation

Weak project selection will result in lower value capture and, to the extent to which
project selection appears to be driven by non-objective factors, undermine
organizational honesty and openness.

Projects selection must be monitored as well as project performance under program
management. This is an area which requires increased focus in the engineering and
construction industry. Changes in market conditions, resource constraints, risk levels
or execution performance may drive a re-evaluation of the portfolio which shows that
redeployment of resources is in the best interest of achieving the programs strategic
business objectives even when sunk costs and commitments are fully considered.

Termination of a previously selected project may be a simpler matter if it is
performing below expectations (schedule delays, cost overruns) but when driven by a
reduction in the benefits that will accrue or value derived it is a much harder matter.
Who wants to be the program manager who terminates a strong performing project
(ahead of schedule, under budget)?

Optimize Multiple Strategic Business Objectives

A key attribute of project selection in major engineering and construction programs is
the need to simultaneously optimize multiple strategic business objectives.




© 2011 Bob Prieto
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 2
PM World Today – June 2011 (Vol. XIII, Issue VI)




This need is driven by the outcomes focus of programs versus the outputs focus that
is more typical of projects. Successful optimization will rest on:

        clear definition of strategic business objectives
        SMART key performance indicators or KPIs for each objective
             o Specific
             o Measurable
             o Achievable
             o Realistic
             o Targeted
        well defined constraints facing the program and individual projects
        delineated interdependencies between projects including any precedence
         requirements
        clarity around attendant risks and uncertainties at the program and project
         level.
        appropriate weighting of benefits and constraints that comprise the project
         portfolio’s evaluation criteria by the executives most focused on strategic
         business objective achievement

Evaluation criteria and constraints may include:
              - Financial
                      Life cycle return on investment
                      Return on assets employed
                      Net present value of cash flows
                      Payback period
                      Total capital expenditures
© 2011 Bob Prieto
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 3
PM World Today – June 2011 (Vol. XIII, Issue VI)


                            Product/project gross margins
                   -    Market
                            Market share
                            Market growth and duration
                            Period of profitable production
                            Product flexibility
                            Customer impacts
                   -    Strategic
                            Flexibility
                            Resiliency
                            Contribution to overall portfolio performance
                            Enablement of SBO achievement
                            Enablement of other portfolio projects
                            Critical resource utilization
                   -    Sustainability or Triple Bottom Line focused criteria
                            Economic
                            Social
                                   Community impacts
                                   Capacity building
                                   New industry/business creation
                                   Stakeholder support
                                   Workforce impacts
                            Environmental, Health & Safety
                                   Airborne emissions
                                   Water consumption
                                   Discharge water quality
                                   Environmental degradation
                                   Worker health and safety
                                   Public health and safety
                   -    Risk
                            Economic or market uncertainties
                            Other event risks
                            Financing uncertainties
                            Cost uncertainties
                            Schedule uncertainties
                            Labor risks
                            Stakeholder risks
                            Sovereign and legislative risks
                            Political risks
                            Technology risks
                            Intellectual property risks
                            Business model risks
                            Project execution risks
© 2011 Bob Prieto
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 4
PM World Today – June 2011 (Vol. XIII, Issue VI)


Weak project evaluation methodologies that seek to reduce all benefits to a singular
cost related value, such as NPV, must be avoided in recognition that:

        Uncertainty in estimates is compounded
        Structured multi-variate risk analysis would produce a better assessment of
         risk
        Benefits of later phase projects are not fully appreciated
        Changes in risk profile over time are not recognized

Avoiding Bias in Project Selection

Objective assessment rests on well defined objectives, constraints and evaluation
metrics that can be mapped to well defined evaluation criteria.


                                                      Constraints




       Strategic
       Business
    Objectives (SBO)

                                                                                                     Optimal
                                                      Evaluation
                                                                                                      Project
                                                       Criteria
                                                                                                     Portfolio




        Evaluation
         Metrics




                                     Avoiding Bias in Project Selection



It is essential that the owner’s team and program manager understand potential
sources of selection bias and carefully review objectives, metrics, constraints and
evaluation criteria to ensure such biases have been minimized and ideally eliminated.
The use of unconscious shortcuts to make complex decisions has been well
documented but may lead to systematic errors in the project portfolio selection
process.


© 2011 Bob Prieto
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net               Page 5
PM World Today – June 2011 (Vol. XIII, Issue VI)


The following table lists some of the biases more commonly observed in programs
with weak project selection.


                           Heuristic Biases Affecting Project Selection


                          Motivation bias
                          Status Quo bias
                          Perception bias
                          Risk aversion
                          Optimism bias
                          Comfort zone bias
                          Wishful thinking
                          Group think
                          Uncertainty acceptance
                          Judgmental biases
                          Sunk cost bias
                          Supporting evidence bias
                          Contradictory evidence avoidance
                          Biased argument framing
                          Anchoring
                          Illusion of control
                          Planning fallacy
                          Semmelweis reflex – (tendency to reject new
                          evidence that contradicts an established
                          paradigm)
                          Bounded awareness
                          Reasoning by analogy


Removing biases from the project selection processes requires a conscious set of
actions that begin with the recognition that potential biases as a result of heuristic
and other processes will exist and that a motivated and conscious effort is required to
remove them from the process.




© 2011 Bob Prieto
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 6
PM World Today – June 2011 (Vol. XIII, Issue VI)



Project Portfolio Evaluation Methodology

Many techniques exist for evaluation of potential project portfolios that will optimally
meet an organization’s Strategic Business Objectives. We have already discussed
the importance of metrics and unbiased evaluation criteria and constraints.

Numerous techniques exist for solving multi-objective project portfolio problems but
proper application is dependent on accurately evaluating benefits and constraints
and so called “rate and weight” methodologies lend themselves to the bias concerns
discussed above and should be avoided.

Project proponent claims, costs, schedule and benefits need to carefully reviewed
and challenged as part of the project selection process and one or more capital
allocation methodologies utilized. These capital allocation methodologies include:

        ranking of potential projects by cost benefit ratios

              o independent projects with singular budget constraint

        linear programming

              o multiple constraints especially when extensive project options being
                considered

        integer programming using “branch and bound” methods

              o most accurate when project options are narrowed

                                there are 2N potential project portfolios, where N is the number of
                                 projects that are either funded or not funded

The standard capital allocation model is derived from work done by Markowitz on
Portfolio Theory and may be written as:

                  N
Maximizing       b x
                  i 1
                         i   i




Where bi is the benefit associated with the ith project; and x is either zero or one
depending if the project is included in the portfolio or not

The above capital allocation model is constrained in such a way that the total cost of
all projects in the portfolio does not exceed some maximum capital cost such that:
© 2011 Bob Prieto
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 7
PM World Today – June 2011 (Vol. XIII, Issue VI)



 N

c x
i 1
       i   i    C


Given that a total budget constraint is typically not as hard as the above formula
would suggest, it may be convenient to understand the sensitivity of the portfolio
optimization to the maximum capital cost level.

This simple capital allocation model can be extended to address:

              multiple benefits (associated with multiple evaluation criteria, appropriately
               weighted)
              benefits spread over time (net present value)
              costs spread over time (net present value)
              future costs associated with implementation of a project (maintenance and
               operating costs; consumables)
              costs associated with not doing a project
              mutually exclusive projects or project alternatives
              project precedence
              partial project benefit interdependency
              cost, schedule other benefit synergies
              multi-period cost constraints
              sensitivity to delay

The “Efficient Frontier”

Solving the capital allocation model does not result in a singular solution but rather
an extensive solution set that may be considered by looking at:

              risk adjusted benefits versus total costs (project portfolio management)

              portfolio returns at various risk levels (portfolio theory)

These potential portfolio solutions may be plotted to create a view of the "efficient
frontier."




© 2011 Bob Prieto
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 8
PM World Today – June 2011 (Vol. XIII, Issue VI)




Identifying and understanding the efficient frontier allows us to identify the best
project portfolios at a given budget level and to assess the lost benefits or added
costs associated with other than optimal portfolio selection.

As cost constraints are relaxed, additional or larger projects can be considered
providing lower incremental returns. This is reflected in the flattening observed in the
efficient frontier and closely mirrors Pareto’s 80/20 rule where 80% of all value
available from all projects may be achieved from doing just 20% of the projects. This
provides the program manager with a convenient tool for management prioritization
and the development of critical controls for the program.

Characteristics of Successful Project Portfolios

Successful project portfolios:

        assure projects are aligned with an organization’s strategic direction
        are based on a sound portfolio decision process
        comprise projects that are resilient to the effects of uncertainties embedded in
         the project selection process
        recognize the shift in constraints as one moves from a project to program
         context




© 2011 Bob Prieto
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 9
PM World Today – June 2011 (Vol. XIII, Issue VI)


                      Constraints Shift Under Program Management

                       Project                                                    Program

Scope                                                       Alignment with Strategic Business
                                                            Objectives
Schedule                                                    Required Resources
Cost                                                        Benefits

Successful project portfolios address key questions related to:

        resources required for program implementation
        critical resource limitations that the program will face
        prioritization of objectives
        identification of critical controls
        projects critical to individual SBO achievement
        consideration of uncertainty and risk
        project interdependencies
        key portfolio risk areas

Successful project portfolios recognize that the critical aspect of the project selection
process is represented by the quality of the decisions made.

Conclusion

Objective driven, bias free project portfolio analysis and selection provides the
program manager with another tool to:

        build organizational alignment

        understand program sensitivities to changes in acceptable risk levels and
         profile

        understand the influence of budget and other constraints on benefit
         maximization

        identify project priorities, sequencing and effects of interdependencies and
         synergies

        establish an appropriate set of critical controls.




© 2011 Bob Prieto
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 10
PM World Today – June 2011 (Vol. XIII, Issue VI)



References:

    1. Markowitz, H.M. (March 1952). "Portfolio Selection". The Journal of Finance 7
         (1): 77–91. doi:10.2307/2975974. http://jstor.org/stable/2975974.

    2. Strategic Program Management; published by the Construction Management
         Association of America (CMAA); ISBN 978-0-9815612-1-9; July 24, 2008

    3. Topics in Strategic Program Management; ISBN 978-0-557-52887-5; July
         2010




© 2011 Bob Prieto
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 11
PM World Today – June 2011 (Vol. XIII, Issue VI)


About the Author


                               Bob Prieto

                               Author




                        Bob Prieto is a Senior Vice President of Fluor Corporation,
                        one of America’s largest engineering, construction and project
management firms, where he is responsible for strategy in support of the firm’s
Industrial & Infrastructure Group and its key clients. He focuses on the development,
delivery and oversight of large, complex projects worldwide. Prior to joining Fluor,
Bob served as chairman of Parsons Brinckerhoff Inc. He served as a member of the
executive committee of the National Center for Asia-Pacific Economic Cooperation, a
member of the Industry Leaders’ Council of the American Society of Civil Engineers
(ASCE), and co-founder of the Disaster Resource Network. He currently serves on a
number of committees looking at issues related to infrastructure delivery and
resiliency and disaster response and rebuilding. Until 2006 he served as one of three
U.S. presidential appointees to the Asia Pacific Economic Cooperation (APEC)
Business Advisory Council (ABAC) and previously served as chairman of the
Engineering and Construction Governors of The World Economic Forum and co-chair
of the infrastructure task force formed after September 11th by the New York City
Chamber of Commerce. He recently completed ten year tenure as a member of the
board of trustees of Polytechnic University of New York culminating in its merger with
New York University. Bob is the author of “Strategic Program Management”
published by the Construction Management Association of America (CMAA) and
more recently a companion work entitled “Topics in Strategic Program Management”.




© 2011 Bob Prieto
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 12

Más contenido relacionado

La actualidad más candente

PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
ejlp12
 

La actualidad más candente (20)

PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
PMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHICPMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHIC
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
 
Project Quality Management powerpoint
Project Quality Management powerpointProject Quality Management powerpoint
Project Quality Management powerpoint
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycle
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
 
Chap 1 Modern Project Management
Chap 1 Modern Project ManagementChap 1 Modern Project Management
Chap 1 Modern Project Management
 
PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoring
 
Excel Project Management
Excel Project ManagementExcel Project Management
Excel Project Management
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Edition
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
Project Cost Management
Project Cost Management Project Cost Management
Project Cost Management
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6
 
Project Management and Process
Project Management and ProcessProject Management and Process
Project Management and Process
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
 
Project Planning & Management
Project Planning & ManagementProject Planning & Management
Project Planning & Management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 

Similar a Project Selection in Large Engineering and Construction Programs

PAPERS72 September 2009 ■ Project Management.docx
PAPERS72 September 2009 ■ Project Management.docxPAPERS72 September 2009 ■ Project Management.docx
PAPERS72 September 2009 ■ Project Management.docx
herbertwilson5999
 
Role of Functional Organization in Large Engineering and Construction Programs
Role of Functional Organization in Large Engineering and Construction ProgramsRole of Functional Organization in Large Engineering and Construction Programs
Role of Functional Organization in Large Engineering and Construction Programs
Bob Prieto
 
Module 1 project planning and appraisal
Module 1 project planning and appraisalModule 1 project planning and appraisal
Module 1 project planning and appraisal
dmkanchepalya
 
LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2
Jose Figueroa
 

Similar a Project Selection in Large Engineering and Construction Programs (20)

Does the project manager stand a chance?
Does the project manager stand a chance?Does the project manager stand a chance?
Does the project manager stand a chance?
 
Sustainability On Large Rev 1 01 31 11
Sustainability On Large Rev 1 01 31 11Sustainability On Large Rev 1 01 31 11
Sustainability On Large Rev 1 01 31 11
 
PMO and Tollgate Process
PMO and Tollgate Process PMO and Tollgate Process
PMO and Tollgate Process
 
PAPERS72 September 2009 ■ Project Management.docx
PAPERS72 September 2009 ■ Project Management.docxPAPERS72 September 2009 ■ Project Management.docx
PAPERS72 September 2009 ■ Project Management.docx
 
Project management
Project managementProject management
Project management
 
Role of Functional Organization in Large Engineering and Construction Programs
Role of Functional Organization in Large Engineering and Construction ProgramsRole of Functional Organization in Large Engineering and Construction Programs
Role of Functional Organization in Large Engineering and Construction Programs
 
Module 1 project planning and appraisal
Module 1 project planning and appraisalModule 1 project planning and appraisal
Module 1 project planning and appraisal
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010
Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010
Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010
 
Opportunity analysis under strategic program management second edition
Opportunity analysis under strategic program management second editionOpportunity analysis under strategic program management second edition
Opportunity analysis under strategic program management second edition
 
Identifying and Recovering Troubled Projects
Identifying and Recovering Troubled ProjectsIdentifying and Recovering Troubled Projects
Identifying and Recovering Troubled Projects
 
Pm chapter 2...
Pm chapter 2...Pm chapter 2...
Pm chapter 2...
 
LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2
 
Pm chapter 2
Pm chapter 2Pm chapter 2
Pm chapter 2
 
Opportunity Analysis
Opportunity AnalysisOpportunity Analysis
Opportunity Analysis
 
Project Development
Project Development Project Development
Project Development
 
Project finance
Project financeProject finance
Project finance
 
Evaluation of business start-up policies by Jonathan Potter, Senior Economist...
Evaluation of business start-up policies by Jonathan Potter, Senior Economist...Evaluation of business start-up policies by Jonathan Potter, Senior Economist...
Evaluation of business start-up policies by Jonathan Potter, Senior Economist...
 
Project appraisal
Project appraisalProject appraisal
Project appraisal
 
Today's Contracting - Contracts Risks and Disputes
Today's Contracting - Contracts Risks and Disputes Today's Contracting - Contracts Risks and Disputes
Today's Contracting - Contracts Risks and Disputes
 

Más de Bob Prieto

Más de Bob Prieto (20)

Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startup
 
Deeper look at the physics of projects
Deeper look at the physics of projectsDeeper look at the physics of projects
Deeper look at the physics of projects
 
Systems nature of large complex projects
Systems nature of large complex projectsSystems nature of large complex projects
Systems nature of large complex projects
 
Governance of mega and giga programs
Governance of mega and giga programsGovernance of mega and giga programs
Governance of mega and giga programs
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project delivery
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface Management
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction Projects
 
Reversing Global Warming
Reversing Global WarmingReversing Global Warming
Reversing Global Warming
 
Improving infrastructure project success
Improving infrastructure project successImproving infrastructure project success
Improving infrastructure project success
 
Large complex project success
Large complex project successLarge complex project success
Large complex project success
 
Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects
 
Decision Making Under Uncertainty
Decision Making Under UncertaintyDecision Making Under Uncertainty
Decision Making Under Uncertainty
 
Post Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasPost Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the Bahamas
 
Debating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentDebating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environment
 
Chapters 11 12 13
Chapters 11  12  13Chapters 11  12  13
Chapters 11 12 13
 
Chapter 10
Chapter 10Chapter 10
Chapter 10
 
Chapter 9
Chapter 9Chapter 9
Chapter 9
 
Chapter 8
Chapter 8Chapter 8
Chapter 8
 
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7
 

Último

Último (20)

HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
 
Wellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxWellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptx
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 

Project Selection in Large Engineering and Construction Programs

  • 1. PM World Today – June 2011 (Vol. XIII, Issue VI) PM WORLD TODAY – FEATURED PAPER – JUNE 2011 Project Selection in Large Engineering Construction Programs By Bob Prieto One of the most important steps in implementation of a program management approach is the selection of the projects which will comprise the program. This selection process, done appropriately, is neither intuitively obvious nor simple. Done poorly, the program may achieve less than optimum results or be exposed to risks which may degrade its value over time. Project selection must flow from strategy which in turn is defined by an organization’s strategic business objectives. Key performance indicators which are established to assure strategic business objectives are met, must cascade down through strategy assessment into overall project portfolio assessment and ultimately into individual projects. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 1
  • 2. PM World Today – June 2011 (Vol. XIII, Issue VI) The selection of the portfolio of projects that will comprise the program must:  optimize multiple strategic business objectives  address sequencing required for optimization  address interdependencies between projects  reflect real world resource constraints  enhance program (and organizational) flexibility and resiliency Programs which experience weak project selection may have failed to:  maintain focus on strategic business objectives allowing biases to enter the process  establish a sufficiently strong methodology for project portfolio evaluation, often only considering one primary strategic business objective without attention to other such objectives  appropriately cascade metrics down to the assessment of project portfolio performance  inadequately reflect uncertainty and risks in portfolio evaluation Weak project selection will result in lower value capture and, to the extent to which project selection appears to be driven by non-objective factors, undermine organizational honesty and openness. Projects selection must be monitored as well as project performance under program management. This is an area which requires increased focus in the engineering and construction industry. Changes in market conditions, resource constraints, risk levels or execution performance may drive a re-evaluation of the portfolio which shows that redeployment of resources is in the best interest of achieving the programs strategic business objectives even when sunk costs and commitments are fully considered. Termination of a previously selected project may be a simpler matter if it is performing below expectations (schedule delays, cost overruns) but when driven by a reduction in the benefits that will accrue or value derived it is a much harder matter. Who wants to be the program manager who terminates a strong performing project (ahead of schedule, under budget)? Optimize Multiple Strategic Business Objectives A key attribute of project selection in major engineering and construction programs is the need to simultaneously optimize multiple strategic business objectives. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 2
  • 3. PM World Today – June 2011 (Vol. XIII, Issue VI) This need is driven by the outcomes focus of programs versus the outputs focus that is more typical of projects. Successful optimization will rest on:  clear definition of strategic business objectives  SMART key performance indicators or KPIs for each objective o Specific o Measurable o Achievable o Realistic o Targeted  well defined constraints facing the program and individual projects  delineated interdependencies between projects including any precedence requirements  clarity around attendant risks and uncertainties at the program and project level.  appropriate weighting of benefits and constraints that comprise the project portfolio’s evaluation criteria by the executives most focused on strategic business objective achievement Evaluation criteria and constraints may include: - Financial  Life cycle return on investment  Return on assets employed  Net present value of cash flows  Payback period  Total capital expenditures © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 3
  • 4. PM World Today – June 2011 (Vol. XIII, Issue VI)  Product/project gross margins - Market  Market share  Market growth and duration  Period of profitable production  Product flexibility  Customer impacts - Strategic  Flexibility  Resiliency  Contribution to overall portfolio performance  Enablement of SBO achievement  Enablement of other portfolio projects  Critical resource utilization - Sustainability or Triple Bottom Line focused criteria  Economic  Social  Community impacts  Capacity building  New industry/business creation  Stakeholder support  Workforce impacts  Environmental, Health & Safety  Airborne emissions  Water consumption  Discharge water quality  Environmental degradation  Worker health and safety  Public health and safety - Risk  Economic or market uncertainties  Other event risks  Financing uncertainties  Cost uncertainties  Schedule uncertainties  Labor risks  Stakeholder risks  Sovereign and legislative risks  Political risks  Technology risks  Intellectual property risks  Business model risks  Project execution risks © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 4
  • 5. PM World Today – June 2011 (Vol. XIII, Issue VI) Weak project evaluation methodologies that seek to reduce all benefits to a singular cost related value, such as NPV, must be avoided in recognition that:  Uncertainty in estimates is compounded  Structured multi-variate risk analysis would produce a better assessment of risk  Benefits of later phase projects are not fully appreciated  Changes in risk profile over time are not recognized Avoiding Bias in Project Selection Objective assessment rests on well defined objectives, constraints and evaluation metrics that can be mapped to well defined evaluation criteria. Constraints Strategic Business Objectives (SBO) Optimal Evaluation Project Criteria Portfolio Evaluation Metrics Avoiding Bias in Project Selection It is essential that the owner’s team and program manager understand potential sources of selection bias and carefully review objectives, metrics, constraints and evaluation criteria to ensure such biases have been minimized and ideally eliminated. The use of unconscious shortcuts to make complex decisions has been well documented but may lead to systematic errors in the project portfolio selection process. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 5
  • 6. PM World Today – June 2011 (Vol. XIII, Issue VI) The following table lists some of the biases more commonly observed in programs with weak project selection. Heuristic Biases Affecting Project Selection Motivation bias Status Quo bias Perception bias Risk aversion Optimism bias Comfort zone bias Wishful thinking Group think Uncertainty acceptance Judgmental biases Sunk cost bias Supporting evidence bias Contradictory evidence avoidance Biased argument framing Anchoring Illusion of control Planning fallacy Semmelweis reflex – (tendency to reject new evidence that contradicts an established paradigm) Bounded awareness Reasoning by analogy Removing biases from the project selection processes requires a conscious set of actions that begin with the recognition that potential biases as a result of heuristic and other processes will exist and that a motivated and conscious effort is required to remove them from the process. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 6
  • 7. PM World Today – June 2011 (Vol. XIII, Issue VI) Project Portfolio Evaluation Methodology Many techniques exist for evaluation of potential project portfolios that will optimally meet an organization’s Strategic Business Objectives. We have already discussed the importance of metrics and unbiased evaluation criteria and constraints. Numerous techniques exist for solving multi-objective project portfolio problems but proper application is dependent on accurately evaluating benefits and constraints and so called “rate and weight” methodologies lend themselves to the bias concerns discussed above and should be avoided. Project proponent claims, costs, schedule and benefits need to carefully reviewed and challenged as part of the project selection process and one or more capital allocation methodologies utilized. These capital allocation methodologies include:  ranking of potential projects by cost benefit ratios o independent projects with singular budget constraint  linear programming o multiple constraints especially when extensive project options being considered  integer programming using “branch and bound” methods o most accurate when project options are narrowed  there are 2N potential project portfolios, where N is the number of projects that are either funded or not funded The standard capital allocation model is derived from work done by Markowitz on Portfolio Theory and may be written as: N Maximizing b x i 1 i i Where bi is the benefit associated with the ith project; and x is either zero or one depending if the project is included in the portfolio or not The above capital allocation model is constrained in such a way that the total cost of all projects in the portfolio does not exceed some maximum capital cost such that: © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 7
  • 8. PM World Today – June 2011 (Vol. XIII, Issue VI) N c x i 1 i i C Given that a total budget constraint is typically not as hard as the above formula would suggest, it may be convenient to understand the sensitivity of the portfolio optimization to the maximum capital cost level. This simple capital allocation model can be extended to address:  multiple benefits (associated with multiple evaluation criteria, appropriately weighted)  benefits spread over time (net present value)  costs spread over time (net present value)  future costs associated with implementation of a project (maintenance and operating costs; consumables)  costs associated with not doing a project  mutually exclusive projects or project alternatives  project precedence  partial project benefit interdependency  cost, schedule other benefit synergies  multi-period cost constraints  sensitivity to delay The “Efficient Frontier” Solving the capital allocation model does not result in a singular solution but rather an extensive solution set that may be considered by looking at:  risk adjusted benefits versus total costs (project portfolio management)  portfolio returns at various risk levels (portfolio theory) These potential portfolio solutions may be plotted to create a view of the "efficient frontier." © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 8
  • 9. PM World Today – June 2011 (Vol. XIII, Issue VI) Identifying and understanding the efficient frontier allows us to identify the best project portfolios at a given budget level and to assess the lost benefits or added costs associated with other than optimal portfolio selection. As cost constraints are relaxed, additional or larger projects can be considered providing lower incremental returns. This is reflected in the flattening observed in the efficient frontier and closely mirrors Pareto’s 80/20 rule where 80% of all value available from all projects may be achieved from doing just 20% of the projects. This provides the program manager with a convenient tool for management prioritization and the development of critical controls for the program. Characteristics of Successful Project Portfolios Successful project portfolios:  assure projects are aligned with an organization’s strategic direction  are based on a sound portfolio decision process  comprise projects that are resilient to the effects of uncertainties embedded in the project selection process  recognize the shift in constraints as one moves from a project to program context © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 9
  • 10. PM World Today – June 2011 (Vol. XIII, Issue VI) Constraints Shift Under Program Management Project Program Scope Alignment with Strategic Business Objectives Schedule Required Resources Cost Benefits Successful project portfolios address key questions related to:  resources required for program implementation  critical resource limitations that the program will face  prioritization of objectives  identification of critical controls  projects critical to individual SBO achievement  consideration of uncertainty and risk  project interdependencies  key portfolio risk areas Successful project portfolios recognize that the critical aspect of the project selection process is represented by the quality of the decisions made. Conclusion Objective driven, bias free project portfolio analysis and selection provides the program manager with another tool to:  build organizational alignment  understand program sensitivities to changes in acceptable risk levels and profile  understand the influence of budget and other constraints on benefit maximization  identify project priorities, sequencing and effects of interdependencies and synergies  establish an appropriate set of critical controls. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 10
  • 11. PM World Today – June 2011 (Vol. XIII, Issue VI) References: 1. Markowitz, H.M. (March 1952). "Portfolio Selection". The Journal of Finance 7 (1): 77–91. doi:10.2307/2975974. http://jstor.org/stable/2975974. 2. Strategic Program Management; published by the Construction Management Association of America (CMAA); ISBN 978-0-9815612-1-9; July 24, 2008 3. Topics in Strategic Program Management; ISBN 978-0-557-52887-5; July 2010 © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 11
  • 12. PM World Today – June 2011 (Vol. XIII, Issue VI) About the Author Bob Prieto Author Bob Prieto is a Senior Vice President of Fluor Corporation, one of America’s largest engineering, construction and project management firms, where he is responsible for strategy in support of the firm’s Industrial & Infrastructure Group and its key clients. He focuses on the development, delivery and oversight of large, complex projects worldwide. Prior to joining Fluor, Bob served as chairman of Parsons Brinckerhoff Inc. He served as a member of the executive committee of the National Center for Asia-Pacific Economic Cooperation, a member of the Industry Leaders’ Council of the American Society of Civil Engineers (ASCE), and co-founder of the Disaster Resource Network. He currently serves on a number of committees looking at issues related to infrastructure delivery and resiliency and disaster response and rebuilding. Until 2006 he served as one of three U.S. presidential appointees to the Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC) and previously served as chairman of the Engineering and Construction Governors of The World Economic Forum and co-chair of the infrastructure task force formed after September 11th by the New York City Chamber of Commerce. He recently completed ten year tenure as a member of the board of trustees of Polytechnic University of New York culminating in its merger with New York University. Bob is the author of “Strategic Program Management” published by the Construction Management Association of America (CMAA) and more recently a companion work entitled “Topics in Strategic Program Management”. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 12