What is building by laws?
• The rules and regulation framed by town planning authorities
covering the requirements of building, ensuring safety of the public
through open spaces, minimum size of rooms and height and area
limitation, are known as building bye-laws.
• Rules and regulations which largely regulate the building activity
should be formulated to get disciplined growth of building and the
better planned development of towns and cities.
Objective of building bye-laws
• pre-planning of building activity.
• allow orderly growth and prevent haphazard development.
• Provisions of by-laws usually afford safety against fire, noise, health
hazard and structure failure.
• Provide proper utilization of space to achieved maximum efficiency in
planning.
• They provide health, safety and comfort to the people who live in
building.
• Due to these bye-laws, each building will have proper approaches,
light, air and ventilation.
Scope of building bye-laws
• Aspects of different type of building in building bye-laws:
1. Building frontage line
2. Minimum plot size
3. Built up area of building
4. Height of building
5. Provision of safety, water supply, drainage, proper light and
ventilation
6. Requirement for off street parking space
7. Size of structural element
Applicability of building bye-laws
• New construction
• Additional and alternations to a building
• Changing of occupancy of building (residential  education etc.)
• Development of land is undertaken
• In demolition
Different types of area
• Built up area
• Plinth area
• Floor area
• Carpet area
• Super built up area
Built up area
• “The area covered by the building immediately above the plinth level”
• It is also known as covered area.
Details to be included Details not to be included
Basement Steps
Building Structure Otta
Ramps Kundi
Swimming pool Soak pit
Reservoir Fountain
Chimney Manhole
Water purification plant Water tank
Plinth area
• Means the built-up covered area measured at the floor level of the
basement or of any storey.
Area to be included in plinth area Area not to be included in plinth area
Area of walls at floor level excluding
plinth offset, external area of projecting
cladding.
Additional floor to accommodate seats in
theatre, assembly hall, or auditorium
Cover of stair Balcony
Barsati Curvature provided to improve
appearance
Machine room Platform without cover terrace above
floor
Porch without cantilever Dome, tower at terrace, spiral stairs
Carpet area
• “it is net usable area within building”.
• Means the net area within a unit of a building excluding walls or
columns, service areas such as washrooms, kitchen and pantry, semi-
open spaces such as veranda or balcony, and corridors or passages.
Floor area
• “It is usable area on each floor”
• It including,
• Porch
• Each flat area in single floor for apartment
• Stairs
• Corridor
• door swing place
Set back distance
Permissible Set Back Distance
Width of road Permissible set back
Up to 12 m 1.5
>12 m 2.0
Road width <3 m and length < 30 m No set- back
Advantage of set-back
• Better condition of air, light and ventilation.
• At corners it improve visibility and safety from traffic.
• Space for parking.
• Protection of building from street nuisance like noise.
• Reduce the danger of fire from neighbor house.
• It provide privacy in building.
Building & control line
• The line up to which the plinth of the building adjoining a street or
road or on future street may lawfully extend is know as building line.
• Building such as cinemas, factories, commercial center which attract
large number of vehicle should be set-back distance apart from the
building line.
• The line up to which such building can be constructed is known as
control line.
Light plan
• The angle of light plan is 450 or 63.500. So the angle of 63.500 set Back
becomes necessary when the total height of the building exceeds
twice the width of road or street.
Floor space index
𝐹𝑆𝐼 =
𝑇𝑜𝑡𝑎𝑙 𝑐𝑜𝑣𝑒𝑟𝑒𝑑 𝑎𝑟𝑒𝑎 𝑜𝑓 𝑎𝑙𝑙 𝑓𝑙𝑜𝑜𝑟𝑠
𝑝𝑙𝑜𝑡 𝑎𝑟𝑒𝑎
Zone Permissible
FSI
Remark
Residential(scheme area) 1 Max at G.F 0.4
Residential(city area) 4 Width of road more than 12m
Residential(city area) 3 Width of road less than 12m
Industrial (scheme area) 1.5 Maximum allowed on G.F 1.0
Commercial (scheme area) 1.33 Maximum allowed on G.F 0.4
How to calculate FSI
New FSI
• Page 95 of GDCR
Principles underlying building bye-laws
• Classifying the building with unit as a family and mentioning the
requirement.
• Classify rooms according use and then specifying minimum standard of
each room with respect to size, height, floor area, ventilation and light.
• Specify height of compound wall and location of gate in wall.
• Controlling projection in marginal space.
• Insisting on suitable FSI or FAR.
• Specify suitable arrangements with respect to drainage and water supply.
• Specify set-backs, light plan and margin.
• Specify minimum size of plots, their dimension and figure.
Building Bye-laws For Residential Area
• Size of plots
• Area limitation
• Margin
• Height of the building
• Plinth height
• Minimum area of rooms
• Basement
• Compound wall
• Projection margin
• Parapet wall
• Mezzanine floor
• staircase
1.Size of plots:
TYPE OF DEVELOPMENT PLOT SIZE FRONTAGE
Detached Building >250 m2 Above 12 m
Semi-detached building 125-250 m2 8-12 m
Row type building 50-125 m2 4.5 to 8 m
2. Area limitation
• The limitation of area and height of the building of diff. type of
construction and occupancy class is achieved by satisfying floor area ratio.
• The FAR is specified taking into account the following aspect:
1. Occupancy class
2. Type of construction
3. Width of street frontage the building and the traffic load.
4. Parking facilities
5. Local fire fighting facilities
6. Water supply and drainage.
• Built up area:
The FSI shall be 1.0 with maximum utilization up to 0.4 on ground floor.
Sr.No. Area of plot Maximum permissible covered area
1. <200 m2 66.67% of the plot area on ground floor and first floor.
Nothing on second floor exceeding 25 % of the ground
floor.
2. 201-500 m2 50 % of the plot area or 133 m2 which ever is more.
3. 501-1000 m2 40 % of the plot area or 250 m2 which ever is more.
4. >1000 m2 33.33 % of the plot area or 400 m2 which ever is more.
Margin
• The open spaces insides and around the building particularly
residential type have to provide to carter for the lighting and
ventilation requirement.
1. Front open space
2. Rear open space
3. Side open space
For building upto 300m2 plot area
Sr. No. Plot area (m2) Front open space Rear open space Sides open space
1. Up to 50 0.75 - -
2. 51 to 75 1.0 1.0 0.5
3. 76 to 100 1.25 1.00 0.5
4. 101 to 150 2.0 2.0 1.25
5. 151 to 200 2.0 2.0 1.25
6. 201 to 300 3.0 2.0 1.50
For building above 300m2 plot area and height upto 13 m
1. Minimum front set back
2. Minimum rear set back is 3 m
3. Minimum side backs
Width of road in m Minimum set back in m
Up to 12 3
12 to 18 4
Above 18 4.5
Plot area Minimum set back
301 to 670 1.5 m or 0.25 of the height
of the building on each side
Above 670 3 m on both side or 0.25 of
height of the building which
is higher
Height Of The Building
• Height of building according to width of street:
1. The maximum height of the building shall not exceed 1.5 times the
width of road.
2. For building in vicinity of aerodromes, the maximum height of the
building is fixed in consultation with civil aviation authorities.
• The height shall not included if building is erected one-third of roof
area, including:
1. Roof tank and its support
2. Ventilating, lift room
3. Roof structure other than pent-house
Plinth height
• The height of the plinth shall not be less than 450 mm ground level.
• Minimum height of 600 mm is the best from drainage or other
consideration.
• It is minimum 900 mm in water logged soils.
Minimum Size Of Diff. Rooms
No. Name of room Minimum area Minimum size of side Height Other
requirement
1. Habitable room
-bed room
-living room
-study room
9.5 m2 2.4 m Not less then
2.75 m from
surface of floor to
lowest point of
ceiling
As per need
2. Kitchen 5 m2 1.8 m Not less than
2.75 m
As per need
3. Bath rooms and
water closets
1.8 m2 If bath and water closet
are combined, its floor
area shall not less than
2.8 m2 with minimum
width 1.2 m
Not less than 2.1
m
As per need
No. Name of room Minimum area Minimum size of
side
Height Other requirement
4. Store room 3 m2 ----- Not less than 2.2 m -----
5. Garage 12.5 m2 3m x 6m Not less than 2.4 m -----
6. Stair case The minimum width
of stair is 0.9 m.
Clear head room
shall be 2.2 m
• Minimum width
of tread without
nosing 250 mm
in residential.
• The maximum
height of rise
shall be 190 mm
for residential
building.
Basement/Cellar
• The basement shall not be used for residential purpose.
• The basement to be constructed within the prescribed set back and
building lines and subject to maximum on entrance floor may be put
to only the following use:
• Storage of household
• Strongrooms, bank cellars
• Parking places
• Air conditioning equipment and other machine
Requirement of basement
• The height of basement from the floor to the underside of the
roofslab or ceiling shall not be less than 2.4 m.
• The maximum height of the ceiling of any basement shall be 0.9 m
and maximum 1.2 m above the average surrounding ground level.
• Adequate arrangement shall be made such that surface drainage does
not enter the basement.
• The walls and floor of the basement shall be watertight.
• The access to the basement shall be separate from the main and
alternative staircase providing access and exit from higher floor.
Compound Wall
• Except with the special permission of the maximum height of
compound wall shall be 1.5 m above center line of front street.
• It is permitted 2.4 m when the top of 0.9 m is open type construction
• In corner plot it is restricted to 0.75 m for a length of 10 m on side
and front intersection.
• The balance height of 0.75 m may be made up through railing and of
design to be approved by the authority.
Projection in margins
Mezzanine Floor
• Minimum height of mezzanine floor shall be 2.2 m.
• The minimum size of the mezzanine floor, if it is to be used as a living
room shall not less than 9.5 m2
• The aggregate area of such mezzanine floor in a building shall in no
case exceed 1/3 the plinth area of the building.
Building  by laws

Más contenido relacionado

La actualidad más candente

Cost effective construction techniques
Cost effective construction techniquesCost effective construction techniques
Cost effective construction techniques
Sayali Darakh
 

La actualidad más candente (20)

Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildings
 
Filler slab
Filler slabFiller slab
Filler slab
 
Building bye laws
Building bye lawsBuilding bye laws
Building bye laws
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
High rise building construction
High rise building constructionHigh rise building construction
High rise building construction
 
Low cost housing
Low cost housingLow cost housing
Low cost housing
 
Classification of Buildings as per National Building Code of India (NBC) 2016
Classification of Buildings as per National Building Code of India (NBC) 2016Classification of Buildings as per National Building Code of India (NBC) 2016
Classification of Buildings as per National Building Code of India (NBC) 2016
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
 
national builiding codes
national builiding codesnational builiding codes
national builiding codes
 
Fire safety as per National Building Code-2016
Fire safety as per National Building Code-2016Fire safety as per National Building Code-2016
Fire safety as per National Building Code-2016
 
Designing for different climatic zones in India
Designing for different climatic zones in IndiaDesigning for different climatic zones in India
Designing for different climatic zones in India
 
Housing
Housing Housing
Housing
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
 
Composite climate
Composite climateComposite climate
Composite climate
 
URDPFI - 2016
URDPFI - 2016URDPFI - 2016
URDPFI - 2016
 
Foundation types
Foundation typesFoundation types
Foundation types
 
Cost effective construction techniques
Cost effective construction techniquesCost effective construction techniques
Cost effective construction techniques
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
By laws Gujrat
By laws GujratBy laws Gujrat
By laws Gujrat
 
Modular coordination
Modular coordinationModular coordination
Modular coordination
 

Destacado (8)

Principal of building planning
Principal of building planningPrincipal of building planning
Principal of building planning
 
Building laws
Building lawsBuilding laws
Building laws
 
Development Plan- Planning Intervention (CRITICAL ANALYSIS OF MASTER PLAN CA...
Development Plan- Planning Intervention (CRITICAL ANALYSIS OF MASTER PLAN  CA...Development Plan- Planning Intervention (CRITICAL ANALYSIS OF MASTER PLAN  CA...
Development Plan- Planning Intervention (CRITICAL ANALYSIS OF MASTER PLAN CA...
 
griha Manual vol i
griha Manual vol igriha Manual vol i
griha Manual vol i
 
Certifcation of Building Using GRIHA Rating System
Certifcation of Building Using GRIHA Rating SystemCertifcation of Building Using GRIHA Rating System
Certifcation of Building Using GRIHA Rating System
 
Development Plan- Planning interventions by (MANIT) Maulana Azad National Ins...
Development Plan- Planning interventions by (MANIT) Maulana Azad National Ins...Development Plan- Planning interventions by (MANIT) Maulana Azad National Ins...
Development Plan- Planning interventions by (MANIT) Maulana Azad National Ins...
 
Town Planning
Town Planning Town Planning
Town Planning
 
Planning concepts
Planning conceptsPlanning concepts
Planning concepts
 

Similar a Building by laws

Similar a Building by laws (20)

buildingby-laws-170216060116 ppt.pptx
buildingby-laws-170216060116 ppt.pptxbuildingby-laws-170216060116 ppt.pptx
buildingby-laws-170216060116 ppt.pptx
 
Building By law.pptx
 Building By law.pptx Building By law.pptx
Building By law.pptx
 
GROUP 4 LITERATURE.pptx
GROUP 4 LITERATURE.pptxGROUP 4 LITERATURE.pptx
GROUP 4 LITERATURE.pptx
 
BY LAWS CLUSTER HOUSING
BY LAWS CLUSTER HOUSINGBY LAWS CLUSTER HOUSING
BY LAWS CLUSTER HOUSING
 
building byelaws
building byelawsbuilding byelaws
building byelaws
 
Case study low raise appartment
Case study  low raise appartmentCase study  low raise appartment
Case study low raise appartment
 
Bye laws
Bye lawsBye laws
Bye laws
 
General Development Control Regulations (GDCR).pptx
General Development Control Regulations (GDCR).pptxGeneral Development Control Regulations (GDCR).pptx
General Development Control Regulations (GDCR).pptx
 
Principles of planning and bye laws pns
Principles of planning and bye laws pnsPrinciples of planning and bye laws pns
Principles of planning and bye laws pns
 
Group Housing (Library Study)
Group Housing (Library Study)Group Housing (Library Study)
Group Housing (Library Study)
 
group housing - Library study
group housing - Library studygroup housing - Library study
group housing - Library study
 
GDCR Planning Regulations
GDCR Planning Regulations GDCR Planning Regulations
GDCR Planning Regulations
 
Building Bye-laws
Building  Bye-lawsBuilding  Bye-laws
Building Bye-laws
 
General Requirments Of Fire Resisting Building.pptx
General Requirments Of Fire Resisting Building.pptxGeneral Requirments Of Fire Resisting Building.pptx
General Requirments Of Fire Resisting Building.pptx
 
MODULE 2 Introduction and Town Planning.pptx
MODULE 2 Introduction and Town Planning.pptxMODULE 2 Introduction and Town Planning.pptx
MODULE 2 Introduction and Town Planning.pptx
 
Litreature study of group housing by rushali grp
Litreature study of group housing by rushali grpLitreature study of group housing by rushali grp
Litreature study of group housing by rushali grp
 
Building_Planning_and_Design_Module_2.pdf
Building_Planning_and_Design_Module_2.pdfBuilding_Planning_and_Design_Module_2.pdf
Building_Planning_and_Design_Module_2.pdf
 
principles of Building planning (BTP) (ECE)
principles of Building planning (BTP) (ECE)principles of Building planning (BTP) (ECE)
principles of Building planning (BTP) (ECE)
 
Ch 8 building planning
Ch 8 building planningCh 8 building planning
Ch 8 building planning
 
What are Development controls
What are Development controlsWhat are Development controls
What are Development controls
 

Último

Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 

Último (20)

Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 

Building by laws

  • 1. Building & Town planning BUILDING BYE-LAWS
  • 3. What is building by laws? • The rules and regulation framed by town planning authorities covering the requirements of building, ensuring safety of the public through open spaces, minimum size of rooms and height and area limitation, are known as building bye-laws. • Rules and regulations which largely regulate the building activity should be formulated to get disciplined growth of building and the better planned development of towns and cities.
  • 4. Objective of building bye-laws • pre-planning of building activity. • allow orderly growth and prevent haphazard development. • Provisions of by-laws usually afford safety against fire, noise, health hazard and structure failure. • Provide proper utilization of space to achieved maximum efficiency in planning. • They provide health, safety and comfort to the people who live in building. • Due to these bye-laws, each building will have proper approaches, light, air and ventilation.
  • 5. Scope of building bye-laws • Aspects of different type of building in building bye-laws: 1. Building frontage line 2. Minimum plot size 3. Built up area of building 4. Height of building 5. Provision of safety, water supply, drainage, proper light and ventilation 6. Requirement for off street parking space 7. Size of structural element
  • 6. Applicability of building bye-laws • New construction • Additional and alternations to a building • Changing of occupancy of building (residential  education etc.) • Development of land is undertaken • In demolition
  • 7. Different types of area • Built up area • Plinth area • Floor area • Carpet area • Super built up area
  • 8. Built up area • “The area covered by the building immediately above the plinth level” • It is also known as covered area. Details to be included Details not to be included Basement Steps Building Structure Otta Ramps Kundi Swimming pool Soak pit Reservoir Fountain Chimney Manhole Water purification plant Water tank
  • 9. Plinth area • Means the built-up covered area measured at the floor level of the basement or of any storey. Area to be included in plinth area Area not to be included in plinth area Area of walls at floor level excluding plinth offset, external area of projecting cladding. Additional floor to accommodate seats in theatre, assembly hall, or auditorium Cover of stair Balcony Barsati Curvature provided to improve appearance Machine room Platform without cover terrace above floor Porch without cantilever Dome, tower at terrace, spiral stairs
  • 10.
  • 11. Carpet area • “it is net usable area within building”. • Means the net area within a unit of a building excluding walls or columns, service areas such as washrooms, kitchen and pantry, semi- open spaces such as veranda or balcony, and corridors or passages.
  • 12. Floor area • “It is usable area on each floor” • It including, • Porch • Each flat area in single floor for apartment • Stairs • Corridor • door swing place
  • 14. Permissible Set Back Distance Width of road Permissible set back Up to 12 m 1.5 >12 m 2.0 Road width <3 m and length < 30 m No set- back
  • 15. Advantage of set-back • Better condition of air, light and ventilation. • At corners it improve visibility and safety from traffic. • Space for parking. • Protection of building from street nuisance like noise. • Reduce the danger of fire from neighbor house. • It provide privacy in building.
  • 16. Building & control line • The line up to which the plinth of the building adjoining a street or road or on future street may lawfully extend is know as building line. • Building such as cinemas, factories, commercial center which attract large number of vehicle should be set-back distance apart from the building line. • The line up to which such building can be constructed is known as control line.
  • 17.
  • 18.
  • 19. Light plan • The angle of light plan is 450 or 63.500. So the angle of 63.500 set Back becomes necessary when the total height of the building exceeds twice the width of road or street.
  • 20. Floor space index 𝐹𝑆𝐼 = 𝑇𝑜𝑡𝑎𝑙 𝑐𝑜𝑣𝑒𝑟𝑒𝑑 𝑎𝑟𝑒𝑎 𝑜𝑓 𝑎𝑙𝑙 𝑓𝑙𝑜𝑜𝑟𝑠 𝑝𝑙𝑜𝑡 𝑎𝑟𝑒𝑎 Zone Permissible FSI Remark Residential(scheme area) 1 Max at G.F 0.4 Residential(city area) 4 Width of road more than 12m Residential(city area) 3 Width of road less than 12m Industrial (scheme area) 1.5 Maximum allowed on G.F 1.0 Commercial (scheme area) 1.33 Maximum allowed on G.F 0.4
  • 22. New FSI • Page 95 of GDCR
  • 23. Principles underlying building bye-laws • Classifying the building with unit as a family and mentioning the requirement. • Classify rooms according use and then specifying minimum standard of each room with respect to size, height, floor area, ventilation and light. • Specify height of compound wall and location of gate in wall. • Controlling projection in marginal space. • Insisting on suitable FSI or FAR. • Specify suitable arrangements with respect to drainage and water supply. • Specify set-backs, light plan and margin. • Specify minimum size of plots, their dimension and figure.
  • 24. Building Bye-laws For Residential Area • Size of plots • Area limitation • Margin • Height of the building • Plinth height • Minimum area of rooms • Basement • Compound wall • Projection margin • Parapet wall • Mezzanine floor • staircase
  • 25. 1.Size of plots: TYPE OF DEVELOPMENT PLOT SIZE FRONTAGE Detached Building >250 m2 Above 12 m Semi-detached building 125-250 m2 8-12 m Row type building 50-125 m2 4.5 to 8 m
  • 26.
  • 27. 2. Area limitation • The limitation of area and height of the building of diff. type of construction and occupancy class is achieved by satisfying floor area ratio. • The FAR is specified taking into account the following aspect: 1. Occupancy class 2. Type of construction 3. Width of street frontage the building and the traffic load. 4. Parking facilities 5. Local fire fighting facilities 6. Water supply and drainage.
  • 28. • Built up area: The FSI shall be 1.0 with maximum utilization up to 0.4 on ground floor. Sr.No. Area of plot Maximum permissible covered area 1. <200 m2 66.67% of the plot area on ground floor and first floor. Nothing on second floor exceeding 25 % of the ground floor. 2. 201-500 m2 50 % of the plot area or 133 m2 which ever is more. 3. 501-1000 m2 40 % of the plot area or 250 m2 which ever is more. 4. >1000 m2 33.33 % of the plot area or 400 m2 which ever is more.
  • 29. Margin • The open spaces insides and around the building particularly residential type have to provide to carter for the lighting and ventilation requirement. 1. Front open space 2. Rear open space 3. Side open space
  • 30. For building upto 300m2 plot area Sr. No. Plot area (m2) Front open space Rear open space Sides open space 1. Up to 50 0.75 - - 2. 51 to 75 1.0 1.0 0.5 3. 76 to 100 1.25 1.00 0.5 4. 101 to 150 2.0 2.0 1.25 5. 151 to 200 2.0 2.0 1.25 6. 201 to 300 3.0 2.0 1.50
  • 31. For building above 300m2 plot area and height upto 13 m 1. Minimum front set back 2. Minimum rear set back is 3 m 3. Minimum side backs Width of road in m Minimum set back in m Up to 12 3 12 to 18 4 Above 18 4.5 Plot area Minimum set back 301 to 670 1.5 m or 0.25 of the height of the building on each side Above 670 3 m on both side or 0.25 of height of the building which is higher
  • 32. Height Of The Building • Height of building according to width of street: 1. The maximum height of the building shall not exceed 1.5 times the width of road. 2. For building in vicinity of aerodromes, the maximum height of the building is fixed in consultation with civil aviation authorities. • The height shall not included if building is erected one-third of roof area, including: 1. Roof tank and its support 2. Ventilating, lift room 3. Roof structure other than pent-house
  • 33. Plinth height • The height of the plinth shall not be less than 450 mm ground level. • Minimum height of 600 mm is the best from drainage or other consideration. • It is minimum 900 mm in water logged soils.
  • 34. Minimum Size Of Diff. Rooms No. Name of room Minimum area Minimum size of side Height Other requirement 1. Habitable room -bed room -living room -study room 9.5 m2 2.4 m Not less then 2.75 m from surface of floor to lowest point of ceiling As per need 2. Kitchen 5 m2 1.8 m Not less than 2.75 m As per need 3. Bath rooms and water closets 1.8 m2 If bath and water closet are combined, its floor area shall not less than 2.8 m2 with minimum width 1.2 m Not less than 2.1 m As per need
  • 35. No. Name of room Minimum area Minimum size of side Height Other requirement 4. Store room 3 m2 ----- Not less than 2.2 m ----- 5. Garage 12.5 m2 3m x 6m Not less than 2.4 m ----- 6. Stair case The minimum width of stair is 0.9 m. Clear head room shall be 2.2 m • Minimum width of tread without nosing 250 mm in residential. • The maximum height of rise shall be 190 mm for residential building.
  • 36.
  • 37. Basement/Cellar • The basement shall not be used for residential purpose. • The basement to be constructed within the prescribed set back and building lines and subject to maximum on entrance floor may be put to only the following use: • Storage of household • Strongrooms, bank cellars • Parking places • Air conditioning equipment and other machine
  • 38. Requirement of basement • The height of basement from the floor to the underside of the roofslab or ceiling shall not be less than 2.4 m. • The maximum height of the ceiling of any basement shall be 0.9 m and maximum 1.2 m above the average surrounding ground level. • Adequate arrangement shall be made such that surface drainage does not enter the basement. • The walls and floor of the basement shall be watertight. • The access to the basement shall be separate from the main and alternative staircase providing access and exit from higher floor.
  • 39. Compound Wall • Except with the special permission of the maximum height of compound wall shall be 1.5 m above center line of front street. • It is permitted 2.4 m when the top of 0.9 m is open type construction • In corner plot it is restricted to 0.75 m for a length of 10 m on side and front intersection. • The balance height of 0.75 m may be made up through railing and of design to be approved by the authority.
  • 41. Mezzanine Floor • Minimum height of mezzanine floor shall be 2.2 m. • The minimum size of the mezzanine floor, if it is to be used as a living room shall not less than 9.5 m2 • The aggregate area of such mezzanine floor in a building shall in no case exceed 1/3 the plinth area of the building.