Mivan shuttering – latest technology in
construction…
 Mivan shuttering is a fast-paced construction technique which offers
strength and durability to a building by use of aluminium formworks.
 With a growing focus on affordable homes and "Housing for All", real
estate stakeholders are increasingly emphasising on the use of new
and innovative construction techniques. One such technology is
Mivan shuttering which is being promoted for its ability to aid mass
construction activity.
So, what exactly is Mivan Technology?
• Mivan is an aluminium formwork system developed by a European construction
company.
• In 1990, the Mivan Company Ltd. from Malaysia started manufacturing these
formwork systems.
• Today, more than 30,000sqm of formwork from Mivan Co. Ltd. is used across the
world.
• There are a number of buildings in India that are being constructed with the
help of the Mivan system, that has proven economical as well as satisfactory for
the overall Indian construction environment.
• The technology has been used extensively in Europe, Gulf Countries, Asia and
other parts of the world.
So, what exactly is Mivan Technology?
• It is suitable for constructing large number of houses in a short span of time
using room size forms to construct walls and slabs in one continuous pour on
concrete. In this system of formwork construction, cast–in–situ concrete wall and
floor slabs cast monolithic provides the structural system in one continuous
pour.
• To facilitate fast construction, early removal of forms can be achieved by hot air
curing / curing compounds.
• Large room sized forms for walls and floor slabs are erected at site.
• These strong and sturdy forms are fabricated with accuracy and are easy to
handle.
• The concrete is produced in RMC batching plants under strict quality control and
convey it to site with transit mixers.
So, what exactly is Mivan Technology?
• The frames for windows, doors and ducts for services are placed in the form
before concreting.
• Staircase flights, façade panels, chajjas and jalis etc. and other pre-fabricated
items are also integrated into the structure.
• This proves to be a major advantage as compared to other modern construction
techniques.
• High quality Mivan Formwork panels ensure consistency of dimensions.
• On the removal of the formwork mould a high quality concrete finish is produced
to accurate tolerances and verticality. The high tolerance of the finish means
that, no further plastering is required.
Sheet Thickness & Panel Sizes
• The concrete face of panels (Al Sheet) is 4 mm thick.
• Standard sizes of Panels are: 2000x600,2000x300,1200x300,850x300.
• Apart from above any size as required can be manufactured and delivered.
Load Carrying Capacity
• High load carrying capacity of 7-8 Tonnes Per square meter
• Light weight is the main advantage over conventional formwork technology.
• Aluminium formwork weighs around 18-20 kg per meter square.
Cycle Time
• Vertical (Wall) Formwork – 12 hours after concreting or when concrete strength
has reached 2N/mm2.
• Horizontal (Deck) Formwork – 36 hours after concreting or when concrete
strength has reached 10N/mm2.
• High speed of construction can be achieved by this system that means faster
completion of project.
• 7 Days per floor.
Uses of Mivan Formwork
• 3S – System of Construction – Speed, Strength, Safety
• Column and beam construction are eliminated
• Walls and slabs are cast in one operation
• Specially designed, easy to handle light weight pre-engineered aluminium forms
• Fitting and erecting the portion of shuttering
• Carrying out concreting of the walls and slabs together
Use in India
• So far, the technology has not been used extensively in India. The
concept is popular in Gulf countries, Europe and some parts of Asia.
However, its use is being promoted in India to realise the most
ambitious government scheme – Housing for All by 2022.
• To make housing affordable for masses, there is a need to focus on
new construction technologies which can reduce construction time
and cost. Mivan Shuttering is the solution to this. In addition to saving
time and money, the technology can also ensure quality and strength
of buildings.
Construction technique
• Setting up the wall reinforcing steel - The wall reinforcing steel is used to give a
structure to the building and support the concrete until they gain half of the
required strength. The aluminium formworks are cast around the steel mesh,
which is factory made and directly erected on the construction site.
• Placement of aluminium formwork – Along the wall reinforcing steel,
prefabricated room sized walls and floor slabs are erected. These aluminium alloy
slabs are accurately made and are easy to handle.
• Spaces for windows, ducts, doors and other features such as staircases, façade
panels and chajjas are also integrated in these structures. The forms are joint
together using the pin and wedge system, which can be dismantled quickly after
the concrete structure is made.
Pouring concrete – After casting the forms, high-quality concrete is
poured. This concrete takes the form and shape of the cast, which is
later removed to make way for a structure made entirely of cement
concrete supported by wall reinforcing steel. The aluminium forms can
be reused at least 250 times, resulting in minimum waste from the
construction site.
Advantages
• Mivan formwork requires relatively less labour
• More seismic resistance
• Increased durability
• Lesser number of joints and reduced leakages
• Higher carpet area
• Smooth finishing of wall and slab
• Uniform quality of construction
• Negligible maintenance
• Faster completion
Limitations of Mivan Technology
• Because of few small sizes finishing lines are seen on the concrete surfaces
Services after completing become slightly difficult due to the small width of
components
• It requires uniform planning as well as uniform elevations to be cost
effective
• The formwork requires number of spacer, wall ties etc. which are placed @
2ft c/c; these produce problems such as seepage, leakages during monsoon
due to box-type construction, contraction cracks are likely to appear
• Heat of hydration is high due to shear walls
• It is rigid in design once placed, as any alteration becomes tough later
Limitations of Mivan Technology
• It remains to be seen if this technology works in the construction industry
considering indigenous technologies are promoted off late. However, if
the advantages of the technology meet the larger goal of 'Housing for All',
it could prove to be a boon for Indian real estate.
Remedial Measures
It is possible to minimize contraction cracks by providing control strips
in the structure which could be concreted with a delay of about 3-7
days after major concreting. The problem of cracking can be avoided by
minimizing the heat of hydration by using flash.
COSTING
Here we considering mivan cost as 120USD per Sqm. without any taxes.
Now 1 USD = @ 62 INR
Hence, for per sq.m the cost is around 7500 I.N.R.
And for one sq.ft. it is around 700 I.N.R.
Mivan shuttering – latest technology in
construction…
CONCLUSION
Concrete construction has gone through significant changes since the
early 1990s and continues to develop innovation in formwork. Some of
the pioneering companies in modern form working system are peri,
doca system, outinord, meva, acrow. Mivan formwork construction is
able to provide high quality construction at unbelievable speed at
reasonable cost. This mivan technology has great potential for
application in India to provide affordable housing to its rising
population.
THANK YOU !

Más contenido relacionado

La actualidad más candente

Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniqueIEI GSC
 
Mivan aluminium formwork
Mivan  aluminium formworkMivan  aluminium formwork
Mivan aluminium formworkAnup Kude
 
automation in construction
automation in constructionautomation in construction
automation in constructionAnand Khare
 
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURESUNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURESVenkateswaran S
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipmentsAshish Parihar
 
Mivan aluminium formwork
Mivan aluminium formworkMivan aluminium formwork
Mivan aluminium formworkMumtaz Alam
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle SlabAkshay Gawade
 
Prefabrication​ structure ppt
Prefabrication​ structure pptPrefabrication​ structure ppt
Prefabrication​ structure pptAbhishekM45
 
Stone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTIONStone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTIONRavindra Patnayaka
 
Buiding construction (part ii)
Buiding construction (part ii)Buiding construction (part ii)
Buiding construction (part ii)Waqas Aslam
 
Application of robotics in construction industry
Application of robotics in construction industryApplication of robotics in construction industry
Application of robotics in construction industryRahul Singh
 
special types of concrete
special types of concretespecial types of concrete
special types of concreteAmit Parchani
 
New Building Materials
New Building MaterialsNew Building Materials
New Building MaterialsDr K M SONI
 

La actualidad más candente (20)

Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
 
MIVAN REPORT.pdf
MIVAN REPORT.pdfMIVAN REPORT.pdf
MIVAN REPORT.pdf
 
Mivan aluminium formwork
Mivan  aluminium formworkMivan  aluminium formwork
Mivan aluminium formwork
 
automation in construction
automation in constructionautomation in construction
automation in construction
 
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURESUNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 
Mivan aluminium formwork
Mivan aluminium formworkMivan aluminium formwork
Mivan aluminium formwork
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
 
Prefabrication​ structure ppt
Prefabrication​ structure pptPrefabrication​ structure ppt
Prefabrication​ structure ppt
 
Stone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTIONStone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTION
 
Jump Formwork
Jump FormworkJump Formwork
Jump Formwork
 
BRICK MASONRY
BRICK MASONRYBRICK MASONRY
BRICK MASONRY
 
Gypsum Products
Gypsum ProductsGypsum Products
Gypsum Products
 
Building Construction
Building Construction Building Construction
Building Construction
 
Brick masonry
Brick masonryBrick masonry
Brick masonry
 
Buiding construction (part ii)
Buiding construction (part ii)Buiding construction (part ii)
Buiding construction (part ii)
 
Application of robotics in construction industry
Application of robotics in construction industryApplication of robotics in construction industry
Application of robotics in construction industry
 
special types of concrete
special types of concretespecial types of concrete
special types of concrete
 
New Building Materials
New Building MaterialsNew Building Materials
New Building Materials
 
CEMENT CONCRETE
CEMENT CONCRETECEMENT CONCRETE
CEMENT CONCRETE
 

Similar a Mivan

Modern Formwork: Mivan
Modern Formwork: Mivan Modern Formwork: Mivan
Modern Formwork: Mivan RPNarwade
 
MIVAN CONSTRUCTION TECHNOLOGY for const
MIVAN CONSTRUCTION TECHNOLOGY  for constMIVAN CONSTRUCTION TECHNOLOGY  for const
MIVAN CONSTRUCTION TECHNOLOGY for constPradeepPandya1
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEDr K M SONI
 
Rapid construction techniques
Rapid construction techniques Rapid construction techniques
Rapid construction techniques Deepak Pradhan
 
404128086-mivan-ppt-0-pptx.pptx.................
404128086-mivan-ppt-0-pptx.pptx.................404128086-mivan-ppt-0-pptx.pptx.................
404128086-mivan-ppt-0-pptx.pptx.................KeshavaPrajwal
 
Monolithic concrete construction system
Monolithic concrete construction systemMonolithic concrete construction system
Monolithic concrete construction systemchirag aggarwal
 
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul IslamGlass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul IslamMd Raijul Islam
 
MIVAN-A Versite aluminium firmwork construction technique
MIVAN-A Versite aluminium firmwork construction techniqueMIVAN-A Versite aluminium firmwork construction technique
MIVAN-A Versite aluminium firmwork construction techniquekvijay31
 
Concrete homes intl_english_20130130(1)
Concrete homes intl_english_20130130(1)Concrete homes intl_english_20130130(1)
Concrete homes intl_english_20130130(1)TSC Global
 
Kitsen Aluminum Formwork -Monolithic Pouring
Kitsen Aluminum Formwork -Monolithic PouringKitsen Aluminum Formwork -Monolithic Pouring
Kitsen Aluminum Formwork -Monolithic PouringAshleyLiKITSEN
 
rapid walls- modular construction technology
rapid walls- modular construction technologyrapid walls- modular construction technology
rapid walls- modular construction technologyAnjith Augustine
 
Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3Yee Len Wan
 
Mivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentationMivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentationCivilTY09AdityaGaval
 
Advantages of precast concrete
Advantages of precast concreteAdvantages of precast concrete
Advantages of precast concretebuiltify
 
Glass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsGlass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsRavi Shankar
 
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSakshiMahadik3
 
Planning and Scheduling of Shuttering System for Multi-Storeyed Building
Planning and Scheduling of Shuttering System for Multi-Storeyed BuildingPlanning and Scheduling of Shuttering System for Multi-Storeyed Building
Planning and Scheduling of Shuttering System for Multi-Storeyed BuildingIRJET Journal
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfGourhariBiswas1
 
TWIN WALL CONSTRUCTION.pptx
TWIN WALL CONSTRUCTION.pptxTWIN WALL CONSTRUCTION.pptx
TWIN WALL CONSTRUCTION.pptxSomeshMathad
 

Similar a Mivan (20)

Modern Formwork: Mivan
Modern Formwork: Mivan Modern Formwork: Mivan
Modern Formwork: Mivan
 
simplex infrastructure
simplex infrastructure simplex infrastructure
simplex infrastructure
 
MIVAN CONSTRUCTION TECHNOLOGY for const
MIVAN CONSTRUCTION TECHNOLOGY  for constMIVAN CONSTRUCTION TECHNOLOGY  for const
MIVAN CONSTRUCTION TECHNOLOGY for const
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
Rapid construction techniques
Rapid construction techniques Rapid construction techniques
Rapid construction techniques
 
404128086-mivan-ppt-0-pptx.pptx.................
404128086-mivan-ppt-0-pptx.pptx.................404128086-mivan-ppt-0-pptx.pptx.................
404128086-mivan-ppt-0-pptx.pptx.................
 
Monolithic concrete construction system
Monolithic concrete construction systemMonolithic concrete construction system
Monolithic concrete construction system
 
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul IslamGlass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
 
MIVAN-A Versite aluminium firmwork construction technique
MIVAN-A Versite aluminium firmwork construction techniqueMIVAN-A Versite aluminium firmwork construction technique
MIVAN-A Versite aluminium firmwork construction technique
 
Concrete homes intl_english_20130130(1)
Concrete homes intl_english_20130130(1)Concrete homes intl_english_20130130(1)
Concrete homes intl_english_20130130(1)
 
Kitsen Aluminum Formwork -Monolithic Pouring
Kitsen Aluminum Formwork -Monolithic PouringKitsen Aluminum Formwork -Monolithic Pouring
Kitsen Aluminum Formwork -Monolithic Pouring
 
rapid walls- modular construction technology
rapid walls- modular construction technologyrapid walls- modular construction technology
rapid walls- modular construction technology
 
Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3
 
Mivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentationMivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentation
 
Advantages of precast concrete
Advantages of precast concreteAdvantages of precast concrete
Advantages of precast concrete
 
Glass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsGlass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panels
 
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
 
Planning and Scheduling of Shuttering System for Multi-Storeyed Building
Planning and Scheduling of Shuttering System for Multi-Storeyed BuildingPlanning and Scheduling of Shuttering System for Multi-Storeyed Building
Planning and Scheduling of Shuttering System for Multi-Storeyed Building
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
 
TWIN WALL CONSTRUCTION.pptx
TWIN WALL CONSTRUCTION.pptxTWIN WALL CONSTRUCTION.pptx
TWIN WALL CONSTRUCTION.pptx
 

Más de Soumitra Smart

Low cost building materials
Low cost building materialsLow cost building materials
Low cost building materialsSoumitra Smart
 
Tall buildings case studies
Tall buildings   case studiesTall buildings   case studies
Tall buildings case studiesSoumitra Smart
 
Resource conserving architecture strategies for existing school
Resource conserving architecture   strategies for existing schoolResource conserving architecture   strategies for existing school
Resource conserving architecture strategies for existing schoolSoumitra Smart
 
Low cost building materials
Low cost building materials Low cost building materials
Low cost building materials Soumitra Smart
 
Low cost building materials
Low cost building materials Low cost building materials
Low cost building materials Soumitra Smart
 
Low cost building materials
Low cost building materials Low cost building materials
Low cost building materials Soumitra Smart
 
Low cost building materials
Low cost building materials Low cost building materials
Low cost building materials Soumitra Smart
 
Low cost building materials
Low cost building materials Low cost building materials
Low cost building materials Soumitra Smart
 
Low cost building materials
Low cost building materials Low cost building materials
Low cost building materials Soumitra Smart
 
Low cost building materials
Low cost building materials Low cost building materials
Low cost building materials Soumitra Smart
 
Futuristic architecture dynamic architecture
Futuristic architecture    dynamic architectureFuturistic architecture    dynamic architecture
Futuristic architecture dynamic architectureSoumitra Smart
 
Contemporary architecture eero saarinen.
Contemporary architecture   eero saarinen.Contemporary architecture   eero saarinen.
Contemporary architecture eero saarinen.Soumitra Smart
 
Conservation site management plan -vishrambaug vada, pune
Conservation   site management plan -vishrambaug vada, puneConservation   site management plan -vishrambaug vada, pune
Conservation site management plan -vishrambaug vada, puneSoumitra Smart
 
Study of a city dubai.
Study of a  city   dubai.Study of a  city   dubai.
Study of a city dubai.Soumitra Smart
 
Lavasa, india's first planned hill city
Lavasa, india's first planned hill cityLavasa, india's first planned hill city
Lavasa, india's first planned hill citySoumitra Smart
 
presentation on M.H.A.D.A. housing
presentation on M.H.A.D.A. housingpresentation on M.H.A.D.A. housing
presentation on M.H.A.D.A. housingSoumitra Smart
 

Más de Soumitra Smart (17)

Low cost building materials
Low cost building materialsLow cost building materials
Low cost building materials
 
Tall buildings case studies
Tall buildings   case studiesTall buildings   case studies
Tall buildings case studies
 
Resource conserving architecture strategies for existing school
Resource conserving architecture   strategies for existing schoolResource conserving architecture   strategies for existing school
Resource conserving architecture strategies for existing school
 
Low cost building materials
Low cost building materials Low cost building materials
Low cost building materials
 
Low cost building materials
Low cost building materials Low cost building materials
Low cost building materials
 
Low cost building materials
Low cost building materials Low cost building materials
Low cost building materials
 
Low cost building materials
Low cost building materials Low cost building materials
Low cost building materials
 
Low cost building materials
Low cost building materials Low cost building materials
Low cost building materials
 
Low cost building materials
Low cost building materials Low cost building materials
Low cost building materials
 
Low cost building materials
Low cost building materials Low cost building materials
Low cost building materials
 
Futuristic architecture dynamic architecture
Futuristic architecture    dynamic architectureFuturistic architecture    dynamic architecture
Futuristic architecture dynamic architecture
 
Contemporary architecture eero saarinen.
Contemporary architecture   eero saarinen.Contemporary architecture   eero saarinen.
Contemporary architecture eero saarinen.
 
Conservation site management plan -vishrambaug vada, pune
Conservation   site management plan -vishrambaug vada, puneConservation   site management plan -vishrambaug vada, pune
Conservation site management plan -vishrambaug vada, pune
 
Study of a city dubai.
Study of a  city   dubai.Study of a  city   dubai.
Study of a city dubai.
 
Lavasa, india's first planned hill city
Lavasa, india's first planned hill cityLavasa, india's first planned hill city
Lavasa, india's first planned hill city
 
Japanese garden
Japanese gardenJapanese garden
Japanese garden
 
presentation on M.H.A.D.A. housing
presentation on M.H.A.D.A. housingpresentation on M.H.A.D.A. housing
presentation on M.H.A.D.A. housing
 

Último

Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringJuanCarlosMorales19600
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 

Último (20)

Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineering
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 

Mivan

  • 1. Mivan shuttering – latest technology in construction…  Mivan shuttering is a fast-paced construction technique which offers strength and durability to a building by use of aluminium formworks.  With a growing focus on affordable homes and "Housing for All", real estate stakeholders are increasingly emphasising on the use of new and innovative construction techniques. One such technology is Mivan shuttering which is being promoted for its ability to aid mass construction activity.
  • 2. So, what exactly is Mivan Technology? • Mivan is an aluminium formwork system developed by a European construction company. • In 1990, the Mivan Company Ltd. from Malaysia started manufacturing these formwork systems. • Today, more than 30,000sqm of formwork from Mivan Co. Ltd. is used across the world. • There are a number of buildings in India that are being constructed with the help of the Mivan system, that has proven economical as well as satisfactory for the overall Indian construction environment. • The technology has been used extensively in Europe, Gulf Countries, Asia and other parts of the world.
  • 3. So, what exactly is Mivan Technology? • It is suitable for constructing large number of houses in a short span of time using room size forms to construct walls and slabs in one continuous pour on concrete. In this system of formwork construction, cast–in–situ concrete wall and floor slabs cast monolithic provides the structural system in one continuous pour. • To facilitate fast construction, early removal of forms can be achieved by hot air curing / curing compounds. • Large room sized forms for walls and floor slabs are erected at site. • These strong and sturdy forms are fabricated with accuracy and are easy to handle. • The concrete is produced in RMC batching plants under strict quality control and convey it to site with transit mixers.
  • 4. So, what exactly is Mivan Technology? • The frames for windows, doors and ducts for services are placed in the form before concreting. • Staircase flights, façade panels, chajjas and jalis etc. and other pre-fabricated items are also integrated into the structure. • This proves to be a major advantage as compared to other modern construction techniques. • High quality Mivan Formwork panels ensure consistency of dimensions. • On the removal of the formwork mould a high quality concrete finish is produced to accurate tolerances and verticality. The high tolerance of the finish means that, no further plastering is required.
  • 5. Sheet Thickness & Panel Sizes • The concrete face of panels (Al Sheet) is 4 mm thick. • Standard sizes of Panels are: 2000x600,2000x300,1200x300,850x300. • Apart from above any size as required can be manufactured and delivered.
  • 6. Load Carrying Capacity • High load carrying capacity of 7-8 Tonnes Per square meter • Light weight is the main advantage over conventional formwork technology. • Aluminium formwork weighs around 18-20 kg per meter square.
  • 7. Cycle Time • Vertical (Wall) Formwork – 12 hours after concreting or when concrete strength has reached 2N/mm2. • Horizontal (Deck) Formwork – 36 hours after concreting or when concrete strength has reached 10N/mm2. • High speed of construction can be achieved by this system that means faster completion of project. • 7 Days per floor.
  • 8. Uses of Mivan Formwork • 3S – System of Construction – Speed, Strength, Safety • Column and beam construction are eliminated • Walls and slabs are cast in one operation • Specially designed, easy to handle light weight pre-engineered aluminium forms • Fitting and erecting the portion of shuttering • Carrying out concreting of the walls and slabs together
  • 9. Use in India • So far, the technology has not been used extensively in India. The concept is popular in Gulf countries, Europe and some parts of Asia. However, its use is being promoted in India to realise the most ambitious government scheme – Housing for All by 2022. • To make housing affordable for masses, there is a need to focus on new construction technologies which can reduce construction time and cost. Mivan Shuttering is the solution to this. In addition to saving time and money, the technology can also ensure quality and strength of buildings.
  • 10. Construction technique • Setting up the wall reinforcing steel - The wall reinforcing steel is used to give a structure to the building and support the concrete until they gain half of the required strength. The aluminium formworks are cast around the steel mesh, which is factory made and directly erected on the construction site. • Placement of aluminium formwork – Along the wall reinforcing steel, prefabricated room sized walls and floor slabs are erected. These aluminium alloy slabs are accurately made and are easy to handle. • Spaces for windows, ducts, doors and other features such as staircases, façade panels and chajjas are also integrated in these structures. The forms are joint together using the pin and wedge system, which can be dismantled quickly after the concrete structure is made.
  • 11.
  • 12.
  • 13.
  • 14. Pouring concrete – After casting the forms, high-quality concrete is poured. This concrete takes the form and shape of the cast, which is later removed to make way for a structure made entirely of cement concrete supported by wall reinforcing steel. The aluminium forms can be reused at least 250 times, resulting in minimum waste from the construction site.
  • 15.
  • 16.
  • 17. Advantages • Mivan formwork requires relatively less labour • More seismic resistance • Increased durability • Lesser number of joints and reduced leakages • Higher carpet area • Smooth finishing of wall and slab • Uniform quality of construction • Negligible maintenance • Faster completion
  • 18. Limitations of Mivan Technology • Because of few small sizes finishing lines are seen on the concrete surfaces Services after completing become slightly difficult due to the small width of components • It requires uniform planning as well as uniform elevations to be cost effective • The formwork requires number of spacer, wall ties etc. which are placed @ 2ft c/c; these produce problems such as seepage, leakages during monsoon due to box-type construction, contraction cracks are likely to appear • Heat of hydration is high due to shear walls • It is rigid in design once placed, as any alteration becomes tough later
  • 19. Limitations of Mivan Technology • It remains to be seen if this technology works in the construction industry considering indigenous technologies are promoted off late. However, if the advantages of the technology meet the larger goal of 'Housing for All', it could prove to be a boon for Indian real estate.
  • 20. Remedial Measures It is possible to minimize contraction cracks by providing control strips in the structure which could be concreted with a delay of about 3-7 days after major concreting. The problem of cracking can be avoided by minimizing the heat of hydration by using flash.
  • 21.
  • 22. COSTING Here we considering mivan cost as 120USD per Sqm. without any taxes. Now 1 USD = @ 62 INR Hence, for per sq.m the cost is around 7500 I.N.R. And for one sq.ft. it is around 700 I.N.R.
  • 23. Mivan shuttering – latest technology in construction…
  • 24. CONCLUSION Concrete construction has gone through significant changes since the early 1990s and continues to develop innovation in formwork. Some of the pioneering companies in modern form working system are peri, doca system, outinord, meva, acrow. Mivan formwork construction is able to provide high quality construction at unbelievable speed at reasonable cost. This mivan technology has great potential for application in India to provide affordable housing to its rising population.