SlideShare una empresa de Scribd logo
1 de 64
Descargar para leer sin conexión
Onondaga County’s 2010 Porous
Pavement Projects
Meeting Stormwater Goals while Managing Costs



                                    March 17, 2011
         Joanne M. Mahoney,
          County Executive
www.SaveTheRain.us

     Dan Wible, P.E., LEED AP
     Senior Project Engineer
Presentation Outline
• Case Studies:
  • City Lot #21 (formerly the “Farmer’s Market
    Lot”
  • City Lot #3
  • Pearl Street Lot (DOT)
  • Creekwalk


• Case Study Topics:
  • Design Components / Goals
  • Pre/Post-Construction Photos
  • Costs and Metrics Summary
  • Lessons Learned
Parking Lot #21   (Formerly “Farmer’s Market Lot”)
Case Study: City Lot #21 (formerly the
“Farmer’s Market Lot”)


 • Design Components
 • Costs and Metrics Summary
 • Lessons Learned
Case Study: City Lot #21 (formerly the
“Farmer’s Market Lot”)
 • Design Components:
   • 5,000sf infiltration system
      • Tree trench (2,000sf) with porous pavers
        and 36” of CU-Structural Soil
      • Aggregate infiltration bed under standard
        asphalt (31” deep)
      • Inlet filter inserts
 • Entire lot repaved (standard asphalt) and
   restriped (6 more spaces)
 • Two outlet control structures with weirs
   (connection to existing storm sewer)
 • Infiltration testing yielded a rate of 20 in/hr
Case Study: City Lot #21 (formerly the
“Farmer’s Market Lot”)

 • Design Components:
   • Impervious area managed: 26,250sf
   • Infiltration area: 5,000sf (loading ratio of
     5.3:1)
   • Runoff capture goal (1”): 2,190cf
   • 6 new trees
   • Total soil: 6,000cf (1,000cf per tree)
   • Total static storage capacity: 4,200cf
     (equates to around 2.1” of runoff capture)
Parking Lot #21     (Formerly “Farmer’s Market Lot”)




                                    After




      Before


CSO Area: Clinton
Case Study: City Lot #21 (formerly the
“Farmer’s Market Lot”)


 • Design Components / Goals
 • Costs and Metrics Summary
 • Lessons Learned
Case Study: City Lot #21 (formerly the
“Farmer’s Market Lot”)


 • Total Project Cost: $188,046
 • Total Estimated CSO Reduction: 328,000 gal
 • Cost per CSO Reduction: $0.57 per gal
Case Study: City Lot #21 (formerly the
“Farmer’s Market Lot”)


 • Design Components / Goals
 • Costs and Metrics Summary
 • Lessons Learned
Case Study: City Lot #21 (formerly the
“Farmer’s Market Lot”)

• Stormwater Details and Specifications
  • Concrete structures preferred
  • Overflow weir plates
  • Concerns over inlet filter inserts
    (maintenance)
Case Study: City Lot #21 (formerly the
“Farmer’s Market Lot”)
• Trees and Plantings
  • Temporary maintenance: emphasize/enforce
    temporary irrigation and initial pruning
  • Species selection and maintenance streamlined
    in the future with the City Arborist
Case Study: City Lot #21 (formerly
 the “Farmer’s Market Lot”)


• Subsurface Materials
  • Infiltration bed stone availability: NYSDOT #3A
    is typically the cleanest, most available stone in
    the size range desired
  • CU-Structural Soil Handling/Acceptance:
    ensure contractor provides appropriate cover
    and maintenance, and perform testing if
    needed
• Porous paver edge termination
Porous Pavement / Infiltration Practices
in Onondaga County, NY

 • Design Assumptions / Guidelines:
   • Static storage of first inch of runoff
   • Maximum loading ratio of 10:1 (impervious
     area to infiltration area); 5:1 is preferred
   • Geotextile liner separating rock from soil
     (non-woven or woven… or sand?)
   • Impervious liner where needed (proximity
     to utilities, buildings, etc)
   • Observation well and cleanouts
   • Perforated distribution pipe and/or
     underdrain
Porous Pavement / Infiltration Practices
in Onondaga County, NY

 • More Design Assumptions / Guidelines:
   • Dewater within 72 hours
   • Level bed/trench bottom
   • Maximum surface grade change of 1-2 feet;
     steeper sloped areas may warrant a change
     in bottom elevation (via berms or other)
   • Upper 3” of the infiltration bed subgrade
     should be scarified prior to bed installation
     (if necessary)
   • Total facility depth should between 24-31
     inches (frost consideration)
   • Protect existing utilities
Porous Pavement / Infiltration Practices
in Onondaga County, NY

 • More Design Assumptions / Guidelines:
   • Setbacks:
      • 10ft to buildings with basements
      • 3ft to buildings without basements
      • 3ft from utility structures, vents, poles,
        etc
City Parking Lot #3
Lot #3




             Porous Concrete
 Captures over 700,000 gallons of stormwater annually

         CSO Area: Erie Blvd
Case Study: City Lot #3



 • Design Components / Goals
 • Costs and Metrics Summary
 • Lessons Learned
Case Study: City Lot #3
 • Design Components:
   • 8,380sf infiltration system
      • Tree trench with 36” of CU-Structural Soil
      • 6” porous concrete / aggregate
        infiltration bed (23” deep)
      • Interior tree plantings
      • Inlet filter inserts and sumps
 • Entire lot repaved (standard asphalt) and
   restriped
 • One outlet control structure with removable
   weir (connection to existing storm sewer)
 • Infiltration testing yielded an average rate of
   0.48 in/hr (0.24 in/hr used for design)
Case Study: City Lot #3

 • Design Components:
   • Impervious area managed: 38,507sf
   • Infiltration area: 8,380sf (loading ratio of
     4.6:1)
   • Runoff capture goal (1”): 3,209cf
   • 23 new trees
   • Total soil: 7,650cf (333cf per tree, not
     including existing soil volume along edge)
   • Total static storage capacity: 3,392cf
     (equates to around 1.1” of runoff capture)
   • Dewatering time: 72 hours (100-year
     storm)
Case Study: City Lot #3



 • Design Components / Goals
 • Costs and Metrics Summary
 • Lessons Learned
Case Study: City Lot #3



 • Total Project Cost: $239,102
 • Total Estimated CSO Reduction: 625,000 gal
 • Cost per CSO Reduction: $0.38 per gal
Case Study: City Lot #3



 • Design Components / Goals
 • Costs and Metrics Summary
 • Lessons Learned
Case Study: City Lot #3

• Stormwater Details and Specifications
  • Inlet restoration – check if necessary
• Porous Concrete
  • Test pad quality control
     • Letter to contractor noting concerns with
       aggregate, water retarder, water content
     • Site installation permitted as 2nd “test pad”
  • Cold weather placement: 7 days curing time
    per specified temperature requirements
Pearl Street Parking Lot
Pearl Street Parking Lot




   CSO Area: Franklin FCF
Case Study: Pearl Street Lot



 • Design Components / Goals
 • Costs and Metrics Summary
 • Lessons Learned
Case Study: Pearl Street Lot
• Design Components:
  • 25,300sf infiltration system
     • Porous asphalt (1.5”) on 3” of asphalt
       treated permeable base (ATPB)
     • Aggregate infiltration bed under both
       standard and porous asphalt (24” deep)
     • Inlet filter inserts and sumps
• Entire lot repaved (standard asphalt) and
  restriped
• One outlet control structure with removable
  weir (connection to existing combined sewer)
• Infiltration testing was variable, but yielded an
  average rate of 7 in/hr (2 in/hr used for design)
Case Study: Pearl Street Lot


 • Design Components:
   • Impervious area managed: 73,172sf
   • Infiltration area: 25,300sf (loading ratio of
     2.9:1)
   • Runoff capture goal (1”): 6,098cf
   • Total static storage capacity: 10,120cf
     (equates to around 1.7” of runoff capture)
   • Dewatering time: 24 hours (100-year
     storm)
Case Study: Pearl Street Lot



 • Design Components / Goals
 • Costs and Metrics Summary
 • Lessons Learned
Case Study: Pearl Street Lot



 • Total Project Cost: $396,772
 • Total Estimated CSO Reduction: 915,000 gal
 • Cost per CSO Reduction: $0.43 per gal
Case Study: Pearl Street Lot



 • Design Components / Goals
 • Costs and Metrics Summary
 • Lessons Learned
Case Study: Pearl Street Lot
 • Subsurface Utility Location – coordinate with
   utilities early; lack of response or delayed
   response resulted in field directives
 • Unforeseen Conditions
   • Subsurface structure demolition: multiple
     building foundations were encountered
   • Balance research costs with schedule and
     field directive costs
 • Ample public notification
Creekwalk
Creekwalk
Revisit Winter 2011: Pearl Street
Revisit Winter 2011: Pearl Street
Revisit Winter 2011: Lot 3
Winter Revisit Notes


 • Pearl Street porous pavement performing well,
   particularly vs. standard pavement, but is
   being over-salted
 • Lot 3 wheelstops – wheelstops vs. curbs with
   inlets
 • Lot 3 porous concrete performing well
 • Snow storage areas
Go Nova!



Thank You!



             Questions?

         Please Visit:
      www.SaveTheRain.us
                                     64

Más contenido relacionado

La actualidad más candente

Nurture the world of tomorrow - Maccaferri on sustainability
Nurture the world of tomorrow - Maccaferri on sustainability Nurture the world of tomorrow - Maccaferri on sustainability
Nurture the world of tomorrow - Maccaferri on sustainability Maccaferri World
 
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipeDSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipeDeltares
 
Geoscience in Offshore Renewables
Geoscience in Offshore RenewablesGeoscience in Offshore Renewables
Geoscience in Offshore RenewablesFarida Ismayilova
 
Capital Improvement Projects Update 2013
Capital Improvement Projects Update 2013Capital Improvement Projects Update 2013
Capital Improvement Projects Update 2013StateCollegePA
 
In-Situ Contaminant Stabilization and Brownfield Redevelopment
In-Situ Contaminant Stabilization and Brownfield RedevelopmentIn-Situ Contaminant Stabilization and Brownfield Redevelopment
In-Situ Contaminant Stabilization and Brownfield RedevelopmentDavid Bausmith
 
Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)Timothy Nikolai
 
Low Density Cellular Concrete
Low Density Cellular ConcreteLow Density Cellular Concrete
Low Density Cellular ConcreteJill Reeves
 
Soil organic carbon: thresholds and soil structure quality
Soil organic carbon: thresholds and soil structure qualitySoil organic carbon: thresholds and soil structure quality
Soil organic carbon: thresholds and soil structure qualityExternalEvents
 
GI Energy - Rehau PowerPoint June 2015
GI Energy - Rehau PowerPoint June 2015GI Energy - Rehau PowerPoint June 2015
GI Energy - Rehau PowerPoint June 2015GI Energy
 
Riverbed mining - Rajasthan
Riverbed mining - RajasthanRiverbed mining - Rajasthan
Riverbed mining - RajasthanUdip Das
 
Soil restoration using compost
Soil restoration using compostSoil restoration using compost
Soil restoration using compostMcGill Compost
 
Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)DC Department of General Services
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Fairfax County
 
Tour of ww collection system 11 4-2011
Tour of ww collection system 11 4-2011Tour of ww collection system 11 4-2011
Tour of ww collection system 11 4-2011kristinemassey
 
Officine Maccaferri: Geosynthetics Products Portfolio 2017
Officine Maccaferri: Geosynthetics Products Portfolio 2017Officine Maccaferri: Geosynthetics Products Portfolio 2017
Officine Maccaferri: Geosynthetics Products Portfolio 2017Maccaferri World
 
ABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel BridgeABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel BridgeJill Reeves
 
Shaw Road Erosion and Sediment Plan
Shaw Road Erosion and Sediment PlanShaw Road Erosion and Sediment Plan
Shaw Road Erosion and Sediment PlanJesse Jones
 
1 Geosynthetics&Geosystems Pilarczyk Pres Final
1 Geosynthetics&Geosystems  Pilarczyk Pres Final1 Geosynthetics&Geosystems  Pilarczyk Pres Final
1 Geosynthetics&Geosystems Pilarczyk Pres FinalKrystian Pilarczyk
 

La actualidad más candente (20)

Nurture the world of tomorrow - Maccaferri on sustainability
Nurture the world of tomorrow - Maccaferri on sustainability Nurture the world of tomorrow - Maccaferri on sustainability
Nurture the world of tomorrow - Maccaferri on sustainability
 
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipeDSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
 
SFPR-Project-Profile_0
SFPR-Project-Profile_0SFPR-Project-Profile_0
SFPR-Project-Profile_0
 
Geoscience in Offshore Renewables
Geoscience in Offshore RenewablesGeoscience in Offshore Renewables
Geoscience in Offshore Renewables
 
Capital Improvement Projects Update 2013
Capital Improvement Projects Update 2013Capital Improvement Projects Update 2013
Capital Improvement Projects Update 2013
 
In-Situ Contaminant Stabilization and Brownfield Redevelopment
In-Situ Contaminant Stabilization and Brownfield RedevelopmentIn-Situ Contaminant Stabilization and Brownfield Redevelopment
In-Situ Contaminant Stabilization and Brownfield Redevelopment
 
Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)
 
Low Density Cellular Concrete
Low Density Cellular ConcreteLow Density Cellular Concrete
Low Density Cellular Concrete
 
Soil organic carbon: thresholds and soil structure quality
Soil organic carbon: thresholds and soil structure qualitySoil organic carbon: thresholds and soil structure quality
Soil organic carbon: thresholds and soil structure quality
 
GI Energy - Rehau PowerPoint June 2015
GI Energy - Rehau PowerPoint June 2015GI Energy - Rehau PowerPoint June 2015
GI Energy - Rehau PowerPoint June 2015
 
Riverbed mining - Rajasthan
Riverbed mining - RajasthanRiverbed mining - Rajasthan
Riverbed mining - Rajasthan
 
Soil restoration using compost
Soil restoration using compostSoil restoration using compost
Soil restoration using compost
 
Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
 
Tour of ww collection system 11 4-2011
Tour of ww collection system 11 4-2011Tour of ww collection system 11 4-2011
Tour of ww collection system 11 4-2011
 
Shopping for a Solution
Shopping for a SolutionShopping for a Solution
Shopping for a Solution
 
Officine Maccaferri: Geosynthetics Products Portfolio 2017
Officine Maccaferri: Geosynthetics Products Portfolio 2017Officine Maccaferri: Geosynthetics Products Portfolio 2017
Officine Maccaferri: Geosynthetics Products Portfolio 2017
 
ABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel BridgeABC in Nebraska: Belden to Laurel Bridge
ABC in Nebraska: Belden to Laurel Bridge
 
Shaw Road Erosion and Sediment Plan
Shaw Road Erosion and Sediment PlanShaw Road Erosion and Sediment Plan
Shaw Road Erosion and Sediment Plan
 
1 Geosynthetics&Geosystems Pilarczyk Pres Final
1 Geosynthetics&Geosystems  Pilarczyk Pres Final1 Geosynthetics&Geosystems  Pilarczyk Pres Final
1 Geosynthetics&Geosystems Pilarczyk Pres Final
 

Destacado

NOISE REDUCTION & STUDY OF NOISE MEASURING EQUIPMENTS
NOISE REDUCTION  & STUDY OF  NOISE MEASURING EQUIPMENTSNOISE REDUCTION  & STUDY OF  NOISE MEASURING EQUIPMENTS
NOISE REDUCTION & STUDY OF NOISE MEASURING EQUIPMENTSSony Madaan
 
Noise reduction in pavement made of rubberized bituminious top layer ppt
Noise reduction in pavement made of rubberized bituminious top layer pptNoise reduction in pavement made of rubberized bituminious top layer ppt
Noise reduction in pavement made of rubberized bituminious top layer pptAbdul Aziz
 
senior seminar presentation
senior seminar presentationsenior seminar presentation
senior seminar presentationAaron Slevin
 
Porous asphalt pavement for stormwater management
Porous asphalt pavement for stormwater managementPorous asphalt pavement for stormwater management
Porous asphalt pavement for stormwater managementBhavin Sharma
 
Porous asphalt pavement
Porous asphalt pavementPorous asphalt pavement
Porous asphalt pavementAshif AR
 
Thirsty concrete (2)
Thirsty concrete (2)Thirsty concrete (2)
Thirsty concrete (2)Karthi Kavya
 
Pervious concrete
Pervious concretePervious concrete
Pervious concretenithianju
 

Destacado (10)

NOISE REDUCTION & STUDY OF NOISE MEASURING EQUIPMENTS
NOISE REDUCTION  & STUDY OF  NOISE MEASURING EQUIPMENTSNOISE REDUCTION  & STUDY OF  NOISE MEASURING EQUIPMENTS
NOISE REDUCTION & STUDY OF NOISE MEASURING EQUIPMENTS
 
Noise reduction in pavement made of rubberized bituminious top layer ppt
Noise reduction in pavement made of rubberized bituminious top layer pptNoise reduction in pavement made of rubberized bituminious top layer ppt
Noise reduction in pavement made of rubberized bituminious top layer ppt
 
senior seminar presentation
senior seminar presentationsenior seminar presentation
senior seminar presentation
 
Porous asphalt pavement for stormwater management
Porous asphalt pavement for stormwater managementPorous asphalt pavement for stormwater management
Porous asphalt pavement for stormwater management
 
Manshu
ManshuManshu
Manshu
 
Porous asphalt pavement
Porous asphalt pavementPorous asphalt pavement
Porous asphalt pavement
 
Thirsty concrete (2)
Thirsty concrete (2)Thirsty concrete (2)
Thirsty concrete (2)
 
Pervious concrete
Pervious concretePervious concrete
Pervious concrete
 
REPORT PPT
REPORT PPTREPORT PPT
REPORT PPT
 
Pervious Concrete
Pervious ConcretePervious Concrete
Pervious Concrete
 

Similar a Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & CSOs

LTCP meeting 11-16-05
LTCP meeting 11-16-05LTCP meeting 11-16-05
LTCP meeting 11-16-05HartTWI
 
Land Subdivisions University Course
Land Subdivisions University CourseLand Subdivisions University Course
Land Subdivisions University CourseNettlemanU
 
Sharing Experiences of Flood Modelling Using MIKE 21
Sharing Experiences of Flood Modelling Using MIKE 21Sharing Experiences of Flood Modelling Using MIKE 21
Sharing Experiences of Flood Modelling Using MIKE 21Stephen Flood
 
APR 23 10 LIVING WITH LID [Compatibility Mode]
APR 23 10 LIVING WITH LID [Compatibility Mode]APR 23 10 LIVING WITH LID [Compatibility Mode]
APR 23 10 LIVING WITH LID [Compatibility Mode]Mike Campbell, AICP, CPSWQ
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxPraveendubey82
 
Capstone Design conference
Capstone Design conferenceCapstone Design conference
Capstone Design conferenceRieley Loch
 
Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020Fairfax County
 
2018 general frc_2018_12
2018 general frc_2018_122018 general frc_2018_12
2018 general frc_2018_12AsuSSEBENA
 
"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...
"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación..."Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...
"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...Instituto del cemento y Hormigón de Chile
 
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...Fairfax County
 
Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...
 Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali... Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...
Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...Fairfax County
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalIEI GSC
 

Similar a Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & CSOs (20)

Lawrence Park PIC 3 slides
Lawrence Park PIC 3 slidesLawrence Park PIC 3 slides
Lawrence Park PIC 3 slides
 
LTCP meeting 11-16-05
LTCP meeting 11-16-05LTCP meeting 11-16-05
LTCP meeting 11-16-05
 
Cold-in-Place Recycling (CIR) use in Urban Areas
Cold-in-Place Recycling (CIR) use in Urban AreasCold-in-Place Recycling (CIR) use in Urban Areas
Cold-in-Place Recycling (CIR) use in Urban Areas
 
Area39 pic 1 panels final
Area39 pic 1 panels finalArea39 pic 1 panels final
Area39 pic 1 panels final
 
Land Subdivisions University Course
Land Subdivisions University CourseLand Subdivisions University Course
Land Subdivisions University Course
 
Area 38 pic 1 final presentation
Area 38 pic 1   final presentationArea 38 pic 1   final presentation
Area 38 pic 1 final presentation
 
Sharing Experiences of Flood Modelling Using MIKE 21
Sharing Experiences of Flood Modelling Using MIKE 21Sharing Experiences of Flood Modelling Using MIKE 21
Sharing Experiences of Flood Modelling Using MIKE 21
 
APR 23 10 LIVING WITH LID [Compatibility Mode]
APR 23 10 LIVING WITH LID [Compatibility Mode]APR 23 10 LIVING WITH LID [Compatibility Mode]
APR 23 10 LIVING WITH LID [Compatibility Mode]
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
 
Pavement
PavementPavement
Pavement
 
Capstone Design conference
Capstone Design conferenceCapstone Design conference
Capstone Design conference
 
Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020
 
CC Intro
CC IntroCC Intro
CC Intro
 
2018 general frc_2018_12
2018 general frc_2018_122018 general frc_2018_12
2018 general frc_2018_12
 
"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...
"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación..."Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...
"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...
 
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...
 
Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...
 Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali... Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...
Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...
 
2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final
 
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canal
 

Más de Onondaga County Save the Rain

Onondaga Earth Corps - Green Infrastructure Maintenance
Onondaga Earth Corps - Green Infrastructure MaintenanceOnondaga Earth Corps - Green Infrastructure Maintenance
Onondaga Earth Corps - Green Infrastructure MaintenanceOnondaga County Save the Rain
 
Green infrastructure asset management in Onondaga County - NYCOM 2012
Green infrastructure asset management in Onondaga County - NYCOM 2012Green infrastructure asset management in Onondaga County - NYCOM 2012
Green infrastructure asset management in Onondaga County - NYCOM 2012Onondaga County Save the Rain
 
Harbor Brook Treatment Wetlands Design Status - Feb 2012
Harbor Brook Treatment Wetlands Design Status - Feb 2012Harbor Brook Treatment Wetlands Design Status - Feb 2012
Harbor Brook Treatment Wetlands Design Status - Feb 2012Onondaga County Save the Rain
 
Clinton Storage Facility Construction Activity 12/19/11
Clinton Storage Facility Construction Activity 12/19/11Clinton Storage Facility Construction Activity 12/19/11
Clinton Storage Facility Construction Activity 12/19/11Onondaga County Save the Rain
 
Challenges with implementing_gi_in_onondaga_county_nycom-pws_oct2011
Challenges with implementing_gi_in_onondaga_county_nycom-pws_oct2011Challenges with implementing_gi_in_onondaga_county_nycom-pws_oct2011
Challenges with implementing_gi_in_onondaga_county_nycom-pws_oct2011Onondaga County Save the Rain
 
Use of gi to reduce stormwater runoff squier - sept 2011
Use of gi to reduce stormwater runoff   squier - sept 2011Use of gi to reduce stormwater runoff   squier - sept 2011
Use of gi to reduce stormwater runoff squier - sept 2011Onondaga County Save the Rain
 
OC harbor brook wetlands stakeholder 6 15-11 final-1
OC harbor brook wetlands stakeholder 6 15-11 final-1OC harbor brook wetlands stakeholder 6 15-11 final-1
OC harbor brook wetlands stakeholder 6 15-11 final-1Onondaga County Save the Rain
 

Más de Onondaga County Save the Rain (19)

Onondaga Earth Corps - Green Infrastructure Maintenance
Onondaga Earth Corps - Green Infrastructure MaintenanceOnondaga Earth Corps - Green Infrastructure Maintenance
Onondaga Earth Corps - Green Infrastructure Maintenance
 
Legnetto GI Maintenance Presentation 2014
Legnetto GI Maintenance Presentation 2014Legnetto GI Maintenance Presentation 2014
Legnetto GI Maintenance Presentation 2014
 
Green infrastructure asset management in Onondaga County - NYCOM 2012
Green infrastructure asset management in Onondaga County - NYCOM 2012Green infrastructure asset management in Onondaga County - NYCOM 2012
Green infrastructure asset management in Onondaga County - NYCOM 2012
 
Save the Rain Presentation - NYSAC 2012
Save the Rain Presentation - NYSAC 2012Save the Rain Presentation - NYSAC 2012
Save the Rain Presentation - NYSAC 2012
 
Project 50 Construction - NYSATE 2012
Project 50 Construction - NYSATE 2012Project 50 Construction - NYSATE 2012
Project 50 Construction - NYSATE 2012
 
Green Infrastructure Maintenance Workshop
Green Infrastructure Maintenance WorkshopGreen Infrastructure Maintenance Workshop
Green Infrastructure Maintenance Workshop
 
Education & Outreach CSO044 - NYWEA 2012
Education & Outreach   CSO044 - NYWEA 2012Education & Outreach   CSO044 - NYWEA 2012
Education & Outreach CSO044 - NYWEA 2012
 
Greening the Gray - NYWEA 2012
Greening the Gray - NYWEA 2012Greening the Gray - NYWEA 2012
Greening the Gray - NYWEA 2012
 
Harbor Brook Treatment Wetlands Design Status - Feb 2012
Harbor Brook Treatment Wetlands Design Status - Feb 2012Harbor Brook Treatment Wetlands Design Status - Feb 2012
Harbor Brook Treatment Wetlands Design Status - Feb 2012
 
NYWEA 2012
NYWEA 2012NYWEA 2012
NYWEA 2012
 
Porous Pavement in Cold Climates Part 2
Porous Pavement in Cold Climates Part 2Porous Pavement in Cold Climates Part 2
Porous Pavement in Cold Climates Part 2
 
Porous Pavement in Cold Climates Part 1
Porous Pavement in Cold Climates Part 1Porous Pavement in Cold Climates Part 1
Porous Pavement in Cold Climates Part 1
 
Clinton Storage Facility Construction Activity 12/19/11
Clinton Storage Facility Construction Activity 12/19/11Clinton Storage Facility Construction Activity 12/19/11
Clinton Storage Facility Construction Activity 12/19/11
 
Challenges with implementing_gi_in_onondaga_county_nycom-pws_oct2011
Challenges with implementing_gi_in_onondaga_county_nycom-pws_oct2011Challenges with implementing_gi_in_onondaga_county_nycom-pws_oct2011
Challenges with implementing_gi_in_onondaga_county_nycom-pws_oct2011
 
Use of gi to reduce stormwater runoff squier - sept 2011
Use of gi to reduce stormwater runoff   squier - sept 2011Use of gi to reduce stormwater runoff   squier - sept 2011
Use of gi to reduce stormwater runoff squier - sept 2011
 
Sept 2011 monthly report
Sept 2011 monthly reportSept 2011 monthly report
Sept 2011 monthly report
 
Dodson 2011 09-26
Dodson 2011 09-26Dodson 2011 09-26
Dodson 2011 09-26
 
Marengo lid symposium_2011-09-25
Marengo lid symposium_2011-09-25Marengo lid symposium_2011-09-25
Marengo lid symposium_2011-09-25
 
OC harbor brook wetlands stakeholder 6 15-11 final-1
OC harbor brook wetlands stakeholder 6 15-11 final-1OC harbor brook wetlands stakeholder 6 15-11 final-1
OC harbor brook wetlands stakeholder 6 15-11 final-1
 

Último

Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperityhemanthkumar470700
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756dollysharma2066
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...allensay1
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfAmzadHosen3
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 

Último (20)

Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 

Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & CSOs

  • 1. Onondaga County’s 2010 Porous Pavement Projects Meeting Stormwater Goals while Managing Costs March 17, 2011 Joanne M. Mahoney, County Executive
  • 2. www.SaveTheRain.us Dan Wible, P.E., LEED AP Senior Project Engineer
  • 3. Presentation Outline • Case Studies: • City Lot #21 (formerly the “Farmer’s Market Lot” • City Lot #3 • Pearl Street Lot (DOT) • Creekwalk • Case Study Topics: • Design Components / Goals • Pre/Post-Construction Photos • Costs and Metrics Summary • Lessons Learned
  • 4. Parking Lot #21 (Formerly “Farmer’s Market Lot”)
  • 5. Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”) • Design Components • Costs and Metrics Summary • Lessons Learned
  • 6. Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”) • Design Components: • 5,000sf infiltration system • Tree trench (2,000sf) with porous pavers and 36” of CU-Structural Soil • Aggregate infiltration bed under standard asphalt (31” deep) • Inlet filter inserts • Entire lot repaved (standard asphalt) and restriped (6 more spaces) • Two outlet control structures with weirs (connection to existing storm sewer) • Infiltration testing yielded a rate of 20 in/hr
  • 7. Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”) • Design Components: • Impervious area managed: 26,250sf • Infiltration area: 5,000sf (loading ratio of 5.3:1) • Runoff capture goal (1”): 2,190cf • 6 new trees • Total soil: 6,000cf (1,000cf per tree) • Total static storage capacity: 4,200cf (equates to around 2.1” of runoff capture)
  • 8.
  • 9.
  • 10.
  • 11. Parking Lot #21 (Formerly “Farmer’s Market Lot”) After Before CSO Area: Clinton
  • 12.
  • 13.
  • 14.
  • 15. Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”) • Design Components / Goals • Costs and Metrics Summary • Lessons Learned
  • 16. Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”) • Total Project Cost: $188,046 • Total Estimated CSO Reduction: 328,000 gal • Cost per CSO Reduction: $0.57 per gal
  • 17. Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”) • Design Components / Goals • Costs and Metrics Summary • Lessons Learned
  • 18. Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”) • Stormwater Details and Specifications • Concrete structures preferred • Overflow weir plates • Concerns over inlet filter inserts (maintenance)
  • 19. Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”) • Trees and Plantings • Temporary maintenance: emphasize/enforce temporary irrigation and initial pruning • Species selection and maintenance streamlined in the future with the City Arborist
  • 20. Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”) • Subsurface Materials • Infiltration bed stone availability: NYSDOT #3A is typically the cleanest, most available stone in the size range desired • CU-Structural Soil Handling/Acceptance: ensure contractor provides appropriate cover and maintenance, and perform testing if needed • Porous paver edge termination
  • 21. Porous Pavement / Infiltration Practices in Onondaga County, NY • Design Assumptions / Guidelines: • Static storage of first inch of runoff • Maximum loading ratio of 10:1 (impervious area to infiltration area); 5:1 is preferred • Geotextile liner separating rock from soil (non-woven or woven… or sand?) • Impervious liner where needed (proximity to utilities, buildings, etc) • Observation well and cleanouts • Perforated distribution pipe and/or underdrain
  • 22. Porous Pavement / Infiltration Practices in Onondaga County, NY • More Design Assumptions / Guidelines: • Dewater within 72 hours • Level bed/trench bottom • Maximum surface grade change of 1-2 feet; steeper sloped areas may warrant a change in bottom elevation (via berms or other) • Upper 3” of the infiltration bed subgrade should be scarified prior to bed installation (if necessary) • Total facility depth should between 24-31 inches (frost consideration) • Protect existing utilities
  • 23. Porous Pavement / Infiltration Practices in Onondaga County, NY • More Design Assumptions / Guidelines: • Setbacks: • 10ft to buildings with basements • 3ft to buildings without basements • 3ft from utility structures, vents, poles, etc
  • 25. Lot #3 Porous Concrete Captures over 700,000 gallons of stormwater annually CSO Area: Erie Blvd
  • 26. Case Study: City Lot #3 • Design Components / Goals • Costs and Metrics Summary • Lessons Learned
  • 27. Case Study: City Lot #3 • Design Components: • 8,380sf infiltration system • Tree trench with 36” of CU-Structural Soil • 6” porous concrete / aggregate infiltration bed (23” deep) • Interior tree plantings • Inlet filter inserts and sumps • Entire lot repaved (standard asphalt) and restriped • One outlet control structure with removable weir (connection to existing storm sewer) • Infiltration testing yielded an average rate of 0.48 in/hr (0.24 in/hr used for design)
  • 28. Case Study: City Lot #3 • Design Components: • Impervious area managed: 38,507sf • Infiltration area: 8,380sf (loading ratio of 4.6:1) • Runoff capture goal (1”): 3,209cf • 23 new trees • Total soil: 7,650cf (333cf per tree, not including existing soil volume along edge) • Total static storage capacity: 3,392cf (equates to around 1.1” of runoff capture) • Dewatering time: 72 hours (100-year storm)
  • 29.
  • 30.
  • 31.
  • 32.
  • 33.
  • 34.
  • 35.
  • 36. Case Study: City Lot #3 • Design Components / Goals • Costs and Metrics Summary • Lessons Learned
  • 37. Case Study: City Lot #3 • Total Project Cost: $239,102 • Total Estimated CSO Reduction: 625,000 gal • Cost per CSO Reduction: $0.38 per gal
  • 38. Case Study: City Lot #3 • Design Components / Goals • Costs and Metrics Summary • Lessons Learned
  • 39. Case Study: City Lot #3 • Stormwater Details and Specifications • Inlet restoration – check if necessary • Porous Concrete • Test pad quality control • Letter to contractor noting concerns with aggregate, water retarder, water content • Site installation permitted as 2nd “test pad” • Cold weather placement: 7 days curing time per specified temperature requirements
  • 41. Pearl Street Parking Lot CSO Area: Franklin FCF
  • 42. Case Study: Pearl Street Lot • Design Components / Goals • Costs and Metrics Summary • Lessons Learned
  • 43. Case Study: Pearl Street Lot • Design Components: • 25,300sf infiltration system • Porous asphalt (1.5”) on 3” of asphalt treated permeable base (ATPB) • Aggregate infiltration bed under both standard and porous asphalt (24” deep) • Inlet filter inserts and sumps • Entire lot repaved (standard asphalt) and restriped • One outlet control structure with removable weir (connection to existing combined sewer) • Infiltration testing was variable, but yielded an average rate of 7 in/hr (2 in/hr used for design)
  • 44. Case Study: Pearl Street Lot • Design Components: • Impervious area managed: 73,172sf • Infiltration area: 25,300sf (loading ratio of 2.9:1) • Runoff capture goal (1”): 6,098cf • Total static storage capacity: 10,120cf (equates to around 1.7” of runoff capture) • Dewatering time: 24 hours (100-year storm)
  • 45.
  • 46.
  • 47.
  • 48.
  • 49.
  • 50. Case Study: Pearl Street Lot • Design Components / Goals • Costs and Metrics Summary • Lessons Learned
  • 51. Case Study: Pearl Street Lot • Total Project Cost: $396,772 • Total Estimated CSO Reduction: 915,000 gal • Cost per CSO Reduction: $0.43 per gal
  • 52. Case Study: Pearl Street Lot • Design Components / Goals • Costs and Metrics Summary • Lessons Learned
  • 53. Case Study: Pearl Street Lot • Subsurface Utility Location – coordinate with utilities early; lack of response or delayed response resulted in field directives • Unforeseen Conditions • Subsurface structure demolition: multiple building foundations were encountered • Balance research costs with schedule and field directive costs • Ample public notification
  • 56.
  • 57.
  • 58.
  • 59.
  • 60. Revisit Winter 2011: Pearl Street
  • 61. Revisit Winter 2011: Pearl Street
  • 63. Winter Revisit Notes • Pearl Street porous pavement performing well, particularly vs. standard pavement, but is being over-salted • Lot 3 wheelstops – wheelstops vs. curbs with inlets • Lot 3 porous concrete performing well • Snow storage areas
  • 64. Go Nova! Thank You! Questions? Please Visit: www.SaveTheRain.us 64