LINEAR PROGRAMING
Definition
Is a branch of mathematics which enables one to solve problems which either the greatest or
minimum/least value of a certain quantity is required under some given limitations or
constraints.
Example
In a big – organization, decision about distribution in order to realize maximum profit or
reduce costs of productionare done by use of linear programming.
Limitation/ constraints are translatedbylinear inequalities.
Greatest value or least value will be expressedas a function (calledthe objective function)
Introduction
Drawing of linear inequalities
Example 01
Draw and show the half plane representedby 8x+2y ≥16
Solution
For 8x +2y≥16; draw 8x+ 2y = 16
For x – intercept, y = 0
8x = 16
X = 2
For y – intercept, x = 0
2y = 16
Y = 8
Using (0, 0) as a test point
8(0) +2(0)≥ 16
0 ≥ 16 (False)
Example 02
Determine the solutionset of the simultaneous inequalities
Solution
x + y ≥ 3 draw x + y = 3 (full line)
x + y = 3
At x – intercept y= 0 at y – intercept x= 0
x = 3 y = 3
For x – 2y ≤ 9, x – 2y = 9
At x – intercept y= 0 at y – intercept, x= 0
X =9 -2y= 9
Y =
Using (0, 0) as a test point Using (0,0) as a test point
x + y ≥ 3 x – 2y≤ 9
0 + 0 ≥ 3 0 – (2)(0) ≤ 9
0 ≥ 3 (F) 0 ≤ 9 (T)
 The clear part is the solutionset
 The solutionset is calledthe feasible region
Questions
Draw by shading unwanted regions of the half planes represented by following
simultaneous inequalities
(i) y≥ 2x – 1, y ≤ -1
(ii) y≤ 2x – 1, y ≥ x – 3, y ≥ -1
(iii) y < 2x – 1, y ≤ -1
(iv) 6x + 9y ≥ 12
0.4x+ 0.1y≥ 0.2
32x+ 10y≥ 20
Evaluationofa functionsatisfiedbythe givenset ofinequalities
→Example
Find the maximum and minimum value of c = 4x + 3y + 38 subjectedto
x + y ≥ 5
0 ≤ y ≤ 6 0 ≤ x ≤ 5
x ≥ 0, y ≥ 0
Solution
For x + y ≥ 5
x + y = 5
When x = 0, y = 5
y = 0, x = 5
For 0 ≤ y ≤ 6
0 = y = 6
Line y = 6
For 0 ≤ x ≤ 5
O = x = 5
Line x = 5
Test points x ≥ 0, shade left of x = 0
(0, 0) y ≥ 0, shade below of x = axis
Corner points C = 4x + 3y + 38
A (5, 0) 4 (5) + 3 (0) +38 = 58
B (5, 6) 4 (5) + 3 (6) + 38 = 76
C (0, 6) 4 (0) + 3 (6) +38 = 56
D (0, 5) 4 (0) + 3 (5) + 38 = 53
: . The maximum value of c = 76 and occurs at (5, 6)
The minimum value of c = 53 and occurs at (0, 5)
Questions
1. Find the maximum and minimum values of the given functions and the value
x and y where they occur
(i) Z = 4x+ 3y
Subject to
x + 2y ≤ 10
3x + y ≤ 5
x ≥ 0, y ≥ 0
(ii) P = 134x+ 20y
Subject to
x + y ≤ 160
10 ≤ x ≤ 60
0 ≤ y ≤ 120
(iii) T = 4x +7y
Subject to.
x + y ≤ 18
5 ≤ x ≤ 10
3 ≤ y ≤ 10
x ≥ 0, y ≥ 0
(iv) P = 2x + 4y
Subject to
2x + 3y ≥ 3
-5x+ 4y ≤ 0
3x + 4y ≤ 18
X ≥ 0, y ≥ 0.
FORMULATION OF A LINEAR PROGRAMMING PROBLEM.
Steps in formulatinga linear programming problem.
1. * Read the problem several times and assess what is known and what is to be determined.
2. * Identify the unknown quantities and assign variables to them, be careful about the units.
3. * Determine the objective function;it involves the quantity to be maximized or minimized.
4. * Translate the constraints into linear inequalities,
* Constraints are limitation or restrictions to the problem for each constraints the units must
be same.
5. * Graph the constraints andfind the feasible solution
6. * Find the corner points of the feasible solution. These are points of intersectionof the graph
7. * Evaluate the objective function. Highest value of the objective function has to be
maximized or smallest value to be minimized.
Example
A student has 120 shillings to spend on exercise books. At a school shop an exercise
book costs 8 shillings, at stationery store an exercise book costs 12 shillings. The school
has only 6 exercise books and the student wants to obtain the greatest number of exercise
books possible usingthe money. Find the greatest number of exercise books he canbuy.
Solution
Let x be number of exercise books to be bought at school shop
Let y be number of exercise books to be bought at stationeryshop
→Objective function
Let f (x, y) = objective function
Then f (x, y) = x + y
→Constrains or linear inequalities
8x + 12y ≤ 120
x ≤ 6
Non – Negative constraints
x ≥ 0
y ≥ 0
→Equations
8x + 12y = 120
4x + 6y = 60
2x + 3y = 30
When x = 0, y = 10
y = 0, x = 15
x = 6, y = 0
x = 6
Corner points F (x, y) = x + y
A (0, 0) 0 + 0 = 0
B (6, 0) 6 + 0 = 6
C ( 6, 6) 6 + 6 = 12
D (0, 10) 0+10 = 10
: . The greatest numbers of exercise books he can buy are 12 books 6 from the school
shop and 6 from stationery.
Example
Student in a certain class are about to take a certain test of BAM which has two sections
A and B; where in section A each question worth 10 marks while in section B; each
worth 25 marks. The student must do at least 3 questions of section A; but not more than
12. A student must also do 4 questions from section B but not more than 15. In addition
students cannot do more than 20 questions. How many questions of each type should the
student do to obtain the maximum scores?
Solution
Let x be number of questions to be done in sectionA
Let y be number of questions to be done in sectionB
→Objective function
f (x, y) = 10x+ 25y
→Constrains
3 ≤ x ≤ 12
4 ≤ y ≤ 15
x + y ≤ 20
x ≥ 0, y ≥ 0
Maximize f (x, y) = 10x+ 25ysubject to;
3 ≤ x ≤ 12
4 ≤ y ≤ 15
x + y ≤ 20
x ≥ 0, y ≥ 0
Equations
3 = x = 12
4 = y = 15
x + y = 20
x = 20, y = 0
x = 0, y = 20
x = 0
y = 0
Corner Points f(x, y) = 10x+ 25y
A (3, 4) 10 (3) + 25 (4) = 130
B (12, 4) 10 (12) + 25 (4) = 220
C (12, 8 ) 10 (12) + 25 (8) = 320
D (5, 15) 10 (5) + 25 (15) = 425
E (3, 15) 10 (3) + 25 (15) = 405
The student should do 5 questions from section A and 15 questions from section B to
obtain maximum score of 425.
Diet problems onlinear programming problem
Example 01
A doctor prescribes a special diet for patients containing the following number of units of
Vitamin A and B per kg of two types of foodF1 and F2
Type of Food Vitamin A Vitamin B
F1 20 units/kg 7 units/kg
F2 15 units /kg 14 units /kg
If the minimum daily intake required is 120 units of A and 70 units of B, what is the least
total mass of fooda patient must have so as to have enough of these vitamins?
EXAMPLE 02
Rice and beans provide maximum levels of protein, calories and vitamin B2. If used as a
staple diet. The food values per kg of uncooked rice and beans are as shown in the table
below.
Protein/kg Calories/kg Vitamin B2/kg Price kg
Rice 60g 3200 cal 0.4 400
Beans 90g 1000 cal 0.1 500
Min daily req. 120 2000 cal 0.2
What is the lowest cost of diet meeting, these specifications?
Solution.
Let x be number of kg of rice to be bought
Let y be number of kg of beans to be bought
→Objective function
400x+ 500y
Constrains
60x+ 90y≤ 120
3200x+ 1000y≤ 2000
0.4x + 0.1y≤ 0.2
Minimize f (x, y) = 400x+ 500ySubject to;
60x+ 90y≤ 120
3200x+ 1000y≤ 2000
0.4x+ 0.1y≤ 0.2
x ≥ 0, y ≥ 0
For 60x+ 90y≥ 120
60x+ 90y= 120
2x + 3y = 4
When x = 0, y = 1.3
Y = 0, x = 2
For 3200x+ 1000y≥ 2000
32x+ 10y= 20
16x+ 5y = 10
When x = 0, y = 2
Y = 0, x = 0.63
For 0.4x + 0.1y ≤ 0.2
0.4x+ 0.1y= 0.2
When x = 0, y = 2
When y = 0, x = 0.5
Corner points F (x, y) = x + y
A (0, 8) 0 + 8 = 8
B (3.6, 3.2) 3.6 + 3.2 = 6.8
C (10,0) 10 + 0 = 10
: . The least total mass a patient should have is 6.8kg i.e. 3.6kg of food 1 and 3.2 kg of
food2.
Question
1. A doctor prescribes that in order to obtain adequate supply of vitamin A and C his patient
should have portions of food 1 and food 2. The number of units of vitamin A and C are given
in the followingtable
A C
Food1 3 2
Food2 1 7
The doctor prescribes a minimum of 14 units of vitamin A and 21 units of vitamin C. What
are the least portions of food1 and food2 that will fit the doctor’s prescriptions?
LINEAR PROGRAMMING PROBLEMS
1. Two printers N and T produce three types of books. N produces 80 types I books
per day, 10 type II books per day and 20 types III books per day, while T produces
20 types I books per day 10 type II books per day and 70 types III books per day.
The orders placed are 1600 type I, 500 type II and 2100 type III books. The daily
operating costs for N shs. 10,000/=, for T shs, 20,000/= how many days should
each printer operate to meet the orders at aminimum cost.
2. A small textile company manufactures three different size of shirts, Large (L),
medium (M) and small (S) at two different plants A and B. The number of shirts
of each size producedand the cost of productionper day are as follows!
A B Monthly demand
Large size per day 50 60 2500
Medium size per day 100 70 3500
Small size per day 100 200 7000
Production Cost per day
T. shs.
2500 3500 _
(i) How many days per month should each factory operate in order to minimize
total cost.
(ii) What is the minimum cost of production
Solution01
Let x be number of days printer N shouldoperate
Let Y be number of days printer T should operate
→Objective function(f(x, y))
10000x+ 20000y
→Constrains
 80x + 20y≥ 1600
 10x + 10y≥ 500
 20x + 70y≥ 2100
 X ≥ 0, y ≥ 0
→Equations
 80x + 20y≥ 1600
80x+ 20y= 1600
8x + 2y = 160
When x = 0, y = 80
y = 0, x = 20
 10x + 10y≥ 500
10x+ 10y= 500
x + y = 50
When x = 0, y = 50
y = 0, x = 50
 20x + 70y≥ 2100
20x+ 70y= 2100
2x + 7y = 210
When x = 0, y = 30
y = 0, x = 105
Corner points F (x, y) = 10000x+ 20000y
A (0, 80) 10000 (0)+ 20000 (80) = 1,600,000
B (28, 22) 10000 (28) + 20000(22) = 720,000
C (105, 0) 10,000 (105)+ 20000 (0)= 1,050,000
Printer N should be operated for 28 days and printer T should work for 22 days to meet the
orders at minimum cost.
Solution02
Let x be number of days per month factoryA shouldoperate
Let y be number of days per month factoryB shouldoperate
→Objective function
F (x, y) = 2500x+ 3500y
→Constrains
 50x + 60y≥ 2500
 100x+ 70y ≥ 3500
 100x+ 200y≥ 7000
 x ≥ 0, y ≥ 0
Minimize f (x, y) = 2500x+ 3500y
Subject to 50x+ 60y≥ 2500
100x+ 70y≥ 3500
100x+ 200y≥ 7000
X ≥ 0, y ≥ 0
→Equations
 50x + 60y= 2500
When y = 0, x = 50
X = 0, y = 41.7
 100x+ 70y = 3500
When y = 0, x = 35
x = 0, y = 50
 100x+ 200y= 7000
When y = 0, x = 70
X = 0, y = 35
Corner points F (x, y) = 2500x+ 3500y
A (0,50) 2500 (0) + 3500(50)= 175,000
B (15, 30) 2500 (15) + 3500 (30) = 142,500
C (20,25) 2500 (20) + 3500 (25) = 137,500
D (70, 0) 2500 (70) + 3500 (0)= 175,000
Factory A should operate for 20 days and factory B should operate for 25 days in order to
minimize total cost.
→Minimum cost of productionis 137,500
3. In a certain garage the manager had the following facts floor space required for a
saloon is 2m2 and for a lorry is 3m2. Four technicians are required to service a
saloon car and three technicians for a lorry per day. He has a maximum of 24m2 of
a floor space and a maximum of 36 technicians available; in addition he is not
allowed to service more Lorries than saloon cars. The profit for serving a saloon
car is 40,000/= and a lorry is 60,000/=. How many motor vehicles of each type
should be serviceddaily in order to maximize the profit?
Solution
Let x be number of salooncars to be serviceddaily
Let y be number of Lorries to be serviceddaily
→Objective function
F (x, y) = 40000x+ 60000y
→Constrains
 2x + 3y ≤ 24
 4x + 3y ≤ 36
 x ≥ y
 x ≥ 0 and y ≥ 0
Maximize f (x, y) = 40000x+ 60000y
Subject to 2x + 3y ≤ 24
4x + 3y ≤ 36
x ≥ y
x ≥ 0 and y ≥ 0
→Equations
 2x + 3y ≤ 24
When x = 0, y = 8
Y = 0, x = 12
 4x + 3y ≤ 36
When x = 0, y = 12
y = 0, x = 9
 x = y
Corner points F (x, y) = 40000x+ 60000y
A (0, 0) 40000 (0) + 60000(0) = 0
B (4.8, 4.8) 40000 (4.8) + 60000 (4.8) = 480,000
C (6,4) 40000 (6)+ 60000 (4) = 480,000
D (9, 0) 40000 (9) + 60000 (0) = 360,000
6 salooncars and 4 Lorries shouldbe serviceddaily to maximize profit to 480,000/=
More example
A builder has two stores, one at S1 and the other at S2. He is building houses at P1, P2, and P3.
He needs 5 tons of bricks at P1, 6 tons of bricks at P2 and 4 tons of bricks at P3. The stores
contain 9 tons of bricks at S1 and 6 tons of bricks at S2. The transport cost per ton are shown
in the diagram
To From P1 P2 P3
S1 6/= 3/= 4/=
S2 4/= 2/= 6/=
How does the builder send his bricks at a minimum cost?What is the minimum overall cost?
Solution
Let the builder send x tons of bricks from S1 to P1 and y tons of bricks from S1 to P2
Then the transportationof bricks to P1, P2 and P3 will be as follow: -
To
From P1 P2 P3
S1 X Y 9 – (x +
y)
S2 5 – x 6 – y 4 – [9 –
(x + y)]
The constrains are obtainedas follows
 x ≥ 0, y ≥ 0
 9 – (x + y) ≥ 0 i.e. x + y ≤ 9
 5 – x ≥ 0 i.e. x ≤ 5
 6 – y ≥ 0 i.e. y ≤ 6
 4 – [9 - (x + y)} ≥ 0 i.e. x + y ≥ 5
Objective function
F (x, y) = 6x + 3y + 4(9 - (x + y)) + 4 (5 – x) + 2(6 – y) +6 [4 – (9 - (x + y)]
= 6x + 3y +36 – 4x+ 4y + 20 – 4x+ 12 – 2y + 24 – 54 + 6x+ 6y
F (x, y) = 4x – 3y+ 38
Minimize f (x, y) = 4x – 3y + 38
Subject to x + y ≤ 9
x + y ≥ 5
x ≤ 5, y ≥ 0
y ≤ 6, y ≥ 0
→Equation
 x + y = 9
When x = 0, y = 9
y = 0, x = 9
 x + y = 5
x = 0, y = 5
y = 0, x = 9
 x = 5
 y = 6
Corner points F (x, y) = 4x + 3y + 38
A (0, 5) 4 (0) + 3 (5) + 38 = 53
B (0, 6) 4 (0) + 3 (6) + 38 = 56
C (3, 6) 4 (3) + 3 (6) + 38 = 68
D (5, 4) 4 (5) + 3 (4) + 38 = 70
E (5, 0) 4 (5) + 3 (0) + 38 = 58
The builder should send the bricks of tons as follows
To
From P1 P2 P3
S1 0 5 4
S2 5 1 0
The overall minimum cost is 53/=
EXERCISE
There is a factory located at each of the places P and Q. From these location a certain
commodity is delivered to each of the three deports situated at A, B and C. The weekly
requirements of the deports are respectively 5,5 and 4 unit of the commodity while the
production capacity of the factories P and Q are 8 and 6 units respectively, just sufficient for
requirement of deports. The cost of transportationper unit is given.
To
From A B C
P 16 10 15
Q 10 12 10
Formulate this linear programming problem and how the commodities can be transported at
minimum cost. What is the overall minimum cost?

Más contenido relacionado

La actualidad más candente

Derivation and solution of the heat equation in 1-D
Derivation and solution of the heat equation in 1-DDerivation and solution of the heat equation in 1-D
Derivation and solution of the heat equation in 1-DIJESM JOURNAL
 
Aptitude Training - RATIO AND PROPORTION 1
Aptitude Training - RATIO AND PROPORTION 1Aptitude Training - RATIO AND PROPORTION 1
Aptitude Training - RATIO AND PROPORTION 1Ajay Chimmani
 
Economics - Long run & short run Production
Economics - Long run & short run ProductionEconomics - Long run & short run Production
Economics - Long run & short run ProductionOnline
 
Lesson 9: The Product and Quotient Rule
Lesson 9: The Product and Quotient RuleLesson 9: The Product and Quotient Rule
Lesson 9: The Product and Quotient RuleMatthew Leingang
 
Interest and discount
Interest and discountInterest and discount
Interest and discountReyman Solas
 
Application of 1st Order ODE
Application of 1st Order ODEApplication of 1st Order ODE
Application of 1st Order ODEAbir Junayed
 
Cost Accounting - Nature & Scope
Cost Accounting  - Nature & ScopeCost Accounting  - Nature & Scope
Cost Accounting - Nature & Scopedebchat123
 
The Cost Of Production - Dealing with Cost - Explicit and Implicit Cost - Eco...
The Cost Of Production - Dealing with Cost - Explicit and Implicit Cost - Eco...The Cost Of Production - Dealing with Cost - Explicit and Implicit Cost - Eco...
The Cost Of Production - Dealing with Cost - Explicit and Implicit Cost - Eco...FaHaD .H. NooR
 
7.8 Simple and Compound Interest
7.8 Simple and Compound Interest7.8 Simple and Compound Interest
7.8 Simple and Compound InterestJessca Lundin
 
Ppt on Cost accounting and its classifications
Ppt on Cost accounting and its classifications Ppt on Cost accounting and its classifications
Ppt on Cost accounting and its classifications Susheel Tiwari
 
Definition cost sheet new
Definition cost sheet newDefinition cost sheet new
Definition cost sheet newVinit Patil
 

La actualidad más candente (20)

Law Of Equi Marginal Utility
Law Of Equi Marginal UtilityLaw Of Equi Marginal Utility
Law Of Equi Marginal Utility
 
Joule thomson effect
Joule thomson effectJoule thomson effect
Joule thomson effect
 
Sets, functions and groups
Sets, functions and groupsSets, functions and groups
Sets, functions and groups
 
Derivation and solution of the heat equation in 1-D
Derivation and solution of the heat equation in 1-DDerivation and solution of the heat equation in 1-D
Derivation and solution of the heat equation in 1-D
 
Aptitude Training - RATIO AND PROPORTION 1
Aptitude Training - RATIO AND PROPORTION 1Aptitude Training - RATIO AND PROPORTION 1
Aptitude Training - RATIO AND PROPORTION 1
 
Economics - Long run & short run Production
Economics - Long run & short run ProductionEconomics - Long run & short run Production
Economics - Long run & short run Production
 
Set Theory and its Applications
Set Theory and its ApplicationsSet Theory and its Applications
Set Theory and its Applications
 
Lesson 9: The Product and Quotient Rule
Lesson 9: The Product and Quotient RuleLesson 9: The Product and Quotient Rule
Lesson 9: The Product and Quotient Rule
 
DIFFERENTIAL EQUATIONS
DIFFERENTIAL EQUATIONSDIFFERENTIAL EQUATIONS
DIFFERENTIAL EQUATIONS
 
Short run and long run
Short run and long runShort run and long run
Short run and long run
 
Thermodynamics
ThermodynamicsThermodynamics
Thermodynamics
 
Group Theory
Group TheoryGroup Theory
Group Theory
 
Interest and discount
Interest and discountInterest and discount
Interest and discount
 
Chapter 6 annuity
Chapter 6 annuityChapter 6 annuity
Chapter 6 annuity
 
Application of 1st Order ODE
Application of 1st Order ODEApplication of 1st Order ODE
Application of 1st Order ODE
 
Cost Accounting - Nature & Scope
Cost Accounting  - Nature & ScopeCost Accounting  - Nature & Scope
Cost Accounting - Nature & Scope
 
The Cost Of Production - Dealing with Cost - Explicit and Implicit Cost - Eco...
The Cost Of Production - Dealing with Cost - Explicit and Implicit Cost - Eco...The Cost Of Production - Dealing with Cost - Explicit and Implicit Cost - Eco...
The Cost Of Production - Dealing with Cost - Explicit and Implicit Cost - Eco...
 
7.8 Simple and Compound Interest
7.8 Simple and Compound Interest7.8 Simple and Compound Interest
7.8 Simple and Compound Interest
 
Ppt on Cost accounting and its classifications
Ppt on Cost accounting and its classifications Ppt on Cost accounting and its classifications
Ppt on Cost accounting and its classifications
 
Definition cost sheet new
Definition cost sheet newDefinition cost sheet new
Definition cost sheet new
 

Similar a LINEAR PROGRAMING

An Introduction to Linear Programming
An Introduction to Linear ProgrammingAn Introduction to Linear Programming
An Introduction to Linear ProgrammingMinh-Tri Pham
 
Linear programming problems
Linear programming problemsLinear programming problems
Linear programming problemsHanna Elise
 
math online kumustahan.pptx
math online kumustahan.pptxmath online kumustahan.pptx
math online kumustahan.pptxJohnleoClaus2
 
introduction to Operation Research
introduction to Operation Research introduction to Operation Research
introduction to Operation Research amanyosama12
 
Problem Application of Antiderivatives
Problem Application of AntiderivativesProblem Application of Antiderivatives
Problem Application of Antiderivativesnyaz26
 
Linear Programming Feasible Region
Linear Programming Feasible RegionLinear Programming Feasible Region
Linear Programming Feasible RegionVARUN MODI
 
Introduction to Operations Research/ Management Science
Introduction to Operations Research/ Management Science Introduction to Operations Research/ Management Science
Introduction to Operations Research/ Management Science um1222
 
A geometrical approach in Linear Programming Problems
A geometrical approach in Linear Programming ProblemsA geometrical approach in Linear Programming Problems
A geometrical approach in Linear Programming ProblemsRaja Agrawal
 
Mathematics TAKS Exit Level Review
Mathematics TAKS Exit Level ReviewMathematics TAKS Exit Level Review
Mathematics TAKS Exit Level Reviewguest3f17823
 
Ccss.math.content.8.ee.c.8b sample question
Ccss.math.content.8.ee.c.8b   sample questionCcss.math.content.8.ee.c.8b   sample question
Ccss.math.content.8.ee.c.8b sample questionPraveen Tyagi
 
sim-140907230908-phpapp01.pptx
sim-140907230908-phpapp01.pptxsim-140907230908-phpapp01.pptx
sim-140907230908-phpapp01.pptxJeffreyEnriquez10
 
5.2 using intercepts
5.2 using intercepts5.2 using intercepts
5.2 using interceptscoolhanddav
 
5.2 using intercepts
5.2 using intercepts5.2 using intercepts
5.2 using interceptscoolhanddav
 
ISI MSQE Entrance Question Paper (2013)
ISI MSQE Entrance Question Paper (2013)ISI MSQE Entrance Question Paper (2013)
ISI MSQE Entrance Question Paper (2013)CrackDSE
 
Linear programming graphical method
Linear programming graphical methodLinear programming graphical method
Linear programming graphical methodDr. Abdulfatah Salem
 

Similar a LINEAR PROGRAMING (20)

Lenier Equation
Lenier EquationLenier Equation
Lenier Equation
 
An Introduction to Linear Programming
An Introduction to Linear ProgrammingAn Introduction to Linear Programming
An Introduction to Linear Programming
 
Linear programming problems
Linear programming problemsLinear programming problems
Linear programming problems
 
math online kumustahan.pptx
math online kumustahan.pptxmath online kumustahan.pptx
math online kumustahan.pptx
 
Decision making
Decision makingDecision making
Decision making
 
Management Science
Management Science Management Science
Management Science
 
introduction to Operation Research
introduction to Operation Research introduction to Operation Research
introduction to Operation Research
 
Problem Application of Antiderivatives
Problem Application of AntiderivativesProblem Application of Antiderivatives
Problem Application of Antiderivatives
 
Linear Programming Feasible Region
Linear Programming Feasible RegionLinear Programming Feasible Region
Linear Programming Feasible Region
 
Introduction to Operations Research/ Management Science
Introduction to Operations Research/ Management Science Introduction to Operations Research/ Management Science
Introduction to Operations Research/ Management Science
 
A geometrical approach in Linear Programming Problems
A geometrical approach in Linear Programming ProblemsA geometrical approach in Linear Programming Problems
A geometrical approach in Linear Programming Problems
 
Mathematics TAKS Exit Level Review
Mathematics TAKS Exit Level ReviewMathematics TAKS Exit Level Review
Mathematics TAKS Exit Level Review
 
Ccss.math.content.8.ee.c.8b sample question
Ccss.math.content.8.ee.c.8b   sample questionCcss.math.content.8.ee.c.8b   sample question
Ccss.math.content.8.ee.c.8b sample question
 
sim-140907230908-phpapp01.pptx
sim-140907230908-phpapp01.pptxsim-140907230908-phpapp01.pptx
sim-140907230908-phpapp01.pptx
 
5.2 using intercepts
5.2 using intercepts5.2 using intercepts
5.2 using intercepts
 
5.2 using intercepts
5.2 using intercepts5.2 using intercepts
5.2 using intercepts
 
ISI MSQE Entrance Question Paper (2013)
ISI MSQE Entrance Question Paper (2013)ISI MSQE Entrance Question Paper (2013)
ISI MSQE Entrance Question Paper (2013)
 
Chapter 5 Using Intercepts
Chapter 5 Using InterceptsChapter 5 Using Intercepts
Chapter 5 Using Intercepts
 
Chapter 5 Using Intercepts
Chapter 5 Using InterceptsChapter 5 Using Intercepts
Chapter 5 Using Intercepts
 
Linear programming graphical method
Linear programming graphical methodLinear programming graphical method
Linear programming graphical method
 

Más de shahzadebaujiti

IMPERIALISM AND TERRITORIAL DIVISION OF THE WORLD (COLONIZATION OF AFRICA)
IMPERIALISM AND TERRITORIAL DIVISION OF THE WORLD (COLONIZATION OF AFRICA)IMPERIALISM AND TERRITORIAL DIVISION OF THE WORLD (COLONIZATION OF AFRICA)
IMPERIALISM AND TERRITORIAL DIVISION OF THE WORLD (COLONIZATION OF AFRICA)shahzadebaujiti
 
THE RISE OF DEMOCRACY IN EUROPE
THE RISE OF DEMOCRACY IN EUROPE THE RISE OF DEMOCRACY IN EUROPE
THE RISE OF DEMOCRACY IN EUROPE shahzadebaujiti
 
THE RISE OF CAPITALISM IN EUROPE
THE RISE OF CAPITALISM IN EUROPETHE RISE OF CAPITALISM IN EUROPE
THE RISE OF CAPITALISM IN EUROPEshahzadebaujiti
 
SUSTAINABLE USE OF FUEL AND POWER
SUSTAINABLE USE OF FUEL AND POWERSUSTAINABLE USE OF FUEL AND POWER
SUSTAINABLE USE OF FUEL AND POWERshahzadebaujiti
 
PHYSICAL GEOGRAPHY 1.5 -STUDY OF SOIL
PHYSICAL GEOGRAPHY 1.5 -STUDY OF SOILPHYSICAL GEOGRAPHY 1.5 -STUDY OF SOIL
PHYSICAL GEOGRAPHY 1.5 -STUDY OF SOILshahzadebaujiti
 
PHYSICAL GEOGRAPHY 1.4-WATER MASSES
PHYSICAL GEOGRAPHY 1.4-WATER MASSESPHYSICAL GEOGRAPHY 1.4-WATER MASSES
PHYSICAL GEOGRAPHY 1.4-WATER MASSESshahzadebaujiti
 
ENVIRONMENTAL ISSUES AND CONSERVATION
ENVIRONMENTAL ISSUES AND CONSERVATIONENVIRONMENTAL ISSUES AND CONSERVATION
ENVIRONMENTAL ISSUES AND CONSERVATIONshahzadebaujiti
 
TRANSPORT AND COMMUNICATION
TRANSPORT AND COMMUNICATIONTRANSPORT AND COMMUNICATION
TRANSPORT AND COMMUNICATIONshahzadebaujiti
 
REGIONAL FOCAL STUDIES - 5.7 ENVIRONMENTAL FRIENDLY TOURISM
REGIONAL FOCAL STUDIES - 5.7 ENVIRONMENTAL FRIENDLY TOURISMREGIONAL FOCAL STUDIES - 5.7 ENVIRONMENTAL FRIENDLY TOURISM
REGIONAL FOCAL STUDIES - 5.7 ENVIRONMENTAL FRIENDLY TOURISMshahzadebaujiti
 
REGIONAL FOCAL STUDIES -5.5 SUSTAINABLE USE OF FORESTRY
REGIONAL FOCAL STUDIES -5.5 SUSTAINABLE USE OF FORESTRYREGIONAL FOCAL STUDIES -5.5 SUSTAINABLE USE OF FORESTRY
REGIONAL FOCAL STUDIES -5.5 SUSTAINABLE USE OF FORESTRYshahzadebaujiti
 
REGIONAL FOCAL STUDIES - 5.6 SUSTAINABLE FISHING
REGIONAL FOCAL STUDIES - 5.6 SUSTAINABLE FISHINGREGIONAL FOCAL STUDIES - 5.6 SUSTAINABLE FISHING
REGIONAL FOCAL STUDIES - 5.6 SUSTAINABLE FISHINGshahzadebaujiti
 
SUSTAINABLE MINING MINERAL EXTRACTION (MINING INDUSTRY)
SUSTAINABLE MINING  MINERAL EXTRACTION (MINING INDUSTRY)SUSTAINABLE MINING  MINERAL EXTRACTION (MINING INDUSTRY)
SUSTAINABLE MINING MINERAL EXTRACTION (MINING INDUSTRY)shahzadebaujiti
 
SOIL DEGRADATION AND CONSERVATION
SOIL DEGRADATION AND CONSERVATIONSOIL DEGRADATION AND CONSERVATION
SOIL DEGRADATION AND CONSERVATIONshahzadebaujiti
 
AGRICULTURAL DEVELOPMENT
AGRICULTURAL DEVELOPMENTAGRICULTURAL DEVELOPMENT
AGRICULTURAL DEVELOPMENTshahzadebaujiti
 
POPULATION AND DEVELOPMENT
POPULATION AND DEVELOPMENTPOPULATION AND DEVELOPMENT
POPULATION AND DEVELOPMENTshahzadebaujiti
 

Más de shahzadebaujiti (20)

IMPERIALISM AND TERRITORIAL DIVISION OF THE WORLD (COLONIZATION OF AFRICA)
IMPERIALISM AND TERRITORIAL DIVISION OF THE WORLD (COLONIZATION OF AFRICA)IMPERIALISM AND TERRITORIAL DIVISION OF THE WORLD (COLONIZATION OF AFRICA)
IMPERIALISM AND TERRITORIAL DIVISION OF THE WORLD (COLONIZATION OF AFRICA)
 
THE RISE OF DEMOCRACY IN EUROPE
THE RISE OF DEMOCRACY IN EUROPE THE RISE OF DEMOCRACY IN EUROPE
THE RISE OF DEMOCRACY IN EUROPE
 
THE RISE OF CAPITALISM IN EUROPE
THE RISE OF CAPITALISM IN EUROPETHE RISE OF CAPITALISM IN EUROPE
THE RISE OF CAPITALISM IN EUROPE
 
CLIMATOLOGY CLIMATOLOGY
CLIMATOLOGY CLIMATOLOGYCLIMATOLOGY CLIMATOLOGY
CLIMATOLOGY CLIMATOLOGY
 
SUSTAINABLE USE OF FUEL AND POWER
SUSTAINABLE USE OF FUEL AND POWERSUSTAINABLE USE OF FUEL AND POWER
SUSTAINABLE USE OF FUEL AND POWER
 
SPACE DYNAMIC
SPACE DYNAMICSPACE DYNAMIC
SPACE DYNAMIC
 
PHYSICAL GEOGRAPHY 1.5 -STUDY OF SOIL
PHYSICAL GEOGRAPHY 1.5 -STUDY OF SOILPHYSICAL GEOGRAPHY 1.5 -STUDY OF SOIL
PHYSICAL GEOGRAPHY 1.5 -STUDY OF SOIL
 
PHYSICAL GEOGRAPHY 1.4-WATER MASSES
PHYSICAL GEOGRAPHY 1.4-WATER MASSESPHYSICAL GEOGRAPHY 1.4-WATER MASSES
PHYSICAL GEOGRAPHY 1.4-WATER MASSES
 
ENVIRONMENTAL ISSUES AND CONSERVATION
ENVIRONMENTAL ISSUES AND CONSERVATIONENVIRONMENTAL ISSUES AND CONSERVATION
ENVIRONMENTAL ISSUES AND CONSERVATION
 
TRANSPORT AND COMMUNICATION
TRANSPORT AND COMMUNICATIONTRANSPORT AND COMMUNICATION
TRANSPORT AND COMMUNICATION
 
MANUFACTURING INDUSTRY
MANUFACTURING INDUSTRYMANUFACTURING INDUSTRY
MANUFACTURING INDUSTRY
 
RIVER BASIN DEVELOPMENT
RIVER BASIN DEVELOPMENTRIVER BASIN DEVELOPMENT
RIVER BASIN DEVELOPMENT
 
REGIONAL FOCAL STUDIES - 5.7 ENVIRONMENTAL FRIENDLY TOURISM
REGIONAL FOCAL STUDIES - 5.7 ENVIRONMENTAL FRIENDLY TOURISMREGIONAL FOCAL STUDIES - 5.7 ENVIRONMENTAL FRIENDLY TOURISM
REGIONAL FOCAL STUDIES - 5.7 ENVIRONMENTAL FRIENDLY TOURISM
 
REGIONAL FOCAL STUDIES -5.5 SUSTAINABLE USE OF FORESTRY
REGIONAL FOCAL STUDIES -5.5 SUSTAINABLE USE OF FORESTRYREGIONAL FOCAL STUDIES -5.5 SUSTAINABLE USE OF FORESTRY
REGIONAL FOCAL STUDIES -5.5 SUSTAINABLE USE OF FORESTRY
 
REGIONAL FOCAL STUDIES - 5.6 SUSTAINABLE FISHING
REGIONAL FOCAL STUDIES - 5.6 SUSTAINABLE FISHINGREGIONAL FOCAL STUDIES - 5.6 SUSTAINABLE FISHING
REGIONAL FOCAL STUDIES - 5.6 SUSTAINABLE FISHING
 
SUSTAINABLE MINING MINERAL EXTRACTION (MINING INDUSTRY)
SUSTAINABLE MINING  MINERAL EXTRACTION (MINING INDUSTRY)SUSTAINABLE MINING  MINERAL EXTRACTION (MINING INDUSTRY)
SUSTAINABLE MINING MINERAL EXTRACTION (MINING INDUSTRY)
 
SOIL DEGRADATION AND CONSERVATION
SOIL DEGRADATION AND CONSERVATIONSOIL DEGRADATION AND CONSERVATION
SOIL DEGRADATION AND CONSERVATION
 
AGRICULTURAL DEVELOPMENT
AGRICULTURAL DEVELOPMENTAGRICULTURAL DEVELOPMENT
AGRICULTURAL DEVELOPMENT
 
POPULATION AND DEVELOPMENT
POPULATION AND DEVELOPMENTPOPULATION AND DEVELOPMENT
POPULATION AND DEVELOPMENT
 
THE BUSINESS OFFICE
THE BUSINESS OFFICETHE BUSINESS OFFICE
THE BUSINESS OFFICE
 

Último

Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfSherif Taha
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxannathomasp01
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17Celine George
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Plant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxPlant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxUmeshTimilsina1
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...Poonam Aher Patil
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxPooja Bhuva
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...pradhanghanshyam7136
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxDr. Sarita Anand
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxmarlenawright1
 
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...Amil baba
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxEsquimalt MFRC
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...Nguyen Thanh Tu Collection
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsKarakKing
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxDr. Ravikiran H M Gowda
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17Celine George
 

Último (20)

Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Plant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxPlant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptx
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 

LINEAR PROGRAMING

  • 1. LINEAR PROGRAMING Definition Is a branch of mathematics which enables one to solve problems which either the greatest or minimum/least value of a certain quantity is required under some given limitations or constraints. Example In a big – organization, decision about distribution in order to realize maximum profit or reduce costs of productionare done by use of linear programming. Limitation/ constraints are translatedbylinear inequalities. Greatest value or least value will be expressedas a function (calledthe objective function) Introduction Drawing of linear inequalities Example 01 Draw and show the half plane representedby 8x+2y ≥16 Solution For 8x +2y≥16; draw 8x+ 2y = 16 For x – intercept, y = 0 8x = 16 X = 2 For y – intercept, x = 0 2y = 16 Y = 8 Using (0, 0) as a test point
  • 2. 8(0) +2(0)≥ 16 0 ≥ 16 (False) Example 02 Determine the solutionset of the simultaneous inequalities Solution x + y ≥ 3 draw x + y = 3 (full line) x + y = 3 At x – intercept y= 0 at y – intercept x= 0 x = 3 y = 3 For x – 2y ≤ 9, x – 2y = 9
  • 3. At x – intercept y= 0 at y – intercept, x= 0 X =9 -2y= 9 Y = Using (0, 0) as a test point Using (0,0) as a test point x + y ≥ 3 x – 2y≤ 9 0 + 0 ≥ 3 0 – (2)(0) ≤ 9 0 ≥ 3 (F) 0 ≤ 9 (T)  The clear part is the solutionset
  • 4.  The solutionset is calledthe feasible region Questions Draw by shading unwanted regions of the half planes represented by following simultaneous inequalities (i) y≥ 2x – 1, y ≤ -1 (ii) y≤ 2x – 1, y ≥ x – 3, y ≥ -1 (iii) y < 2x – 1, y ≤ -1 (iv) 6x + 9y ≥ 12 0.4x+ 0.1y≥ 0.2 32x+ 10y≥ 20 Evaluationofa functionsatisfiedbythe givenset ofinequalities →Example Find the maximum and minimum value of c = 4x + 3y + 38 subjectedto x + y ≥ 5 0 ≤ y ≤ 6 0 ≤ x ≤ 5 x ≥ 0, y ≥ 0 Solution For x + y ≥ 5 x + y = 5 When x = 0, y = 5 y = 0, x = 5 For 0 ≤ y ≤ 6 0 = y = 6 Line y = 6 For 0 ≤ x ≤ 5 O = x = 5 Line x = 5 Test points x ≥ 0, shade left of x = 0 (0, 0) y ≥ 0, shade below of x = axis
  • 5. Corner points C = 4x + 3y + 38 A (5, 0) 4 (5) + 3 (0) +38 = 58
  • 6. B (5, 6) 4 (5) + 3 (6) + 38 = 76 C (0, 6) 4 (0) + 3 (6) +38 = 56 D (0, 5) 4 (0) + 3 (5) + 38 = 53 : . The maximum value of c = 76 and occurs at (5, 6) The minimum value of c = 53 and occurs at (0, 5) Questions 1. Find the maximum and minimum values of the given functions and the value x and y where they occur (i) Z = 4x+ 3y Subject to x + 2y ≤ 10 3x + y ≤ 5 x ≥ 0, y ≥ 0 (ii) P = 134x+ 20y Subject to x + y ≤ 160 10 ≤ x ≤ 60 0 ≤ y ≤ 120 (iii) T = 4x +7y Subject to. x + y ≤ 18 5 ≤ x ≤ 10 3 ≤ y ≤ 10 x ≥ 0, y ≥ 0 (iv) P = 2x + 4y Subject to 2x + 3y ≥ 3 -5x+ 4y ≤ 0 3x + 4y ≤ 18 X ≥ 0, y ≥ 0. FORMULATION OF A LINEAR PROGRAMMING PROBLEM. Steps in formulatinga linear programming problem. 1. * Read the problem several times and assess what is known and what is to be determined.
  • 7. 2. * Identify the unknown quantities and assign variables to them, be careful about the units. 3. * Determine the objective function;it involves the quantity to be maximized or minimized. 4. * Translate the constraints into linear inequalities, * Constraints are limitation or restrictions to the problem for each constraints the units must be same. 5. * Graph the constraints andfind the feasible solution 6. * Find the corner points of the feasible solution. These are points of intersectionof the graph 7. * Evaluate the objective function. Highest value of the objective function has to be maximized or smallest value to be minimized. Example A student has 120 shillings to spend on exercise books. At a school shop an exercise book costs 8 shillings, at stationery store an exercise book costs 12 shillings. The school has only 6 exercise books and the student wants to obtain the greatest number of exercise books possible usingthe money. Find the greatest number of exercise books he canbuy. Solution Let x be number of exercise books to be bought at school shop Let y be number of exercise books to be bought at stationeryshop →Objective function Let f (x, y) = objective function Then f (x, y) = x + y →Constrains or linear inequalities 8x + 12y ≤ 120 x ≤ 6 Non – Negative constraints x ≥ 0 y ≥ 0 →Equations 8x + 12y = 120 4x + 6y = 60 2x + 3y = 30 When x = 0, y = 10 y = 0, x = 15 x = 6, y = 0
  • 8. x = 6 Corner points F (x, y) = x + y A (0, 0) 0 + 0 = 0 B (6, 0) 6 + 0 = 6 C ( 6, 6) 6 + 6 = 12 D (0, 10) 0+10 = 10
  • 9. : . The greatest numbers of exercise books he can buy are 12 books 6 from the school shop and 6 from stationery. Example Student in a certain class are about to take a certain test of BAM which has two sections A and B; where in section A each question worth 10 marks while in section B; each worth 25 marks. The student must do at least 3 questions of section A; but not more than 12. A student must also do 4 questions from section B but not more than 15. In addition students cannot do more than 20 questions. How many questions of each type should the student do to obtain the maximum scores? Solution Let x be number of questions to be done in sectionA Let y be number of questions to be done in sectionB →Objective function f (x, y) = 10x+ 25y →Constrains 3 ≤ x ≤ 12 4 ≤ y ≤ 15 x + y ≤ 20 x ≥ 0, y ≥ 0 Maximize f (x, y) = 10x+ 25ysubject to; 3 ≤ x ≤ 12 4 ≤ y ≤ 15 x + y ≤ 20 x ≥ 0, y ≥ 0 Equations 3 = x = 12 4 = y = 15 x + y = 20 x = 20, y = 0 x = 0, y = 20 x = 0
  • 10. y = 0 Corner Points f(x, y) = 10x+ 25y A (3, 4) 10 (3) + 25 (4) = 130 B (12, 4) 10 (12) + 25 (4) = 220 C (12, 8 ) 10 (12) + 25 (8) = 320 D (5, 15) 10 (5) + 25 (15) = 425 E (3, 15) 10 (3) + 25 (15) = 405 The student should do 5 questions from section A and 15 questions from section B to obtain maximum score of 425. Diet problems onlinear programming problem Example 01 A doctor prescribes a special diet for patients containing the following number of units of Vitamin A and B per kg of two types of foodF1 and F2 Type of Food Vitamin A Vitamin B F1 20 units/kg 7 units/kg F2 15 units /kg 14 units /kg
  • 11. If the minimum daily intake required is 120 units of A and 70 units of B, what is the least total mass of fooda patient must have so as to have enough of these vitamins? EXAMPLE 02 Rice and beans provide maximum levels of protein, calories and vitamin B2. If used as a staple diet. The food values per kg of uncooked rice and beans are as shown in the table below. Protein/kg Calories/kg Vitamin B2/kg Price kg Rice 60g 3200 cal 0.4 400 Beans 90g 1000 cal 0.1 500 Min daily req. 120 2000 cal 0.2 What is the lowest cost of diet meeting, these specifications? Solution. Let x be number of kg of rice to be bought Let y be number of kg of beans to be bought →Objective function 400x+ 500y Constrains 60x+ 90y≤ 120 3200x+ 1000y≤ 2000 0.4x + 0.1y≤ 0.2 Minimize f (x, y) = 400x+ 500ySubject to; 60x+ 90y≤ 120 3200x+ 1000y≤ 2000
  • 12. 0.4x+ 0.1y≤ 0.2 x ≥ 0, y ≥ 0 For 60x+ 90y≥ 120 60x+ 90y= 120 2x + 3y = 4 When x = 0, y = 1.3 Y = 0, x = 2 For 3200x+ 1000y≥ 2000 32x+ 10y= 20 16x+ 5y = 10 When x = 0, y = 2 Y = 0, x = 0.63 For 0.4x + 0.1y ≤ 0.2 0.4x+ 0.1y= 0.2 When x = 0, y = 2 When y = 0, x = 0.5
  • 13. Corner points F (x, y) = x + y A (0, 8) 0 + 8 = 8 B (3.6, 3.2) 3.6 + 3.2 = 6.8 C (10,0) 10 + 0 = 10 : . The least total mass a patient should have is 6.8kg i.e. 3.6kg of food 1 and 3.2 kg of food2. Question 1. A doctor prescribes that in order to obtain adequate supply of vitamin A and C his patient should have portions of food 1 and food 2. The number of units of vitamin A and C are given in the followingtable A C
  • 14. Food1 3 2 Food2 1 7 The doctor prescribes a minimum of 14 units of vitamin A and 21 units of vitamin C. What are the least portions of food1 and food2 that will fit the doctor’s prescriptions? LINEAR PROGRAMMING PROBLEMS 1. Two printers N and T produce three types of books. N produces 80 types I books per day, 10 type II books per day and 20 types III books per day, while T produces 20 types I books per day 10 type II books per day and 70 types III books per day. The orders placed are 1600 type I, 500 type II and 2100 type III books. The daily operating costs for N shs. 10,000/=, for T shs, 20,000/= how many days should each printer operate to meet the orders at aminimum cost. 2. A small textile company manufactures three different size of shirts, Large (L), medium (M) and small (S) at two different plants A and B. The number of shirts of each size producedand the cost of productionper day are as follows! A B Monthly demand Large size per day 50 60 2500 Medium size per day 100 70 3500 Small size per day 100 200 7000 Production Cost per day T. shs. 2500 3500 _ (i) How many days per month should each factory operate in order to minimize total cost. (ii) What is the minimum cost of production Solution01 Let x be number of days printer N shouldoperate
  • 15. Let Y be number of days printer T should operate →Objective function(f(x, y)) 10000x+ 20000y →Constrains  80x + 20y≥ 1600  10x + 10y≥ 500  20x + 70y≥ 2100  X ≥ 0, y ≥ 0 →Equations  80x + 20y≥ 1600 80x+ 20y= 1600 8x + 2y = 160 When x = 0, y = 80 y = 0, x = 20  10x + 10y≥ 500 10x+ 10y= 500 x + y = 50 When x = 0, y = 50 y = 0, x = 50  20x + 70y≥ 2100 20x+ 70y= 2100 2x + 7y = 210 When x = 0, y = 30
  • 16. y = 0, x = 105 Corner points F (x, y) = 10000x+ 20000y A (0, 80) 10000 (0)+ 20000 (80) = 1,600,000 B (28, 22) 10000 (28) + 20000(22) = 720,000 C (105, 0) 10,000 (105)+ 20000 (0)= 1,050,000 Printer N should be operated for 28 days and printer T should work for 22 days to meet the orders at minimum cost. Solution02 Let x be number of days per month factoryA shouldoperate Let y be number of days per month factoryB shouldoperate →Objective function
  • 17. F (x, y) = 2500x+ 3500y →Constrains  50x + 60y≥ 2500  100x+ 70y ≥ 3500  100x+ 200y≥ 7000  x ≥ 0, y ≥ 0 Minimize f (x, y) = 2500x+ 3500y Subject to 50x+ 60y≥ 2500 100x+ 70y≥ 3500 100x+ 200y≥ 7000 X ≥ 0, y ≥ 0 →Equations  50x + 60y= 2500 When y = 0, x = 50 X = 0, y = 41.7  100x+ 70y = 3500 When y = 0, x = 35 x = 0, y = 50  100x+ 200y= 7000 When y = 0, x = 70 X = 0, y = 35
  • 18. Corner points F (x, y) = 2500x+ 3500y A (0,50) 2500 (0) + 3500(50)= 175,000 B (15, 30) 2500 (15) + 3500 (30) = 142,500 C (20,25) 2500 (20) + 3500 (25) = 137,500 D (70, 0) 2500 (70) + 3500 (0)= 175,000 Factory A should operate for 20 days and factory B should operate for 25 days in order to minimize total cost. →Minimum cost of productionis 137,500 3. In a certain garage the manager had the following facts floor space required for a saloon is 2m2 and for a lorry is 3m2. Four technicians are required to service a saloon car and three technicians for a lorry per day. He has a maximum of 24m2 of
  • 19. a floor space and a maximum of 36 technicians available; in addition he is not allowed to service more Lorries than saloon cars. The profit for serving a saloon car is 40,000/= and a lorry is 60,000/=. How many motor vehicles of each type should be serviceddaily in order to maximize the profit? Solution Let x be number of salooncars to be serviceddaily Let y be number of Lorries to be serviceddaily →Objective function F (x, y) = 40000x+ 60000y →Constrains  2x + 3y ≤ 24  4x + 3y ≤ 36  x ≥ y  x ≥ 0 and y ≥ 0 Maximize f (x, y) = 40000x+ 60000y Subject to 2x + 3y ≤ 24 4x + 3y ≤ 36 x ≥ y x ≥ 0 and y ≥ 0 →Equations  2x + 3y ≤ 24 When x = 0, y = 8
  • 20. Y = 0, x = 12  4x + 3y ≤ 36 When x = 0, y = 12 y = 0, x = 9  x = y Corner points F (x, y) = 40000x+ 60000y A (0, 0) 40000 (0) + 60000(0) = 0 B (4.8, 4.8) 40000 (4.8) + 60000 (4.8) = 480,000 C (6,4) 40000 (6)+ 60000 (4) = 480,000 D (9, 0) 40000 (9) + 60000 (0) = 360,000 6 salooncars and 4 Lorries shouldbe serviceddaily to maximize profit to 480,000/=
  • 21. More example A builder has two stores, one at S1 and the other at S2. He is building houses at P1, P2, and P3. He needs 5 tons of bricks at P1, 6 tons of bricks at P2 and 4 tons of bricks at P3. The stores contain 9 tons of bricks at S1 and 6 tons of bricks at S2. The transport cost per ton are shown in the diagram To From P1 P2 P3 S1 6/= 3/= 4/= S2 4/= 2/= 6/= How does the builder send his bricks at a minimum cost?What is the minimum overall cost? Solution Let the builder send x tons of bricks from S1 to P1 and y tons of bricks from S1 to P2 Then the transportationof bricks to P1, P2 and P3 will be as follow: - To From P1 P2 P3 S1 X Y 9 – (x + y) S2 5 – x 6 – y 4 – [9 – (x + y)] The constrains are obtainedas follows  x ≥ 0, y ≥ 0  9 – (x + y) ≥ 0 i.e. x + y ≤ 9  5 – x ≥ 0 i.e. x ≤ 5  6 – y ≥ 0 i.e. y ≤ 6  4 – [9 - (x + y)} ≥ 0 i.e. x + y ≥ 5
  • 22. Objective function F (x, y) = 6x + 3y + 4(9 - (x + y)) + 4 (5 – x) + 2(6 – y) +6 [4 – (9 - (x + y)] = 6x + 3y +36 – 4x+ 4y + 20 – 4x+ 12 – 2y + 24 – 54 + 6x+ 6y F (x, y) = 4x – 3y+ 38 Minimize f (x, y) = 4x – 3y + 38 Subject to x + y ≤ 9 x + y ≥ 5 x ≤ 5, y ≥ 0 y ≤ 6, y ≥ 0 →Equation  x + y = 9 When x = 0, y = 9 y = 0, x = 9  x + y = 5 x = 0, y = 5 y = 0, x = 9  x = 5  y = 6
  • 23. Corner points F (x, y) = 4x + 3y + 38 A (0, 5) 4 (0) + 3 (5) + 38 = 53 B (0, 6) 4 (0) + 3 (6) + 38 = 56 C (3, 6) 4 (3) + 3 (6) + 38 = 68 D (5, 4) 4 (5) + 3 (4) + 38 = 70 E (5, 0) 4 (5) + 3 (0) + 38 = 58 The builder should send the bricks of tons as follows To From P1 P2 P3 S1 0 5 4 S2 5 1 0
  • 24. The overall minimum cost is 53/= EXERCISE There is a factory located at each of the places P and Q. From these location a certain commodity is delivered to each of the three deports situated at A, B and C. The weekly requirements of the deports are respectively 5,5 and 4 unit of the commodity while the production capacity of the factories P and Q are 8 and 6 units respectively, just sufficient for requirement of deports. The cost of transportationper unit is given. To From A B C P 16 10 15 Q 10 12 10 Formulate this linear programming problem and how the commodities can be transported at minimum cost. What is the overall minimum cost?