PROJECT MONITORING
SHOWAIB AHMED CHOWDHURY
Lecturer
Department of Building Engineering & Construction Management
Rajshahi University of Engineering & Technology(RUET)
Project Monitoring refers to the process of keeping track of
all project-related metrics including team performance and
task duration, identifying potential problems and taking
corrective actions necessary to ensure that the project is
within scope, on budget and meets the specified deadlines.
It clarifies the objectives of the project, links the activities to
the objectives, sets the target, reports the progress to the
management and keeps the management aware of the
problems which crop up during the implementation of the
project.
Why Project monitoring?
• To assess the project results
•To improve process planning
• To promote learning
• To understand stakeholder’s perspectives
• To ensure accountability
Questions have to be answered through Project
Monitoring
Are tasks being carried out as planned?
Are there any unforeseen consequences that arise as a
result of these tasks?
How is your team performing at a given period of
time?
What are the elements of the project that needs
changing?
What is the impact of these changes?
Will these actions lead you to your expected results?
EARNED VALUE ANALYSIS
• Earned value analysis is the project monitoring tool that is used
to measure project progress which compares the actual work
completed at any time with respect to the original budget and
schedule.
• It also compares the work achieved with the cost of achieving
that work. From these three pieces of data, performance can be
trended and metrics calculated to express the status of the project.
• This is the practice of determining how much of the contract
budget has been ‘earned’ on the basis of the actual progress
which has been made to date and comparing this to the amount of
cost incurred and to the planned value.
Earned Value Calculation
Performing the earned value calculation at each predefined
status points is a 5 step process.
1. Gather Work Performance Information
2. Determine Schedule Status
3. Determine Cost Status
4. Forecasting
5. Reporting
Gathering Work Performance Information
To start, the project manager gathers four pieces of information
for each task:
Budget at Completion (BAC)
Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)
These are the inputs to the earned value analysis.
Budget at Completion (BAC): Refers to the budget of each
task. This is determined during project planning phase.
Planned Value (PV): Also called the Budgeted Cost of Work
Scheduled (BCWS). It is the amount that the project is
supposed to be complete up to that status point.
Earned Value (EV): Also called the Budget Cost of Work
Performed (BCWP), the EV is the measure of the work
performed at a specific point in time, expressed in terms of
the approved budget authorized for that work. It is the
amount that the project is actually complete up to that status
point.
Actual Cost (AC): Also called the Actual Cost of Work
Performed (ACWP), the AC is the realized cost for the work
performed during a specific time period. It is the actual
cost of the work up to that status point. Generally employee
hours need to be converted into a cost, and all project costs
need to be added up, such as the following items:
 Labor
 Materials
 Equipment
 Fixed cost items, like subcontractors
Determine Schedule Status
It’s time to answer the question:
How far ahead or behind schedule is the project?
To do this, we will calculate two variables from the initial
four we gathered from the project data, above:
 Schedule Variance (SV)
 Schedule Performance Index (SPI)
• Schedule Variance (SV): The schedule variance, usually
abbreviated SV, tells how far ahead or behind schedule the
task is in terms of the task budget. It is expressed in terms of
the task budget, not the actual hours or days ahead or behind
schedule.
The formula is:
SV = EV – PV
 If SV is negative, the task is behind schedule.
 If SV is zero, the task is on schedule
 If SV is positive, the task is ahead of schedule.
• Schedule Performance Index (SPI): The Schedule
Performance Index, normally abbreviated SPI, is similar to
the Schedule Variance (SV). It also tells how far ahead or
behind schedule the task is in terms of the task budget, but it
is a relative measure rather than an absolute one. The
formula is:
SPI = EV / PV
If SPI is less than 1, the task is behind schedule.
If SPI is one, the task is on schedule
If SPI is greater than 1, the task is ahead of schedule.
Determine Cost Status
In this step, we seek to answer the following question.
How far over or under budget is the project?
To do this we will calculate two more variables from the initial
four we gathered from the project data.
• Cost Variance (CV)
• Cost Performance Index (CPI)
• Cost Variance (CV): The Cost Variance, usually abbreviated
CV, is the amount that the task is over or under its budget. It
must be calculated for each task and summed to produce the
overall project’s cost variance.
The formula is:
CV = EV – AC
 If CV is negative, the task is over budget.
 If CV is zero, the task is on budget.
 If CV is positive, the task is under budget.
Cost Performance Index (CPI): The Cost Performance
Index, usually abbreviated CPI, like the Cost Variance, is a
measure of the cost performance of the project.
The formula is:
CPI = EV / AC
If CPI is less than 1, the task is over budget.
If CPI is one, the task is on budget.
If CPI is greater than 1, the task is under budget.
Project monitoring lecture 1

Más contenido relacionado

La actualidad más candente

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Project control & Monitoring
Project control & MonitoringProject control & Monitoring
Project control & MonitoringJawad Ahmad
 
PMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementPMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementOleksandr Lutsaievskyi
 
Project Management Control
Project Management ControlProject Management Control
Project Management Controlahmad bassiouny
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS Akash Prasanna
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseVladimir Vujovic
 
Project Monitoring and Controlling Processes
Project Monitoring and Controlling ProcessesProject Monitoring and Controlling Processes
Project Monitoring and Controlling ProcessesNishant Munjal
 
Project scheduling and tracking
Project scheduling and  trackingProject scheduling and  tracking
Project scheduling and trackingComputer_ at_home
 
EVMS for Commercial projects
EVMS for Commercial projectsEVMS for Commercial projects
EVMS for Commercial projectsGlen Alleman
 
IWP Timeline
IWP TimelineIWP Timeline
IWP TimelineScot Fyfe
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling Reema
 
Cost management plan tyre recycling plant
Cost management plan  tyre recycling plantCost management plan  tyre recycling plant
Cost management plan tyre recycling plantabhishekthakur309
 
Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)Mayur Rahangdale
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systemsLibra chudry
 
Management Control of Projects
Management Control of ProjectsManagement Control of Projects
Management Control of ProjectsE P John
 

La actualidad más candente (20)

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project control & Monitoring
Project control & MonitoringProject control & Monitoring
Project control & Monitoring
 
PMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementPMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost Management
 
Project Management Control
Project Management ControlProject Management Control
Project Management Control
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation course
 
Project Monitoring and Controlling Processes
Project Monitoring and Controlling ProcessesProject Monitoring and Controlling Processes
Project Monitoring and Controlling Processes
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Project scheduling and tracking
Project scheduling and  trackingProject scheduling and  tracking
Project scheduling and tracking
 
Cost management
Cost managementCost management
Cost management
 
EVMS for Commercial projects
EVMS for Commercial projectsEVMS for Commercial projects
EVMS for Commercial projects
 
Project management
Project managementProject management
Project management
 
IWP Timeline
IWP TimelineIWP Timeline
IWP Timeline
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling
 
Cost management plan tyre recycling plant
Cost management plan  tyre recycling plantCost management plan  tyre recycling plant
Cost management plan tyre recycling plant
 
Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systems
 
Management Control of Projects
Management Control of ProjectsManagement Control of Projects
Management Control of Projects
 
Project managment 6
Project managment 6Project managment 6
Project managment 6
 

Similar a Project monitoring lecture 1

Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneWaleed Hamdy Albana
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfVarunSubramanyam
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
Project Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptProject Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptadabotor7
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project managementselinasimpson1601
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
Earned value management
Earned value managementEarned value management
Earned value managementGautam Kumar
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 

Similar a Project monitoring lecture 1 (20)

Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdf
 
formation.docx
formation.docxformation.docx
formation.docx
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Project Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptProject Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.ppt
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 

Último

lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxsomshekarkn64
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 

Último (20)

lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptx
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 

Project monitoring lecture 1

  • 1. PROJECT MONITORING SHOWAIB AHMED CHOWDHURY Lecturer Department of Building Engineering & Construction Management Rajshahi University of Engineering & Technology(RUET)
  • 2. Project Monitoring refers to the process of keeping track of all project-related metrics including team performance and task duration, identifying potential problems and taking corrective actions necessary to ensure that the project is within scope, on budget and meets the specified deadlines. It clarifies the objectives of the project, links the activities to the objectives, sets the target, reports the progress to the management and keeps the management aware of the problems which crop up during the implementation of the project.
  • 3. Why Project monitoring? • To assess the project results •To improve process planning • To promote learning • To understand stakeholder’s perspectives • To ensure accountability
  • 4. Questions have to be answered through Project Monitoring Are tasks being carried out as planned? Are there any unforeseen consequences that arise as a result of these tasks? How is your team performing at a given period of time? What are the elements of the project that needs changing? What is the impact of these changes? Will these actions lead you to your expected results?
  • 6. • Earned value analysis is the project monitoring tool that is used to measure project progress which compares the actual work completed at any time with respect to the original budget and schedule. • It also compares the work achieved with the cost of achieving that work. From these three pieces of data, performance can be trended and metrics calculated to express the status of the project. • This is the practice of determining how much of the contract budget has been ‘earned’ on the basis of the actual progress which has been made to date and comparing this to the amount of cost incurred and to the planned value.
  • 7.
  • 8. Earned Value Calculation Performing the earned value calculation at each predefined status points is a 5 step process. 1. Gather Work Performance Information 2. Determine Schedule Status 3. Determine Cost Status 4. Forecasting 5. Reporting
  • 9. Gathering Work Performance Information To start, the project manager gathers four pieces of information for each task: Budget at Completion (BAC) Planned Value (PV) Earned Value (EV) Actual Cost (AC) These are the inputs to the earned value analysis.
  • 10. Budget at Completion (BAC): Refers to the budget of each task. This is determined during project planning phase. Planned Value (PV): Also called the Budgeted Cost of Work Scheduled (BCWS). It is the amount that the project is supposed to be complete up to that status point. Earned Value (EV): Also called the Budget Cost of Work Performed (BCWP), the EV is the measure of the work performed at a specific point in time, expressed in terms of the approved budget authorized for that work. It is the amount that the project is actually complete up to that status point.
  • 11. Actual Cost (AC): Also called the Actual Cost of Work Performed (ACWP), the AC is the realized cost for the work performed during a specific time period. It is the actual cost of the work up to that status point. Generally employee hours need to be converted into a cost, and all project costs need to be added up, such as the following items:  Labor  Materials  Equipment  Fixed cost items, like subcontractors
  • 12. Determine Schedule Status It’s time to answer the question: How far ahead or behind schedule is the project? To do this, we will calculate two variables from the initial four we gathered from the project data, above:  Schedule Variance (SV)  Schedule Performance Index (SPI)
  • 13. • Schedule Variance (SV): The schedule variance, usually abbreviated SV, tells how far ahead or behind schedule the task is in terms of the task budget. It is expressed in terms of the task budget, not the actual hours or days ahead or behind schedule. The formula is: SV = EV – PV  If SV is negative, the task is behind schedule.  If SV is zero, the task is on schedule  If SV is positive, the task is ahead of schedule.
  • 14. • Schedule Performance Index (SPI): The Schedule Performance Index, normally abbreviated SPI, is similar to the Schedule Variance (SV). It also tells how far ahead or behind schedule the task is in terms of the task budget, but it is a relative measure rather than an absolute one. The formula is: SPI = EV / PV If SPI is less than 1, the task is behind schedule. If SPI is one, the task is on schedule If SPI is greater than 1, the task is ahead of schedule.
  • 15. Determine Cost Status In this step, we seek to answer the following question. How far over or under budget is the project? To do this we will calculate two more variables from the initial four we gathered from the project data. • Cost Variance (CV) • Cost Performance Index (CPI)
  • 16. • Cost Variance (CV): The Cost Variance, usually abbreviated CV, is the amount that the task is over or under its budget. It must be calculated for each task and summed to produce the overall project’s cost variance. The formula is: CV = EV – AC  If CV is negative, the task is over budget.  If CV is zero, the task is on budget.  If CV is positive, the task is under budget.
  • 17. Cost Performance Index (CPI): The Cost Performance Index, usually abbreviated CPI, like the Cost Variance, is a measure of the cost performance of the project. The formula is: CPI = EV / AC If CPI is less than 1, the task is over budget. If CPI is one, the task is on budget. If CPI is greater than 1, the task is under budget.