General Consultancy (GC) Services for Different Field Offices and
Head Quarter Office at Bhubaneswar under CAO/Con/BBS
TECHNICAL PRESENTATION ON
APPROACH, METHODOLOGY AND
WORK PLAN
12th January 2024
THE PRESENTERS TODAY
Padman Kumar Padhi
Chief Design & Estimation Expert
Rinku Mandal
Chief Project Scheduler & Data Operator
Sujeet Kumar Swain
Chief Surveyor cum AutoCAD Expert
Mariano Alvarez Arce
Country Manager
Saumya Ranjan Pallaur
Chief Contract Management Expert
Sahadev Singh
Team Leader
INDEX
01: Reasons to Choose Us
02: Project Overview
03: Key Personnel’s and Proposed Organisation Chart
04: Approach & Methodology
05: Key Performance Indicators
06: Monitoring Mechanism
07: Work Programme & Flowchart of Activities
Reasons to Choose Us
Key Figures
Reasons to Choose Us
KEY FIGURES
640 million €
Turnover
No. of Employees
Years of Experience
Metro + Railways
(Km)
Presence in Countries
11,000
40+ Countries
57+ Years
1500+ Km
• Leading Engineering firm from Europe with a strong presence in India.
• Working in India for the last 14 years.
• Extensive experienced team of more than 400+ staff in India and globally more than 11,000 technical staff.
• Extensive General Consultancy Works including Design & Supervision Experience with Indian Metro/Railway organizations
across India & SAARC such as RVNL, MRVC, DMRC, NCRTC, UPMRC, CMRL, JMRC and North Frontier Railways (Indian
Railways).
• Proven Track record in Project delivery on time with Quality & Performance.
• Metros – Lucknow Metro, Mumbai Metro Line 7 & 2B, NCRTC-Delhi Meerut RRTS
• Railways – North Frontier Railway, RVNL – South Central Railway – Kadapa Nellore District, A.P., Bangladesh Railways.
• Highways – Purvanchal Expressway, Agra Lucknow Expressway.
• Established and dedicated team of Design & Supervision experts available in Delhi, Mumbai and Kolkata.
REASONS TO CHOOSE US
HEADLINE GOES HERE
Project Overview
PROJECT OVERVIEW
Ministry of Railways through CAO/Construction in East Coast Railway intends to appoint General
Consultant (GC) pertaining to the construction and execution of following works:
S. No Components
1. Carrying out feasibility study, preparation of Detailed Project Report
2.
Station Redevelopment, Passenger Amenities Works, Traffic Facilities Works, Road Safety and Level Crossing
Works
3. Road under Bridges(RUB) and Road Over Bridges (ROB)
4. Signalling and Telecommunication works such as EI,RRI
5. Lifts & Escalators, Workshops including production unit work
6. Electrification of sidings
7. Coal connectivity to new line projects
HEADLINE GOES HERE
Key Personnel and
Proposed Organisation
Chart
KEY PERSONNEL AND PROPOSED ORGANISATION CHART
S. No. Key Position Name Key Qualification
1
Team Leader
cum Financial
Expert
Sahadeva
Singh
• M.Tech (Civil), Indian Institution of Technology (IIT), Delhi
• B.E. (Civil), Indian Institution of Technology (IIT), Roorkee
• 40+ years of relevant experience
2
Chief Contract
Management
Expert
Saumya
Ranjan
Pallaur
• B.Tech (Civil), Biju Pattanayak University, Odisha
• 10+ years of relevant experience
3
Chief Design and
Estimation
Expert
Padman
Kumar Padhi
• M.Tech (Structural), Karnataka State Open University
• B.Tech (Civil), Biju Patnaik University of Technology, Orissa
• 15+ years of relevant experience
4
Chief Surveyor
cum AutoCAD
expert
Sujeet Kumar
Swain
• Diploma (Civil), SCTE & VT, Odisha
• 13+ years of relevant experience
5
Chief Project
Scheduler and
Data Operator
Rinku Mandal
• B.Tech (Civil), West Bengal University of Technology
• Post Graduate Programme (Construction Management), NICMAR Pune
• Primavera Project Management from Project Management Institute
• 8+ years of relevant experience
KEY PERSONNEL AND PROPOSED ORGANISATION CHART
HEADLINE GOES HERE
Approach & Methodology
Consultant’s Approach-Overview
Task 1- Team Mobilization & Setting of GC office
Task 2- Design Review of DPR & Coordination, Technical & Financial
Advisory
Task 3- Programme Monitoring, Contract Management & Performance
Management
Task 4- Procurement and Bid Process Management
Task 5- Support during DLP
Consultant’s Approach-Overview
• An experienced Team under the leadership of Team leader who will anchor coordination between Client– Project Office/s
– Head Offices.
• A regular coordination with the Client to present the progress on the execution of works and to discuss the challenges
and issues to be solved.
• GC will establish office at CAO/Construction as per the requirements of the project.
• Swift mobilization of personnel according to deployment program is paramount for the success of the project.
• Considering a 15 days commencement period we are in a position to promptly to deploy the personnel.
The likely places of posting and approx. nos. of staff are as indicated below:
Task 1-Team Mobilization & Setting of PMO office
S.No. Place of Posting Approx Nos. of Staff
1 Bhubaneshwar 69
2 Vishakapatnam 15
3 Angul 15
4 Boudh 11
5 Bolangir 08
S.No. Place of Posting Approx Nos. of Staff
6 Jajpur-Keonjhar Road 11
7 Sambalpur 12
8 Koraput 20
9 Jagdalpur 05
10 Rayagada 05
Technical Advisory
• Design review team of GC will closely coordinate with
Detail Design Consultants / Lead Proof Checking
Consultant, EPC Contractor/ Non-EPC contractors, etc.
• Checking DBR cluster layouts, construction method
statement, Construction drawings, specifications
including associated works and construction drawing
submitted by the Contractor.
• Design Review Follow-up with lead Detail
Designers/Proof Check consultants.
• Issuance of NOC for Preliminary, Detail Designs and As-
built Drawings.
Financial Advisory
• Overall Billing Management
• Variation and claim Management
• Cash Flow Projections and Management
Contractor/DDC Consultants Submits
Documents
Design Review Team of GC
Review/Approved document
recorded under PMIS
CAO Railway Information and
client approval
Contractor/Consultants
Issuance approval/comments
Design Review Flowchart
Task 2- Design Review of DPR & Coordination, Technical & Financial Advisory
1. Preparation of various schedules.
2. Integrated schedules.
3. Define timelines and Key Dates.
4. Review of detailed schedules
submitted by contractors.
5. Analysis of critical path.
6. Report and mitigation on breach
of critical path.
7. Work programme review and update.
8. Create early warning system and
mitigation options.
9. Resource analysis.
10.Cash flow analysis.
11.Project control.
12.Document control.
Project Schedule
Management
Cost Control Including Budgeting &
Accounting
Approval
Management
1. Baseline program cost, budget and
cash flow.
2. Monitor the baselines with respect
to actual.
3. Cost reporting.
4. Assessment of financial position
and project long-term financial
statement.
5. Assistance to Client to forecast
fund requirements.
6. Cost control procedures for the
payment to contractor.
7. Development and maintenance of
claim register.
1. Planning & procedures.
2. Assistance in approvals &
clearance from statutory and
relevant authorities such as
environmental, safety, EIG, etc.
3. Scheduling of approval requirements.
4. Clarification and support.
5. Contract management and
administration.
6. Dispute negotiation and claims
management.
7. Contract closures and termination
strategy.
8. Contractual correspondences.
Task 3- Programme Monitoring, Contract Management & Performance Management
1. Prompt reporting system on project
development and project
performance.
2. Assessment of project cost, budget
information and reporting.
3. Key Performance Indicators.
4. Evaluation Matrix for various
stakeholder parties like
Independent/Authority
Engineer/Project Management
Consultancy (PMC)/Project
Supervision Services Agency (PSSA).
Performance
Management of various Consultants
Communication
Management
Contract
Management
1. Establishment of procedure for
communication between client,
contractor, supplier and other
stakeholders.
2. Reporting of communications to
relevant stakeholders.
3. Contractual communications.
4. Functional communications.
5. Project schedule status.
1. Baseline program cost, budget and
cash flow.
2. Monitor the baselines with respect
to actual.
3. Cost reporting.
4. Assessment of financial position
and project long-term financial
statement.
5. Cost control procedures for the
payment to contractor.
6. Development and maintenance of
claim register.
7. Development and maintenance of
variation register.
Task 3- Programme Monitoring, Contract Management & Performance Management
Task 3- Programme Monitoring, Contract Management & Performance Management -
PMIS
Existing Portal/Tools: - e-DAS – E Drawings approval system | IRPSM – IR Project Sanction and Management | IRWCMS – IR Work Contract Management System
1. Strategy
2. Risk
Identification
3. Risk
Assessment
4. Risk
Mitigation
5. Monitoring
6. Assurance
7. Feedback
and Reporting
• All construction work involves risk, and the consequences
of unforeseen circumstances frequently result in
additional cost and time.
• Risks may be technical, contractual, administrative,
governmental (e.g., tax revisions), or others such as force
majeure. The risk assessment needs to be
correspondingly comprehensive and vigilant.
• A systematic approach is essential to maximize project
understanding, enabling informed decisions to be made
and objectives to be met.
• The approach is team-oriented drawing on the
professional experience of GC’s team to enable threats to
the project to be identified, eliminated, mitigated,
transferred or retained.
• GC will develop the risk management plan at the outset
and implement continuous review and regular updates.
Task 3- Programme Monitoring, Contract Management & Performance Management
Task 4- Procurement and Bid Process Management
“Procurement Strategy” will be planned and finalized by GC in consultation
with the client authorities.
Following sub-tasks:
• Identifying Contract packages and finalizing scope, technical
specifications, and contract Conditions.
• Designing and developing the various Contract & Bidding forms to be used.
• Finalizing Pre-Qualification or Post-Qualification procedures and the
Invitation to Bid documents.
• Interfacing requirements, various manuals and Key dates schedule.
• Prepare BOQ, cost estimates and payment schedule.
• Conducting pre-bid meetings, reviewing, and finalizing qualification
criteria.
• Evaluating bids received for responsiveness.
• Assisting the tender committee in identifying the most Responsive and
Responsible Contractor.
• Getting the Contract executed and ensuring compliance with receipt of
submissions of all Guarantees, insurance and regulatory papers as may be
required.
Task 5- Support During DLP
• During DLP Period:
• Assist the Authority in arbitration proceedings, the appeal of arbitration or litigation relating to the works (if any).
• Identification of defect, rectification plan and getting it rectified.
• Review of Contractor’s payment and contract closure.
• Reporting to client and other stakeholders.
Key Performance
Indicators
Monitoring Work of the Professionals to be deployed
by GC
Key Performance Indicators
Stage 1 Stage 2 Stage 3 Stage 4 Stage 5
• Evaluation can be done yearly or half-yearly based on requirement.
• Personnel, Line Manager and HoD are involved in entire evaluation process.
• Transparent and effective tool for the development of personal growth.
• Feedback sessions are very effective for the improvement areas, if any.
• Generate a sense of belonging in the personnel.
• Training modules, short-term courses and performance review sessions are conducted.
December January-February March April May
SELF EVALUATION EVALUATION VALIDATION FEEDBACK REVIEW
Key Performance Indicators
Key Performance Indicators
• The Key aspect to the successful delivery of the project will be effective monitoring of Key Professionals. GC’s approach
towards this will include:
• Initial Mobilisation plan will be submitted at the award stage.
• Rolling mobilisation plan will be discussed with client & stakeholders during the execution stage on quarterly basis.
• Preference to Local Available Talent : For Deployment of other Key & Non-Key Experts quickly, we are effectively
evaluating and identifying existing staff (who are being de-mobilised from our existing project in Mumbai) in case of
award. We would prefer to engage residents of existing staff from locally from Odisha and other neighbouring states.
This will generate jobs in the state as well as reduce demobilisation of candidates.
• Performance Indicators and Retention policy : We have a performance management system & policy in place to
monitor performance of our experts.
• During Project execution stage, GC will implement steps like Retention bonus policy so that existing staff can be
retained for successful implementation of Eastern Coast Railway project and also re-approval & deployment
procedure can be avoided in best possible way. This has been implemented in our existing projects and the attrition of
staff has been reduced drastically.
Key Performance Indicators
Monitoring Mechanism
Project Monitoring Tools
Claims Management
Project Monitoring Tools
Project Monitoring Tools
Project Monitoring Tools
Project Monitoring Tools
Claims Management
1. Proactive Monitoring of Contract issues.
2. Deploying a dedicated Contract Supervisory Committee and
peer Group.
3. Innovative Quasi-legal Approach.
4. Establishing a “Contract Partnering” Program.
5. “Claims Management Decision Support and Expert
System”.
INNOVATIVE
MANAGEMENT
PRACTICE
INNOVATIVE
QUASI LEGAL
PRACTICE
Contract
Supervisory
Committee
AI Based
Decision
Support System
for Claims
Proactive
Contract
Monitoring
INNOVATIVE
MANAGEMENT
PRACTICE
Contract
Partnering
INNOVATIVE
TECHNOLOGY
PRACTICE
Giventhe inherently complex natureof Construction andRailwayConstruction project, “claims” arean inevitablefactof most construction projects.
Claims Management
Claims Management
Claims Management
Claims Management
Work Programme &
Flowchart of Activities
Flowchart of Activity/Work Programme
Time is the essence of the contract. Internal target dates/Project Milestones and other days/duration as specified in the EPC/BOQ Agreement/s, will be
strictly adhered to by the GC, using appropriate scheduling software i.e. Primavera/MS Project.
THANK YOU

Más contenido relacionado

Similar a AYESA Presentation - GC East Coast Railway_12th January.pdf

Resume- Project Management Analyst
Resume- Project Management AnalystResume- Project Management Analyst
Resume- Project Management AnalystAmol Gaikwad
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&tNishant Pandey
 
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...Egyptian Engineers Association
 
Impact of RERA in India on Real Estate Project Management Service
Impact of RERA in India on Real Estate Project Management Service Impact of RERA in India on Real Estate Project Management Service
Impact of RERA in India on Real Estate Project Management Service Rudresh K V
 
Rajib paul resume
Rajib paul   resumeRajib paul   resume
Rajib paul resumeRajib Paul
 
Rajib paul Resume
Rajib paul   ResumeRajib paul   Resume
Rajib paul ResumeRajib Paul
 
Rajib paul resume
Rajib paul   resumeRajib paul   resume
Rajib paul resumeRajib Paul
 
Darryl Poulton - Presentation - Project Portfolio Management
Darryl Poulton - Presentation - Project Portfolio ManagementDarryl Poulton - Presentation - Project Portfolio Management
Darryl Poulton - Presentation - Project Portfolio ManagementDarryl Poulton
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectivessombat nirund
 
Resume-Anupam Phanse
Resume-Anupam PhanseResume-Anupam Phanse
Resume-Anupam PhanseAnupam Phanse
 
Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBrown Smith Wallace
 
- CV Planning Engr - Clinton Chidi -Jan 2023.docx
- CV Planning Engr - Clinton Chidi -Jan 2023.docx- CV Planning Engr - Clinton Chidi -Jan 2023.docx
- CV Planning Engr - Clinton Chidi -Jan 2023.docxMbachu Clinton
 
Epm dimensys introductie gvk
Epm dimensys introductie gvkEpm dimensys introductie gvk
Epm dimensys introductie gvkGlenn Van_kooijk
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business planfarouq umar
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology OverviewDaniel Brody
 

Similar a AYESA Presentation - GC East Coast Railway_12th January.pdf (20)

Resume- Project Management Analyst
Resume- Project Management AnalystResume- Project Management Analyst
Resume- Project Management Analyst
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&t
 
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
 
4
44
4
 
Impact of RERA in India on Real Estate Project Management Service
Impact of RERA in India on Real Estate Project Management Service Impact of RERA in India on Real Estate Project Management Service
Impact of RERA in India on Real Estate Project Management Service
 
Module 1 : Projects in IT
Module 1 : Projects in ITModule 1 : Projects in IT
Module 1 : Projects in IT
 
Rajib paul resume
Rajib paul   resumeRajib paul   resume
Rajib paul resume
 
Rajib paul Resume
Rajib paul   ResumeRajib paul   Resume
Rajib paul Resume
 
Rajib paul resume
Rajib paul   resumeRajib paul   resume
Rajib paul resume
 
Darryl Poulton - Presentation - Project Portfolio Management
Darryl Poulton - Presentation - Project Portfolio ManagementDarryl Poulton - Presentation - Project Portfolio Management
Darryl Poulton - Presentation - Project Portfolio Management
 
Planner's Resume
Planner's ResumePlanner's Resume
Planner's Resume
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectives
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Resume-Anupam Phanse
Resume-Anupam PhanseResume-Anupam Phanse
Resume-Anupam Phanse
 
Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction Projects
 
- CV Planning Engr - Clinton Chidi -Jan 2023.docx
- CV Planning Engr - Clinton Chidi -Jan 2023.docx- CV Planning Engr - Clinton Chidi -Jan 2023.docx
- CV Planning Engr - Clinton Chidi -Jan 2023.docx
 
Epm dimensys introductie gvk
Epm dimensys introductie gvkEpm dimensys introductie gvk
Epm dimensys introductie gvk
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business plan
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview
 

Último

Unlocking Growth The Power of Outsourcing for CPA Firms
Unlocking Growth The Power of Outsourcing for CPA FirmsUnlocking Growth The Power of Outsourcing for CPA Firms
Unlocking Growth The Power of Outsourcing for CPA FirmsYourLegal Accounting
 
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdfInnomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdfInnomantra
 
The Art of Decision-Making: Navigating Complexity and Uncertainty
The Art of Decision-Making: Navigating Complexity and UncertaintyThe Art of Decision-Making: Navigating Complexity and Uncertainty
The Art of Decision-Making: Navigating Complexity and Uncertaintycapivisgroup
 
Mastering The Art Of 'Closing The Sale'.
Mastering The Art Of 'Closing The Sale'.Mastering The Art Of 'Closing The Sale'.
Mastering The Art Of 'Closing The Sale'.SNSW group8
 
What are the differences between an international company, a global company, ...
What are the differences between an international company, a global company, ...What are the differences between an international company, a global company, ...
What are the differences between an international company, a global company, ...AbhishekSharma823325
 
What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...srcw2322l101
 
Understanding Financial Accounting 3rd Canadian Edition by Christopher D. Bur...
Understanding Financial Accounting 3rd Canadian Edition by Christopher D. Bur...Understanding Financial Accounting 3rd Canadian Edition by Christopher D. Bur...
Understanding Financial Accounting 3rd Canadian Edition by Christopher D. Bur...ssuserf63bd7
 
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg Pfizer
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg PfizerJual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg Pfizer
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg PfizerPusat Herbal Resmi BPOM
 
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptxGoal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptxNetapsFoundationAdmi
 
Navigating Tax Season with Confidence Streamlines CPA Firms
Navigating Tax Season with Confidence Streamlines CPA FirmsNavigating Tax Season with Confidence Streamlines CPA Firms
Navigating Tax Season with Confidence Streamlines CPA FirmsYourLegal Accounting
 
wagamamaLab presentation @MIT 20240509 IRODORI
wagamamaLab presentation @MIT 20240509 IRODORIwagamamaLab presentation @MIT 20240509 IRODORI
wagamamaLab presentation @MIT 20240509 IRODORIIRODORI inc.
 
Elevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO ServicesElevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO ServicesHaseebBashir5
 
Pitch Deck Teardown: Goodcarbon's $5.5m Seed deck
Pitch Deck Teardown: Goodcarbon's $5.5m Seed deckPitch Deck Teardown: Goodcarbon's $5.5m Seed deck
Pitch Deck Teardown: Goodcarbon's $5.5m Seed deckHajeJanKamps
 
10 Easiest Ways To Buy Verified TransferWise Accounts
10 Easiest Ways To Buy Verified TransferWise Accounts10 Easiest Ways To Buy Verified TransferWise Accounts
10 Easiest Ways To Buy Verified TransferWise Accountshttps://localsmmshop.com/
 
How Bookkeeping helps you in Cost Saving, Tax Saving and Smooth Business Runn...
How Bookkeeping helps you in Cost Saving, Tax Saving and Smooth Business Runn...How Bookkeeping helps you in Cost Saving, Tax Saving and Smooth Business Runn...
How Bookkeeping helps you in Cost Saving, Tax Saving and Smooth Business Runn...YourLegal Accounting
 
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证ogawka
 
Toyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & TransformationsToyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & TransformationsStefan Wolpers
 

Último (20)

Unlocking Growth The Power of Outsourcing for CPA Firms
Unlocking Growth The Power of Outsourcing for CPA FirmsUnlocking Growth The Power of Outsourcing for CPA Firms
Unlocking Growth The Power of Outsourcing for CPA Firms
 
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdfInnomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
 
The Art of Decision-Making: Navigating Complexity and Uncertainty
The Art of Decision-Making: Navigating Complexity and UncertaintyThe Art of Decision-Making: Navigating Complexity and Uncertainty
The Art of Decision-Making: Navigating Complexity and Uncertainty
 
Mastering The Art Of 'Closing The Sale'.
Mastering The Art Of 'Closing The Sale'.Mastering The Art Of 'Closing The Sale'.
Mastering The Art Of 'Closing The Sale'.
 
What are the differences between an international company, a global company, ...
What are the differences between an international company, a global company, ...What are the differences between an international company, a global company, ...
What are the differences between an international company, a global company, ...
 
WAM Corporate Presentation May 2024_w.pdf
WAM Corporate Presentation May 2024_w.pdfWAM Corporate Presentation May 2024_w.pdf
WAM Corporate Presentation May 2024_w.pdf
 
Home Furnishings Ecommerce Platform Short Pitch 2024
Home Furnishings Ecommerce Platform Short Pitch 2024Home Furnishings Ecommerce Platform Short Pitch 2024
Home Furnishings Ecommerce Platform Short Pitch 2024
 
What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...
 
Understanding Financial Accounting 3rd Canadian Edition by Christopher D. Bur...
Understanding Financial Accounting 3rd Canadian Edition by Christopher D. Bur...Understanding Financial Accounting 3rd Canadian Edition by Christopher D. Bur...
Understanding Financial Accounting 3rd Canadian Edition by Christopher D. Bur...
 
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg Pfizer
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg PfizerJual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg Pfizer
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg Pfizer
 
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptxGoal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
 
Obat Aborsi Malang 0851\7696\3835 Jual Obat Cytotec Di Malang
Obat Aborsi Malang 0851\7696\3835 Jual Obat Cytotec Di MalangObat Aborsi Malang 0851\7696\3835 Jual Obat Cytotec Di Malang
Obat Aborsi Malang 0851\7696\3835 Jual Obat Cytotec Di Malang
 
Navigating Tax Season with Confidence Streamlines CPA Firms
Navigating Tax Season with Confidence Streamlines CPA FirmsNavigating Tax Season with Confidence Streamlines CPA Firms
Navigating Tax Season with Confidence Streamlines CPA Firms
 
wagamamaLab presentation @MIT 20240509 IRODORI
wagamamaLab presentation @MIT 20240509 IRODORIwagamamaLab presentation @MIT 20240509 IRODORI
wagamamaLab presentation @MIT 20240509 IRODORI
 
Elevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO ServicesElevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO Services
 
Pitch Deck Teardown: Goodcarbon's $5.5m Seed deck
Pitch Deck Teardown: Goodcarbon's $5.5m Seed deckPitch Deck Teardown: Goodcarbon's $5.5m Seed deck
Pitch Deck Teardown: Goodcarbon's $5.5m Seed deck
 
10 Easiest Ways To Buy Verified TransferWise Accounts
10 Easiest Ways To Buy Verified TransferWise Accounts10 Easiest Ways To Buy Verified TransferWise Accounts
10 Easiest Ways To Buy Verified TransferWise Accounts
 
How Bookkeeping helps you in Cost Saving, Tax Saving and Smooth Business Runn...
How Bookkeeping helps you in Cost Saving, Tax Saving and Smooth Business Runn...How Bookkeeping helps you in Cost Saving, Tax Saving and Smooth Business Runn...
How Bookkeeping helps you in Cost Saving, Tax Saving and Smooth Business Runn...
 
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证
 
Toyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & TransformationsToyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & Transformations
 

AYESA Presentation - GC East Coast Railway_12th January.pdf

  • 1. General Consultancy (GC) Services for Different Field Offices and Head Quarter Office at Bhubaneswar under CAO/Con/BBS TECHNICAL PRESENTATION ON APPROACH, METHODOLOGY AND WORK PLAN 12th January 2024
  • 2. THE PRESENTERS TODAY Padman Kumar Padhi Chief Design & Estimation Expert Rinku Mandal Chief Project Scheduler & Data Operator Sujeet Kumar Swain Chief Surveyor cum AutoCAD Expert Mariano Alvarez Arce Country Manager Saumya Ranjan Pallaur Chief Contract Management Expert Sahadev Singh Team Leader
  • 3. INDEX 01: Reasons to Choose Us 02: Project Overview 03: Key Personnel’s and Proposed Organisation Chart 04: Approach & Methodology 05: Key Performance Indicators 06: Monitoring Mechanism 07: Work Programme & Flowchart of Activities
  • 4. Reasons to Choose Us Key Figures Reasons to Choose Us
  • 5. KEY FIGURES 640 million € Turnover No. of Employees Years of Experience Metro + Railways (Km) Presence in Countries 11,000 40+ Countries 57+ Years 1500+ Km
  • 6. • Leading Engineering firm from Europe with a strong presence in India. • Working in India for the last 14 years. • Extensive experienced team of more than 400+ staff in India and globally more than 11,000 technical staff. • Extensive General Consultancy Works including Design & Supervision Experience with Indian Metro/Railway organizations across India & SAARC such as RVNL, MRVC, DMRC, NCRTC, UPMRC, CMRL, JMRC and North Frontier Railways (Indian Railways). • Proven Track record in Project delivery on time with Quality & Performance. • Metros – Lucknow Metro, Mumbai Metro Line 7 & 2B, NCRTC-Delhi Meerut RRTS • Railways – North Frontier Railway, RVNL – South Central Railway – Kadapa Nellore District, A.P., Bangladesh Railways. • Highways – Purvanchal Expressway, Agra Lucknow Expressway. • Established and dedicated team of Design & Supervision experts available in Delhi, Mumbai and Kolkata. REASONS TO CHOOSE US
  • 8. PROJECT OVERVIEW Ministry of Railways through CAO/Construction in East Coast Railway intends to appoint General Consultant (GC) pertaining to the construction and execution of following works: S. No Components 1. Carrying out feasibility study, preparation of Detailed Project Report 2. Station Redevelopment, Passenger Amenities Works, Traffic Facilities Works, Road Safety and Level Crossing Works 3. Road under Bridges(RUB) and Road Over Bridges (ROB) 4. Signalling and Telecommunication works such as EI,RRI 5. Lifts & Escalators, Workshops including production unit work 6. Electrification of sidings 7. Coal connectivity to new line projects
  • 9. HEADLINE GOES HERE Key Personnel and Proposed Organisation Chart
  • 10. KEY PERSONNEL AND PROPOSED ORGANISATION CHART S. No. Key Position Name Key Qualification 1 Team Leader cum Financial Expert Sahadeva Singh • M.Tech (Civil), Indian Institution of Technology (IIT), Delhi • B.E. (Civil), Indian Institution of Technology (IIT), Roorkee • 40+ years of relevant experience 2 Chief Contract Management Expert Saumya Ranjan Pallaur • B.Tech (Civil), Biju Pattanayak University, Odisha • 10+ years of relevant experience 3 Chief Design and Estimation Expert Padman Kumar Padhi • M.Tech (Structural), Karnataka State Open University • B.Tech (Civil), Biju Patnaik University of Technology, Orissa • 15+ years of relevant experience 4 Chief Surveyor cum AutoCAD expert Sujeet Kumar Swain • Diploma (Civil), SCTE & VT, Odisha • 13+ years of relevant experience 5 Chief Project Scheduler and Data Operator Rinku Mandal • B.Tech (Civil), West Bengal University of Technology • Post Graduate Programme (Construction Management), NICMAR Pune • Primavera Project Management from Project Management Institute • 8+ years of relevant experience
  • 11. KEY PERSONNEL AND PROPOSED ORGANISATION CHART
  • 12. HEADLINE GOES HERE Approach & Methodology Consultant’s Approach-Overview Task 1- Team Mobilization & Setting of GC office Task 2- Design Review of DPR & Coordination, Technical & Financial Advisory Task 3- Programme Monitoring, Contract Management & Performance Management Task 4- Procurement and Bid Process Management Task 5- Support during DLP
  • 14. • An experienced Team under the leadership of Team leader who will anchor coordination between Client– Project Office/s – Head Offices. • A regular coordination with the Client to present the progress on the execution of works and to discuss the challenges and issues to be solved. • GC will establish office at CAO/Construction as per the requirements of the project. • Swift mobilization of personnel according to deployment program is paramount for the success of the project. • Considering a 15 days commencement period we are in a position to promptly to deploy the personnel. The likely places of posting and approx. nos. of staff are as indicated below: Task 1-Team Mobilization & Setting of PMO office S.No. Place of Posting Approx Nos. of Staff 1 Bhubaneshwar 69 2 Vishakapatnam 15 3 Angul 15 4 Boudh 11 5 Bolangir 08 S.No. Place of Posting Approx Nos. of Staff 6 Jajpur-Keonjhar Road 11 7 Sambalpur 12 8 Koraput 20 9 Jagdalpur 05 10 Rayagada 05
  • 15. Technical Advisory • Design review team of GC will closely coordinate with Detail Design Consultants / Lead Proof Checking Consultant, EPC Contractor/ Non-EPC contractors, etc. • Checking DBR cluster layouts, construction method statement, Construction drawings, specifications including associated works and construction drawing submitted by the Contractor. • Design Review Follow-up with lead Detail Designers/Proof Check consultants. • Issuance of NOC for Preliminary, Detail Designs and As- built Drawings. Financial Advisory • Overall Billing Management • Variation and claim Management • Cash Flow Projections and Management Contractor/DDC Consultants Submits Documents Design Review Team of GC Review/Approved document recorded under PMIS CAO Railway Information and client approval Contractor/Consultants Issuance approval/comments Design Review Flowchart Task 2- Design Review of DPR & Coordination, Technical & Financial Advisory
  • 16. 1. Preparation of various schedules. 2. Integrated schedules. 3. Define timelines and Key Dates. 4. Review of detailed schedules submitted by contractors. 5. Analysis of critical path. 6. Report and mitigation on breach of critical path. 7. Work programme review and update. 8. Create early warning system and mitigation options. 9. Resource analysis. 10.Cash flow analysis. 11.Project control. 12.Document control. Project Schedule Management Cost Control Including Budgeting & Accounting Approval Management 1. Baseline program cost, budget and cash flow. 2. Monitor the baselines with respect to actual. 3. Cost reporting. 4. Assessment of financial position and project long-term financial statement. 5. Assistance to Client to forecast fund requirements. 6. Cost control procedures for the payment to contractor. 7. Development and maintenance of claim register. 1. Planning & procedures. 2. Assistance in approvals & clearance from statutory and relevant authorities such as environmental, safety, EIG, etc. 3. Scheduling of approval requirements. 4. Clarification and support. 5. Contract management and administration. 6. Dispute negotiation and claims management. 7. Contract closures and termination strategy. 8. Contractual correspondences. Task 3- Programme Monitoring, Contract Management & Performance Management
  • 17. 1. Prompt reporting system on project development and project performance. 2. Assessment of project cost, budget information and reporting. 3. Key Performance Indicators. 4. Evaluation Matrix for various stakeholder parties like Independent/Authority Engineer/Project Management Consultancy (PMC)/Project Supervision Services Agency (PSSA). Performance Management of various Consultants Communication Management Contract Management 1. Establishment of procedure for communication between client, contractor, supplier and other stakeholders. 2. Reporting of communications to relevant stakeholders. 3. Contractual communications. 4. Functional communications. 5. Project schedule status. 1. Baseline program cost, budget and cash flow. 2. Monitor the baselines with respect to actual. 3. Cost reporting. 4. Assessment of financial position and project long-term financial statement. 5. Cost control procedures for the payment to contractor. 6. Development and maintenance of claim register. 7. Development and maintenance of variation register. Task 3- Programme Monitoring, Contract Management & Performance Management
  • 18. Task 3- Programme Monitoring, Contract Management & Performance Management - PMIS Existing Portal/Tools: - e-DAS – E Drawings approval system | IRPSM – IR Project Sanction and Management | IRWCMS – IR Work Contract Management System
  • 19. 1. Strategy 2. Risk Identification 3. Risk Assessment 4. Risk Mitigation 5. Monitoring 6. Assurance 7. Feedback and Reporting • All construction work involves risk, and the consequences of unforeseen circumstances frequently result in additional cost and time. • Risks may be technical, contractual, administrative, governmental (e.g., tax revisions), or others such as force majeure. The risk assessment needs to be correspondingly comprehensive and vigilant. • A systematic approach is essential to maximize project understanding, enabling informed decisions to be made and objectives to be met. • The approach is team-oriented drawing on the professional experience of GC’s team to enable threats to the project to be identified, eliminated, mitigated, transferred or retained. • GC will develop the risk management plan at the outset and implement continuous review and regular updates. Task 3- Programme Monitoring, Contract Management & Performance Management
  • 20. Task 4- Procurement and Bid Process Management “Procurement Strategy” will be planned and finalized by GC in consultation with the client authorities. Following sub-tasks: • Identifying Contract packages and finalizing scope, technical specifications, and contract Conditions. • Designing and developing the various Contract & Bidding forms to be used. • Finalizing Pre-Qualification or Post-Qualification procedures and the Invitation to Bid documents. • Interfacing requirements, various manuals and Key dates schedule. • Prepare BOQ, cost estimates and payment schedule. • Conducting pre-bid meetings, reviewing, and finalizing qualification criteria. • Evaluating bids received for responsiveness. • Assisting the tender committee in identifying the most Responsive and Responsible Contractor. • Getting the Contract executed and ensuring compliance with receipt of submissions of all Guarantees, insurance and regulatory papers as may be required.
  • 21. Task 5- Support During DLP • During DLP Period: • Assist the Authority in arbitration proceedings, the appeal of arbitration or litigation relating to the works (if any). • Identification of defect, rectification plan and getting it rectified. • Review of Contractor’s payment and contract closure. • Reporting to client and other stakeholders.
  • 22. Key Performance Indicators Monitoring Work of the Professionals to be deployed by GC
  • 23. Key Performance Indicators Stage 1 Stage 2 Stage 3 Stage 4 Stage 5 • Evaluation can be done yearly or half-yearly based on requirement. • Personnel, Line Manager and HoD are involved in entire evaluation process. • Transparent and effective tool for the development of personal growth. • Feedback sessions are very effective for the improvement areas, if any. • Generate a sense of belonging in the personnel. • Training modules, short-term courses and performance review sessions are conducted. December January-February March April May SELF EVALUATION EVALUATION VALIDATION FEEDBACK REVIEW
  • 26. • The Key aspect to the successful delivery of the project will be effective monitoring of Key Professionals. GC’s approach towards this will include: • Initial Mobilisation plan will be submitted at the award stage. • Rolling mobilisation plan will be discussed with client & stakeholders during the execution stage on quarterly basis. • Preference to Local Available Talent : For Deployment of other Key & Non-Key Experts quickly, we are effectively evaluating and identifying existing staff (who are being de-mobilised from our existing project in Mumbai) in case of award. We would prefer to engage residents of existing staff from locally from Odisha and other neighbouring states. This will generate jobs in the state as well as reduce demobilisation of candidates. • Performance Indicators and Retention policy : We have a performance management system & policy in place to monitor performance of our experts. • During Project execution stage, GC will implement steps like Retention bonus policy so that existing staff can be retained for successful implementation of Eastern Coast Railway project and also re-approval & deployment procedure can be avoided in best possible way. This has been implemented in our existing projects and the attrition of staff has been reduced drastically. Key Performance Indicators
  • 27. Monitoring Mechanism Project Monitoring Tools Claims Management
  • 32. Claims Management 1. Proactive Monitoring of Contract issues. 2. Deploying a dedicated Contract Supervisory Committee and peer Group. 3. Innovative Quasi-legal Approach. 4. Establishing a “Contract Partnering” Program. 5. “Claims Management Decision Support and Expert System”. INNOVATIVE MANAGEMENT PRACTICE INNOVATIVE QUASI LEGAL PRACTICE Contract Supervisory Committee AI Based Decision Support System for Claims Proactive Contract Monitoring INNOVATIVE MANAGEMENT PRACTICE Contract Partnering INNOVATIVE TECHNOLOGY PRACTICE Giventhe inherently complex natureof Construction andRailwayConstruction project, “claims” arean inevitablefactof most construction projects.
  • 37. Work Programme & Flowchart of Activities
  • 38. Flowchart of Activity/Work Programme Time is the essence of the contract. Internal target dates/Project Milestones and other days/duration as specified in the EPC/BOQ Agreement/s, will be strictly adhered to by the GC, using appropriate scheduling software i.e. Primavera/MS Project.