SlideShare una empresa de Scribd logo
Earned Value
Management –
Project
Controls
Prepared by: Amr Omar
12-Apr-2021
Agenda
1. Introduction to Project Controls
2. What is Planned Value
3. What is % Complete and what is Earned Value
4. What is Actual Costs
5. Project Performance Metrics
• SPI and Schedule Variance
• CPI and Cost Variance
What is Project Controls?
• Project Controls are an ongoing process which Project Managers
continuously perform through the lifecycle of the project. This process is
aimed to measure project performance and be enable the project
manager to forecast the finish.
• Main Areas of Controls:
1. Scope
2. Schedule
3. Cost
4. Quality
Introduction
to Schedule
Controls
Schedule Phases
• The phases of the schedule development
1. During Estimate Phase : Initial Schedule or Estimate Schedule
• High level estimate to estimate durations based on the understanding of the scope
• Performed by the Estimating Team
2. After Contract Award: Baseline Schedule
• Typically published after 10 business days from contract award and is discussed in the kick-
off meeting with the client.
• Should be more refined than the initial schedule and client buy-in is obtained
• Once Client buys-in it is stored and named as the Baseline Schedule
• Baseline schedule is the playbook of all project schedules and is always referred back to in
all stages of the project.
• All Schedule Controls are performed throughout the project to measure against the baseline
schedule
Baseline Schedule Example:
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
A
B
C
D
E
GANTT CHART presentation for Baseline Schedule
Further Development of Baseline Schedule
Activity Duration Budget
A 5 $20,000
B 3 $15,000
C 4 $20,000
D 2 $4,000
E 3 $18,000
TOTAL BUDGET
(BAC)
$77,000
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
A 4k 4k 4k 4k 4k
B 5k 5k 5k
C 5k 5k 5k 5k
D 2k 2k
E 6k 6k 6k
Schedule Example - Continued
Question:
- By day 3, per the baseline,
how much did we PLAN to
spend?
- Answer: PV = $12k
- By day 7, what is our
planned value?
- Answer: PV= $40k
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
A 4k 4k 4k 4k 4k
B 5k 5k 5k
C 5k 5k 5k 5k
D 2k 2k
E 6k 6k 6k
Planned Value - Continued
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
A 4k 4k 4k 4k 4k
B 5k 5k 5k
C 5k 5k 5k 5k
D 2k 2k
E 6k 6k 6k
PV 4k 8k 12k 16k 20k 30k 40k 50k 55k 57k 59k 65k 71k 77k
Earned Value
• Earned value is how much actual progress was completed for any given
activity at a certain point in time (DATA DATE).
• It is a derived as a percentage of the original budget, based on scope
completion
• The % complete is always the percentage completed of SCOPE
Therefore:
EARNED VALUE = % Complete of SCOPE x Budget (BAC)
Earned Value Example
Activity Duration Budget
A 5 $20,000
B 3 $15,000
C 4 $20,000
D 2 $4,000
E 3 $18,000
TOTAL BUDGET
(BAC)
$77,000
Activity % Comp
A 100 %
B 50%
C 100%
D 0%
E 0%
TOTAL EARNED VALUE
(EV)
AFTER 6
days OR
by day 7
DATA
DATE
EV
$20,000
$7,500
$20,000
0
0
$47,500
Earned Value – Schedule Metrics
• At day 7:
• EV =$47,500
• PV = $40,000
Question:
How is our schedule
performance?
Answer:
We’re doing well!
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
A 4k 4k 4k 4k 4k
B 5k 5k 5k
C 5k 5k 5k 5k
D 2k 2k
E 6k 6k 6k
P
V
4k 8k 12
k
16
k
20
k
30
k
40
k
50
k
55
k
57
k
59
k
65
k
71
k
77
k
EV @
day 7
$20,000
$7,500
$20,000
0
0
$47,500
Example Continue- Schedule-wise, How well
are we doing?
• EV = $47,500
• PV = $40,000
• Since we actually earned better than we planned, (EV > PV), then . We’re ahead of schedule
• IF EV< PV, then we’re behind schedule
• Further dissection:
• At day 7 (our data date – when we collected all data), our schedule earnings were how much higher than
planned??? (This is called Schedule Variance)
• Schedule Variance = EV – PV = $7,500 (positive number)
• OR
• At day 7 , how much did we earn compared to planned (just a simple division)
• EV / PV = 47500 / 40000 = 1.1875
• THIS IS CALLED SCHEDULE PERFOMANCE INDEX = SPI
Schedule Controls Summary
• Planned Value = PV = What was planned at the baseline schedule in terms of budget
• Earned Value = EV = How much we earned of what was budgeted for
EV= ACTUAL % COMPLETE OF SCOPE x Budget
• Schedule Variance = SV = Earned Value – Planned Value = EV - PV
IF SV = Positive Number , then we’re ahead of schedule
IF SV = Negative Number, then we’re behind schedule
• Schedule Performance Index = SPI = Earned Value / Planned Value = EV/PV
IF SPI is greater than 1, then we’re ahead of schedule
IF SPI is less than 1, then we’re behind schedule
Exercise for the team
• Question: The total budget at completion for the entire project is $800,000. The
project has a total planned value of $180,000 after 5 days, per the baseline
schedule. After 5 days, the percent complete for the project was calculated at
20%. Please calculate the Schedule Variance, Schedule Performance Index
and determine whether the project is ahead or behind schedule.
• Answer:
• EV = 20%x 800,000 = $160,000
• SV = EV-PV = $160,000 - $180,000 = ($ - 20,000)
• SPI = EV/PV = $160/180 = 0.88
• Therefore, the project is running behind schedule
Exercise for the team
• At a given data date for project XYZ, the SPI was 0.8. The planned value at
the data date was $380,000 and the overall budget at completion is
$800,000. What is the percentage completed of scope at this data date?

Más contenido relacionado

Similar a Earned Value Management - Project Controls - Schedule Only.pptx

EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
Fahad Ali
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
Dhamo daran
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis training
Paul King
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
Ahmed Elshaboury,PMP,LEED GA
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
Anand Bobade
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
BECM, RUET, Bangladesh
 
IT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.pptIT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.ppt
DILIP KUMAR M.Tech (ACT)
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
sajidkhan82714
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
Anand Bobade
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
Saqib Raza
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
Qais Ur Rehman Rasooli, PMP
 
S-Curve Presentation- 20130529
S-Curve Presentation- 20130529S-Curve Presentation- 20130529
S-Curve Presentation- 20130529
James Zhang (Chi, Zhang)
 
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
SN Panigrahi, PMP
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
Nikhil Raj
 
Mark blum ubc tool box execution - powerpoint presentation
Mark blum   ubc tool box execution - powerpoint presentationMark blum   ubc tool box execution - powerpoint presentation
Mark blum ubc tool box execution - powerpoint presentation
CDN_Irony
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown Structure
John Carter
 

Similar a Earned Value Management - Project Controls - Schedule Only.pptx (20)

EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis training
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
IT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.pptIT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.ppt
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
 
S-Curve Presentation- 20130529
S-Curve Presentation- 20130529S-Curve Presentation- 20130529
S-Curve Presentation- 20130529
 
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Mark blum ubc tool box execution - powerpoint presentation
Mark blum   ubc tool box execution - powerpoint presentationMark blum   ubc tool box execution - powerpoint presentation
Mark blum ubc tool box execution - powerpoint presentation
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown Structure
 

Último

CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
Prakhyath Rai
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
GauravCar
 
Introduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptxIntroduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptx
MiscAnnoy1
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
UReason
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
sachin chaurasia
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
Hematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood CountHematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood Count
shahdabdulbaset
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
RamonNovais6
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
PKavitha10
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
architagupta876
 

Último (20)

CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
 
Introduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptxIntroduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptx
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
Hematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood CountHematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood Count
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
 

Earned Value Management - Project Controls - Schedule Only.pptx

  • 2. Agenda 1. Introduction to Project Controls 2. What is Planned Value 3. What is % Complete and what is Earned Value 4. What is Actual Costs 5. Project Performance Metrics • SPI and Schedule Variance • CPI and Cost Variance
  • 3. What is Project Controls? • Project Controls are an ongoing process which Project Managers continuously perform through the lifecycle of the project. This process is aimed to measure project performance and be enable the project manager to forecast the finish. • Main Areas of Controls: 1. Scope 2. Schedule 3. Cost 4. Quality
  • 5. Schedule Phases • The phases of the schedule development 1. During Estimate Phase : Initial Schedule or Estimate Schedule • High level estimate to estimate durations based on the understanding of the scope • Performed by the Estimating Team 2. After Contract Award: Baseline Schedule • Typically published after 10 business days from contract award and is discussed in the kick- off meeting with the client. • Should be more refined than the initial schedule and client buy-in is obtained • Once Client buys-in it is stored and named as the Baseline Schedule • Baseline schedule is the playbook of all project schedules and is always referred back to in all stages of the project. • All Schedule Controls are performed throughout the project to measure against the baseline schedule
  • 6. Baseline Schedule Example: 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 A B C D E GANTT CHART presentation for Baseline Schedule
  • 7. Further Development of Baseline Schedule Activity Duration Budget A 5 $20,000 B 3 $15,000 C 4 $20,000 D 2 $4,000 E 3 $18,000 TOTAL BUDGET (BAC) $77,000 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 A 4k 4k 4k 4k 4k B 5k 5k 5k C 5k 5k 5k 5k D 2k 2k E 6k 6k 6k
  • 8. Schedule Example - Continued Question: - By day 3, per the baseline, how much did we PLAN to spend? - Answer: PV = $12k - By day 7, what is our planned value? - Answer: PV= $40k 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 A 4k 4k 4k 4k 4k B 5k 5k 5k C 5k 5k 5k 5k D 2k 2k E 6k 6k 6k
  • 9. Planned Value - Continued 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 A 4k 4k 4k 4k 4k B 5k 5k 5k C 5k 5k 5k 5k D 2k 2k E 6k 6k 6k PV 4k 8k 12k 16k 20k 30k 40k 50k 55k 57k 59k 65k 71k 77k
  • 10. Earned Value • Earned value is how much actual progress was completed for any given activity at a certain point in time (DATA DATE). • It is a derived as a percentage of the original budget, based on scope completion • The % complete is always the percentage completed of SCOPE Therefore: EARNED VALUE = % Complete of SCOPE x Budget (BAC)
  • 11. Earned Value Example Activity Duration Budget A 5 $20,000 B 3 $15,000 C 4 $20,000 D 2 $4,000 E 3 $18,000 TOTAL BUDGET (BAC) $77,000 Activity % Comp A 100 % B 50% C 100% D 0% E 0% TOTAL EARNED VALUE (EV) AFTER 6 days OR by day 7 DATA DATE EV $20,000 $7,500 $20,000 0 0 $47,500
  • 12. Earned Value – Schedule Metrics • At day 7: • EV =$47,500 • PV = $40,000 Question: How is our schedule performance? Answer: We’re doing well! 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 A 4k 4k 4k 4k 4k B 5k 5k 5k C 5k 5k 5k 5k D 2k 2k E 6k 6k 6k P V 4k 8k 12 k 16 k 20 k 30 k 40 k 50 k 55 k 57 k 59 k 65 k 71 k 77 k EV @ day 7 $20,000 $7,500 $20,000 0 0 $47,500
  • 13. Example Continue- Schedule-wise, How well are we doing? • EV = $47,500 • PV = $40,000 • Since we actually earned better than we planned, (EV > PV), then . We’re ahead of schedule • IF EV< PV, then we’re behind schedule • Further dissection: • At day 7 (our data date – when we collected all data), our schedule earnings were how much higher than planned??? (This is called Schedule Variance) • Schedule Variance = EV – PV = $7,500 (positive number) • OR • At day 7 , how much did we earn compared to planned (just a simple division) • EV / PV = 47500 / 40000 = 1.1875 • THIS IS CALLED SCHEDULE PERFOMANCE INDEX = SPI
  • 14. Schedule Controls Summary • Planned Value = PV = What was planned at the baseline schedule in terms of budget • Earned Value = EV = How much we earned of what was budgeted for EV= ACTUAL % COMPLETE OF SCOPE x Budget • Schedule Variance = SV = Earned Value – Planned Value = EV - PV IF SV = Positive Number , then we’re ahead of schedule IF SV = Negative Number, then we’re behind schedule • Schedule Performance Index = SPI = Earned Value / Planned Value = EV/PV IF SPI is greater than 1, then we’re ahead of schedule IF SPI is less than 1, then we’re behind schedule
  • 15. Exercise for the team • Question: The total budget at completion for the entire project is $800,000. The project has a total planned value of $180,000 after 5 days, per the baseline schedule. After 5 days, the percent complete for the project was calculated at 20%. Please calculate the Schedule Variance, Schedule Performance Index and determine whether the project is ahead or behind schedule. • Answer: • EV = 20%x 800,000 = $160,000 • SV = EV-PV = $160,000 - $180,000 = ($ - 20,000) • SPI = EV/PV = $160/180 = 0.88 • Therefore, the project is running behind schedule
  • 16. Exercise for the team • At a given data date for project XYZ, the SPI was 0.8. The planned value at the data date was $380,000 and the overall budget at completion is $800,000. What is the percentage completed of scope at this data date?