Okay, let's solve this step-by-step: * Planned Value (PV) at data date = $380,000 * Overall Budget at Completion (BAC) = $800,000 * We're given: Schedule Performance Index (SPI) = 0.8 * By the formula: SPI = Earned Value (EV) / Planned Value (PV) * Set up the equation: 0.8 = EV / $380,000 * Solve for EV: EV = 0.8 * $380,000 = $304,000 * To get the % complete, take EV / BAC * EV = $304,000 * BAC = $800,