Mini Project Report
On
PREPARATION OF BILL OF QUANTITY & TENDER DOCUMENT
In partial fulfillment for the degree of
Bachelor of Technology
In
Civil Engineering
SUBMITTED By
MAYANK SINGH
ROLL NO:- 2000640000003
Under the Guidance of
Mr. KULDEEP KUSHWAH
DEPARTMENT OF CIVIL ENGINEERING
HINDUSTAN COLLEGE OF SCIENCE AND TECHNOLOGY Farah
Mathura Uttar Pradesh APJ Abdul Kalam Technical University
ACKNOWLEDGEMENT
I feel very proud to say that due to keen knowledge of the
faculty of the CIVIL DEPARTMENT of the HINDUSTAN
COLLEGE OF SCIENCE AND TECHNOLOGY. It was very easy for
me to learn a lot of knowledge regarding the “Preparation of bill
of quantity & tender document”.
I am greatly thankful to our guide Mr. KULDEEP KUSHWAH for his
kind support and guidance to successfully complete my Project. I
have highly benefited by this Project and have gained a lot of
knowledge about the various problem of, preparation of
presentation of layout plan of a building and marking on ground.
Finally I would like to thanks all the faculty members and senior
teachers who have helped me and co-operated with me during
my project work.
Name: MAYANK SINGH
Roll No: 2000640000003
CHAPTER 2
2.0 STANDARD SCHEDULES OF RATES
All the Government / Departments every year prepare and
update rates of normally used building items / Materials / works
item. Number of such items may range from 500 to 1000. This is
called Schedule of Rates.
 S.O.R is the list of rates of various items of work.
 To facilitate the preparation of estimates and also to
Serve as guide in setting rate in connection with contract
Agreements.
 It is maintained in the form of printed books known as
Schedule of Rates ( S.O.R ).
 It consists of group of items such as excavation items ,
Concrete items , demolition items , plumbing items ,
Electrification works etc.
 S.O.R is prepared by Central Public Works Department
(CPWD) which is premier construction organization of
Government of India.
 The S.O.R consists rates about 2500-3000 items under
Different subheads like Building work , Water supply ,
Sanitary etc.
Fig 2.1 Discussion bill and quantity
Fig 2.2 Different types of workers

Más contenido relacionado

Similar a mp 11.docx

HYDERABAD METRO RAIL - IMPACT ON EXISTING TRAFFIC, FUTURE TRAFFIC AND SUSTAIN...
HYDERABAD METRO RAIL - IMPACT ON EXISTING TRAFFIC, FUTURE TRAFFIC AND SUSTAIN...HYDERABAD METRO RAIL - IMPACT ON EXISTING TRAFFIC, FUTURE TRAFFIC AND SUSTAIN...
HYDERABAD METRO RAIL - IMPACT ON EXISTING TRAFFIC, FUTURE TRAFFIC AND SUSTAIN...
L&W BUILDING SOLUTIONS PVT. LMT.
 
Tawfig Khidir - CV
Tawfig Khidir - CVTawfig Khidir - CV
Tawfig Khidir - CV
Tawfig Adham
 
Brony Electrical Engineer INDIA
Brony Electrical Engineer INDIABrony Electrical Engineer INDIA
Brony Electrical Engineer INDIA
brony mc
 
FINAL Summer Internship REPORT NICMAR
FINAL Summer Internship REPORT NICMARFINAL Summer Internship REPORT NICMAR
FINAL Summer Internship REPORT NICMAR
Kamlesh Chaudhary
 
Furrukh Shahzad CV Quantity Surveyor
Furrukh Shahzad CV Quantity SurveyorFurrukh Shahzad CV Quantity Surveyor
Furrukh Shahzad CV Quantity Surveyor
Furrukh Shahzad
 

Similar a mp 11.docx (20)

Chapter 1
Chapter 1Chapter 1
Chapter 1
 
HYDERABAD METRO RAIL - IMPACT ON EXISTING TRAFFIC, FUTURE TRAFFIC AND SUSTAIN...
HYDERABAD METRO RAIL - IMPACT ON EXISTING TRAFFIC, FUTURE TRAFFIC AND SUSTAIN...HYDERABAD METRO RAIL - IMPACT ON EXISTING TRAFFIC, FUTURE TRAFFIC AND SUSTAIN...
HYDERABAD METRO RAIL - IMPACT ON EXISTING TRAFFIC, FUTURE TRAFFIC AND SUSTAIN...
 
project planning of water management
 project planning of water management project planning of water management
project planning of water management
 
CV Sujit pdf
CV Sujit pdfCV Sujit pdf
CV Sujit pdf
 
final year civil engineering training report
final year civil engineering training report final year civil engineering training report
final year civil engineering training report
 
Resume_[Sr. Estimator - Sr. QS]
Resume_[Sr. Estimator - Sr. QS]Resume_[Sr. Estimator - Sr. QS]
Resume_[Sr. Estimator - Sr. QS]
 
4
44
4
 
Dhruv atal 030
Dhruv atal 030Dhruv atal 030
Dhruv atal 030
 
Updated cv (2)
Updated cv (2)Updated cv (2)
Updated cv (2)
 
Construction management
Construction managementConstruction management
Construction management
 
Tawfig Khidir - CV
Tawfig Khidir - CVTawfig Khidir - CV
Tawfig Khidir - CV
 
ARC 425 - LECTURE RESOURCE 1 - Const Mgt.pdf
ARC 425 - LECTURE RESOURCE 1  - Const Mgt.pdfARC 425 - LECTURE RESOURCE 1  - Const Mgt.pdf
ARC 425 - LECTURE RESOURCE 1 - Const Mgt.pdf
 
riyasdeen - qs
riyasdeen - qsriyasdeen - qs
riyasdeen - qs
 
Brony Electrical Engineer INDIA
Brony Electrical Engineer INDIABrony Electrical Engineer INDIA
Brony Electrical Engineer INDIA
 
Training report on highway project
Training report on highway projectTraining report on highway project
Training report on highway project
 
Curriculum Vitae
Curriculum VitaeCurriculum Vitae
Curriculum Vitae
 
Internship Report Semester 2 Civil Engineering.
Internship Report Semester 2 Civil Engineering.Internship Report Semester 2 Civil Engineering.
Internship Report Semester 2 Civil Engineering.
 
FINAL Summer Internship REPORT NICMAR
FINAL Summer Internship REPORT NICMARFINAL Summer Internship REPORT NICMAR
FINAL Summer Internship REPORT NICMAR
 
Furrukh Shahzad CV Quantity Surveyor
Furrukh Shahzad CV Quantity SurveyorFurrukh Shahzad CV Quantity Surveyor
Furrukh Shahzad CV Quantity Surveyor
 
induarial trainin report
induarial trainin reportinduarial trainin report
induarial trainin report
 

Último

Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 

Último (20)

NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 

mp 11.docx

  • 1. A Mini Project Report On PREPARATION OF BILL OF QUANTITY & TENDER DOCUMENT In partial fulfillment for the degree of Bachelor of Technology In Civil Engineering SUBMITTED By MAYANK SINGH ROLL NO:- 2000640000003 Under the Guidance of Mr. KULDEEP KUSHWAH DEPARTMENT OF CIVIL ENGINEERING HINDUSTAN COLLEGE OF SCIENCE AND TECHNOLOGY Farah Mathura Uttar Pradesh APJ Abdul Kalam Technical University
  • 2. ACKNOWLEDGEMENT I feel very proud to say that due to keen knowledge of the faculty of the CIVIL DEPARTMENT of the HINDUSTAN COLLEGE OF SCIENCE AND TECHNOLOGY. It was very easy for me to learn a lot of knowledge regarding the “Preparation of bill of quantity & tender document”. I am greatly thankful to our guide Mr. KULDEEP KUSHWAH for his kind support and guidance to successfully complete my Project. I have highly benefited by this Project and have gained a lot of knowledge about the various problem of, preparation of presentation of layout plan of a building and marking on ground. Finally I would like to thanks all the faculty members and senior teachers who have helped me and co-operated with me during my project work. Name: MAYANK SINGH Roll No: 2000640000003
  • 3. CHAPTER 2 2.0 STANDARD SCHEDULES OF RATES All the Government / Departments every year prepare and update rates of normally used building items / Materials / works item. Number of such items may range from 500 to 1000. This is called Schedule of Rates.  S.O.R is the list of rates of various items of work.  To facilitate the preparation of estimates and also to Serve as guide in setting rate in connection with contract Agreements.  It is maintained in the form of printed books known as Schedule of Rates ( S.O.R ).  It consists of group of items such as excavation items , Concrete items , demolition items , plumbing items , Electrification works etc.  S.O.R is prepared by Central Public Works Department (CPWD) which is premier construction organization of Government of India.  The S.O.R consists rates about 2500-3000 items under Different subheads like Building work , Water supply , Sanitary etc.
  • 4. Fig 2.1 Discussion bill and quantity
  • 5. Fig 2.2 Different types of workers