The Project is located within the geographic area of the mining concession Toquepala mine (in the south of Peru), department of Tacna, comprising a tunnel in a straight line from the southwest of the pit to the existing mill site. The mine is located at an altitude of 3,300 meters. The project includes construction of a tunnel 2.19 km long, stretching from the projected location of the primary crushing building up the pile of intermediates, which will be connected to the transport of ore through a conveyor belt. In addition it is performed two tunnels, a short mine tunnel of 155 m long and a false tunnel crossing under current rail tracks. The lithotypes affected by the tunnels are andesites, rhyolites, intrusives rock and quaternary deposits. Finally it is made the final project of the tunnel ventilation to ensure the safety of the workers.