This document provides a progress summary of the Silliman University Integrated Coastal Resource Management Project (SU-ICRMP). It outlines the following key points:
1. The project has components related to institutional development, biodiversity, coastal resource management, education, legal, and information/education/communication work.
2. Project leaders and specialists are identified for each component.
3. The first phase involved team composition, partner selection, training, and research proposals.
4. The second phase involves ongoing training and capacity building activities across each component for partners.
5. An operation (third) phase is planned to begin activities outlined in the first two phases.
3. Component Leaders
Project Leader Ben S. Malayang III
Specialists
Enrique G. Oracion Institutional
Angel C. Alcala Biodiversity
Hilconida P. Calumpong Coastal Resource Management
Betsy Joy B. Tan Education
Mikhail Lee Maxino Legal
Mark Raygan E. Garcia Information, Education, Communication
Carol Bartolata Finance
24. First Phase
SU-ICRMP Team Composition
SU-ICRMP Team WFP
RICs Selection (see “Evaluation Form”)
MoA Signing
List of RIC Personnel
Proposed Civil Works & Equipment
Training Guides
Approved Research Proposals
39. Second Phase
Biodiversity
Activity Status
Research Proposal Writing Training Completed
SCUBA Training Completed
40. Second Phase
Biodiversity
Activity Status
Research Proposal Writing Training Completed
SCUBA Training Completed
Fish Visual Census Training Completed
Fish Catch Monitoring Training Completed
41. Second Phase
Biodiversity
Activity Status
Research Proposal Writing Training Completed
SCUBA Training Completed
Fish Visual Census Training Completed
Fish Catch Monitoring Training Completed
GIS Mapping Training Completed
MPA Management Training Completed
42. Second Phase
Biodiversity
Activity Status
Research Proposal Writing Training Completed
SCUBA Training Completed
Fish Visual Census Training Completed
Fish Catch Monitoring Training Completed
GIS Mapping Training Completed
MPA Management Training Completed
Technical Writing Training Completed
52. Second Phase
Coastal Resource Management
Activity Status
CRM Training Series Completed
53. Second Phase
Coastal Resource Management
Activity Status
CRM Training Series Completed
Marine Vertebrae Assessment Completed
Water Quality Analysis Completed
54. Second Phase
Coastal Resource Management
Activity Status
CRM Training Series Completed
Marine Vertebrae Assessment Completed
Water Quality Analysis Completed
Marine Vertebrae Assessment Completed
Risk Vulnerability & Carrying Capacity Completed
55. Second Phase
Coastal Resource Management
Activity Status
CRM Training Series Completed
Marine Vertebrae Assessment Completed
Water Quality Analysis Completed
Marine Vertebrae Assessment Completed
Risk Vulnerability & Carrying Capacity Completed
Specimen Collection, Analysis & Recording Completed
Species Identification Completed
63. Second Phase
Information, Education &
Communication
64. Second Phase
Information, Education &
Communication
Activity Status
Cluster 1 Completed
5Rs of IEC Completed
65. Second Phase
Information, Education &
Communication
Activity Status
Cluster 1 Completed
5Rs of IEC Completed
Social Marketing & Social Mobilization Completed
Marketing Segmentation Completed
66. Second Phase
Information, Education &
Communication
Activity Status
Cluster 1 Completed
5Rs of IEC Completed
Social Marketing & Social Mobilization Completed
Marketing Segmentation Completed
3P IEC Issue Analysis Completed
Cluster 2 March
67. Second Phase
Information, Education &
Communication
Activity Status
Cluster 1 Completed
5Rs of IEC Completed
Social Marketing & Social Mobilization Completed
Marketing Segmentation Completed
3P IEC Issue Analysis Completed
Cluster 2 March
Cluster 3 March
76. Second Phase
Education
Activity Status
Curriculum & Module Development Training April
Service-Learning in CRM Training April
77. Second Phase
Education
Activity Status
Curriculum & Module Development Training April
Service-Learning in CRM Training April
Comm. Organizing & Social Facilitation Training April