How do we ensure the
assessment of
infrastructure resilience is
www.isngi.org
proportionate to the risk?

The following are confirmed contributors to the business and policy dialogue in Sydney:
•

Rick Sawers (National Australia Bank)

•

Nick Greiner (Chairman (Infrastructure NSW)

Monday, 30th September 2013: Business & policy Dialogue

Tuesday 1 October to Thursday, 3rd October: Academic and Policy
Dialogue

Presented by: Matthew Holmes, Civil Engineering & Geosciences
Newcastle University

www.isngi.org
How do we ensure the assessment of
infrastructure resilience is proportionate
to the risk?
Matthew Holmes a, Anna Provost b, Derek Clucas b, Sean Wilkinson a
a. Civil Engineering & Geosciences, Newcastle University, Newcastle-upon-Tyne, NE1 7RU
b. United Utilities Plc., Lingley Mere Business Park, Warrington, WA5 3LP

International Symposium for Next Generation Infrastructure
Wollongong, Australia
1st October 2013

2
Industrial Doctorate - Acknowledgements

Dr. Sean Wilkinson
Prof. Richard Dawson

David Owen
Dr. Matt Hill

Anna Provost
Derek Clucas

Mark Jones

Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk
For further information; m.j.holmes@ncl.ac.uk

3
The challenge facing
infrastructure risk managers

4
The Risk Manager’s Challenge:

Development & Infrastructure
More demand
More capital to invest

Development
Infrastructure
provision
Infrastructure
supports development

Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk
For further information; m.j.holmes@ncl.ac.uk

5
The Risk Manager’s Challenge:

Vulnerability & Resilience
Greater
dependency on
infrastructure

Society is more
vulnerable to
failure

Development permits investment

Development
Infrastructure
provision

More reliable
infrastructure

Infrastructure
needs to be
more resilient

Investment
treats the most
salient risks

Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk
For further information; m.j.holmes@ncl.ac.uk

6
The Risk Manager’s Challenge:

Risk Identification

Risk managers have
to consider an
increasing wide
range of risks

Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk
For further information; m.j.holmes@ncl.ac.uk

7
The Risk Manager’s Challenge:

Risk Selection

Photo: Kyodo/Reuters
Photo: AP

Managers have to
consider an
increasingly wide
range of risks

They cannot
assess every
risk in detail

Their selection
process must
be robust and
accountable

Photo: Daily Telegraph
Photo: AP

Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk
For further information; m.j.holmes@ncl.ac.uk

8
Alternative approaches to
selecting risks
1. Likelihood
vs.
Consequence

2. Subjective
appraisal of
uncertainty

3. Formalised
appraisal of
uncertainty

9
Likelihood vs. Consequence

10
Approaches to selecting risks:

Likelihood versus Consequence
High consequence
risks facing the
United Kingdom
(after UK Cabinet Office
2010, red line added)

Risks of natural hazards
and major accidents
(UK Cabinet Office 2012)

Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk
For further information; m.j.holmes@ncl.ac.uk

11
Approaches to selecting risks:

L vs. C, with uncertainty
Indicative National
Risks
N.B. Axes reversed
compared to the UK version
(IPENZ 2012)

Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk
For further information; m.j.holmes@ncl.ac.uk

12
Subjective Appraisal of
Uncertainty

13
Cost of
obtaining
information

Value of
information
obtained

The problem with highly uncertain
appraisals

Uncertainty

Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk
For further information; m.j.holmes@ncl.ac.uk

14
Approaches to selecting risks:

Subjective Appraisal of Uncertainty
Risk selection
based upon the
uncertainty of the
probability
assessment
(adapted from the UK
Cabinet Office diagram in
slide 9)

Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk
For further information; m.j.holmes@ncl.ac.uk

15
Formal Appraisal of Uncertainty

16
Approaches to selecting risks:

Formalised Appraisal of Uncertainty

Loss of access to
PS1
P(Snow & ice)
Snow & ice

Loss of access to
PS3
Loss of access to
WwTW

P(Cold weather)
Cold weather

Loss of power to
PS1

Storms & gales
Cyber attacks:
infrastructure
Public disorder

Loss of access to
PS2

P(Loss of power)
Loss of power

Loss of power to
PS2
Loss of power to
PS3
Loss of power to
WwTW

P(Loss of access
to PS1)
P(Loss of access
to PS2)
P(Loss of access
to PS3)
P(Loss of access
to WwTW)
P(Loss of power
to PS1)
P(Loss of power
to PS2
P(Loss of power
to PS3)
P(Loss of power
to WwTW)

Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk
For further information; m.j.holmes@ncl.ac.uk

17
Approaches to selecting risks:

Results

Cold
Weather

Storms &
Gales
• High risk
• Large spread of
results: low
precision

• Medium – high
risk
• Probability
restricted to a
narrow band

Cyber Attacks:
Infrastructure

Public
Disorder

• Low risk
• Large
uncertainty

• Very low risk
• Low uncertainty
(only 1 failure
mode)

Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk
For further information; m.j.holmes@ncl.ac.uk

18
Approaches to selecting risks:

Comparison with Likelihood vs. Consequence
Likelihood versus Consequence

2.0
Cold
Weather

1.5

1.0
Public
0.5
Disorder
0.0
0.00

Cyber Attack:
Infrastructure

Storms &
Gales

2.0
Cold
Weather

1.5

1.0
Cyber Attack:
Infrastructure

0.5

Public
Disorder

0.0
0.02

0.04

0.06

0.08

Mean:
Probability of at least one failure

•
•
•

2.5

Storms &
Gales

Mean: Flooding Volume [ML]

Mean: Flooding Volume [ML]

2.5

Uncertainty versus Consequence

0.10

1.0

0.8

0.6

0.4

0.2

0.0

Coefficient of Variation:
Probability of at least one failure

Does the new information materially affect the selection?
Is this extra information worth the extra effort?
How reliable is a risk manager’s judgement?

Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk
For further information; m.j.holmes@ncl.ac.uk

19
Discussion & Conclusion

20
Discussion
1. Omitting uncertainty at the risk screening phase is not
inherently flawed.
2. However, it misses an opportunity to justifiably eliminate some
risks whose assessment adds little value.
3. Incorporating subjective information on the uncertainty over
probability is more perceptive, but subjective and opaque.
4. Formalising this process reduces opacity, but the extra
complexity and cost may exceed the value of the new
information.

Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk
For further information; m.j.holmes@ncl.ac.uk

21
Conclusion
1.

The cost of assessing
marginal risks

We are more reliant on
infrastructure

We are more vulnerable
to failure

We need to assess
increasingly marginal
risks

We require new
methods required to
select risks to assess

2.

The more formal appraisal of uncertainty is interesting but flawed
because:
a) It does not eliminate subjectivity, just moves and exposes it.
b) The effort required to do it is self-defeating, given we are
looking for new ways to screen risks.

3.

Therefore, the subjective appraisal looks the most promising
approach.

Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk
For further information; m.j.holmes@ncl.ac.uk

22
Thank you

References:

Any questions?

Cabinet Office (2013) National risk register of civil
emergencies 2013 edition. London: Cabinet Office.

matthew.holmes@stream-idc.net

Cabinet Office (2011) Keeping the country running: natural
hazards and infrastructure. London: Cabinet Office.

IPNEZ (2012) A safer New Zealand: reducing our exposure
to natural hazards. Wellington: IPENZ

23

Más contenido relacionado

Destacado (16)

Lozzi irene 2011-12_esercizio4
Lozzi irene 2011-12_esercizio4Lozzi irene 2011-12_esercizio4
Lozzi irene 2011-12_esercizio4
 
זיהוי חשיפות מס בפעילות בינלאומית
זיהוי חשיפות מס בפעילות בינלאומיתזיהוי חשיפות מס בפעילות בינלאומית
זיהוי חשיפות מס בפעילות בינלאומית
 
Scan0001
Scan0001Scan0001
Scan0001
 
Friend2
Friend2Friend2
Friend2
 
Healthcare Reform and Changing Service Delivery Models
Healthcare Reform and Changing Service Delivery ModelsHealthcare Reform and Changing Service Delivery Models
Healthcare Reform and Changing Service Delivery Models
 
מערך סגור
מערך סגורמערך סגור
מערך סגור
 
Barcelona, Catalunya
Barcelona, CatalunyaBarcelona, Catalunya
Barcelona, Catalunya
 
Ed810 group presentation1[1]
Ed810 group presentation1[1]Ed810 group presentation1[1]
Ed810 group presentation1[1]
 
Prototype presentation
Prototype presentationPrototype presentation
Prototype presentation
 
zheng ma
zheng mazheng ma
zheng ma
 
Pp 3
Pp 3Pp 3
Pp 3
 
こじらせ概論
こじらせ概論こじらせ概論
こじらせ概論
 
Celebridades del siglo xx
Celebridades del siglo xxCelebridades del siglo xx
Celebridades del siglo xx
 
Video slides
Video slidesVideo slides
Video slides
 
Odd
OddOdd
Odd
 
ใบงานที่ 2
ใบงานที่ 2ใบงานที่ 2
ใบงานที่ 2
 

Similar a SMART International Symposium for Next Generation Infrastructure: How do we ensure the assessment of infrastructure resilience is proportionate to the risk?

Powering Sydney's Future Forum June 2014 - Relability Standards - Tim George
Powering Sydney's Future Forum June 2014 - Relability Standards - Tim GeorgePowering Sydney's Future Forum June 2014 - Relability Standards - Tim George
Powering Sydney's Future Forum June 2014 - Relability Standards - Tim George
TransGrid AU
 
TunnelSafetyFireProtection_WEB
TunnelSafetyFireProtection_WEBTunnelSafetyFireProtection_WEB
TunnelSafetyFireProtection_WEB
Natasha Shepanski
 
ICLR Friday Forum: A Profile of Earthquake Risk in Canada (April 17, 2020)
ICLR Friday Forum: A Profile of Earthquake Risk in Canada (April 17, 2020) ICLR Friday Forum: A Profile of Earthquake Risk in Canada (April 17, 2020)
ICLR Friday Forum: A Profile of Earthquake Risk in Canada (April 17, 2020)
glennmcgillivray
 
745592main 2013 falker_presentation_chicago
745592main 2013 falker_presentation_chicago745592main 2013 falker_presentation_chicago
745592main 2013 falker_presentation_chicago
Clifford Stone
 
ENG29 Queensland Energy
ENG29 Queensland EnergyENG29 Queensland Energy
ENG29 Queensland Energy
Aimee Horgan
 

Similar a SMART International Symposium for Next Generation Infrastructure: How do we ensure the assessment of infrastructure resilience is proportionate to the risk? (20)

UCl-IRDR Cascading Disasters Research Group
UCl-IRDR Cascading Disasters Research GroupUCl-IRDR Cascading Disasters Research Group
UCl-IRDR Cascading Disasters Research Group
 
Powering Sydney's Future Forum June 2014 - Relability Standards - Tim George
Powering Sydney's Future Forum June 2014 - Relability Standards - Tim GeorgePowering Sydney's Future Forum June 2014 - Relability Standards - Tim George
Powering Sydney's Future Forum June 2014 - Relability Standards - Tim George
 
TunnelSafetyFireProtection_WEB
TunnelSafetyFireProtection_WEBTunnelSafetyFireProtection_WEB
TunnelSafetyFireProtection_WEB
 
Science advice to government - Auckland conference
Science advice to government - Auckland conferenceScience advice to government - Auckland conference
Science advice to government - Auckland conference
 
ICLR Friday Forum: A Profile of Earthquake Risk in Canada (April 17, 2020)
ICLR Friday Forum: A Profile of Earthquake Risk in Canada (April 17, 2020) ICLR Friday Forum: A Profile of Earthquake Risk in Canada (April 17, 2020)
ICLR Friday Forum: A Profile of Earthquake Risk in Canada (April 17, 2020)
 
SMART International Symposium for Next Generation Infrastructure: Modelling I...
SMART International Symposium for Next Generation Infrastructure: Modelling I...SMART International Symposium for Next Generation Infrastructure: Modelling I...
SMART International Symposium for Next Generation Infrastructure: Modelling I...
 
Dr Mike Willis
Dr Mike WillisDr Mike Willis
Dr Mike Willis
 
Env sys igibs envinfo_nov11
Env sys igibs envinfo_nov11Env sys igibs envinfo_nov11
Env sys igibs envinfo_nov11
 
RES Risk 2016 Conference brochure - 18-20 May 2016, Sydney
RES Risk 2016 Conference brochure - 18-20 May 2016, SydneyRES Risk 2016 Conference brochure - 18-20 May 2016, Sydney
RES Risk 2016 Conference brochure - 18-20 May 2016, Sydney
 
Sgcp13burston
Sgcp13burstonSgcp13burston
Sgcp13burston
 
745592main 2013 falker_presentation_chicago
745592main 2013 falker_presentation_chicago745592main 2013 falker_presentation_chicago
745592main 2013 falker_presentation_chicago
 
Project professionals: Ready for the future? APM Skills, Julie Morris
Project professionals: Ready for the future? APM Skills, Julie MorrisProject professionals: Ready for the future? APM Skills, Julie Morris
Project professionals: Ready for the future? APM Skills, Julie Morris
 
Uncertainty quantification in geology
Uncertainty quantification in geologyUncertainty quantification in geology
Uncertainty quantification in geology
 
ENG29 Queensland Energy
ENG29 Queensland EnergyENG29 Queensland Energy
ENG29 Queensland Energy
 
UCLA - Solar Canal Feasibility Study
UCLA - Solar Canal Feasibility StudyUCLA - Solar Canal Feasibility Study
UCLA - Solar Canal Feasibility Study
 
Going Global: The appliance of science in a complex global context
Going Global: The appliance of science in a complex global contextGoing Global: The appliance of science in a complex global context
Going Global: The appliance of science in a complex global context
 
EnergyTech2015 Program Guide
EnergyTech2015 Program GuideEnergyTech2015 Program Guide
EnergyTech2015 Program Guide
 
SMART Infrastructure Business and Policy Dialogue 2014: Reflections on UK inf...
SMART Infrastructure Business and Policy Dialogue 2014: Reflections on UK inf...SMART Infrastructure Business and Policy Dialogue 2014: Reflections on UK inf...
SMART Infrastructure Business and Policy Dialogue 2014: Reflections on UK inf...
 
Hector Pearson, National Grid, NAAONB Conference 2015
Hector Pearson, National Grid, NAAONB Conference 2015Hector Pearson, National Grid, NAAONB Conference 2015
Hector Pearson, National Grid, NAAONB Conference 2015
 
The Resilience of the Electric Power Delivery System in Response to Bushfires...
The Resilience of the Electric Power Delivery System in Response to Bushfires...The Resilience of the Electric Power Delivery System in Response to Bushfires...
The Resilience of the Electric Power Delivery System in Response to Bushfires...
 

Más de SMART Infrastructure Facility

Más de SMART Infrastructure Facility (20)

SMART Seminar Series: "Cognitive Illusions in Virtual Reality: What do I mean...
SMART Seminar Series: "Cognitive Illusions in Virtual Reality: What do I mean...SMART Seminar Series: "Cognitive Illusions in Virtual Reality: What do I mean...
SMART Seminar Series: "Cognitive Illusions in Virtual Reality: What do I mean...
 
SMART Seminar Series: "Trusted Autonomous Systems as System of Systems". Pres...
SMART Seminar Series: "Trusted Autonomous Systems as System of Systems". Pres...SMART Seminar Series: "Trusted Autonomous Systems as System of Systems". Pres...
SMART Seminar Series: "Trusted Autonomous Systems as System of Systems". Pres...
 
SMART Seminar Series: "User-centric digital collaboration to build resilient ...
SMART Seminar Series: "User-centric digital collaboration to build resilient ...SMART Seminar Series: "User-centric digital collaboration to build resilient ...
SMART Seminar Series: "User-centric digital collaboration to build resilient ...
 
SMART Seminar Series: "The Evolution of the Metric System: From Precious Lump...
SMART Seminar Series: "The Evolution of the Metric System: From Precious Lump...SMART Seminar Series: "The Evolution of the Metric System: From Precious Lump...
SMART Seminar Series: "The Evolution of the Metric System: From Precious Lump...
 
SMART Seminar Series: "Using AI and edge computing devices for traffic flow m...
SMART Seminar Series: "Using AI and edge computing devices for traffic flow m...SMART Seminar Series: "Using AI and edge computing devices for traffic flow m...
SMART Seminar Series: "Using AI and edge computing devices for traffic flow m...
 
SMART Seminar Series: "Blockchain and its Applications". Presented by Prof Wi...
SMART Seminar Series: "Blockchain and its Applications". Presented by Prof Wi...SMART Seminar Series: "Blockchain and its Applications". Presented by Prof Wi...
SMART Seminar Series: "Blockchain and its Applications". Presented by Prof Wi...
 
SMART Seminar Series: "From an IoT cloud based architecture to Edge for dynam...
SMART Seminar Series: "From an IoT cloud based architecture to Edge for dynam...SMART Seminar Series: "From an IoT cloud based architecture to Edge for dynam...
SMART Seminar Series: "From an IoT cloud based architecture to Edge for dynam...
 
SMART Seminar Series: "Is bus bunching serious in Sydney? Preliminary finding...
SMART Seminar Series: "Is bus bunching serious in Sydney? Preliminary finding...SMART Seminar Series: "Is bus bunching serious in Sydney? Preliminary finding...
SMART Seminar Series: "Is bus bunching serious in Sydney? Preliminary finding...
 
SMART Seminar Series: "Keep it SMART, keep it simple! – Challenging complexit...
SMART Seminar Series: "Keep it SMART, keep it simple! – Challenging complexit...SMART Seminar Series: "Keep it SMART, keep it simple! – Challenging complexit...
SMART Seminar Series: "Keep it SMART, keep it simple! – Challenging complexit...
 
SMART Seminar Series: "Risk-based bridge assessment under changing load-deman...
SMART Seminar Series: "Risk-based bridge assessment under changing load-deman...SMART Seminar Series: "Risk-based bridge assessment under changing load-deman...
SMART Seminar Series: "Risk-based bridge assessment under changing load-deman...
 
SMART Seminar Series: "Deep Learning: Fundamentals and Practice". Presented b...
SMART Seminar Series: "Deep Learning: Fundamentals and Practice". Presented b...SMART Seminar Series: "Deep Learning: Fundamentals and Practice". Presented b...
SMART Seminar Series: "Deep Learning: Fundamentals and Practice". Presented b...
 
SMART Seminar Series: "Infrastructure Resilience: Planning for Future Extreme...
SMART Seminar Series: "Infrastructure Resilience: Planning for Future Extreme...SMART Seminar Series: "Infrastructure Resilience: Planning for Future Extreme...
SMART Seminar Series: "Infrastructure Resilience: Planning for Future Extreme...
 
SMART Seminar Series: "Potential use of drones for infrastructure inspection ...
SMART Seminar Series: "Potential use of drones for infrastructure inspection ...SMART Seminar Series: "Potential use of drones for infrastructure inspection ...
SMART Seminar Series: "Potential use of drones for infrastructure inspection ...
 
SMART Seminar Series: "A journey in the zoo of Turing patterns: the topology ...
SMART Seminar Series: "A journey in the zoo of Turing patterns: the topology ...SMART Seminar Series: "A journey in the zoo of Turing patterns: the topology ...
SMART Seminar Series: "A journey in the zoo of Turing patterns: the topology ...
 
SMART Seminar Series: "Human behaviour modelling and simulation for crisis ma...
SMART Seminar Series: "Human behaviour modelling and simulation for crisis ma...SMART Seminar Series: "Human behaviour modelling and simulation for crisis ma...
SMART Seminar Series: "Human behaviour modelling and simulation for crisis ma...
 
SMART Seminar Series: "Dealing with uncertainty: With the observer in the loo...
SMART Seminar Series: "Dealing with uncertainty: With the observer in the loo...SMART Seminar Series: "Dealing with uncertainty: With the observer in the loo...
SMART Seminar Series: "Dealing with uncertainty: With the observer in the loo...
 
SMART Seminar Series: "Smart Cities: The Good, The Bad & The Ugly"
SMART Seminar Series: "Smart Cities: The Good, The Bad & The Ugly"SMART Seminar Series: "Smart Cities: The Good, The Bad & The Ugly"
SMART Seminar Series: "Smart Cities: The Good, The Bad & The Ugly"
 
SMART Seminar Series: "How to improve the order of evolutionary models in age...
SMART Seminar Series: "How to improve the order of evolutionary models in age...SMART Seminar Series: "How to improve the order of evolutionary models in age...
SMART Seminar Series: "How to improve the order of evolutionary models in age...
 
SMART Seminar Series: "OneM2M – Towards end-to-end interoperability of the IoT"
SMART Seminar Series: "OneM2M – Towards end-to-end interoperability of the IoT"SMART Seminar Series: "OneM2M – Towards end-to-end interoperability of the IoT"
SMART Seminar Series: "OneM2M – Towards end-to-end interoperability of the IoT"
 
SMART Seminar Series: "Blue-Green vs. Grey-Black infrastructure – which is be...
SMART Seminar Series: "Blue-Green vs. Grey-Black infrastructure – which is be...SMART Seminar Series: "Blue-Green vs. Grey-Black infrastructure – which is be...
SMART Seminar Series: "Blue-Green vs. Grey-Black infrastructure – which is be...
 

Último

Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 

Último (20)

Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Plant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxPlant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptx
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 
Basic Intentional Injuries Health Education
Basic Intentional Injuries Health EducationBasic Intentional Injuries Health Education
Basic Intentional Injuries Health Education
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
latest AZ-104 Exam Questions and Answers
latest AZ-104 Exam Questions and Answerslatest AZ-104 Exam Questions and Answers
latest AZ-104 Exam Questions and Answers
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 

SMART International Symposium for Next Generation Infrastructure: How do we ensure the assessment of infrastructure resilience is proportionate to the risk?

  • 1. ENDORSING PARTNERS How do we ensure the assessment of infrastructure resilience is www.isngi.org proportionate to the risk? The following are confirmed contributors to the business and policy dialogue in Sydney: • Rick Sawers (National Australia Bank) • Nick Greiner (Chairman (Infrastructure NSW) Monday, 30th September 2013: Business & policy Dialogue Tuesday 1 October to Thursday, 3rd October: Academic and Policy Dialogue Presented by: Matthew Holmes, Civil Engineering & Geosciences Newcastle University www.isngi.org
  • 2. How do we ensure the assessment of infrastructure resilience is proportionate to the risk? Matthew Holmes a, Anna Provost b, Derek Clucas b, Sean Wilkinson a a. Civil Engineering & Geosciences, Newcastle University, Newcastle-upon-Tyne, NE1 7RU b. United Utilities Plc., Lingley Mere Business Park, Warrington, WA5 3LP International Symposium for Next Generation Infrastructure Wollongong, Australia 1st October 2013 2
  • 3. Industrial Doctorate - Acknowledgements Dr. Sean Wilkinson Prof. Richard Dawson David Owen Dr. Matt Hill Anna Provost Derek Clucas Mark Jones Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk For further information; m.j.holmes@ncl.ac.uk 3
  • 5. The Risk Manager’s Challenge: Development & Infrastructure More demand More capital to invest Development Infrastructure provision Infrastructure supports development Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk For further information; m.j.holmes@ncl.ac.uk 5
  • 6. The Risk Manager’s Challenge: Vulnerability & Resilience Greater dependency on infrastructure Society is more vulnerable to failure Development permits investment Development Infrastructure provision More reliable infrastructure Infrastructure needs to be more resilient Investment treats the most salient risks Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk For further information; m.j.holmes@ncl.ac.uk 6
  • 7. The Risk Manager’s Challenge: Risk Identification Risk managers have to consider an increasing wide range of risks Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk For further information; m.j.holmes@ncl.ac.uk 7
  • 8. The Risk Manager’s Challenge: Risk Selection Photo: Kyodo/Reuters Photo: AP Managers have to consider an increasingly wide range of risks They cannot assess every risk in detail Their selection process must be robust and accountable Photo: Daily Telegraph Photo: AP Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk For further information; m.j.holmes@ncl.ac.uk 8
  • 9. Alternative approaches to selecting risks 1. Likelihood vs. Consequence 2. Subjective appraisal of uncertainty 3. Formalised appraisal of uncertainty 9
  • 11. Approaches to selecting risks: Likelihood versus Consequence High consequence risks facing the United Kingdom (after UK Cabinet Office 2010, red line added) Risks of natural hazards and major accidents (UK Cabinet Office 2012) Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk For further information; m.j.holmes@ncl.ac.uk 11
  • 12. Approaches to selecting risks: L vs. C, with uncertainty Indicative National Risks N.B. Axes reversed compared to the UK version (IPENZ 2012) Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk For further information; m.j.holmes@ncl.ac.uk 12
  • 14. Cost of obtaining information Value of information obtained The problem with highly uncertain appraisals Uncertainty Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk For further information; m.j.holmes@ncl.ac.uk 14
  • 15. Approaches to selecting risks: Subjective Appraisal of Uncertainty Risk selection based upon the uncertainty of the probability assessment (adapted from the UK Cabinet Office diagram in slide 9) Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk For further information; m.j.holmes@ncl.ac.uk 15
  • 16. Formal Appraisal of Uncertainty 16
  • 17. Approaches to selecting risks: Formalised Appraisal of Uncertainty Loss of access to PS1 P(Snow & ice) Snow & ice Loss of access to PS3 Loss of access to WwTW P(Cold weather) Cold weather Loss of power to PS1 Storms & gales Cyber attacks: infrastructure Public disorder Loss of access to PS2 P(Loss of power) Loss of power Loss of power to PS2 Loss of power to PS3 Loss of power to WwTW P(Loss of access to PS1) P(Loss of access to PS2) P(Loss of access to PS3) P(Loss of access to WwTW) P(Loss of power to PS1) P(Loss of power to PS2 P(Loss of power to PS3) P(Loss of power to WwTW) Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk For further information; m.j.holmes@ncl.ac.uk 17
  • 18. Approaches to selecting risks: Results Cold Weather Storms & Gales • High risk • Large spread of results: low precision • Medium – high risk • Probability restricted to a narrow band Cyber Attacks: Infrastructure Public Disorder • Low risk • Large uncertainty • Very low risk • Low uncertainty (only 1 failure mode) Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk For further information; m.j.holmes@ncl.ac.uk 18
  • 19. Approaches to selecting risks: Comparison with Likelihood vs. Consequence Likelihood versus Consequence 2.0 Cold Weather 1.5 1.0 Public 0.5 Disorder 0.0 0.00 Cyber Attack: Infrastructure Storms & Gales 2.0 Cold Weather 1.5 1.0 Cyber Attack: Infrastructure 0.5 Public Disorder 0.0 0.02 0.04 0.06 0.08 Mean: Probability of at least one failure • • • 2.5 Storms & Gales Mean: Flooding Volume [ML] Mean: Flooding Volume [ML] 2.5 Uncertainty versus Consequence 0.10 1.0 0.8 0.6 0.4 0.2 0.0 Coefficient of Variation: Probability of at least one failure Does the new information materially affect the selection? Is this extra information worth the extra effort? How reliable is a risk manager’s judgement? Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk For further information; m.j.holmes@ncl.ac.uk 19
  • 21. Discussion 1. Omitting uncertainty at the risk screening phase is not inherently flawed. 2. However, it misses an opportunity to justifiably eliminate some risks whose assessment adds little value. 3. Incorporating subjective information on the uncertainty over probability is more perceptive, but subjective and opaque. 4. Formalising this process reduces opacity, but the extra complexity and cost may exceed the value of the new information. Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk For further information; m.j.holmes@ncl.ac.uk 21
  • 22. Conclusion 1. The cost of assessing marginal risks We are more reliant on infrastructure We are more vulnerable to failure We need to assess increasingly marginal risks We require new methods required to select risks to assess 2. The more formal appraisal of uncertainty is interesting but flawed because: a) It does not eliminate subjectivity, just moves and exposes it. b) The effort required to do it is self-defeating, given we are looking for new ways to screen risks. 3. Therefore, the subjective appraisal looks the most promising approach. Civil Engineering and Geosciences • Cassie Building • Newcastle University • Newcastle upon Tyne • NE1 7RU • UK • www.ceg.ncl.ac.uk For further information; m.j.holmes@ncl.ac.uk 22
  • 23. Thank you References: Any questions? Cabinet Office (2013) National risk register of civil emergencies 2013 edition. London: Cabinet Office. matthew.holmes@stream-idc.net Cabinet Office (2011) Keeping the country running: natural hazards and infrastructure. London: Cabinet Office. IPNEZ (2012) A safer New Zealand: reducing our exposure to natural hazards. Wellington: IPENZ 23