RESOURCE SCHEDULING OF
RESIDENTIAL PROJECT USING
PRIMAVERA
 The main aim of this project is to study the plan
of a residential building project (G+4) and
scheduling of construction activities and
budgeting by Using suitable method of Project
management techniques (CPM,PERT) with help
of primavera software.
AIM OF PROJECT
 Study the basics of primavera
 Selection of project and preparation of typical plan for (G+4)
Residential building.
 Estimation of quantities
 Preparation of activity layout and calculating duration of each
activity.
 Scheduling the activities
 Preparation of WBS layout.
 Budgeting the project.
 Preparation of reports &document
Schedule of project
 1. Primavera is a tool for planner, project managers and
any person needs to plan - control a project.
 2.It is a product of primavera system in since 1982-
oracle corporation -2008(p6)
 Oracle's Primavera P6 Enterprise Project Management
is the most powerful and easy-to-use solution for
globally prioritizing, planning, managing, and executing
projects, programs.
Concept of primavera
&Oracle corporation review
 p6 is specified in managing all types of projects
small, medium & large
 Methods of Working:-
Pm is using critical path method (CPM) in
calculating project duration and floats of the activities
 It has types of charts (view/display)
Gantt Bar chart
Specified & method of working
 Construction management
 Scheduling
 Tracking
 Resources
 Man-day
 Budget
 Project: Any undertaken work is called project, it requires
resources and fund to complete. We can get some out put by
doing project.
 Ex: catering, wedding planning, construction of building,
software development.
Key words& their definitions
&uses
 The components that may be measured and controlled using
planning and scheduling software
Time
Resource
Cost
Project Planning Components&
Parameters
 Thinking & documenting what needs to be done to complete the
project
 Defining Responsibilities(AR,OW,CONTRACTER)
 Defining the phases (DP, EP, FP)
 Calculating Activity duration
 Adding the logic links between activities
 Assigning resources and cost to activities
 Define calendars
 Create a work break down structure
 Preparing work schedules
 Developing an acceptable budget
 Provide a base line which progresses is measured
Planning the project by means
 Ensuring the project is being executed according to
the plan measuring performance
 Compare the projects progress with the original plan
 Suggesting correction action when needed
 Inform the team about progress
 Identifying the improvement of performance of team
 Forecast Problems
Monitoring and controlling means:-
 The time span between the start and competition of
project. Represents the project
 life cycle which varies from few months to few years
The life cycle of project can be broadly divided into the
following:-
Project life cycle (Plc.)
 a) Formation stage / inception stage
. Feasibility studies
.Invest appraisal(budget)
.project definition
 b) Mobilization / preparation Stage
.Project Preliminary plan
.Design & drawing
.Specification and tendering(contract finalization)
.resource Mobilization
 C) Construction stage / Execution stage
. Planning & controlling execution
.Inducting Resources
.Construction
.Final handing over to the client
Project updating cycle
cre
THE PROGRAM CAN BE SEE IN
PRIMAVERA SOFTWARE IN
PRACTICALY

Más contenido relacionado

La actualidad más candente

Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
saurabmi2
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
Aravind Samala
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Charlie Jackson
 

La actualidad más candente (20)

Construction project management
Construction project managementConstruction project management
Construction project management
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
 
Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Construction Project Management ppt
Construction Project Management pptConstruction Project Management ppt
Construction Project Management ppt
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
project time management
 project time management project time management
project time management
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
What is construction management & its Benefits?
What is construction management & its Benefits?What is construction management & its Benefits?
What is construction management & its Benefits?
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Primavara
PrimavaraPrimavara
Primavara
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
Primavera software
Primavera softwarePrimavera software
Primavera software
 

Similar a ppt for primevera

Primavera6.0
Primavera6.0Primavera6.0
Primavera6.0
niict
 

Similar a ppt for primevera (20)

IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET-  	  Planning, Scheduling, and Optimization of Labor Resources in the C...IRJET-  	  Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
 
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Primavera6.0
Primavera6.0Primavera6.0
Primavera6.0
 
Project Preparation and Management
Project Preparation and ManagementProject Preparation and Management
Project Preparation and Management
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
 
Primavera P6
Primavera P6Primavera P6
Primavera P6
 
Enterprise Project Management using Primavera P6 EPPM
Enterprise Project Management using Primavera P6 EPPMEnterprise Project Management using Primavera P6 EPPM
Enterprise Project Management using Primavera P6 EPPM
 
A Software For Project Management Process
A Software For Project Management ProcessA Software For Project Management Process
A Software For Project Management Process
 
MIS Project management
MIS Project managementMIS Project management
MIS Project management
 
Tools & Techniques.pptx
Tools & Techniques.pptxTools & Techniques.pptx
Tools & Techniques.pptx
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
 
Project Management : Project Planning by iFour Technolab Pvt. Ltd.
Project Management : Project Planning by iFour Technolab Pvt. Ltd.Project Management : Project Planning by iFour Technolab Pvt. Ltd.
Project Management : Project Planning by iFour Technolab Pvt. Ltd.
 
Project typed
Project typedProject typed
Project typed
 
]project-open[ OSS Project Mangement
]project-open[ OSS Project Mangement]project-open[ OSS Project Mangement
]project-open[ OSS Project Mangement
 
Project Management
Project ManagementProject Management
Project Management
 
Project Management
Project ManagementProject Management
Project Management
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 

ppt for primevera

  • 1. RESOURCE SCHEDULING OF RESIDENTIAL PROJECT USING PRIMAVERA
  • 2.  The main aim of this project is to study the plan of a residential building project (G+4) and scheduling of construction activities and budgeting by Using suitable method of Project management techniques (CPM,PERT) with help of primavera software. AIM OF PROJECT
  • 3.  Study the basics of primavera  Selection of project and preparation of typical plan for (G+4) Residential building.  Estimation of quantities  Preparation of activity layout and calculating duration of each activity.  Scheduling the activities  Preparation of WBS layout.  Budgeting the project.  Preparation of reports &document Schedule of project
  • 4.  1. Primavera is a tool for planner, project managers and any person needs to plan - control a project.  2.It is a product of primavera system in since 1982- oracle corporation -2008(p6)  Oracle's Primavera P6 Enterprise Project Management is the most powerful and easy-to-use solution for globally prioritizing, planning, managing, and executing projects, programs. Concept of primavera &Oracle corporation review
  • 5.  p6 is specified in managing all types of projects small, medium & large  Methods of Working:- Pm is using critical path method (CPM) in calculating project duration and floats of the activities  It has types of charts (view/display) Gantt Bar chart Specified & method of working
  • 6.  Construction management  Scheduling  Tracking  Resources  Man-day  Budget  Project: Any undertaken work is called project, it requires resources and fund to complete. We can get some out put by doing project.  Ex: catering, wedding planning, construction of building, software development. Key words& their definitions &uses
  • 7.  The components that may be measured and controlled using planning and scheduling software Time Resource Cost Project Planning Components& Parameters
  • 8.  Thinking & documenting what needs to be done to complete the project  Defining Responsibilities(AR,OW,CONTRACTER)  Defining the phases (DP, EP, FP)  Calculating Activity duration  Adding the logic links between activities  Assigning resources and cost to activities  Define calendars  Create a work break down structure  Preparing work schedules  Developing an acceptable budget  Provide a base line which progresses is measured Planning the project by means
  • 9.  Ensuring the project is being executed according to the plan measuring performance  Compare the projects progress with the original plan  Suggesting correction action when needed  Inform the team about progress  Identifying the improvement of performance of team  Forecast Problems Monitoring and controlling means:-
  • 10.  The time span between the start and competition of project. Represents the project  life cycle which varies from few months to few years The life cycle of project can be broadly divided into the following:- Project life cycle (Plc.)
  • 11.  a) Formation stage / inception stage . Feasibility studies .Invest appraisal(budget) .project definition  b) Mobilization / preparation Stage .Project Preliminary plan .Design & drawing .Specification and tendering(contract finalization) .resource Mobilization  C) Construction stage / Execution stage . Planning & controlling execution .Inducting Resources .Construction .Final handing over to the client
  • 13. cre
  • 14.
  • 15.
  • 16.
  • 17.
  • 18.
  • 19.
  • 20. THE PROGRAM CAN BE SEE IN PRIMAVERA SOFTWARE IN PRACTICALY