Introduction to SAP Project Systems
PS Training
Trainer Mr.Soumya De
Designation PS Functional Lead
Target Audience
This course is intended for the following audiences:
Project teams
SAP Consultants
Objectives
At the completion of this course, Participants
should be able to:
understand the Overview of SAP Project System Module
Understand Project System structures.
Understand the Projects Life Cycle for
Internal projects
External projects
Understand Operative data for projects.
Understand Planning and Budgeting activities against projects.
Understand Material and Service value flows.
Become familiar with project integration points.
Become familiar with periodic settlements & closure related steps.
Become familiar with year end processes.
Understand the various Project Finance Reports in the system.
Lesson 0: Introduction
Lesson 1: Project Structures
Lesson 2: Project Planning
Lesson 3: Project Budgeting
Contents
Lesson 4: Scheduling & Execution
Table of contents
Lesson 5: Project Period End Closing
Lesson 6: Project Analysis & Reporting
Lesson 7: Other SAP Proj. Mgt. Tools
Introduction - Project Systems
What is a Project?
A temporary endeavor undertaken to create an unique product or service, as a result
that a company carries out, characterized by the uniqueness of its general conditions
and constraints. These conditions include,
Objectives of the project
Time frame for executing it
Financial and capacity-related restrictions
SAP PS
SAP PS is a project management tool that assists you throughout all the phases of
your project. Through the high level of integration between SAP PS and other SAP
functions, such as Logistics, Accounting, and Human Resources, SAP PS ensures
that the necessary business processes are handled quickly and efficiently.
Projects usually involve cross-
departmental and highly complex
business processes.
Projects are often cost-intensive, time-
consuming, and of strategic importance.
Project
Constraints
Introduction - Project Systems
Project Types
Internal Projects
Projects financed internally with in the Organization for their New, Expansions, Overheads,
R&D and so on. These project types are:
Overhead Cost Projects (Ex: Maintenance, shutdown and R&D projects)
Capital Investment Projects (Ex: Building a factory, Expanding existing facility)
External Projects
executing/undertaking Organization.
Customer Projects (Ex: Building a Cell Tower, building roads and Bridges etc)
Key Functions:
To carry out complex, unique, and high degree of risk
activities in a structured manner.
To monitor dates and schedules.
To monitor costs and revenues.
To Control of budget .
To trigger Billing schedules, cash flow plans.
Resource allocation and monitoring.
To monitor, track and control Project purchases.
To monitor the Project progress w.r.t. Cost, Time,
Revenue and % of completion.
Simulations and Flexible reporting
Introduction -
Introduction -
Comparison with Other Applications:
Flexibility of PS making its use more common
Flexibility to Operate Higher level with in the
Organization.
Flexibility in integrating with other external
applications.
PS has very tight integration with the FI/CO modules
FI/CO has a much broader usage on projects.
Flexible Reporting and Monitoring tools
Tight integration with new generation Project Management
tools
Introduction -
Project System Org. Structure Elements
The Project System has no organizational structures of its own. Various elements
already defined in Accounting and Logistics will be used in Projects. These
elements will be assigned to various Project Structure elements. Required
elements are:
Controlling Area
Business Area if defined
Company Code
Profit Centre
Plant
Currency
Technical Location/Equipment
Responsible Cost Center
Investment Program
Joint Venture
Jurisdiction Code
Purchase Organization
Purchase Group
Storage Location
Investment Project Process
Production Administration Maintenance
I M
Inv. Prog
Approval
Budgeting
Implementation
Retirement
Replacement
investment
Planning
Idea
Appropriation
Request
Investment
Measure
-
Business Planning
Settlement and
capitalization
Maintenance
and use
PS
Customer Project Process ( ETO)
Create Quotation
Create Sales Order
SD
Create Enquiry
Proj. Planning
Budgeting &
Approvals
Procurement
Settlement
Project Close
Proj. Creation
Proj. Execution
Delivery
PS
Billing & Invoicing
Customer Project Process - Construction
Create Project
Enquiry to Proj.
Create Enquiry
PS
.
. . .
.
.
.
.
.
. .
Standard WBS
Standard Network
Concept & Product
Development
Schedule Project
Vendor Quotations
Price Comparison
Make Or Buy
BuyMake
Assign Mat to Proj.
Proj. Simulation
Create PO
GR
Create Sale Order
Create Billing &
Invoice Plan
Release Project
Production Order
Execute Order
Confirm Order
GR for Order
Release Execution
Delivery & Billing
Project Close
PP MMSD
Integration Functions With Other Modules
-Sales promotion
Proj
-Sales Campaign
- ETO process
- Milestone Billing
- Stocks
- reservations
- Material issue
- Material Value
- Direct Capitalization
- Invoice receipt
- Revenue recognition
- Person Responsible
- Workflow
- Partner functions
- Confirmation with
personnel number
-Capitalisation
- Depreciation
- AuC
- Asset balances
- Financial Statements
- Purchasing
- Contract
- Goods receipt
- Invoice receipt
- Assembly
processing
- IM Program
- Position ID
- AR
- Budget Distribution
- Proj. Creation
- Internal Order
controlling
- Settlement
- Cost Centre
accounting
- Settlement CC
SD
MM
FI
CO IM
PP
MM
AM
HR
Project Systems
Project Structure
History
PS
- Order Creation
- Planning
- Budgeting
- Order Cost control
- AuC, Fixed Asset
P
M
.
. . .
.
.
.
.
.
. .
Lesson 0: Introduction
Lesson 1: Project Structures
Lesson 2: Project Planning
Lesson 3: Project Budgeting
Contents
Lesson 4: Scheduling & Execution
Table of contents
Lesson 5: Project Period End Closing
Lesson 6: Project Analysis & Reporting
Lesson 7: Other SAP Proj. Mgt. Tools
To carry end to end process of a project, the project goals must be defined and activities
to be carried out must be structured. A clearly defined structured project is the basis for
its planning, monitoring, control and success.
Project Structures
Depending on the type of project and the monitoring needs, projects in the Project System can be
structured using:
Work breakdown structure (WBS)
We can use either Operative Projects or Standard projects for structuring the Project. Standard
WBS and standard networks allow you to standardize and reuse structures and sequences of
events in a project.
Networks/Activities
Unit Contents
Work Breakdown Structure
Networks
Activities
Milestones
Standard Work Breakdown Structures
Standard Networks
Project Builder
Planning Board
Structure Planning
Project Structures
Work Breakdown Structure
WBS Elements
A work breakdown structure is a model of a project, and
shows the project activities to be carried out as a hierarchical
structure there by split the project into manageable units. You
can define WBS hierarchy based on:
Logic and Process oriented
Function Oriented
Object Oriented
WBS divides the project step-by-step into structure elements, these elements are called
work breakdown structure elements (WBS Elements). The various work packages in the
project are described in individual work breakdown structure elements (WBS elements).
You can further divide these elements at various levels until you reach the level of detail
you require.
Project Definitions
Work Breakdown Structures
WBS Elements
Project Definitions
Project Definition and Work Breakdown Structure
Structure of a Project
Project Definition
CP-0001
Cell Tower
WBS Element
CP-0001
CP-0001- 1
Engineering
CP-0001- 2
Procurement
CP-0001- 3
Erection
CP-0001- 4
Acceptance
CP-0001- 1 - 1
Civil
CP-0001- 1 - 2
Mechanical
CP-0001- 2 - 1
PSU
CP-0001- 2 - 2
Electronic
CP-0001-2 -3
Cabin
Work Breakdown
Structure
Cell tower Construction
Confirmation
Goods Issue
Resource usage
Basic Dates
Scheduled Dates
Actual Dates
Original Budget
Budget Updates
Release Budgets
Availability Control
Purchase Requisition
Purchase Order
Dates:
Budget:
Commitments:
Execution:
Planned Costs/Revenues
Actual costs/Revenue
Costs & Revenues:
Overheads
Settlement
Earned Value Analysis
Periodic Processing:
Breakdown Structures used for?
Work Breakdown Structure
Prerequisites for WBS creation:
Project profile
Project Coding mask
Project Definition
Data for WBS elements:
Basic Data
Project Responsibilities
Organization Data
Control Data
Documents
Project Summarization Data
Settlement Rules
Tax Depreciation Simulation Data
Assets Under Construction
Capital Investment Measures
Control
Field Key
Simulation
Status Profile
Validation
Substitution
Controlling
Object Class
Planner Profile
Budget Profile
Settlement Profile
investment Profile
Planning Board / Dates
WBS Scheduling
Planning Board Profile
Hierarchy Graphic
Network Profile
Capacity req Planning
Organization
Controlling Area
Company Code
Business Area
Profit center
Plant
Proj Currency
Project Profile
Project Profile
Project Coding Mask
Special Characters for Projects
Length
of
Coding
Length
control
Entry
Tool
Entry
Tool
Coded
Proj only
Auto
Number
Assignm
ent
Coding Mask
Lock
Operative
structure
Lock
Standard
structure
I
Key 0 = number
X= Alphanumerical
Project Definition
Project Definition
Project definition: It is a framework for a business undertaking with a fixed goal to achieve
with given resources. It contains dates and organizational information that are binding for the
entire project.
Project Definition Description
Person Responsible
Applicant number
Organization units
Dates
Data for WBS elements
12
3
4
5
6
1. Operative indicators
2. Responsibilities
3. Org. Assignments
4. Controlling Profiles
5. WBS Dates
6. User Fields
Project Creation Methods
Project Builder
Hierarchy Graphic
Incorporate
Copy
Manual
= Operative Structure
= Standard Structure
1 2
3
4
Project Creation
Using Project Builder
Current
project
Selected
Object
Overviews of
selected Object
Detailed screen for
Selected Object
Work List &
Templates
Templates and Work Breakdown Structures
XX-9999 CP-0001
CX- 9999-01 CX-9999-02 CP-0001-01
Template Operative
CP-0001-02
Start
Finish
Include
Template
1 1
1.01 1.02 1.01
Template Operative
1.02
Include Template
CRTD
CRTD CRTD
CRTD CRTD CRTD CRTD
PREL
PREL REL
CRTD REL REL REL
What is Status control used for?
To allow or Block certain business
transactions.
How?
Status are activated manually or
automatically by the system.
Which elements?
Project definition and WBS
elements are affected.
Why system and user status?
User status adds detail to the
system Status.
System Status & User Status Control
System Status
SYSTEM STATUS
The following status are set by the system/user as the project progress through
different stages:
CRTD Created (Automatic)
REL Released (Manual)
LKD Locked (Manual)
UNLK Unlock (Manual)
BUDG Project Budgeted (Automatic)
AVAC Availability Control Activated (Automatic)
A status set by the user to complement the system status for a given status object. You can
use only a user status belonging to a status profile (defined in Customizing) and assigned to
the relevant status object.
User statuses enable you to extend the control of business processes managed by the
system status. You can set and delete user statuses manually when carrying out business
transactions.
WBS User Status
In the following steps you add the system status provided by SAP to your user status.
You can define a user status for:
Project_definitions
WBS elements
Network headers and network activities
Created (CRTD)
Use
Initial system status for new WBS elements
Allows project structuring, date and cost planning.
Allows Budgeting
Prerequisites
The superior WBS element MUST have status Created
Released (REL)
Use
Allows costs and revenues to be posted to the project
Passed onto lower level WBS elements
Prerequisites
Created must have been set
CREATED
RELEASED
System Status (1)
Technically Complete (TECO)
Use
For projects completed from a technical point of view.
Allows costs and revenues to be posted to the project.
Prerequisites
Created or Released must have been set.
Closed (CLSD)
Use
Prevents actual postings.
Prevents network creation.
Prerequisites
Released or Technically complete must have been set.
TECHNICALLY COMPLETE
FLAGGED FOR DELETION
CLOSED
Deletion Flag (DLFL)
Use
Objects are deleted logically, but not physically.
Prerequisites
Allowed if all costs have been settled completely.
Allowed if there are no reservations or commitments.
System Status (2)
Demo & Exercises
Menu path: Logistics Project System Project CJ20N
Project Builder
Transaction: CJ20N
Menu path: Logistics Project System Information System
Structures Individual Overviews WBS Elements
S_ALR_87015066 WBS Elements
Transaction: S_ALR_87015066
Menu path: SAP Customizing Implementation Guide Project
System Operative Structures Work Breakdown Structure
(WBS) Create Project Profile
Transaction: OPSA
Networks and Activities
Network / Activities
Networks
A network represents the flow of a project or of a task within a
project.
During the life of a project, networks are used as a basis for planning,
analyzing, controlling and monitoring schedules, dates and resources
(such as people, machines, materials, documents and drawings). You
can assign networks to a project.
A network is a special type of work order that has the same structure
as production orders, maintenance orders, and inspection orders in
the System.
Activities
Individual tasks in the project are mapped as activities in a network.
Activities having the following characteristics:
They have a duration.
They have a defined start and a defined finish.
Resources are needed to execute them.
They incur costs.
Milestone Trend analysis
Billing Milestones
Work
Dates, Capacities
Costs
Dates
Costs
Commitments
Payments
Dates
Costs
Commitments
Payments
Purchased Parts
Overheads
Settlement
Process Costs
Dates
Costs
Payments
Activities and Networks - Functions
Internal Activity:
External Activity /
Service:
Material:
Periodic Processing:
Costs Activity:
Milestones: April
7
May
June
A network consists of the following:
Activities
Activity elements
Relationships
Networks Structure (1)
Engineering 40 Design 50 Production 60 Assembly 70 Start Up
30 Procurement
10
20 Work
Scheduling
Activity Relation shipLegend
Networks Structure (2)
External
Service
Reference Dates from Activity
Start or Finish
Activity Elements
Work
External
Costs
Service
Four Types of Activities
Internal Processing
External Processing
Costs, services
General Cost Activities
Engineering Assembly
Activity Relation shipLegend
Sub Networks
Production Start Up
Settlement Rule
Profit Center
Other data
Sub Network
Network
Network Field Requirements
1
2
3
4
5
6
7
8
1. Network No and Description
2. Dates
3. Scheduling Parameters
4. Allocation (Header or Activity)
5. Assignment to Org Elements
6. MRP relevant control
7. Costing base from Profile
8. Purchase Requisition Control
Network Graphic Details
Activity
number
Control
key
Duration
Description
Earliest
finish
Latest
finishFloats
Relationship
Activity
Resource Planning
External
External Processing
Internal Processing
Labor requirements
Capacity requirements
Materials
Documents, PS Texts
Milestones
W
Documents Materials
Internal
PS Texts Milestones
Activities
Activity No
Control Key
Assignment
Work Related
Execution
factor
Execution
Constraints
assignments
External
Activity
Activity to which the
milestone is
assigned
Parameter for
Progress Analysis
Parameter for
planned date in
relation to activity
Manual
planned date
Unique Milestone
number
Milestone Data
Network Settings
Network
Network Types
Network Profile
Parameters for
Network Types
Settlement Profile
Status Profile
Number range
Planning Element
Classification Control
Planner Group
Procurement Indicator
Field Key
Graphic Profiles
Activity Parameters
External Activity
Internal Activity
Cost Activity
Service Activity
Settlement strategy
Release Strategy
Plan Cost Variant
Actual Cost Variant
Assignment type
PS-PP integration
Change Document control
Valid Receivers
Allocation Structure
Source Structure
PA transfer Structure
% of settlement
No of Distribution rules Allowed
Status number
Authorization Key
Business Transaction control
Stock Priority
PR for Network along with Resv.
Item Category
Change Profile Activity Change control
Activity Element Change Control
Component Change control
PRT change Control
Costing Types
Costing Variant
Cost Component Structure
Costing Variants to Network Types
Message Types
Network Assignment
WBS & Network comparison
WBS1
WBS1.1 WBS1.2
WBS1.1.1 WBS1.1.2 WBS1.2.1 WBS1.2.2
10
30
20
40 Network
WBS
Cost Control and Reporting
Reflects Ownership
Hierarchical Structuring
NETWORK
Work Control
Reflects Execution Process
Spread across Different WBS
elements
Activities Assignment to WBS Elements
WBS1
WBS1.1 WBS1.2
WBS1.1.1 WBS1.1.2 WBS1.2.1 WBS1.2.2
10
30
20
40 Network
Planning dates
Planning Costs
Settlement rules
Milestones
Billing Plans
Network Creation Methods
Project Builder
Network Structure
Graphic
= Operative Structure
= Standard Structure
2
Manual
1
Copy 3
Incorporate 4
Copy Project Incl. Activities
5
Network Creation
Click & Hold
Drop here
Result
Click & Hold
Drop here
Result
Activity Creation
Activity Element Creation
Click & Hold
Drop here
Result
Demo & Exercises
Menu path: Logistics Project System Project
CJ20N Project Builder
Transaction: CJ20N
Standard Structures
Be defining standard projects and networks you can standardize project management
referring back to data that has been derived from existing projects. Standardization is one
method of ensuring in the initial phase that projects are structured efficiently and
economically. A further advantage of standardizing project structures is that it makes the
processing of projects more transparent, enables the comparison of projects and
subsequently facilitates project controlling.
In the Project System there are several different standard structures that you can use as
templates to create operative structures.
Standard project definitions
Standard networks
Standard work breakdown structures
Standard milestones
Standard Structures (Cont..)
Standard project definitions
Neutral project definition, which can be used to create operative project definitions or
standard project definitions as templates. Project definitions are the frameworks of
projects and contains basic Organizational data i. e.
Controlling Area
Business area
Company code
Plant
Factory calendar
Standard networks
Project-neutral network structure, which can be used as a template when creating other
standard networks or operative networks. Creating operative networks by using standard
networks will save the time and increase the consistency of business process.
You can link standard networks with standard work breakdown structures in order to
create project templates, which contain both the project structure and the activities
assigned to the structure.
From Standard Networks
While creating operative network using standard
network, if the standard Network is linked to standard
WBS, system will create operative WBS as well.
1
From Sale order
2
Creating operative network from Sales Order using
standard Network, system will create operative Network
with activities as standard Network and materials from
sales order.
From milestone
3
Creating operative Milestone from
standard milestone system will create
operative network from Standard Network
which is attached to standard Milestone.
= Operative Structure
= Standard Structure
= Direct Assignment
= indirect Assignment
Standard Structures (Cont..)
Standard work breakdown structures
Neutral work breakdown structure that can be used more than once and serves as a
template for creating operative work breakdown structures
From Standard WBS
While creating operative WBS from standard WBS,
if WBS is linked with standard network, system
will not create operative network
2WBS From Standard Networks
While creating operative network using standard
network, if the standard Network is linked to standard
WBS, system will create operative WBS as well.
1
Standard milestones
Standard milestones are used for creating milestones and other standard milestones.
You can combine different standard Milestones in a milestone group.
From milestone
3
Standard Structures (Cont..)
The Project Builder is a user-friendly method of accessing the Project System, which
enables you to edit your projects quickly and efficiently.
It gives the option of Context sensitive menus, Drag & Drop, and the capability to define
your own worklist and templates pool.
Use:
Create, change or display all project structure data in one transaction
Graphic views (hierarchy and network graphic)
Project planning board with all its overviews (capacity, costs, component, and
maintenance order overviews)
Can define a user-specific worklist and a user-specific templates pool
Can make user-specific changes to the settings
Project Builder
Project Builder
Structure
Tree
Worklist and
Templates
Work Area
Selected Project
& Project Tree
Worklists &
templates
Proj. Definition
and Structure
Work Area
Worklists and Templates
Planning Board
Entry Area
Worklist Preview Of
last Project
Gantt Chart
Over view buttons
WBS structure
Templates & individual
objects
Hierarchy Graphic
Gantt Chart
Network Graphic
Business Graphic
Graphics of Planning Board
Structure Planning
Structure planning will be used if you have a more precise idea of the structure of the project.
Using structure planning you can enter WBS elements and Activities together. Structure
planning is having two views i.e.
WBS elements
Network activities
Use:
Create Projects and activities
Maintain already created projects
Analysis
Capacity leveling
Cost overviews as for activities
Structure Planning (Cont..)
WBS element View
Network View
Demo & Exercises
Menu path: Logistics Project System Project
CJ20N Project Builder
Transaction: CJ20N
Menu path: Logistics Project System Project
CJ27 Project Planning Board
Transaction: CJ27, CJ2B and CJ2C
Menu path: Logistics Project System Project
Special Maintenance Functions CJ2D
Structure Planning
Transaction: CJ2D, CJ20 and CJ2A
Lesson Summary
Project Header
WBS structure
Networks
Sub networks
Activities
Activity Elements
Standard structures
Standard Networks
Standard milestones
Project builder
Project Planning Board
Network Graphic
Project coding mask
Project profiles
Reference links
1. http://help.sap.com/saphelp_46c/helpdata/en/04/926eae46f3
11d189470000e829fbbd/frameset.htm

Más contenido relacionado

La actualidad más candente

sap-ps-project-systems
 sap-ps-project-systems sap-ps-project-systems
sap-ps-project-systemshollabackgirl1
 
Project Systems
Project SystemsProject Systems
Project Systemschalah
 
Rohit demo sap ps_module_training
Rohit demo sap ps_module_trainingRohit demo sap ps_module_training
Rohit demo sap ps_module_trainingmultimediasunil
 
Sap ps training material
Sap ps training materialSap ps training material
Sap ps training materialSoumya De
 
Ps user manual
Ps user manualPs user manual
Ps user manualSoumya De
 
PS Module Overview
PS Module OverviewPS Module Overview
PS Module Overviewitplant
 
SAP Training ( PS , Material PR , Service PR ,Cost Planning , Budgeting , PO...
SAP Training ( PS , Material PR , Service PR ,Cost Planning , Budgeting ,  PO...SAP Training ( PS , Material PR , Service PR ,Cost Planning , Budgeting ,  PO...
SAP Training ( PS , Material PR , Service PR ,Cost Planning , Budgeting , PO...Soumya De
 
Sap auc internal orders as investment measures
Sap auc internal orders as investment measuresSap auc internal orders as investment measures
Sap auc internal orders as investment measuresSURESH BABU MUCHINTHALA
 
SAP Project Management
SAP Project ManagementSAP Project Management
SAP Project ManagementKumar M.
 
Ps project manager 2013
Ps project manager 2013Ps project manager 2013
Ps project manager 2013Subhash reddy1
 
Project system overview
Project system overviewProject system overview
Project system overviewAmlan Sarkar
 
2007 how to use sap project system for revenue recognition in professional se...
2007 how to use sap project system for revenue recognition in professional se...2007 how to use sap project system for revenue recognition in professional se...
2007 how to use sap project system for revenue recognition in professional se...Soumya De
 
Project Systems: Materials
Project Systems: MaterialsProject Systems: Materials
Project Systems: Materialsvnhardik
 
Sap solutions presentation
Sap solutions presentationSap solutions presentation
Sap solutions presentationKumar M.
 
Presentation on resource related billing
Presentation on resource related billingPresentation on resource related billing
Presentation on resource related billingAmlan Sarkar
 
Budget upload process in SAP PS
Budget upload process in SAP PSBudget upload process in SAP PS
Budget upload process in SAP PSgovil79
 

La actualidad más candente (20)

sap-ps-project-systems
 sap-ps-project-systems sap-ps-project-systems
sap-ps-project-systems
 
SAP PS Intro
SAP PS IntroSAP PS Intro
SAP PS Intro
 
Project Systems
Project SystemsProject Systems
Project Systems
 
Rohit demo sap ps_module_training
Rohit demo sap ps_module_trainingRohit demo sap ps_module_training
Rohit demo sap ps_module_training
 
Sap ps training material
Sap ps training materialSap ps training material
Sap ps training material
 
Ps user manual
Ps user manualPs user manual
Ps user manual
 
PS Module Overview
PS Module OverviewPS Module Overview
PS Module Overview
 
SAP Training ( PS , Material PR , Service PR ,Cost Planning , Budgeting , PO...
SAP Training ( PS , Material PR , Service PR ,Cost Planning , Budgeting ,  PO...SAP Training ( PS , Material PR , Service PR ,Cost Planning , Budgeting ,  PO...
SAP Training ( PS , Material PR , Service PR ,Cost Planning , Budgeting , PO...
 
SAP Project Systems with Success Factors
SAP Project Systems with Success FactorsSAP Project Systems with Success Factors
SAP Project Systems with Success Factors
 
Sap auc internal orders as investment measures
Sap auc internal orders as investment measuresSap auc internal orders as investment measures
Sap auc internal orders as investment measures
 
SAP PPM 6.0 powered by HANA
SAP PPM 6.0 powered by HANASAP PPM 6.0 powered by HANA
SAP PPM 6.0 powered by HANA
 
SAP Project Management
SAP Project ManagementSAP Project Management
SAP Project Management
 
Ps project manager 2013
Ps project manager 2013Ps project manager 2013
Ps project manager 2013
 
Project system overview
Project system overviewProject system overview
Project system overview
 
2007 how to use sap project system for revenue recognition in professional se...
2007 how to use sap project system for revenue recognition in professional se...2007 how to use sap project system for revenue recognition in professional se...
2007 how to use sap project system for revenue recognition in professional se...
 
Project Systems: Materials
Project Systems: MaterialsProject Systems: Materials
Project Systems: Materials
 
Balco ps user manual
Balco ps user manualBalco ps user manual
Balco ps user manual
 
Sap solutions presentation
Sap solutions presentationSap solutions presentation
Sap solutions presentation
 
Presentation on resource related billing
Presentation on resource related billingPresentation on resource related billing
Presentation on resource related billing
 
Budget upload process in SAP PS
Budget upload process in SAP PSBudget upload process in SAP PS
Budget upload process in SAP PS
 

Similar a Introduction to sap project systems

vdocument.in_sap-ps-presentation.pdf
vdocument.in_sap-ps-presentation.pdfvdocument.in_sap-ps-presentation.pdf
vdocument.in_sap-ps-presentation.pdfNethajiSathpatheNeth
 
Presentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics ProjectPresentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics ProjectSharad Srivastava
 
SAP SAP Project Systems_capabilities.pptx
SAP SAP Project Systems_capabilities.pptxSAP SAP Project Systems_capabilities.pptx
SAP SAP Project Systems_capabilities.pptxssuserad3af4
 
Lecture 3 Project Management.ppt
Lecture 3 Project Management.pptLecture 3 Project Management.ppt
Lecture 3 Project Management.pptMehediHasan636262
 
Project Management Presentation Template.pdf
Project Management Presentation Template.pdfProject Management Presentation Template.pdf
Project Management Presentation Template.pdfapoorvaguptaspn27
 
Primavera6.0
Primavera6.0Primavera6.0
Primavera6.0niict
 
Northern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentNorthern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentSiwawong Wuttipongprasert
 
Primavara
PrimavaraPrimavara
Primavaradanabl
 
PM Session 4
PM Session 4PM Session 4
PM Session 4dmdk12
 
Abel_Missier_Business Analyst_Cards
Abel_Missier_Business Analyst_CardsAbel_Missier_Business Analyst_Cards
Abel_Missier_Business Analyst_CardsAbel Missier
 
Epm dimensys introductie gvk
Epm dimensys introductie gvkEpm dimensys introductie gvk
Epm dimensys introductie gvkGlenn Van_kooijk
 
]project-open[ OSS Project Mangement
]project-open[ OSS Project Mangement]project-open[ OSS Project Mangement
]project-open[ OSS Project MangementKlaus Hofeditz
 
Bridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems pptBridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems pptp6academy
 

Similar a Introduction to sap project systems (20)

vdocument.in_sap-ps-presentation.pdf
vdocument.in_sap-ps-presentation.pdfvdocument.in_sap-ps-presentation.pdf
vdocument.in_sap-ps-presentation.pdf
 
Presentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics ProjectPresentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics Project
 
SAP SAP Project Systems_capabilities.pptx
SAP SAP Project Systems_capabilities.pptxSAP SAP Project Systems_capabilities.pptx
SAP SAP Project Systems_capabilities.pptx
 
Kogent approach
Kogent approachKogent approach
Kogent approach
 
Lecture 3 Project Management.ppt
Lecture 3 Project Management.pptLecture 3 Project Management.ppt
Lecture 3 Project Management.ppt
 
MIS Project management
MIS Project managementMIS Project management
MIS Project management
 
tcc primavera
tcc primaveratcc primavera
tcc primavera
 
Project Management Presentation Template.pdf
Project Management Presentation Template.pdfProject Management Presentation Template.pdf
Project Management Presentation Template.pdf
 
Primavera6.0
Primavera6.0Primavera6.0
Primavera6.0
 
Project management case analysis
Project management case analysisProject management case analysis
Project management case analysis
 
Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Project
 
Northern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentNorthern Finishing School: IT Project Managment
Northern Finishing School: IT Project Managment
 
Chapter 3
Chapter 3Chapter 3
Chapter 3
 
Primavara
PrimavaraPrimavara
Primavara
 
PM Session 4
PM Session 4PM Session 4
PM Session 4
 
Abel_Missier_Business Analyst_Cards
Abel_Missier_Business Analyst_CardsAbel_Missier_Business Analyst_Cards
Abel_Missier_Business Analyst_Cards
 
Epm dimensys introductie gvk
Epm dimensys introductie gvkEpm dimensys introductie gvk
Epm dimensys introductie gvk
 
]project-open[ OSS Project Mangement
]project-open[ OSS Project Mangement]project-open[ OSS Project Mangement
]project-open[ OSS Project Mangement
 
Bridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems pptBridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems ppt
 
Adi CV Tech Manager
Adi CV Tech ManagerAdi CV Tech Manager
Adi CV Tech Manager
 

Más de Soumya De

Activate Methodology
Activate MethodologyActivate Methodology
Activate MethodologySoumya De
 
S/4 HANA Hand Written Notes
S/4 HANA Hand Written NotesS/4 HANA Hand Written Notes
S/4 HANA Hand Written NotesSoumya De
 
SWOT-Analysis
SWOT-AnalysisSWOT-Analysis
SWOT-AnalysisSoumya De
 
SWOT-Analysis_PPT
SWOT-Analysis_PPTSWOT-Analysis_PPT
SWOT-Analysis_PPTSoumya De
 
SWOT ANALYSIS
SWOT ANALYSISSWOT ANALYSIS
SWOT ANALYSISSoumya De
 
Excel Fundamentals
Excel Fundamentals Excel Fundamentals
Excel Fundamentals Soumya De
 
Methodologies in Project Management
Methodologies in Project ManagementMethodologies in Project Management
Methodologies in Project ManagementSoumya De
 
Agile Course Presentation
Agile Course PresentationAgile Course Presentation
Agile Course PresentationSoumya De
 
What Is DevOps?
What Is DevOps?What Is DevOps?
What Is DevOps?Soumya De
 
Product Management
Product ManagementProduct Management
Product ManagementSoumya De
 
Scrum Guide & SAFe Agile booklet
Scrum Guide & SAFe Agile bookletScrum Guide & SAFe Agile booklet
Scrum Guide & SAFe Agile bookletSoumya De
 
Changes Between Different Versions Scrum Guides
Changes Between Different Versions Scrum GuidesChanges Between Different Versions Scrum Guides
Changes Between Different Versions Scrum GuidesSoumya De
 
PMP GLOSSARY
PMP GLOSSARYPMP GLOSSARY
PMP GLOSSARYSoumya De
 
Agile Processes - Scrum
Agile Processes - ScrumAgile Processes - Scrum
Agile Processes - ScrumSoumya De
 
Microsoft Azure
Microsoft AzureMicrosoft Azure
Microsoft AzureSoumya De
 
Sap S4 HANA Everything You Need To Know
Sap S4 HANA Everything You Need To Know Sap S4 HANA Everything You Need To Know
Sap S4 HANA Everything You Need To Know Soumya De
 
PMP APPLICATION FILLING TIPS AND PMBOK GUIDE REVESION SLIDES WITH FEW TIPS ...
PMP APPLICATION FILLING TIPS AND PMBOK GUIDE REVESION SLIDES WITH FEW TIPS ...PMP APPLICATION FILLING TIPS AND PMBOK GUIDE REVESION SLIDES WITH FEW TIPS ...
PMP APPLICATION FILLING TIPS AND PMBOK GUIDE REVESION SLIDES WITH FEW TIPS ...Soumya De
 
Ps configuration manual
Ps configuration manualPs configuration manual
Ps configuration manualSoumya De
 
Sap S/4 HANA New Implementation
Sap S/4 HANA New ImplementationSap S/4 HANA New Implementation
Sap S/4 HANA New ImplementationSoumya De
 
User status profile
User status profileUser status profile
User status profileSoumya De
 

Más de Soumya De (20)

Activate Methodology
Activate MethodologyActivate Methodology
Activate Methodology
 
S/4 HANA Hand Written Notes
S/4 HANA Hand Written NotesS/4 HANA Hand Written Notes
S/4 HANA Hand Written Notes
 
SWOT-Analysis
SWOT-AnalysisSWOT-Analysis
SWOT-Analysis
 
SWOT-Analysis_PPT
SWOT-Analysis_PPTSWOT-Analysis_PPT
SWOT-Analysis_PPT
 
SWOT ANALYSIS
SWOT ANALYSISSWOT ANALYSIS
SWOT ANALYSIS
 
Excel Fundamentals
Excel Fundamentals Excel Fundamentals
Excel Fundamentals
 
Methodologies in Project Management
Methodologies in Project ManagementMethodologies in Project Management
Methodologies in Project Management
 
Agile Course Presentation
Agile Course PresentationAgile Course Presentation
Agile Course Presentation
 
What Is DevOps?
What Is DevOps?What Is DevOps?
What Is DevOps?
 
Product Management
Product ManagementProduct Management
Product Management
 
Scrum Guide & SAFe Agile booklet
Scrum Guide & SAFe Agile bookletScrum Guide & SAFe Agile booklet
Scrum Guide & SAFe Agile booklet
 
Changes Between Different Versions Scrum Guides
Changes Between Different Versions Scrum GuidesChanges Between Different Versions Scrum Guides
Changes Between Different Versions Scrum Guides
 
PMP GLOSSARY
PMP GLOSSARYPMP GLOSSARY
PMP GLOSSARY
 
Agile Processes - Scrum
Agile Processes - ScrumAgile Processes - Scrum
Agile Processes - Scrum
 
Microsoft Azure
Microsoft AzureMicrosoft Azure
Microsoft Azure
 
Sap S4 HANA Everything You Need To Know
Sap S4 HANA Everything You Need To Know Sap S4 HANA Everything You Need To Know
Sap S4 HANA Everything You Need To Know
 
PMP APPLICATION FILLING TIPS AND PMBOK GUIDE REVESION SLIDES WITH FEW TIPS ...
PMP APPLICATION FILLING TIPS AND PMBOK GUIDE REVESION SLIDES WITH FEW TIPS ...PMP APPLICATION FILLING TIPS AND PMBOK GUIDE REVESION SLIDES WITH FEW TIPS ...
PMP APPLICATION FILLING TIPS AND PMBOK GUIDE REVESION SLIDES WITH FEW TIPS ...
 
Ps configuration manual
Ps configuration manualPs configuration manual
Ps configuration manual
 
Sap S/4 HANA New Implementation
Sap S/4 HANA New ImplementationSap S/4 HANA New Implementation
Sap S/4 HANA New Implementation
 
User status profile
User status profileUser status profile
User status profile
 

Último

Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenHervé Boutemy
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Patryk Bandurski
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piececharlottematthew16
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embeddingZilliz
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Wonjun Hwang
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 

Último (20)

Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache Maven
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piece
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embedding
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 

Introduction to sap project systems

  • 1. Introduction to SAP Project Systems PS Training Trainer Mr.Soumya De Designation PS Functional Lead
  • 2. Target Audience This course is intended for the following audiences: Project teams SAP Consultants
  • 3. Objectives At the completion of this course, Participants should be able to: understand the Overview of SAP Project System Module Understand Project System structures. Understand the Projects Life Cycle for Internal projects External projects Understand Operative data for projects. Understand Planning and Budgeting activities against projects. Understand Material and Service value flows. Become familiar with project integration points. Become familiar with periodic settlements & closure related steps. Become familiar with year end processes. Understand the various Project Finance Reports in the system.
  • 4. Lesson 0: Introduction Lesson 1: Project Structures Lesson 2: Project Planning Lesson 3: Project Budgeting Contents Lesson 4: Scheduling & Execution Table of contents Lesson 5: Project Period End Closing Lesson 6: Project Analysis & Reporting Lesson 7: Other SAP Proj. Mgt. Tools
  • 5. Introduction - Project Systems What is a Project? A temporary endeavor undertaken to create an unique product or service, as a result that a company carries out, characterized by the uniqueness of its general conditions and constraints. These conditions include, Objectives of the project Time frame for executing it Financial and capacity-related restrictions SAP PS SAP PS is a project management tool that assists you throughout all the phases of your project. Through the high level of integration between SAP PS and other SAP functions, such as Logistics, Accounting, and Human Resources, SAP PS ensures that the necessary business processes are handled quickly and efficiently. Projects usually involve cross- departmental and highly complex business processes. Projects are often cost-intensive, time- consuming, and of strategic importance. Project Constraints
  • 6. Introduction - Project Systems Project Types Internal Projects Projects financed internally with in the Organization for their New, Expansions, Overheads, R&D and so on. These project types are: Overhead Cost Projects (Ex: Maintenance, shutdown and R&D projects) Capital Investment Projects (Ex: Building a factory, Expanding existing facility) External Projects executing/undertaking Organization. Customer Projects (Ex: Building a Cell Tower, building roads and Bridges etc)
  • 7. Key Functions: To carry out complex, unique, and high degree of risk activities in a structured manner. To monitor dates and schedules. To monitor costs and revenues. To Control of budget . To trigger Billing schedules, cash flow plans. Resource allocation and monitoring. To monitor, track and control Project purchases. To monitor the Project progress w.r.t. Cost, Time, Revenue and % of completion. Simulations and Flexible reporting Introduction -
  • 8. Introduction - Comparison with Other Applications: Flexibility of PS making its use more common Flexibility to Operate Higher level with in the Organization. Flexibility in integrating with other external applications. PS has very tight integration with the FI/CO modules FI/CO has a much broader usage on projects. Flexible Reporting and Monitoring tools Tight integration with new generation Project Management tools
  • 9. Introduction - Project System Org. Structure Elements The Project System has no organizational structures of its own. Various elements already defined in Accounting and Logistics will be used in Projects. These elements will be assigned to various Project Structure elements. Required elements are: Controlling Area Business Area if defined Company Code Profit Centre Plant Currency Technical Location/Equipment Responsible Cost Center Investment Program Joint Venture Jurisdiction Code Purchase Organization Purchase Group Storage Location
  • 10. Investment Project Process Production Administration Maintenance I M Inv. Prog Approval Budgeting Implementation Retirement Replacement investment Planning Idea Appropriation Request Investment Measure - Business Planning Settlement and capitalization Maintenance and use PS
  • 11. Customer Project Process ( ETO) Create Quotation Create Sales Order SD Create Enquiry Proj. Planning Budgeting & Approvals Procurement Settlement Project Close Proj. Creation Proj. Execution Delivery PS Billing & Invoicing
  • 12. Customer Project Process - Construction Create Project Enquiry to Proj. Create Enquiry PS . . . . . . . . . . . Standard WBS Standard Network Concept & Product Development Schedule Project Vendor Quotations Price Comparison Make Or Buy BuyMake Assign Mat to Proj. Proj. Simulation Create PO GR Create Sale Order Create Billing & Invoice Plan Release Project Production Order Execute Order Confirm Order GR for Order Release Execution Delivery & Billing Project Close PP MMSD
  • 13. Integration Functions With Other Modules -Sales promotion Proj -Sales Campaign - ETO process - Milestone Billing - Stocks - reservations - Material issue - Material Value - Direct Capitalization - Invoice receipt - Revenue recognition - Person Responsible - Workflow - Partner functions - Confirmation with personnel number -Capitalisation - Depreciation - AuC - Asset balances - Financial Statements - Purchasing - Contract - Goods receipt - Invoice receipt - Assembly processing - IM Program - Position ID - AR - Budget Distribution - Proj. Creation - Internal Order controlling - Settlement - Cost Centre accounting - Settlement CC SD MM FI CO IM PP MM AM HR Project Systems Project Structure History PS - Order Creation - Planning - Budgeting - Order Cost control - AuC, Fixed Asset P M . . . . . . . . . . .
  • 14. Lesson 0: Introduction Lesson 1: Project Structures Lesson 2: Project Planning Lesson 3: Project Budgeting Contents Lesson 4: Scheduling & Execution Table of contents Lesson 5: Project Period End Closing Lesson 6: Project Analysis & Reporting Lesson 7: Other SAP Proj. Mgt. Tools
  • 15. To carry end to end process of a project, the project goals must be defined and activities to be carried out must be structured. A clearly defined structured project is the basis for its planning, monitoring, control and success. Project Structures Depending on the type of project and the monitoring needs, projects in the Project System can be structured using: Work breakdown structure (WBS) We can use either Operative Projects or Standard projects for structuring the Project. Standard WBS and standard networks allow you to standardize and reuse structures and sequences of events in a project. Networks/Activities
  • 16. Unit Contents Work Breakdown Structure Networks Activities Milestones Standard Work Breakdown Structures Standard Networks Project Builder Planning Board Structure Planning Project Structures
  • 17. Work Breakdown Structure WBS Elements A work breakdown structure is a model of a project, and shows the project activities to be carried out as a hierarchical structure there by split the project into manageable units. You can define WBS hierarchy based on: Logic and Process oriented Function Oriented Object Oriented WBS divides the project step-by-step into structure elements, these elements are called work breakdown structure elements (WBS Elements). The various work packages in the project are described in individual work breakdown structure elements (WBS elements). You can further divide these elements at various levels until you reach the level of detail you require.
  • 18. Project Definitions Work Breakdown Structures WBS Elements Project Definitions Project Definition and Work Breakdown Structure
  • 19. Structure of a Project Project Definition CP-0001 Cell Tower WBS Element CP-0001 CP-0001- 1 Engineering CP-0001- 2 Procurement CP-0001- 3 Erection CP-0001- 4 Acceptance CP-0001- 1 - 1 Civil CP-0001- 1 - 2 Mechanical CP-0001- 2 - 1 PSU CP-0001- 2 - 2 Electronic CP-0001-2 -3 Cabin Work Breakdown Structure Cell tower Construction
  • 20. Confirmation Goods Issue Resource usage Basic Dates Scheduled Dates Actual Dates Original Budget Budget Updates Release Budgets Availability Control Purchase Requisition Purchase Order Dates: Budget: Commitments: Execution: Planned Costs/Revenues Actual costs/Revenue Costs & Revenues: Overheads Settlement Earned Value Analysis Periodic Processing: Breakdown Structures used for?
  • 21. Work Breakdown Structure Prerequisites for WBS creation: Project profile Project Coding mask Project Definition Data for WBS elements: Basic Data Project Responsibilities Organization Data Control Data Documents Project Summarization Data Settlement Rules Tax Depreciation Simulation Data Assets Under Construction Capital Investment Measures
  • 22. Control Field Key Simulation Status Profile Validation Substitution Controlling Object Class Planner Profile Budget Profile Settlement Profile investment Profile Planning Board / Dates WBS Scheduling Planning Board Profile Hierarchy Graphic Network Profile Capacity req Planning Organization Controlling Area Company Code Business Area Profit center Plant Proj Currency Project Profile Project Profile
  • 23. Project Coding Mask Special Characters for Projects Length of Coding Length control Entry Tool Entry Tool Coded Proj only Auto Number Assignm ent Coding Mask Lock Operative structure Lock Standard structure I Key 0 = number X= Alphanumerical
  • 24. Project Definition Project Definition Project definition: It is a framework for a business undertaking with a fixed goal to achieve with given resources. It contains dates and organizational information that are binding for the entire project. Project Definition Description Person Responsible Applicant number Organization units Dates
  • 25. Data for WBS elements 12 3 4 5 6 1. Operative indicators 2. Responsibilities 3. Org. Assignments 4. Controlling Profiles 5. WBS Dates 6. User Fields
  • 26. Project Creation Methods Project Builder Hierarchy Graphic Incorporate Copy Manual = Operative Structure = Standard Structure 1 2 3 4
  • 27. Project Creation Using Project Builder Current project Selected Object Overviews of selected Object Detailed screen for Selected Object Work List & Templates
  • 28. Templates and Work Breakdown Structures XX-9999 CP-0001 CX- 9999-01 CX-9999-02 CP-0001-01 Template Operative CP-0001-02
  • 29. Start Finish Include Template 1 1 1.01 1.02 1.01 Template Operative 1.02 Include Template
  • 30. CRTD CRTD CRTD CRTD CRTD CRTD CRTD PREL PREL REL CRTD REL REL REL What is Status control used for? To allow or Block certain business transactions. How? Status are activated manually or automatically by the system. Which elements? Project definition and WBS elements are affected. Why system and user status? User status adds detail to the system Status. System Status & User Status Control
  • 31. System Status SYSTEM STATUS The following status are set by the system/user as the project progress through different stages: CRTD Created (Automatic) REL Released (Manual) LKD Locked (Manual) UNLK Unlock (Manual) BUDG Project Budgeted (Automatic) AVAC Availability Control Activated (Automatic)
  • 32. A status set by the user to complement the system status for a given status object. You can use only a user status belonging to a status profile (defined in Customizing) and assigned to the relevant status object. User statuses enable you to extend the control of business processes managed by the system status. You can set and delete user statuses manually when carrying out business transactions. WBS User Status In the following steps you add the system status provided by SAP to your user status. You can define a user status for: Project_definitions WBS elements Network headers and network activities
  • 33. Created (CRTD) Use Initial system status for new WBS elements Allows project structuring, date and cost planning. Allows Budgeting Prerequisites The superior WBS element MUST have status Created Released (REL) Use Allows costs and revenues to be posted to the project Passed onto lower level WBS elements Prerequisites Created must have been set CREATED RELEASED System Status (1)
  • 34. Technically Complete (TECO) Use For projects completed from a technical point of view. Allows costs and revenues to be posted to the project. Prerequisites Created or Released must have been set. Closed (CLSD) Use Prevents actual postings. Prevents network creation. Prerequisites Released or Technically complete must have been set. TECHNICALLY COMPLETE FLAGGED FOR DELETION CLOSED Deletion Flag (DLFL) Use Objects are deleted logically, but not physically. Prerequisites Allowed if all costs have been settled completely. Allowed if there are no reservations or commitments. System Status (2)
  • 35. Demo & Exercises Menu path: Logistics Project System Project CJ20N Project Builder Transaction: CJ20N Menu path: Logistics Project System Information System Structures Individual Overviews WBS Elements S_ALR_87015066 WBS Elements Transaction: S_ALR_87015066 Menu path: SAP Customizing Implementation Guide Project System Operative Structures Work Breakdown Structure (WBS) Create Project Profile Transaction: OPSA
  • 36. Networks and Activities Network / Activities Networks A network represents the flow of a project or of a task within a project. During the life of a project, networks are used as a basis for planning, analyzing, controlling and monitoring schedules, dates and resources (such as people, machines, materials, documents and drawings). You can assign networks to a project. A network is a special type of work order that has the same structure as production orders, maintenance orders, and inspection orders in the System. Activities Individual tasks in the project are mapped as activities in a network. Activities having the following characteristics: They have a duration. They have a defined start and a defined finish. Resources are needed to execute them. They incur costs.
  • 37. Milestone Trend analysis Billing Milestones Work Dates, Capacities Costs Dates Costs Commitments Payments Dates Costs Commitments Payments Purchased Parts Overheads Settlement Process Costs Dates Costs Payments Activities and Networks - Functions Internal Activity: External Activity / Service: Material: Periodic Processing: Costs Activity: Milestones: April 7 May June
  • 38. A network consists of the following: Activities Activity elements Relationships Networks Structure (1) Engineering 40 Design 50 Production 60 Assembly 70 Start Up 30 Procurement 10 20 Work Scheduling Activity Relation shipLegend
  • 39. Networks Structure (2) External Service Reference Dates from Activity Start or Finish Activity Elements Work External Costs Service Four Types of Activities Internal Processing External Processing Costs, services General Cost Activities
  • 40. Engineering Assembly Activity Relation shipLegend Sub Networks Production Start Up Settlement Rule Profit Center Other data Sub Network Network
  • 41. Network Field Requirements 1 2 3 4 5 6 7 8 1. Network No and Description 2. Dates 3. Scheduling Parameters 4. Allocation (Header or Activity) 5. Assignment to Org Elements 6. MRP relevant control 7. Costing base from Profile 8. Purchase Requisition Control
  • 43. Resource Planning External External Processing Internal Processing Labor requirements Capacity requirements Materials Documents, PS Texts Milestones W Documents Materials Internal PS Texts Milestones
  • 44. Activities Activity No Control Key Assignment Work Related Execution factor Execution Constraints assignments External Activity
  • 45. Activity to which the milestone is assigned Parameter for Progress Analysis Parameter for planned date in relation to activity Manual planned date Unique Milestone number Milestone Data
  • 46. Network Settings Network Network Types Network Profile Parameters for Network Types Settlement Profile Status Profile Number range Planning Element Classification Control Planner Group Procurement Indicator Field Key Graphic Profiles Activity Parameters External Activity Internal Activity Cost Activity Service Activity Settlement strategy Release Strategy Plan Cost Variant Actual Cost Variant Assignment type PS-PP integration Change Document control Valid Receivers Allocation Structure Source Structure PA transfer Structure % of settlement No of Distribution rules Allowed Status number Authorization Key Business Transaction control Stock Priority PR for Network along with Resv. Item Category Change Profile Activity Change control Activity Element Change Control Component Change control PRT change Control Costing Types Costing Variant Cost Component Structure Costing Variants to Network Types Message Types Network Assignment
  • 47. WBS & Network comparison WBS1 WBS1.1 WBS1.2 WBS1.1.1 WBS1.1.2 WBS1.2.1 WBS1.2.2 10 30 20 40 Network WBS Cost Control and Reporting Reflects Ownership Hierarchical Structuring NETWORK Work Control Reflects Execution Process Spread across Different WBS elements
  • 48. Activities Assignment to WBS Elements WBS1 WBS1.1 WBS1.2 WBS1.1.1 WBS1.1.2 WBS1.2.1 WBS1.2.2 10 30 20 40 Network Planning dates Planning Costs Settlement rules Milestones Billing Plans
  • 49. Network Creation Methods Project Builder Network Structure Graphic = Operative Structure = Standard Structure 2 Manual 1 Copy 3 Incorporate 4 Copy Project Incl. Activities 5
  • 50. Network Creation Click & Hold Drop here Result
  • 51. Click & Hold Drop here Result Activity Creation
  • 52. Activity Element Creation Click & Hold Drop here Result
  • 53. Demo & Exercises Menu path: Logistics Project System Project CJ20N Project Builder Transaction: CJ20N
  • 54. Standard Structures Be defining standard projects and networks you can standardize project management referring back to data that has been derived from existing projects. Standardization is one method of ensuring in the initial phase that projects are structured efficiently and economically. A further advantage of standardizing project structures is that it makes the processing of projects more transparent, enables the comparison of projects and subsequently facilitates project controlling. In the Project System there are several different standard structures that you can use as templates to create operative structures. Standard project definitions Standard networks Standard work breakdown structures Standard milestones
  • 55. Standard Structures (Cont..) Standard project definitions Neutral project definition, which can be used to create operative project definitions or standard project definitions as templates. Project definitions are the frameworks of projects and contains basic Organizational data i. e. Controlling Area Business area Company code Plant Factory calendar Standard networks Project-neutral network structure, which can be used as a template when creating other standard networks or operative networks. Creating operative networks by using standard networks will save the time and increase the consistency of business process. You can link standard networks with standard work breakdown structures in order to create project templates, which contain both the project structure and the activities assigned to the structure.
  • 56. From Standard Networks While creating operative network using standard network, if the standard Network is linked to standard WBS, system will create operative WBS as well. 1 From Sale order 2 Creating operative network from Sales Order using standard Network, system will create operative Network with activities as standard Network and materials from sales order. From milestone 3 Creating operative Milestone from standard milestone system will create operative network from Standard Network which is attached to standard Milestone. = Operative Structure = Standard Structure = Direct Assignment = indirect Assignment Standard Structures (Cont..)
  • 57. Standard work breakdown structures Neutral work breakdown structure that can be used more than once and serves as a template for creating operative work breakdown structures From Standard WBS While creating operative WBS from standard WBS, if WBS is linked with standard network, system will not create operative network 2WBS From Standard Networks While creating operative network using standard network, if the standard Network is linked to standard WBS, system will create operative WBS as well. 1 Standard milestones Standard milestones are used for creating milestones and other standard milestones. You can combine different standard Milestones in a milestone group. From milestone 3 Standard Structures (Cont..)
  • 58. The Project Builder is a user-friendly method of accessing the Project System, which enables you to edit your projects quickly and efficiently. It gives the option of Context sensitive menus, Drag & Drop, and the capability to define your own worklist and templates pool. Use: Create, change or display all project structure data in one transaction Graphic views (hierarchy and network graphic) Project planning board with all its overviews (capacity, costs, component, and maintenance order overviews) Can define a user-specific worklist and a user-specific templates pool Can make user-specific changes to the settings Project Builder
  • 59. Project Builder Structure Tree Worklist and Templates Work Area Selected Project & Project Tree Worklists & templates Proj. Definition and Structure Work Area
  • 61. Planning Board Entry Area Worklist Preview Of last Project Gantt Chart Over view buttons WBS structure Templates & individual objects
  • 62. Hierarchy Graphic Gantt Chart Network Graphic Business Graphic Graphics of Planning Board
  • 63. Structure Planning Structure planning will be used if you have a more precise idea of the structure of the project. Using structure planning you can enter WBS elements and Activities together. Structure planning is having two views i.e. WBS elements Network activities Use: Create Projects and activities Maintain already created projects Analysis Capacity leveling Cost overviews as for activities
  • 64. Structure Planning (Cont..) WBS element View Network View
  • 65. Demo & Exercises Menu path: Logistics Project System Project CJ20N Project Builder Transaction: CJ20N Menu path: Logistics Project System Project CJ27 Project Planning Board Transaction: CJ27, CJ2B and CJ2C Menu path: Logistics Project System Project Special Maintenance Functions CJ2D Structure Planning Transaction: CJ2D, CJ20 and CJ2A
  • 66. Lesson Summary Project Header WBS structure Networks Sub networks Activities Activity Elements Standard structures Standard Networks Standard milestones Project builder Project Planning Board Network Graphic Project coding mask Project profiles