This document provides instructions for laying heavy duty cement concrete flooring in three layers: a sub-base, base course layer 35mm thick, and a wearing top/finishing layer 15mm thick. It details the materials, equipment, and procedures required, including batching ratios for the concrete mixes and application techniques. Recommendations are provided for placement, finishing, joints, curing and ensuring the proper level, slope and linearity of the finished floor.
10. Sensitivity: LNT Construction Internal Use
1 Hardener
4 Cement
1 : 4
Weight Batching
1 : 2
Volume Batching
1 Hardener –Cement Mix
2 Stone grit (6mm down)
11. Sensitivity: LNT Construction Internal Use
Application of neat cement slurry
@ 2.75Kg. of cement per m2.
Applied by brush
12. Sensitivity: LNT Construction Internal Use
• Mitred joints at the corners
• Straight line at intermediate
with panel joints
13. Sensitivity: LNT Construction Internal Use
Cement concrete shall be placed in position and
beaten with trowel and finished smooth.
Beating shall cease as soon as surface is found
covered with cream of mortar.
14. Sensitivity: LNT Construction Internal Use
The mixture so obtained shall then be
laid on the base course within 2 to 4
hours of latter's laying
15. Sensitivity: LNT Construction Internal Use
After the starting of initial setting, the
surface shall be finished smooth and true
with steel floats