Johnwoods Street Closure – Summary Response
The following provides a summary of the major questions asked at the Public Information
Meeting on May 4th
, 2016 and the responses.
1. What was the Approval Process for Fairwinds West Subdivision and Johnwoods Street?
 Mattamy applied for a Plan of Subdivision at 33 Johnwoods Street in November 2007
 The statutory Public Meeting, per the Planning Act for this Plan of Subdivision was held
on March 21st
, 2008.
 Johnwoods Street closure formed a part of this public meeting and discussion
 The subdivision was placed on hold due to area-wide servicing constraints associated
with the Carp River from 2008 to 2012.
 The traffic study for the subdivision was updated in June 2013, a specific report on
Johnwoods Street was provided as an addendum to document the traffic impact
resulting from the closure. The impact on the existing and proposed road network was
deemed to be negligible.
 The Ward Councillor (Shad Qadri) declared a conflict of interest in Fall of 2013.
 Fairwinds West Subdivision was approved by the Manager of Suburban Services,
Development Review under Delegated Authority in October 2013 with the concurrence
of the Chair and Vice-Chair of Planning Committee, which included the closure of
Johnwoods Street as a condition.
 Notice of the decision, along with conditions of draft approval, were circulated to all
parties who attended the public meeting or whom had provided comments throughout
the process, per Planning Act requirements. This notice also included information on
appeal rights to the Ontario Municipal Board.
 No appeals were received, and the draft approval took effect November 26th, 2013.
 A notification and concept were posted to the public information portal for this
subdivision on the City of Ottawa website.
 The City conducted a technical circulation to internal City departments including
transportation and right-of-ways and received technical concurrence to proceed with
closure, per Condition 32(a) of the Agreement.
 The Subdivision Agreement was registered in February 2015.
 The public information meeting, held on May 4th, 2016, was with respect to Condition
#32(b) of the Subdivision Agreement.
2. When was the final decision made to close Johnwoods to vehicle traffic?
 The timeline notes that the decision to close Johnwoods Street to vehicle traffic was
made at time of draft approval, following the discussions through the approval process
of the plan of subdivision.
 The internal technical circulation within city departments and external agencies
between draft approval and registration confirmed that Johnwoods closure would be
acceptable operationally, and with minimal traffic impact on the existing and future
communities. Indeed, the traffic evaluation indicated there would be a benefit from
reduced cut-through traffic.
 Between Draft Approval in November 2013 and Registration of the subdivision
agreement in February 2015, the City still retained an opportunity to entirely reconsider
the closure if major concerns were identified through the circulation.
 Following draft approval, the intent was to have Mattamy go through a concept design
with community input on the future look, function and timing of the repurposed
roadway conversion.
 As no appeals or comments had been received on the draft approval of the subdivision
at large and impacts were considered minor in nature and primarily on future residents,
and similar closures have been welcomed in other neighbourhoods, the planning
department moved forward on registration and did not prioritize the circling back with
the existing community to provide an advisory meeting between draft approval and
registration, as had been suggested to the community and the Councillor.
 After the subdivision was registered in February 2015, staff recognized that there
remained a need to circle back with the community on what the look, function and
timing would be of the multi-use pathway corridor going forward into implementation.
 It was not clearly recognized that there would be such opposition to the closure from
the existing residents. This was an error for which the planning department apologizes.
 Staff continue to advise that the closure of Johnwoods will provide a positive benefit to
the existing and future communities through reducing cut-through traffic and restoring
a local road network, and through provision of additional community open space and
improvement of a poorly used corridor.
 However, staff also accept responsibility for the lack of communication on the process,
and failure to discuss the forthcoming plans for Johnwoods with residents until such a
late date.
3. What is the benefit to existing and future residents by closing Johnwoods?
 Johnwoods is operating as a cut-through route for traffic through the community, and is
not operating in a local road capacity. Closing this section of Johnwoods removes the
direct route for cut-through traffic, reduces speeds, and pushes traffic to the major road
network.
 At the time of the public notification and consultation for this application, the City had
received comments from many residents regarding concerns about volume and speed
of traffic on Johnwoods Street.
 At the time, the issues stemmed from an underdeveloped road network, because key
roads identified in the Kanata West Concept Plan had not been constructed, resulting in
Johnwoods Street becoming an attractive route for cut-through traffic between
Hazeldean Road and Maple Grove Road.
 Since then, the construction of Huntmar Drive and the widening of Hazeldean Road
have brought improvements to the street network and reduced dependence on
Johnwoods Street.
 Because a new collector road in the subdivision, east of Johnwoods Street, would serve
as the collector road between Rosehill Avenue and Maple Grove Road, there would be
minimal impact on local streets in the Bryanston Gate neighbourhood.
 The proposed multi-use pathway in the Johnwoods Street road allowance would reduce
traffic volumes on the southerly part of the street and provide an improved connection
for pedestrians and cyclists in the community.
 Closing this section to vehicle traffic provides a community benefit, additional useable
open space and amenity to the existing and future residents of the area.
 The corridor as it stands is a sub-standard portion of roadway that is unsightly and
would require significant municipal expense to bring to minor collector standards.
 Mattamy is conditioned to develop this design, decommission existing infrastructure
and provide landscaping to City standards at their sole cost and responsibility.
 Johnwoods is identified as a cycling route in the Ottawa Cycling Plan, with an ultimate
connection north to the future Kanata West District Park. The Johnwoods multi-use
pathway conversion is a step towards achieving this connection.
4. What is the timeline for opening Maple Grove to Stittsville Main Street?
 Maple Grove is intended to be part of the local street network, and not part of the
major road network. As such, the construction of this is a function of the development
of adjacent land parcels that will ultimately require access for roads and services.
 Connecting Stittsville Main Street ahead of the extension to Highway 417 will result in a
significant increase of traffic on Stittsville Main Street and Maple Grove.
 Stittsville Main Street is designated as a major collector, and is part of the major road
network for the City. It is intended to be extended north to Highway 417 in Phase 3 of
the Transportation Master Plan (2025-2031) with exact timing depending upon
development occurring in the Kanata West Town Centre area.
 Future traffic increases on Maple Grove, with or without a connection to Stittsville Main
Street, will need to be coordinated with improvements to the intersection at Maple
Grove and Huntmar. This intersection is currently proposed for upgrading after 2018.
5. When will Johnwoods be closed to vehicle traffic?
 Condition 4(g)(iv) of the subdivision agreement notes that closure of Johnwoods will not
occur until Santolina Street and Rosehill Avenue are constructed and are open to
vehicular traffic. Planning staff interpret this to mean Rosehill open from Johnwoods to
Huntmar.
 Santolina is now open for public use. Rosehill is dependent upon the construction
schedule of Poole Creek Village, and is anticipated to be complete and open for public
use in early 2017.
 Construction of Johnwoods conversion to a multi-use pathway would occur once these
roads are open.
 Discussions with Mattamy as to the exact timing are with respect to the level of
acceptable construction activity on Rosehill, such that the route is indeed available as a
direct, viable and attractive connection for the new traffic pattern. This includes full
provision of all sidewalks and substantial completion of all fronting homes on Rosehill
and Santolina Streets.
6. What traffic analysis was done for the Fairwinds subdivision and Johnwoods closure?
 Traffic data and analysis for subdivision applications are based upon City of Ottawa
Traffic Impact Assessment Guidelines, and Institute of Transportation Engineers (ITE)
Manual 8, updated from time to time.
 Traffic counts are collected annually on the major road network (arterials and major
collectors) and on an as-needed basis for local roads. Traffic counts were collected at
Hazeldean and Johnwoods as part of the Fairwinds Subdivision application.
 Traffic moving to and from the Queensway is considered to be the function of the Major
Road Network. Johnwoods is not part of the major road network.
 Johnwoods and Rosehill are considered to be part of the local street network system
and are classified as minor collectors.
 Minor collectors are designed to only provide service to local streets and direct traffic
from immediately adjacent neighbourhoods to the major road network.
 The major and minor road network is re-evaluated every 5 years through updates to the
Transportation Master Plan, which forms part of the Official Plan of the City of Ottawa.
7. Is the design for the section of Johnwoods to be closed finalized?
 Yes, aspects of the design can change with input from the community. The concept at
this stage is a high-level concept, and was a preliminary proposal.
 The refined concept plan would be circulated to the Councillor’s office for comment and
community input on the design.
 This will not be a formal park as this will continue to be a City right-of-way, under the
ownership of the City. However, the maintenance and look-and-feel will be to the
standard that the City looks for in park designs.
 While Mattamy is conditioned to decommission existing infrastructure and construct a
multi-use pathway and landscaping to City standards at their sole cost and
responsibility, the City retains the option to supplement the design with further
amenities as may be suggested, with the understanding that any additional works would
be at the cost to the City and not Mattamy and subject to funding availability.
8. What is the traffic impact on the existing community?
 Johnwoods is operating as a cut-through route for traffic from outside the community,
and is not operating in a local road capacity. Closing this section of Johnwoods removes
the direct route for cut-through traffic, reduces speeds, and pushes traffic to the major
road network.
 A traffic analysis has been conducted by Stantec Consulting Ltd. as an addendum to the
Community Transportation Impact Study, and demonstrates that an additional 50
vehicles per hour will be diverted to the Rosehill minor collector. This is projected to be
far below the carrying capacity of this roadway, even after Fairwinds West and Poole
Creek Village are fully built and occupied.
 No significant traffic movement from closure of Johnwoods is considered to pass
through Bryanston Gate via Alon Street. The shortest travel path between Maple Grove
Road and Hazeldean Road will be via Huntmar Drive or through the Fairwinds / Poole
Creek communities – not through the Bryanston Gate community.
 Rosehill is designed as a minor collector between Johnwoods Street and Huntmar Drive,
and will be the most attractive route for motorists who chose not to use the Hazeldean
Road / Huntmar major road network.
9. Why not keep Johnwoods open?
 Johnwoods is operating as a cut-through route for traffic through the community, and is
not operating in a local road capacity.
 Leaving Johnwoods open will continue to offer an attractive direct route for cut-through
traffic from Hazeldean to Maple Grove, not in keeping with the local network
designation of this road. This would increase as development occurs on the vacant land
parcels north of Maple Grove, as is proposed in the Kanata West Concept Plan.
 The proposal to close Johnwoods went through a technical circulation of all affected City
departments and was deemed to be acceptable.
 Closing this section of Johnwoods removes the direct route for cut-through traffic,
reduces speeds, and pushes traffic to the major road network. This shifts Johnwoods to
a local level of service, in keeping with the Kanata West Concept Plan.
10. Where has the City closed other roads and done similar conversions?
 The City has closed other collectors for conversion into multi-use paths and community
open space. This includes Richardson Side Road, from Kanata Avenue to Terry Fox Drive.
 The former alignment of Strandherd Drive in Barrhaven was converted from a major
road to a local road, and ultimately, to linear open space and pathways from 2009 to
today. New multi-use pathways and parks spaces created from the decommissioned
road include include Fraser Fields Parkette, and Harthill Way Linear Park.
 There has been no negative impact on adjacent homes and local roads. These are now
seen as community assets.
 In future, the City will be closing the Greenbank Road alignment in Barrhaven South and
converting the right-of-way and bridge into a multi-use pathway upon construction of
the new Greenbank Road alignment.
11. What are the Next Steps?
 Mattamy is required to prepare a refined Concept Plan, including a decommissioning
report for all necessary roads infrastructures.
 The Concept Plan will be circulated for final review and approval by internal city
agencies (accessibility, forestry, parks, buildings, ground services etc.) and circulated to
the Ward Councillor for comment and community input on the design.
 Following approval of the Concept Plan, detailed design drawings (landscaping, utilities
plans etc.) are to be developed by Mattamy, and provided for internal circulation and
review by City departments.
 A traffic management plan will be prepared, and public notification and signage will be
posted to notify of a change in traffic patterns ahead of the closure. This will include any
identified mitigation measures, signage and traffic calming required on existing roads
(Alon Street), and may include monitoring before and after implementation to ensure
future traffic patterns match the proposal.
 Dependent upon the above municipal approvals and opening of Rosehill Avenue as a
viable route, construction on the Johnwoods multi-use path corridor would occur in
summer 2017.

Más contenido relacionado

La actualidad más candente

Remove oma+amo boards
Remove oma+amo boardsRemove oma+amo boards
Remove oma+amo boardsGardinerEast
 
Replace as+gg booklet
Replace as+gg bookletReplace as+gg booklet
Replace as+gg bookletGardinerEast
 
Splost Presentation 2008
Splost Presentation 2008Splost Presentation 2008
Splost Presentation 2008Brett Deaton
 
Bgi visionfor piers7-12
Bgi visionfor piers7-12Bgi visionfor piers7-12
Bgi visionfor piers7-12jpetr0s
 
Replace west8+dtah+cbagu booklet
Replace west8+dtah+cbagu bookletReplace west8+dtah+cbagu booklet
Replace west8+dtah+cbagu bookletGardinerEast
 
BCRT Overview
BCRT OverviewBCRT Overview
BCRT Overviewtstaley
 
Medical District Trunk Line Easement on Park Property
Medical District Trunk Line Easement on Park PropertyMedical District Trunk Line Easement on Park Property
Medical District Trunk Line Easement on Park PropertyCity of College Station
 
Replace as+gg boards
Replace as+gg boardsReplace as+gg boards
Replace as+gg boardsGardinerEast
 
Public Utility Corridor in Lick Creek Park
Public Utility Corridor in Lick Creek ParkPublic Utility Corridor in Lick Creek Park
Public Utility Corridor in Lick Creek ParkCity of College Station
 
1065. genesis of footbridge design, from a community perspective radnor bri...
1065. genesis of footbridge design, from a community perspective   radnor bri...1065. genesis of footbridge design, from a community perspective   radnor bri...
1065. genesis of footbridge design, from a community perspective radnor bri...Interrelated
 
20120201 061327 multi-use_trail_bid_award
20120201 061327 multi-use_trail_bid_award20120201 061327 multi-use_trail_bid_award
20120201 061327 multi-use_trail_bid_awardSamat Jain
 
Improve dsr+aa boards
Improve dsr+aa boardsImprove dsr+aa boards
Improve dsr+aa boardsGardinerEast
 
Overpass Solution
Overpass SolutionOverpass Solution
Overpass Solutionjgabateman
 
Paldiresidentialneighborhoodpart1
Paldiresidentialneighborhoodpart1Paldiresidentialneighborhoodpart1
Paldiresidentialneighborhoodpart1Riddhi Dash
 

La actualidad más candente (20)

Remove oma+amo boards
Remove oma+amo boardsRemove oma+amo boards
Remove oma+amo boards
 
CMAA Riverwalk Presentation
CMAA Riverwalk PresentationCMAA Riverwalk Presentation
CMAA Riverwalk Presentation
 
Replace as+gg booklet
Replace as+gg bookletReplace as+gg booklet
Replace as+gg booklet
 
Splost Presentation 2008
Splost Presentation 2008Splost Presentation 2008
Splost Presentation 2008
 
Street Name Changes
Street Name ChangesStreet Name Changes
Street Name Changes
 
Bgi visionfor piers7-12
Bgi visionfor piers7-12Bgi visionfor piers7-12
Bgi visionfor piers7-12
 
Replace west8+dtah+cbagu booklet
Replace west8+dtah+cbagu bookletReplace west8+dtah+cbagu booklet
Replace west8+dtah+cbagu booklet
 
BCRT Overview
BCRT OverviewBCRT Overview
BCRT Overview
 
feb2014 3
feb2014 3feb2014 3
feb2014 3
 
Six Points Reconfiguration - Community Update June, 2014
Six Points Reconfiguration - Community Update June, 2014Six Points Reconfiguration - Community Update June, 2014
Six Points Reconfiguration - Community Update June, 2014
 
Medical District Trunk Line Easement on Park Property
Medical District Trunk Line Easement on Park PropertyMedical District Trunk Line Easement on Park Property
Medical District Trunk Line Easement on Park Property
 
Replace as+gg boards
Replace as+gg boardsReplace as+gg boards
Replace as+gg boards
 
Public Utility Corridor in Lick Creek Park
Public Utility Corridor in Lick Creek ParkPublic Utility Corridor in Lick Creek Park
Public Utility Corridor in Lick Creek Park
 
Pic 2 panels june 23 2015
Pic 2 panels june 23 2015Pic 2 panels june 23 2015
Pic 2 panels june 23 2015
 
Public Meeting #2 Information Materials
Public Meeting #2 Information MaterialsPublic Meeting #2 Information Materials
Public Meeting #2 Information Materials
 
1065. genesis of footbridge design, from a community perspective radnor bri...
1065. genesis of footbridge design, from a community perspective   radnor bri...1065. genesis of footbridge design, from a community perspective   radnor bri...
1065. genesis of footbridge design, from a community perspective radnor bri...
 
20120201 061327 multi-use_trail_bid_award
20120201 061327 multi-use_trail_bid_award20120201 061327 multi-use_trail_bid_award
20120201 061327 multi-use_trail_bid_award
 
Improve dsr+aa boards
Improve dsr+aa boardsImprove dsr+aa boards
Improve dsr+aa boards
 
Overpass Solution
Overpass SolutionOverpass Solution
Overpass Solution
 
Paldiresidentialneighborhoodpart1
Paldiresidentialneighborhoodpart1Paldiresidentialneighborhoodpart1
Paldiresidentialneighborhoodpart1
 

Similar a Planning Department Response to Primary Questions re: Johnwoods

Stantec Johnwoods street closure memo, March 2016
Stantec Johnwoods street closure memo, March 2016Stantec Johnwoods street closure memo, March 2016
Stantec Johnwoods street closure memo, March 2016StittsvilleCentral.ca
 
Georgia DOT Comments Regarding State Route 53 Over Chattahoochee River At Lak...
Georgia DOT Comments Regarding State Route 53 Over Chattahoochee River At Lak...Georgia DOT Comments Regarding State Route 53 Over Chattahoochee River At Lak...
Georgia DOT Comments Regarding State Route 53 Over Chattahoochee River At Lak...Arthur Prescott
 
Planning And Decision Making In Transport Infrastructure Dev.
Planning And Decision Making In Transport Infrastructure Dev.Planning And Decision Making In Transport Infrastructure Dev.
Planning And Decision Making In Transport Infrastructure Dev.ceal2005
 
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...Maureen Kenney
 
Harbor Ring Campaign
Harbor Ring CampaignHarbor Ring Campaign
Harbor Ring CampaignNY_Bicycling
 
Center City Streetcar Info Flyer
Center City Streetcar Info FlyerCenter City Streetcar Info Flyer
Center City Streetcar Info FlyerZach Shaner
 
Campbellford Bridge Detailed Design Council Update.pdf
Campbellford Bridge Detailed Design Council Update.pdfCampbellford Bridge Detailed Design Council Update.pdf
Campbellford Bridge Detailed Design Council Update.pdfKatrinaMcCullough2
 
Honolulu land use ordinance amendment
Honolulu land use ordinance amendmentHonolulu land use ordinance amendment
Honolulu land use ordinance amendmentHonolulu Civil Beat
 
Sb s written report cjm46
Sb s written report cjm46Sb s written report cjm46
Sb s written report cjm46cjm46
 
Streetcar Report Final CP Front
Streetcar Report Final CP FrontStreetcar Report Final CP Front
Streetcar Report Final CP FrontLeumis Richardson
 

Similar a Planning Department Response to Primary Questions re: Johnwoods (20)

Stantec Johnwoods street closure memo, March 2016
Stantec Johnwoods street closure memo, March 2016Stantec Johnwoods street closure memo, March 2016
Stantec Johnwoods street closure memo, March 2016
 
Somerville Broadway Streetscape Project, CAPS comments to MassDOT, March 2011
Somerville Broadway Streetscape Project, CAPS comments to MassDOT, March 2011 Somerville Broadway Streetscape Project, CAPS comments to MassDOT, March 2011
Somerville Broadway Streetscape Project, CAPS comments to MassDOT, March 2011
 
2015_Bridge_Road
2015_Bridge_Road2015_Bridge_Road
2015_Bridge_Road
 
Georgia DOT Comments Regarding State Route 53 Over Chattahoochee River At Lak...
Georgia DOT Comments Regarding State Route 53 Over Chattahoochee River At Lak...Georgia DOT Comments Regarding State Route 53 Over Chattahoochee River At Lak...
Georgia DOT Comments Regarding State Route 53 Over Chattahoochee River At Lak...
 
Planning And Decision Making In Transport Infrastructure Dev.
Planning And Decision Making In Transport Infrastructure Dev.Planning And Decision Making In Transport Infrastructure Dev.
Planning And Decision Making In Transport Infrastructure Dev.
 
Technical Report
Technical ReportTechnical Report
Technical Report
 
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
 
Qand A meeting 2
Qand A meeting 2Qand A meeting 2
Qand A meeting 2
 
Harbor Ring Campaign
Harbor Ring CampaignHarbor Ring Campaign
Harbor Ring Campaign
 
Waterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display PanelsWaterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display Panels
 
APWA mid atlantic awards
APWA mid atlantic awardsAPWA mid atlantic awards
APWA mid atlantic awards
 
Center City Streetcar Info Flyer
Center City Streetcar Info FlyerCenter City Streetcar Info Flyer
Center City Streetcar Info Flyer
 
Campbellford Bridge Detailed Design Council Update.pdf
Campbellford Bridge Detailed Design Council Update.pdfCampbellford Bridge Detailed Design Council Update.pdf
Campbellford Bridge Detailed Design Council Update.pdf
 
Honolulu land use ordinance amendment
Honolulu land use ordinance amendmentHonolulu land use ordinance amendment
Honolulu land use ordinance amendment
 
2017 Comp Plan/UDO Review
2017 Comp Plan/UDO Review2017 Comp Plan/UDO Review
2017 Comp Plan/UDO Review
 
How the West was One Gold Rush Survival Kit
How the West was One Gold Rush Survival KitHow the West was One Gold Rush Survival Kit
How the West was One Gold Rush Survival Kit
 
Comp Plan - UDO Annual Review
Comp Plan - UDO Annual ReviewComp Plan - UDO Annual Review
Comp Plan - UDO Annual Review
 
Ntaylor_FLL_CompPlanAmendments
Ntaylor_FLL_CompPlanAmendmentsNtaylor_FLL_CompPlanAmendments
Ntaylor_FLL_CompPlanAmendments
 
Sb s written report cjm46
Sb s written report cjm46Sb s written report cjm46
Sb s written report cjm46
 
Streetcar Report Final CP Front
Streetcar Report Final CP FrontStreetcar Report Final CP Front
Streetcar Report Final CP Front
 

Más de StittsvilleCentral.ca

Bill Teron's 2010 lecture to Heritage Ottawa on Beaverbrook
Bill Teron's 2010 lecture to Heritage Ottawa on BeaverbrookBill Teron's 2010 lecture to Heritage Ottawa on Beaverbrook
Bill Teron's 2010 lecture to Heritage Ottawa on BeaverbrookStittsvilleCentral.ca
 
Kanata-Stittsville LRT Planning & EA - Open House #2
Kanata-Stittsville LRT Planning & EA - Open House #2Kanata-Stittsville LRT Planning & EA - Open House #2
Kanata-Stittsville LRT Planning & EA - Open House #2StittsvilleCentral.ca
 
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiations
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiationsMayor Jim Watson letter re: RendezVous LeBreton Group negotiations
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiationsStittsvilleCentral.ca
 
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove road
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove roadPublic Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove road
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove roadStittsvilleCentral.ca
 
Carp-Hazeldean collision data, 2011-2015
Carp-Hazeldean collision data, 2011-2015Carp-Hazeldean collision data, 2011-2015
Carp-Hazeldean collision data, 2011-2015StittsvilleCentral.ca
 
Memo - 2017 Road Resurfacing Program and Additional Resurfacing Projects
Memo - 2017 Road Resurfacing Program and Additional Resurfacing ProjectsMemo - 2017 Road Resurfacing Program and Additional Resurfacing Projects
Memo - 2017 Road Resurfacing Program and Additional Resurfacing ProjectsStittsvilleCentral.ca
 
Kanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment StudyKanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment StudyStittsvilleCentral.ca
 
Kanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment StudyKanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment StudyStittsvilleCentral.ca
 
Stittsville Fernbank Haliburton Park Concept Plan
Stittsville Fernbank Haliburton Park Concept PlanStittsville Fernbank Haliburton Park Concept Plan
Stittsville Fernbank Haliburton Park Concept PlanStittsvilleCentral.ca
 
Stittsville Fernbank Haliburton Park Concept Images
Stittsville Fernbank Haliburton Park Concept ImagesStittsville Fernbank Haliburton Park Concept Images
Stittsville Fernbank Haliburton Park Concept ImagesStittsvilleCentral.ca
 
Ontario Court of Justice - Appeal Decision April 19, 2017
Ontario Court of Justice - Appeal Decision April 19, 2017Ontario Court of Justice - Appeal Decision April 19, 2017
Ontario Court of Justice - Appeal Decision April 19, 2017StittsvilleCentral.ca
 
March 21 letter from Waste Management to City of Ottawa
March 21 letter from Waste Management to City of OttawaMarch 21 letter from Waste Management to City of Ottawa
March 21 letter from Waste Management to City of OttawaStittsvilleCentral.ca
 
Memo to council about West Carleton Environmental Centre ECA amendment
Memo to council about West Carleton Environmental Centre ECA amendmentMemo to council about West Carleton Environmental Centre ECA amendment
Memo to council about West Carleton Environmental Centre ECA amendmentStittsvilleCentral.ca
 
Cash For Trash 7628 Flewellyn - September 2016 presentation
Cash For Trash 7628 Flewellyn - September 2016 presentationCash For Trash 7628 Flewellyn - September 2016 presentation
Cash For Trash 7628 Flewellyn - September 2016 presentationStittsvilleCentral.ca
 
Potter's Key Community Information Session on January 11, 2017
Potter's Key Community Information Session on January 11, 2017Potter's Key Community Information Session on January 11, 2017
Potter's Key Community Information Session on January 11, 2017StittsvilleCentral.ca
 
Zoning application summary - Farmers' Markets
Zoning application summary - Farmers' MarketsZoning application summary - Farmers' Markets
Zoning application summary - Farmers' MarketsStittsvilleCentral.ca
 
Memo: Acquisition of Urban Natural Features (UNF)
Memo: Acquisition of Urban Natural Features (UNF)Memo: Acquisition of Urban Natural Features (UNF)
Memo: Acquisition of Urban Natural Features (UNF)StittsvilleCentral.ca
 

Más de StittsvilleCentral.ca (20)

Bill Teron's 2010 lecture to Heritage Ottawa on Beaverbrook
Bill Teron's 2010 lecture to Heritage Ottawa on BeaverbrookBill Teron's 2010 lecture to Heritage Ottawa on Beaverbrook
Bill Teron's 2010 lecture to Heritage Ottawa on Beaverbrook
 
Kanata-Stittsville LRT Planning & EA - Open House #2
Kanata-Stittsville LRT Planning & EA - Open House #2Kanata-Stittsville LRT Planning & EA - Open House #2
Kanata-Stittsville LRT Planning & EA - Open House #2
 
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiations
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiationsMayor Jim Watson letter re: RendezVous LeBreton Group negotiations
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiations
 
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove road
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove roadPublic Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove road
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove road
 
Carp-Hazeldean collision data, 2011-2015
Carp-Hazeldean collision data, 2011-2015Carp-Hazeldean collision data, 2011-2015
Carp-Hazeldean collision data, 2011-2015
 
Ottawa BIA overview
Ottawa BIA overviewOttawa BIA overview
Ottawa BIA overview
 
Ontario BIA handbook 2010
Ontario BIA handbook 2010Ontario BIA handbook 2010
Ontario BIA handbook 2010
 
Memo - 2017 Road Resurfacing Program and Additional Resurfacing Projects
Memo - 2017 Road Resurfacing Program and Additional Resurfacing ProjectsMemo - 2017 Road Resurfacing Program and Additional Resurfacing Projects
Memo - 2017 Road Resurfacing Program and Additional Resurfacing Projects
 
Kanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment StudyKanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment Study
 
Kanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment StudyKanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment Study
 
Stittsville Fernbank Haliburton Park Concept Plan
Stittsville Fernbank Haliburton Park Concept PlanStittsville Fernbank Haliburton Park Concept Plan
Stittsville Fernbank Haliburton Park Concept Plan
 
Stittsville Fernbank Haliburton Park Concept Images
Stittsville Fernbank Haliburton Park Concept ImagesStittsville Fernbank Haliburton Park Concept Images
Stittsville Fernbank Haliburton Park Concept Images
 
City of Ottawa Noise By-Law Review
City of Ottawa Noise By-Law ReviewCity of Ottawa Noise By-Law Review
City of Ottawa Noise By-Law Review
 
Ontario Court of Justice - Appeal Decision April 19, 2017
Ontario Court of Justice - Appeal Decision April 19, 2017Ontario Court of Justice - Appeal Decision April 19, 2017
Ontario Court of Justice - Appeal Decision April 19, 2017
 
March 21 letter from Waste Management to City of Ottawa
March 21 letter from Waste Management to City of OttawaMarch 21 letter from Waste Management to City of Ottawa
March 21 letter from Waste Management to City of Ottawa
 
Memo to council about West Carleton Environmental Centre ECA amendment
Memo to council about West Carleton Environmental Centre ECA amendmentMemo to council about West Carleton Environmental Centre ECA amendment
Memo to council about West Carleton Environmental Centre ECA amendment
 
Cash For Trash 7628 Flewellyn - September 2016 presentation
Cash For Trash 7628 Flewellyn - September 2016 presentationCash For Trash 7628 Flewellyn - September 2016 presentation
Cash For Trash 7628 Flewellyn - September 2016 presentation
 
Potter's Key Community Information Session on January 11, 2017
Potter's Key Community Information Session on January 11, 2017Potter's Key Community Information Session on January 11, 2017
Potter's Key Community Information Session on January 11, 2017
 
Zoning application summary - Farmers' Markets
Zoning application summary - Farmers' MarketsZoning application summary - Farmers' Markets
Zoning application summary - Farmers' Markets
 
Memo: Acquisition of Urban Natural Features (UNF)
Memo: Acquisition of Urban Natural Features (UNF)Memo: Acquisition of Urban Natural Features (UNF)
Memo: Acquisition of Urban Natural Features (UNF)
 

Último

Experience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming TrendExperience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming TrendFabwelt
 
Quiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsQuiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsnaxymaxyy
 
VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012ankitnayak356677
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkbhavenpr
 
Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkbhavenpr
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdfGerald Furnkranz
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest2
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeAbdulGhani778830
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.NaveedKhaskheli1
 

Último (10)

Experience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming TrendExperience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming Trend
 
Quiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsQuiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the rounds
 
VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
 
Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpk
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global News
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf
 
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for Justice
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.
 

Planning Department Response to Primary Questions re: Johnwoods

  • 1. Johnwoods Street Closure – Summary Response The following provides a summary of the major questions asked at the Public Information Meeting on May 4th , 2016 and the responses. 1. What was the Approval Process for Fairwinds West Subdivision and Johnwoods Street?  Mattamy applied for a Plan of Subdivision at 33 Johnwoods Street in November 2007  The statutory Public Meeting, per the Planning Act for this Plan of Subdivision was held on March 21st , 2008.  Johnwoods Street closure formed a part of this public meeting and discussion  The subdivision was placed on hold due to area-wide servicing constraints associated with the Carp River from 2008 to 2012.  The traffic study for the subdivision was updated in June 2013, a specific report on Johnwoods Street was provided as an addendum to document the traffic impact resulting from the closure. The impact on the existing and proposed road network was deemed to be negligible.  The Ward Councillor (Shad Qadri) declared a conflict of interest in Fall of 2013.  Fairwinds West Subdivision was approved by the Manager of Suburban Services, Development Review under Delegated Authority in October 2013 with the concurrence of the Chair and Vice-Chair of Planning Committee, which included the closure of Johnwoods Street as a condition.  Notice of the decision, along with conditions of draft approval, were circulated to all parties who attended the public meeting or whom had provided comments throughout the process, per Planning Act requirements. This notice also included information on appeal rights to the Ontario Municipal Board.  No appeals were received, and the draft approval took effect November 26th, 2013.  A notification and concept were posted to the public information portal for this subdivision on the City of Ottawa website.  The City conducted a technical circulation to internal City departments including transportation and right-of-ways and received technical concurrence to proceed with closure, per Condition 32(a) of the Agreement.  The Subdivision Agreement was registered in February 2015.  The public information meeting, held on May 4th, 2016, was with respect to Condition #32(b) of the Subdivision Agreement. 2. When was the final decision made to close Johnwoods to vehicle traffic?  The timeline notes that the decision to close Johnwoods Street to vehicle traffic was made at time of draft approval, following the discussions through the approval process of the plan of subdivision.  The internal technical circulation within city departments and external agencies between draft approval and registration confirmed that Johnwoods closure would be acceptable operationally, and with minimal traffic impact on the existing and future communities. Indeed, the traffic evaluation indicated there would be a benefit from reduced cut-through traffic.
  • 2.  Between Draft Approval in November 2013 and Registration of the subdivision agreement in February 2015, the City still retained an opportunity to entirely reconsider the closure if major concerns were identified through the circulation.  Following draft approval, the intent was to have Mattamy go through a concept design with community input on the future look, function and timing of the repurposed roadway conversion.  As no appeals or comments had been received on the draft approval of the subdivision at large and impacts were considered minor in nature and primarily on future residents, and similar closures have been welcomed in other neighbourhoods, the planning department moved forward on registration and did not prioritize the circling back with the existing community to provide an advisory meeting between draft approval and registration, as had been suggested to the community and the Councillor.  After the subdivision was registered in February 2015, staff recognized that there remained a need to circle back with the community on what the look, function and timing would be of the multi-use pathway corridor going forward into implementation.  It was not clearly recognized that there would be such opposition to the closure from the existing residents. This was an error for which the planning department apologizes.  Staff continue to advise that the closure of Johnwoods will provide a positive benefit to the existing and future communities through reducing cut-through traffic and restoring a local road network, and through provision of additional community open space and improvement of a poorly used corridor.  However, staff also accept responsibility for the lack of communication on the process, and failure to discuss the forthcoming plans for Johnwoods with residents until such a late date. 3. What is the benefit to existing and future residents by closing Johnwoods?  Johnwoods is operating as a cut-through route for traffic through the community, and is not operating in a local road capacity. Closing this section of Johnwoods removes the direct route for cut-through traffic, reduces speeds, and pushes traffic to the major road network.  At the time of the public notification and consultation for this application, the City had received comments from many residents regarding concerns about volume and speed of traffic on Johnwoods Street.  At the time, the issues stemmed from an underdeveloped road network, because key roads identified in the Kanata West Concept Plan had not been constructed, resulting in Johnwoods Street becoming an attractive route for cut-through traffic between Hazeldean Road and Maple Grove Road.  Since then, the construction of Huntmar Drive and the widening of Hazeldean Road have brought improvements to the street network and reduced dependence on Johnwoods Street.  Because a new collector road in the subdivision, east of Johnwoods Street, would serve as the collector road between Rosehill Avenue and Maple Grove Road, there would be minimal impact on local streets in the Bryanston Gate neighbourhood.
  • 3.  The proposed multi-use pathway in the Johnwoods Street road allowance would reduce traffic volumes on the southerly part of the street and provide an improved connection for pedestrians and cyclists in the community.  Closing this section to vehicle traffic provides a community benefit, additional useable open space and amenity to the existing and future residents of the area.  The corridor as it stands is a sub-standard portion of roadway that is unsightly and would require significant municipal expense to bring to minor collector standards.  Mattamy is conditioned to develop this design, decommission existing infrastructure and provide landscaping to City standards at their sole cost and responsibility.  Johnwoods is identified as a cycling route in the Ottawa Cycling Plan, with an ultimate connection north to the future Kanata West District Park. The Johnwoods multi-use pathway conversion is a step towards achieving this connection. 4. What is the timeline for opening Maple Grove to Stittsville Main Street?  Maple Grove is intended to be part of the local street network, and not part of the major road network. As such, the construction of this is a function of the development of adjacent land parcels that will ultimately require access for roads and services.  Connecting Stittsville Main Street ahead of the extension to Highway 417 will result in a significant increase of traffic on Stittsville Main Street and Maple Grove.  Stittsville Main Street is designated as a major collector, and is part of the major road network for the City. It is intended to be extended north to Highway 417 in Phase 3 of the Transportation Master Plan (2025-2031) with exact timing depending upon development occurring in the Kanata West Town Centre area.  Future traffic increases on Maple Grove, with or without a connection to Stittsville Main Street, will need to be coordinated with improvements to the intersection at Maple Grove and Huntmar. This intersection is currently proposed for upgrading after 2018. 5. When will Johnwoods be closed to vehicle traffic?  Condition 4(g)(iv) of the subdivision agreement notes that closure of Johnwoods will not occur until Santolina Street and Rosehill Avenue are constructed and are open to vehicular traffic. Planning staff interpret this to mean Rosehill open from Johnwoods to Huntmar.  Santolina is now open for public use. Rosehill is dependent upon the construction schedule of Poole Creek Village, and is anticipated to be complete and open for public use in early 2017.  Construction of Johnwoods conversion to a multi-use pathway would occur once these roads are open.  Discussions with Mattamy as to the exact timing are with respect to the level of acceptable construction activity on Rosehill, such that the route is indeed available as a direct, viable and attractive connection for the new traffic pattern. This includes full provision of all sidewalks and substantial completion of all fronting homes on Rosehill and Santolina Streets.
  • 4. 6. What traffic analysis was done for the Fairwinds subdivision and Johnwoods closure?  Traffic data and analysis for subdivision applications are based upon City of Ottawa Traffic Impact Assessment Guidelines, and Institute of Transportation Engineers (ITE) Manual 8, updated from time to time.  Traffic counts are collected annually on the major road network (arterials and major collectors) and on an as-needed basis for local roads. Traffic counts were collected at Hazeldean and Johnwoods as part of the Fairwinds Subdivision application.  Traffic moving to and from the Queensway is considered to be the function of the Major Road Network. Johnwoods is not part of the major road network.  Johnwoods and Rosehill are considered to be part of the local street network system and are classified as minor collectors.  Minor collectors are designed to only provide service to local streets and direct traffic from immediately adjacent neighbourhoods to the major road network.  The major and minor road network is re-evaluated every 5 years through updates to the Transportation Master Plan, which forms part of the Official Plan of the City of Ottawa. 7. Is the design for the section of Johnwoods to be closed finalized?  Yes, aspects of the design can change with input from the community. The concept at this stage is a high-level concept, and was a preliminary proposal.  The refined concept plan would be circulated to the Councillor’s office for comment and community input on the design.  This will not be a formal park as this will continue to be a City right-of-way, under the ownership of the City. However, the maintenance and look-and-feel will be to the standard that the City looks for in park designs.  While Mattamy is conditioned to decommission existing infrastructure and construct a multi-use pathway and landscaping to City standards at their sole cost and responsibility, the City retains the option to supplement the design with further amenities as may be suggested, with the understanding that any additional works would be at the cost to the City and not Mattamy and subject to funding availability. 8. What is the traffic impact on the existing community?  Johnwoods is operating as a cut-through route for traffic from outside the community, and is not operating in a local road capacity. Closing this section of Johnwoods removes the direct route for cut-through traffic, reduces speeds, and pushes traffic to the major road network.  A traffic analysis has been conducted by Stantec Consulting Ltd. as an addendum to the Community Transportation Impact Study, and demonstrates that an additional 50 vehicles per hour will be diverted to the Rosehill minor collector. This is projected to be far below the carrying capacity of this roadway, even after Fairwinds West and Poole Creek Village are fully built and occupied.  No significant traffic movement from closure of Johnwoods is considered to pass through Bryanston Gate via Alon Street. The shortest travel path between Maple Grove
  • 5. Road and Hazeldean Road will be via Huntmar Drive or through the Fairwinds / Poole Creek communities – not through the Bryanston Gate community.  Rosehill is designed as a minor collector between Johnwoods Street and Huntmar Drive, and will be the most attractive route for motorists who chose not to use the Hazeldean Road / Huntmar major road network. 9. Why not keep Johnwoods open?  Johnwoods is operating as a cut-through route for traffic through the community, and is not operating in a local road capacity.  Leaving Johnwoods open will continue to offer an attractive direct route for cut-through traffic from Hazeldean to Maple Grove, not in keeping with the local network designation of this road. This would increase as development occurs on the vacant land parcels north of Maple Grove, as is proposed in the Kanata West Concept Plan.  The proposal to close Johnwoods went through a technical circulation of all affected City departments and was deemed to be acceptable.  Closing this section of Johnwoods removes the direct route for cut-through traffic, reduces speeds, and pushes traffic to the major road network. This shifts Johnwoods to a local level of service, in keeping with the Kanata West Concept Plan. 10. Where has the City closed other roads and done similar conversions?  The City has closed other collectors for conversion into multi-use paths and community open space. This includes Richardson Side Road, from Kanata Avenue to Terry Fox Drive.  The former alignment of Strandherd Drive in Barrhaven was converted from a major road to a local road, and ultimately, to linear open space and pathways from 2009 to today. New multi-use pathways and parks spaces created from the decommissioned road include include Fraser Fields Parkette, and Harthill Way Linear Park.  There has been no negative impact on adjacent homes and local roads. These are now seen as community assets.  In future, the City will be closing the Greenbank Road alignment in Barrhaven South and converting the right-of-way and bridge into a multi-use pathway upon construction of the new Greenbank Road alignment. 11. What are the Next Steps?  Mattamy is required to prepare a refined Concept Plan, including a decommissioning report for all necessary roads infrastructures.  The Concept Plan will be circulated for final review and approval by internal city agencies (accessibility, forestry, parks, buildings, ground services etc.) and circulated to the Ward Councillor for comment and community input on the design.  Following approval of the Concept Plan, detailed design drawings (landscaping, utilities plans etc.) are to be developed by Mattamy, and provided for internal circulation and review by City departments.
  • 6.  A traffic management plan will be prepared, and public notification and signage will be posted to notify of a change in traffic patterns ahead of the closure. This will include any identified mitigation measures, signage and traffic calming required on existing roads (Alon Street), and may include monitoring before and after implementation to ensure future traffic patterns match the proposal.  Dependent upon the above municipal approvals and opening of Rosehill Avenue as a viable route, construction on the Johnwoods multi-use path corridor would occur in summer 2017.