Revised Construction Drawing Flow Chart_2016_01_11
1. Issue Revise Construction Drawing
Step 1:
This process involve LS ( Cost Consultants) review & feedback
LS/ Relevant consultants to provide brief or estimation cost
analysis. RFV must get client Approval
Estimate 10 days for LS combine all information & cost analysis
Step 2:
Step 3:
Step 4:
Allow Turner (2-3 working day) stamp & send back.
(drawing number, revision numbers & clouds with AI references
Step 5:
Allow Consultants (1-2 working days)
upload & transmit to Architect
Step 6:
Allow Consultants print out full size drawing 5 working days
CRCC to correct from consultant office every Tuesday afternoon
If Tuesday is Public Holiday, will be collect by following day
Step Description Duration
Consultants issue RFV and copy to VA/TURNER/LS 1
LS brief or estimate cost analysis and VA consent 10
2 Consultants issues AI to Contractor 2
3 Consultants releases construction drawing for Turner stamping 1
4 Turner review, stamping & send back 3
5 Consultant upload into aconex and transmit 2
6 Issue hardcopy drawing to contractors & other consultants 5
Total 24
BENEFITS:
A Ensure Client understands the estimate cost of the variation based on the cost consultant/ specialist consultant estimate of cost analysis
B Reduce EOT claim by contractor compared to less detailed of cost analysis.
C Less affected on physical works of construction.
RISK
A EOT may be claimed by contractor due to late release revised construction drawing.
B Based on estimate cost provided by specialist consultant or cost consultant, there might have cost different compared with cost submitted by the contractor.
C Consultant may not follow specify a time frame in providing cost analysis, and this will delay the release of construction drawing to the contractor.
1
Consultants Transmit
Construction Drawing
to Main-Contractor
Consultants Provide
Full Size Hardcopy
Construction Drawing
to Main-contractor
Consultants
Issues AIs/EIs to Contractors
Only approval RFV can be issues AI to
Turner Stamping & send
back to individual
Consultants Officially
issue by Transmitting
Construction Drawing
to Main-Contractor
Consultants Provide
Full Size Hardcopy
Construction Drawing
to Main-contractor
Consultants
(NRY, Wilson. VADI, ALT, Light Cibles, Belt
Collin, IHD, GDSS, CKP, KTA, MEINHARDT,
VADI and other)
Issue RFV to Cost Consultants, Turner and
Venus Assets (Client)
Consultants
Release Revised Construction Drawing for
stamping by Turner
All the changes must Clouds and indicated
the change refer to AI numbers.