3326 Washington Street
Project Update & Article 85 Community Meeting
Sep 19, 2019
Today
Where are we in the process?
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
TONIGHT’S AGENDA
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
I. Community & BLC Notice Statement
II. Historic Information + Public Input
III. Alternatives to Demolition
VI. Proposed Project
VII. Q&A
3 min
10 min
10 min
10 min
30 min
COMMUNITY NOTICE STATEMENT
is community meetingis being held as part of an
Article 85 Demolition Delay application to demolish
the building at 3326 Washington.
e purposeof this meetingis to inform thecommunity
abouttheproposeddemolition and to present
alternativesto thedemolition. Allinterested partiesare
welcometo attend,and will have theopportunity to
comment and ask questions.
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
COMMUNITY NOTICE STATEMENT
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
is community meetingDOES NOT take theplace
of theBoston Landmarks Commissionpublic
hearing.
All interestedpartiesareencouragedto attendtheBLC
public hearing to express their views on the
proposed demolition, or to submit
written commentsto the BLC if they are
unable to attend.
COMMUNITY NOTICE STATEMENT
Pleasesubmit written comments by thehearing date
to: Boston Landmarks Commission
Boston City Hall, Room
709 1City Hall Square
Boston, MA 02201
or fax to 617-635-3435,
or email a PDF with signature to: BLC@boston.gov
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
BLC NOTICE STATEMENT
Pursuant to reviewunder Section 5, Article 85,Chapter
665of theActs of 1956 as amended, the sta of the
Boston Landmarks Commission (BLC) has found the
existing structure 3326 Washington Street in
Jamaica Plain, MA 02130 to be signi cant under
criteria (A)and
(D) of Section 85.5.3. is application will, therefore,
be presented at a BLC hearing to
determine whether the buildings will be
subject to demolition delay.
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
A. Section 85.5.3(a) states “...the building is listed
in the Landmarks Commission’s Comprehensive
Preservation Survey as a building that is: (i)
listedon the National Register of Historic
Places;(ii) recommended for such listing; or
(iii) thesubject of a pending application for
such listing…”
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
BLC NOTICE STATEMENT
D. Section 85.5.3(d) states“...the building has an
important associationwith one or more historic
persons or events, or with the broad
architectural, cultural, political, economic, or
social history of thecity...”
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
BLC NOTICE STATEMENT
Property Photos
Exterior Facades
First Floor
Basement L1 Rear Garage
Second Floor
Historic Information
1851-1891
School
1892-1958
House
1958-2019
Auto Shop
History of the Building
1851: Primary school opens as “ No 3. on the Turnpike”
1851-92: In operation at 3326 Washington St (41 years)
Comparable Buildings
Washington Street School near Forest Hills Chestnut Avenue School (still exists today)
1892: School moves to new building at 25 Glen Road, renamed
“ Margaret Fuller Elementary School”
1892-present: This building is the oldest continuously operating
school in Boston Public School district (127 years)
Washington Street Elevated
1912
Redlining Along Washington Street
SITE LOCATION
Future of Washington Street
Additional information from attendees
on history and significance of property
Alternatives to
Demolition
EXISTING BUILDING
PROPERTYLINE
1. As-of-Right Use
EXISTING PARKING LOT
AREA AVAILABLE FORNEW CONSTRUCTION
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
1. As-of-Right Use
35’-0” Tall Industrial Building, FAR 1.0
Washington Street Elevation
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
Glen Road Elevation
2. Restore and Build Around Existing Structure
• Existing structure renovated for residential use
• New development to be built around existing
structure
• BPDA does not support this option
• Cannot meet Plan: JP/Rox affordability, height
and urban design goals at the same time
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
2. Restore and Build Around Existing Structure
Elevations from Washington St
EXISTING
BUILDING
NEW BUILDING
2A
0% affordability
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
2. Restore and Build Around Existing Structure
Elevations from Washington St
EXISTING
BUILDING
NEW BUILDING
2A
0% affordability
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
2B
Not enough
affordability (13-18%)
2. Restore and Build Around Existing Structure
Elevations from Washington St
EXISTING
BUILDING
NEW BUILDING
2A
0% affordability
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
2B
Not enough
affordability (13-18%)
2C
Too tall
3. Relocate Building to New Site
• The property owner will offer the existing building
to any individual or institution that can move it to a
new site
• The move must be completed by June 2020
• Many physical, logistical, nancial challenges
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
4. Reconstruct Front Facade in New Development
Washington Street Elevation
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
Glen Road Elevation
4. Reconstruct Front Facade in New Development
TRASH
MECH
BIKE PARKING
FITNESS
LOBBY
COMMERCIAL
COMMERCIAL
1 BR COMPACT
2 BR COMPACT
2 BR COMPACT
1 BR COMPACT
1 BR COMPACT 1 BR COMPACT STUDIO2 BR COMPACT
2 BR COMPACT 1 BR COMPACT 1 BR COMPACT 1 BR COMPACT
1 BR COMPACT
2 BR COMPACT
2 BR COMPACT1 BR COMPACT 1 BR COMPACT
Ground Floor Plan
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
Typical Residential Plan
4. Reconstruct Front Facade in New Development
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
Proposed Project
Terraced Gardens
!
!!
Terraced Gardens
Original Proposal (June 2019)
So what’s changed?
Previous: 20% Affordable
24% AFFORDABLE
11 units total
Previous: All units at 70 AMI
DEEPER
AFFORDABILITY
Previous: 45,000 Total SF
REDUCED FOOTPRINT
BY 4000 SF
GREATER STEPBACKS
Previous: No front facade stepback
HONORING HISTORY
+
MATERIAL REUSE
Previous: Material reuse only
Terraced Gardens Updated Proposal
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
Washington Street Elevation
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
Glen Road Elevation
Terraced Gardens
Terraced Gardens Lobby Museum
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
Terraced Gardens Lobby Museum
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
1 BR1 BR COMPACT 1 BR COMPACT
1 BR COMPACT 1 BR COMPACT 2 BRFITNESS
LOBBY
COMMERCIAL
COMMERCIAL
TRASHMECH
1 BR COMPACT 1 BR COMPACT 1 BR COMPACT
2 BR COMPACT
STUDIO
479 sq ft
STUDIO
1 BR COMPACT
1 BR
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
2 BR COMPACT
2 BR COMPACT
Terraced Gardens Updated Floorplans
Ground Floor Plan Typical Residential Plan
47 Units Total
6 Studios
31 One Bedrooms
10 Two Bedrooms
11 Affordable Units
Mix of 30, 50, 70% AMI
Average 60% AMI
60 AMI
2 Bedroom Unit
$1,266
60 AMI
$1,266
2 Bedroom Unit
60 AMI
$1,266
$1139
2 Bedroom Unit
Even deeper affordability:
$1,266
$1,139
2 BR
$1,120
$1,008
1 BR STUDIO
$955
$859
| 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
•24% Affordable
•Respects Urban Context
•Supports Local Business
•Promotes Biking
•Promotes T ridership
•Builds Sustainably
•Preserves Character
Terraced Gardens
Q&A

Más contenido relacionado

Similar a 3326 washington article 85 meeting 9_19_2019

SUTTMAN BUILDING REDEVELOPMENTDowntown Miamisburg, Ohio.docx
SUTTMAN BUILDING REDEVELOPMENTDowntown Miamisburg, Ohio.docxSUTTMAN BUILDING REDEVELOPMENTDowntown Miamisburg, Ohio.docx
SUTTMAN BUILDING REDEVELOPMENTDowntown Miamisburg, Ohio.docx
mabelf3
 
Calhoun Practicum Presentation WAD + LAF 3.0
Calhoun Practicum Presentation WAD + LAF 3.0Calhoun Practicum Presentation WAD + LAF 3.0
Calhoun Practicum Presentation WAD + LAF 3.0
Kelly Calhoun
 
Presentation_to_PMI-Calumet_Northwestern_Indiana_Region
Presentation_to_PMI-Calumet_Northwestern_Indiana_RegionPresentation_to_PMI-Calumet_Northwestern_Indiana_Region
Presentation_to_PMI-Calumet_Northwestern_Indiana_Region
Kevin Lovell, PMP
 
Fairgrounds Roadway Widening Public Hearing (March 17, 2015)
Fairgrounds Roadway Widening Public Hearing (March 17, 2015)Fairgrounds Roadway Widening Public Hearing (March 17, 2015)
Fairgrounds Roadway Widening Public Hearing (March 17, 2015)
City of Midland
 

Similar a 3326 washington article 85 meeting 9_19_2019 (20)

DOW Public Meeting Slides 2.5.20
DOW Public Meeting Slides 2.5.20DOW Public Meeting Slides 2.5.20
DOW Public Meeting Slides 2.5.20
 
DOW Public Meeting Slides 12.19.19
DOW Public Meeting Slides 12.19.19DOW Public Meeting Slides 12.19.19
DOW Public Meeting Slides 12.19.19
 
SUTTMAN BUILDING REDEVELOPMENTDowntown Miamisburg, Ohio.docx
SUTTMAN BUILDING REDEVELOPMENTDowntown Miamisburg, Ohio.docxSUTTMAN BUILDING REDEVELOPMENTDowntown Miamisburg, Ohio.docx
SUTTMAN BUILDING REDEVELOPMENTDowntown Miamisburg, Ohio.docx
 
Calhoun Practicum Presentation WAD + LAF 3.0
Calhoun Practicum Presentation WAD + LAF 3.0Calhoun Practicum Presentation WAD + LAF 3.0
Calhoun Practicum Presentation WAD + LAF 3.0
 
190 S Orange
190 S Orange190 S Orange
190 S Orange
 
Item # 4 - 820 Cambridge Compatibility
Item # 4 - 820 Cambridge Compatibility Item # 4 - 820 Cambridge Compatibility
Item # 4 - 820 Cambridge Compatibility
 
9 10ebcctbrownfieldsseminarfinal 100914104154 Phpapp01
9 10ebcctbrownfieldsseminarfinal 100914104154 Phpapp019 10ebcctbrownfieldsseminarfinal 100914104154 Phpapp01
9 10ebcctbrownfieldsseminarfinal 100914104154 Phpapp01
 
9-10ebcctbrownfieldsseminarfinal-100914104154-phpapp01
9-10ebcctbrownfieldsseminarfinal-100914104154-phpapp019-10ebcctbrownfieldsseminarfinal-100914104154-phpapp01
9-10ebcctbrownfieldsseminarfinal-100914104154-phpapp01
 
How to Clear the First Hurdle in Site Redevelopment
How to Clear the First Hurdle in Site RedevelopmentHow to Clear the First Hurdle in Site Redevelopment
How to Clear the First Hurdle in Site Redevelopment
 
Bath, Maine Design And Resiliency Team (DART) Project
Bath, Maine Design And Resiliency Team (DART) ProjectBath, Maine Design And Resiliency Team (DART) Project
Bath, Maine Design And Resiliency Team (DART) Project
 
Item #5 PPT 222 Castano
Item #5   PPT 222 CastanoItem #5   PPT 222 Castano
Item #5 PPT 222 Castano
 
Public Consultation Presentation: 468-476 James St N, Hamilton
Public Consultation Presentation: 468-476 James St N, HamiltonPublic Consultation Presentation: 468-476 James St N, Hamilton
Public Consultation Presentation: 468-476 James St N, Hamilton
 
October 1 referendum presentation Haddonfield BOE
October 1 referendum presentation Haddonfield BOEOctober 1 referendum presentation Haddonfield BOE
October 1 referendum presentation Haddonfield BOE
 
Presentation_to_PMI-Calumet_Northwestern_Indiana_Region
Presentation_to_PMI-Calumet_Northwestern_Indiana_RegionPresentation_to_PMI-Calumet_Northwestern_Indiana_Region
Presentation_to_PMI-Calumet_Northwestern_Indiana_Region
 
The Paterson Greenway Project
The Paterson Greenway ProjectThe Paterson Greenway Project
The Paterson Greenway Project
 
AH CCM 5.11.20
AH CCM 5.11.20AH CCM 5.11.20
AH CCM 5.11.20
 
Gloucester, VA Gov. Reports August 2014 Departmental Reports
Gloucester, VA Gov. Reports August 2014 Departmental ReportsGloucester, VA Gov. Reports August 2014 Departmental Reports
Gloucester, VA Gov. Reports August 2014 Departmental Reports
 
DOPWIC Program Year 2017 Applicant Workshop
DOPWIC Program Year 2017 Applicant WorkshopDOPWIC Program Year 2017 Applicant Workshop
DOPWIC Program Year 2017 Applicant Workshop
 
Fairgrounds Roadway Widening Public Hearing (March 17, 2015)
Fairgrounds Roadway Widening Public Hearing (March 17, 2015)Fairgrounds Roadway Widening Public Hearing (March 17, 2015)
Fairgrounds Roadway Widening Public Hearing (March 17, 2015)
 
OPDC second revised draft Local Plan consultation - Design & Environment
OPDC second revised draft Local Plan consultation - Design & EnvironmentOPDC second revised draft Local Plan consultation - Design & Environment
OPDC second revised draft Local Plan consultation - Design & Environment
 

Más de timothygreardon

If You Build It, Do They Come?
If You Build It, Do They Come? If You Build It, Do They Come?
If You Build It, Do They Come?
timothygreardon
 

Más de timothygreardon (12)

35 brookley bpda public meeting_102419
35 brookley bpda public meeting_10241935 brookley bpda public meeting_102419
35 brookley bpda public meeting_102419
 
Reardon_EssexAssessorsAssoc_10_25_17
Reardon_EssexAssessorsAssoc_10_25_17Reardon_EssexAssessorsAssoc_10_25_17
Reardon_EssexAssessorsAssoc_10_25_17
 
Soe 2017 update_executivesummary
Soe 2017 update_executivesummarySoe 2017 update_executivesummary
Soe 2017 update_executivesummary
 
Planjprox summary proposed changes 12.8.16
Planjprox   summary proposed changes 12.8.16Planjprox   summary proposed changes 12.8.16
Planjprox summary proposed changes 12.8.16
 
Massachusetts Vehicle Census 2009 - 2014
Massachusetts Vehicle Census 2009 - 2014Massachusetts Vehicle Census 2009 - 2014
Massachusetts Vehicle Census 2009 - 2014
 
Local Access Scores Overview
Local Access Scores OverviewLocal Access Scores Overview
Local Access Scores Overview
 
Building for the Middle - Housing Greater Boston's Workforce - Release event
Building for the Middle - Housing Greater Boston's Workforce - Release eventBuilding for the Middle - Housing Greater Boston's Workforce - Release event
Building for the Middle - Housing Greater Boston's Workforce - Release event
 
If You Build It, Do They Come?
If You Build It, Do They Come? If You Build It, Do They Come?
If You Build It, Do They Come?
 
Reardon Massachusetts Housing Institute
Reardon Massachusetts Housing InstituteReardon Massachusetts Housing Institute
Reardon Massachusetts Housing Institute
 
Prioritizing Complete Streets -- Utility & Gap Analysis
Prioritizing Complete Streets -- Utility & Gap AnalysisPrioritizing Complete Streets -- Utility & Gap Analysis
Prioritizing Complete Streets -- Utility & Gap Analysis
 
Reardon trb 4_13_2015
Reardon trb 4_13_2015Reardon trb 4_13_2015
Reardon trb 4_13_2015
 
3200 wash esna_summary_3_25
3200 wash esna_summary_3_253200 wash esna_summary_3_25
3200 wash esna_summary_3_25
 

Último

Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Menggugurkan Kandungan 087776558899
 
Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdf
ScottMeyers35
 
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
MadhuKothuru
 

Último (20)

Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
 
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
 
Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdf
 
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
 
2024: The FAR, Federal Acquisition Regulations, Part 32
2024: The FAR, Federal Acquisition Regulations, Part 322024: The FAR, Federal Acquisition Regulations, Part 32
2024: The FAR, Federal Acquisition Regulations, Part 32
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
 
2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31
 
Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019
 
Finance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCFinance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCC
 
tOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTRtOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTR
 
sponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfsponsor for poor old age person food.pdf
sponsor for poor old age person food.pdf
 
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdf
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdfPeace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdf
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdf
 
NGO working for orphan children’s education
NGO working for orphan children’s educationNGO working for orphan children’s education
NGO working for orphan children’s education
 
An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCC
 
Delivery in 20 Mins Call Girls Malappuram { 9332606886 } VVIP NISHA Call Girl...
Delivery in 20 Mins Call Girls Malappuram { 9332606886 } VVIP NISHA Call Girl...Delivery in 20 Mins Call Girls Malappuram { 9332606886 } VVIP NISHA Call Girl...
Delivery in 20 Mins Call Girls Malappuram { 9332606886 } VVIP NISHA Call Girl...
 
2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.
 
Panchayath circular KLC -Panchayath raj act s 169, 218
Panchayath circular KLC -Panchayath raj act s 169, 218Panchayath circular KLC -Panchayath raj act s 169, 218
Panchayath circular KLC -Panchayath raj act s 169, 218
 
Private Call Girls Bidar 9332606886Call Girls Advance Cash On Delivery Service
Private Call Girls Bidar  9332606886Call Girls Advance Cash On Delivery ServicePrivate Call Girls Bidar  9332606886Call Girls Advance Cash On Delivery Service
Private Call Girls Bidar 9332606886Call Girls Advance Cash On Delivery Service
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 

3326 washington article 85 meeting 9_19_2019

  • 1. 3326 Washington Street Project Update & Article 85 Community Meeting Sep 19, 2019
  • 2. Today Where are we in the process? | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
  • 3. TONIGHT’S AGENDA | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING I. Community & BLC Notice Statement II. Historic Information + Public Input III. Alternatives to Demolition VI. Proposed Project VII. Q&A 3 min 10 min 10 min 10 min 30 min
  • 4. COMMUNITY NOTICE STATEMENT is community meetingis being held as part of an Article 85 Demolition Delay application to demolish the building at 3326 Washington. e purposeof this meetingis to inform thecommunity abouttheproposeddemolition and to present alternativesto thedemolition. Allinterested partiesare welcometo attend,and will have theopportunity to comment and ask questions. | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
  • 5. COMMUNITY NOTICE STATEMENT | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING is community meetingDOES NOT take theplace of theBoston Landmarks Commissionpublic hearing. All interestedpartiesareencouragedto attendtheBLC public hearing to express their views on the proposed demolition, or to submit written commentsto the BLC if they are unable to attend.
  • 6. COMMUNITY NOTICE STATEMENT Pleasesubmit written comments by thehearing date to: Boston Landmarks Commission Boston City Hall, Room 709 1City Hall Square Boston, MA 02201 or fax to 617-635-3435, or email a PDF with signature to: BLC@boston.gov | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
  • 7. BLC NOTICE STATEMENT Pursuant to reviewunder Section 5, Article 85,Chapter 665of theActs of 1956 as amended, the sta of the Boston Landmarks Commission (BLC) has found the existing structure 3326 Washington Street in Jamaica Plain, MA 02130 to be signi cant under criteria (A)and (D) of Section 85.5.3. is application will, therefore, be presented at a BLC hearing to determine whether the buildings will be subject to demolition delay. | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
  • 8. A. Section 85.5.3(a) states “...the building is listed in the Landmarks Commission’s Comprehensive Preservation Survey as a building that is: (i) listedon the National Register of Historic Places;(ii) recommended for such listing; or (iii) thesubject of a pending application for such listing…” | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING BLC NOTICE STATEMENT
  • 9. D. Section 85.5.3(d) states“...the building has an important associationwith one or more historic persons or events, or with the broad architectural, cultural, political, economic, or social history of thecity...” | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING BLC NOTICE STATEMENT
  • 17. 1851: Primary school opens as “ No 3. on the Turnpike”
  • 18. 1851-92: In operation at 3326 Washington St (41 years)
  • 19. Comparable Buildings Washington Street School near Forest Hills Chestnut Avenue School (still exists today)
  • 20. 1892: School moves to new building at 25 Glen Road, renamed “ Margaret Fuller Elementary School”
  • 21. 1892-present: This building is the oldest continuously operating school in Boston Public School district (127 years)
  • 23. Redlining Along Washington Street SITE LOCATION
  • 25.
  • 26. Additional information from attendees on history and significance of property
  • 28. EXISTING BUILDING PROPERTYLINE 1. As-of-Right Use EXISTING PARKING LOT AREA AVAILABLE FORNEW CONSTRUCTION | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
  • 29. 1. As-of-Right Use 35’-0” Tall Industrial Building, FAR 1.0 Washington Street Elevation | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING Glen Road Elevation
  • 30. 2. Restore and Build Around Existing Structure • Existing structure renovated for residential use • New development to be built around existing structure • BPDA does not support this option • Cannot meet Plan: JP/Rox affordability, height and urban design goals at the same time | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
  • 31. 2. Restore and Build Around Existing Structure Elevations from Washington St EXISTING BUILDING NEW BUILDING 2A 0% affordability | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
  • 32. 2. Restore and Build Around Existing Structure Elevations from Washington St EXISTING BUILDING NEW BUILDING 2A 0% affordability | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING 2B Not enough affordability (13-18%)
  • 33. 2. Restore and Build Around Existing Structure Elevations from Washington St EXISTING BUILDING NEW BUILDING 2A 0% affordability | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING 2B Not enough affordability (13-18%) 2C Too tall
  • 34. 3. Relocate Building to New Site • The property owner will offer the existing building to any individual or institution that can move it to a new site • The move must be completed by June 2020 • Many physical, logistical, nancial challenges | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
  • 35. 4. Reconstruct Front Facade in New Development Washington Street Elevation | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING Glen Road Elevation
  • 36. 4. Reconstruct Front Facade in New Development TRASH MECH BIKE PARKING FITNESS LOBBY COMMERCIAL COMMERCIAL 1 BR COMPACT 2 BR COMPACT 2 BR COMPACT 1 BR COMPACT 1 BR COMPACT 1 BR COMPACT STUDIO2 BR COMPACT 2 BR COMPACT 1 BR COMPACT 1 BR COMPACT 1 BR COMPACT 1 BR COMPACT 2 BR COMPACT 2 BR COMPACT1 BR COMPACT 1 BR COMPACT Ground Floor Plan | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING Typical Residential Plan
  • 37. 4. Reconstruct Front Facade in New Development | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
  • 39.
  • 42. Previous: 20% Affordable 24% AFFORDABLE 11 units total
  • 43. Previous: All units at 70 AMI DEEPER AFFORDABILITY
  • 44. Previous: 45,000 Total SF REDUCED FOOTPRINT BY 4000 SF
  • 45. GREATER STEPBACKS Previous: No front facade stepback
  • 47. Terraced Gardens Updated Proposal | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
  • 48. Washington Street Elevation | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING Glen Road Elevation Terraced Gardens
  • 49. Terraced Gardens Lobby Museum | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
  • 50. Terraced Gardens Lobby Museum | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING
  • 51. 1 BR1 BR COMPACT 1 BR COMPACT 1 BR COMPACT 1 BR COMPACT 2 BRFITNESS LOBBY COMMERCIAL COMMERCIAL TRASHMECH 1 BR COMPACT 1 BR COMPACT 1 BR COMPACT 2 BR COMPACT STUDIO 479 sq ft STUDIO 1 BR COMPACT 1 BR | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING 2 BR COMPACT 2 BR COMPACT Terraced Gardens Updated Floorplans Ground Floor Plan Typical Residential Plan
  • 52. 47 Units Total 6 Studios 31 One Bedrooms 10 Two Bedrooms
  • 53. 11 Affordable Units Mix of 30, 50, 70% AMI Average 60% AMI
  • 54. 60 AMI 2 Bedroom Unit $1,266
  • 57. Even deeper affordability: $1,266 $1,139 2 BR $1,120 $1,008 1 BR STUDIO $955 $859
  • 58. | 3326 WASHINGTON ST | PROJECT UPDATE & ARTICLE 85 COMMUNITY MEETING •24% Affordable •Respects Urban Context •Supports Local Business •Promotes Biking •Promotes T ridership •Builds Sustainably •Preserves Character Terraced Gardens
  • 59. Q&A