SlideShare una empresa de Scribd logo
1 de 3
Descargar para leer sin conexión
GPTC GUIDE FOR GAS TRANSMISSION AND                                                                §192.465
DISTRIBUTION PIPING SYSTEMS: 2009 Edition                                                        SUBPART I


          (6) Cracks in gouges.
          (7) Coating defects.
      (b) No individual in-line inspection tool is universally applicable for the identification, measurement,
          and assessment of every type of anomaly. Tool selection and performance may be dependent
          upon the following parameters.
          (1) Type and size of anomalies to be detected.
          (2) Desired data resolution and sizing accuracy of anomalies.
          (3) Length of pipe to be inspected.
          (4) Ability to couple tool to pipe wall.
          (5) Desired tool speed.
          (6) Physical condition of the pipeline.
              (i) Internal cleanliness.
              (ii) Pipe wall deformations.
              (iii) Change in pipe wall or grade.

10.4 Reference.
     See guide material under §192.150.



                                                §192.467
                       External corrosion control: Electrical isolation.
                                                                                    [Effective Date: 09/05/78]

     (a) Each buried or submerged pipeline must be electrically isolated from other underground
metallic structures, unless the pipeline and the other structures are electrically interconnected and
cathodically protected as a single unit.
     (b) One or more insulating devices must be installed where electrical isolation of a portion of a
pipeline is necessary to facilitate the application of corrosion control.
     (c) Except for unprotected copper inserted in ferrous pipe, each pipeline must be electrically
isolated from metallic casings that are a part of the underground system. However, if isolation is not
achieved because it is impractical, other measures must be taken to minimize corrosion of the
pipeline inside the casing.
     (d) Inspection and electrical tests must be made to assure that electrical isolation is adequate.
     (e) An insulating device may not be installed in an area where a combustible atmosphere is
anticipated unless precautions are taken to prevent arcing.
     (f) Where a pipeline is located in close proximity to electrical transmission tower footings,
ground cables or counterpoise, or in other areas where fault currents or unusual risk of lightning
may be anticipated, it must be provided with protection against damage due to fault currents or
lightning, and protective measures must also be taken at insulating devices.

[Issued by Amdt. 192-4, 36 FR 12297, June 30, 1971; Amdt. 192-33, 43 FR 39389, Sept. 5, 1978]


                                            GUIDE MATERIAL

1   ELECTRICAL ISOLATION (§192.467(a), (b), and (c))

1.1 Insulating devices. (§192.467(a) and (b))
    Insulating devices may consist of insulating flange assemblies (see guide material under §192.147),
    unions or couplings, or fabricated insulating joints. These devices should be properly rated for
    temperature, pressure, and dielectric strength. Typical locations where electrical insulating devices
    should be considered include the following.


Addendum 5, November 2010                           181
GPTC GUIDE FOR GAS TRANSMISSION AND                                                                   §192.467
DISTRIBUTION PIPING SYSTEMS: 2009 Edition                                                           SUBPART I


    (a) At supporting pipe stanchions, bridge structures, tunnel enclosures, piling, and reinforced concrete
        foundations where electrical contact would preclude effective cathodic protection (CP). It may be
        necessary to electrically isolate the piping from such a structure, or the piping and structure from
        adjacent underground piping.
    (b) At metallic curb boxes and valve enclosures. These should be designed, fabricated and installed in
        such a manner that electrical isolation from the piping system will be maintained.
    (c) Where a pipe enters a building through a metallic wall sleeve and where it is intended to maintain
        electrical isolation between the sleeve and the pipe. To accomplish this, insulating spacers should
        be used.
    (d) At river weights, pipeline anchors, and metallic reinforcement in weight coatings. These should be
        electrically isolated from the carrier pipe and installed so that coating damage will not occur.
    (e) Points at which facilities change ownership, such as meter stations and well heads.
    (f) Connections to main line piping systems such as gathering or distribution system laterals.
    (g) Inlet and outlet piping of inline measuring or pressure regulating stations or both.
    (h) Compressor or pumping stations, either in the suction and discharge piping or in the main line
        immediately upstream and downstream of the station.
    (i) In stray current areas.
    (j) At the termination of service line connections and entrance piping to prevent electrical continuity with
        other metallic systems.

1.2 Casings. (§192.467(c))
    (a) New installations.
        (1) Spacers and sealing. All new construction of cased metallic pipelines should provide for the
            installation of insulating type casing spacers or other suitable means to prevent physical contact
            between the carrier pipe and casing. The ends of the casing may be sealed with a
            non-conductive sealing method to prevent mud, silt, and water from entering the annular space
            between the casing and the carrier pipe. It may be necessary to fill this annular space with a
            non-conductive type casing filler to ensure continued isolation in those installations where end
            seals alone may not be sufficient to resist the entrance of water.
        (2) Joining. Lengths of casing should be joined by a full weld, or other type of joint that will provide
            an adequate seal against water entrance. Any holes in the casing should be closed by welding,
            or otherwise sealed.
        (3) Insertion. Care should be taken during installation to reduce the possibility of electrical shorts.
            The carrier pipe should be as straight as practical. The internal diameter of the casing should be
            adequate to ensure physical clearance from the carrier pipe. The carrier pipe should be carefully
            inspected and all coating damage repaired. Care should be taken during insertion of the carrier
            pipe. To prevent damage to the coating and spacer, the casing should be clear of any mud,
            water, or debris prior to insertion of the carrier pipe. When existing buried pipe is being used as
            the casing, steps should be taken to ensure that the casing pipe is free of weld protrusions and
            other obstructions that might cause jamming of the carrier pipe during insertion.
            Where insulating type casing spacers are used, one should be installed as close as practical to
            each end of the casing. Vent connections, when required, should be installed prior to the
            insertion of the carrier pipe to preclude the possibility of damage to the carrier pipe.
    (b) Existing installations.
        Where there is an indication on existing installations that corrosion is occurring on the carrier pipe or
        where a CP installation is rendered inadequate as a result of low resistance between the casing and
        carrier pipe, practical measures to help ensure adequate corrosion protection on the pipeline may
        consist of one or more of the following.
        (1) Filling the annular space between the carrier pipe and casing with a non-conductive filler.
        (2) Applying additional CP to the pipe.
        (3) In some cases where the carrier pipe is electrically shorted to the casing, it may be practical to
            expose the ends of the casing and physically realign the carrier pipe to give enough clearance
            for inserting electric insulating material in sheet form between the casing and carrier pipe. The
            feasibility of safely moving the carrier pipe to clear a short should be determined prior to
            performing the work. See 4 of the guide material under §192.703.

Addendum 5, November 2010                         182
GPTC GUIDE FOR GAS TRANSMISSION AND                                                                    §192.467
DISTRIBUTION PIPING SYSTEMS: 2009 Edition                                                            SUBPART I


2   INSPECTION AND TESTING (§192.467(d))

    The required monitoring of CP systems and the evaluation of such test data is generally sufficient to
    ensure that electrical isolation is adequate on cathodically protected piping. However, specific electrical
    tests on insulating devices should be made where deemed necessary to ensure the adequacy of
    electrical isolation and to pinpoint operational problems on CP systems.

3   COMBUSTIBLE ATMOSPHERE (§192.467(e))

    (a) Precautions to prevent arcing may be taken by installing galvanic anode type grounding cells or
        commercial lightning or fault arrestors across the insulating devices.
    (b) Where lightning arrestors are installed across insulating devices within a building or other confined
        space anticipated to have a combustible atmosphere, the physical installation of the lightning
        arrestors should be made outside the confined space. Electrical conductors of adequate size
        should be installed from the insulating point to the lightning arrestors.

4   PROTECTION OF INSULATING DEVICES (§192.467(f))

    It is recommended that the operator make a study in collaboration with the electric company on the
    common problems of corrosion and electrolysis, taking into consideration the following factors.
    (a) The possibility of the pipeline carrying either unbalanced line currents or fault currents.
    (b) The possibility of lightning or fault currents inducing voltages sufficient to puncture pipe coatings or
          pipe.
    (c) CP of the pipeline, including the location of ground beds. (This is particularly important if the electric
          line is carried on steel towers.)
    (d) Bonding connections that exist between the pipeline and the overhead electric system at the
          following.
          (1) The steel tower footing;
          (2) The buried grounding facility; or
          (3) The ground wire.
    (e) Protection of insulating joints in the pipeline against induced voltages or currents resulting from
          lightning strikes. This can be obtained by:
          (1) Connecting buried sacrificial anodes to the pipe near the insulating joints;
          (2) Bridging the pipeline insulator with a spark-gap; or
          (3) Other effective means.
    (f) Cable connections from insulating devices to lightning and fault current arrestors should be short,
          direct, and of a size suitable for short-term, high current loading.
    (g) The electrical properties of nonwelded joints. (Where the objective is to ensure electrical continuity,
          it may be achieved by using fittings manufactured for this purpose or by bonding the mechanical
          joints in an approved manner. Conversely, if an insulating joint is required, a device manufactured
          to perform this function should be used. In either case, these fittings should be installed in
          accordance with the manufacturer's instructions.)

5   REFERENCES

    (a) NACE RP0177, "Mitigation of Alternating Current and Lightning Effects on Metallic Structures and
        Corrosion Control Systems."
    (b) NACE RP0200, "Steel-Cased Pipeline Practices."




                                                     183

Más contenido relacionado

La actualidad más candente

Hawke Universal Cable Glands - Installation Instruction
Hawke Universal Cable Glands - Installation InstructionHawke Universal Cable Glands - Installation Instruction
Hawke Universal Cable Glands - Installation InstructionThorne & Derrick International
 
Cablofil Cable Basket - Wire Cable Basket (Galvanised & Stainless Steel) Cata...
Cablofil Cable Basket - Wire Cable Basket (Galvanised & Stainless Steel) Cata...Cablofil Cable Basket - Wire Cable Basket (Galvanised & Stainless Steel) Cata...
Cablofil Cable Basket - Wire Cable Basket (Galvanised & Stainless Steel) Cata...Thorne & Derrick International
 
Plz Join us in Invitation Elecrama exhibition (18 22 jan2020 and new product...
Plz Join us in Invitation Elecrama exhibition  (18 22 jan2020 and new product...Plz Join us in Invitation Elecrama exhibition  (18 22 jan2020 and new product...
Plz Join us in Invitation Elecrama exhibition (18 22 jan2020 and new product...Mahesh Chandra Manav
 
36 td conventional
36 td conventional36 td conventional
36 td conventionalDixie23
 
Fm 00064 ams composite standing seam ii panel june, 2009_129236159432863269
Fm 00064 ams composite standing seam ii panel  june, 2009_129236159432863269Fm 00064 ams composite standing seam ii panel  june, 2009_129236159432863269
Fm 00064 ams composite standing seam ii panel june, 2009_129236159432863269Shaik Abdulla
 
Cswip 11-01 - plant inspection- Week 2 cours
Cswip 11-01 - plant inspection- Week 2 coursCswip 11-01 - plant inspection- Week 2 cours
Cswip 11-01 - plant inspection- Week 2 coursRafik Guerbous
 
Marechal Distribution Boxes - Marechal Express Boxes, Marechal Express Fire B...
Marechal Distribution Boxes - Marechal Express Boxes, Marechal Express Fire B...Marechal Distribution Boxes - Marechal Express Boxes, Marechal Express Fire B...
Marechal Distribution Boxes - Marechal Express Boxes, Marechal Express Fire B...Thorne & Derrick International
 
Api 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answersApi 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answersJasminder singh
 
Installation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvInstallation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvAlexander Decker
 
Trsv overview external
Trsv overview externalTrsv overview external
Trsv overview externalManuel Coxe
 
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...Thorne & Derrick International
 
Craig and Derricott Isolators & Switch Disconnectors - Isolation Equipment an...
Craig and Derricott Isolators & Switch Disconnectors - Isolation Equipment an...Craig and Derricott Isolators & Switch Disconnectors - Isolation Equipment an...
Craig and Derricott Isolators & Switch Disconnectors - Isolation Equipment an...Thorne & Derrick International
 

La actualidad más candente (17)

Hawke Universal Cable Glands - Installation Instruction
Hawke Universal Cable Glands - Installation InstructionHawke Universal Cable Glands - Installation Instruction
Hawke Universal Cable Glands - Installation Instruction
 
Cablofil Cable Basket - Wire Cable Basket (Galvanised & Stainless Steel) Cata...
Cablofil Cable Basket - Wire Cable Basket (Galvanised & Stainless Steel) Cata...Cablofil Cable Basket - Wire Cable Basket (Galvanised & Stainless Steel) Cata...
Cablofil Cable Basket - Wire Cable Basket (Galvanised & Stainless Steel) Cata...
 
Plz Join us in Invitation Elecrama exhibition (18 22 jan2020 and new product...
Plz Join us in Invitation Elecrama exhibition  (18 22 jan2020 and new product...Plz Join us in Invitation Elecrama exhibition  (18 22 jan2020 and new product...
Plz Join us in Invitation Elecrama exhibition (18 22 jan2020 and new product...
 
36 td conventional
36 td conventional36 td conventional
36 td conventional
 
Fm 00064 ams composite standing seam ii panel june, 2009_129236159432863269
Fm 00064 ams composite standing seam ii panel  june, 2009_129236159432863269Fm 00064 ams composite standing seam ii panel  june, 2009_129236159432863269
Fm 00064 ams composite standing seam ii panel june, 2009_129236159432863269
 
Cswip 11-01 - plant inspection- Week 2 cours
Cswip 11-01 - plant inspection- Week 2 coursCswip 11-01 - plant inspection- Week 2 cours
Cswip 11-01 - plant inspection- Week 2 cours
 
Cathodic Protection
Cathodic ProtectionCathodic Protection
Cathodic Protection
 
Hawke 501/453 Universal Cable Gland A M20
Hawke 501/453 Universal Cable Gland A M20Hawke 501/453 Universal Cable Gland A M20
Hawke 501/453 Universal Cable Gland A M20
 
Anmol bhargava casing basics
Anmol bhargava   casing basicsAnmol bhargava   casing basics
Anmol bhargava casing basics
 
Marechal Distribution Boxes - Marechal Express Boxes, Marechal Express Fire B...
Marechal Distribution Boxes - Marechal Express Boxes, Marechal Express Fire B...Marechal Distribution Boxes - Marechal Express Boxes, Marechal Express Fire B...
Marechal Distribution Boxes - Marechal Express Boxes, Marechal Express Fire B...
 
3M Heat Shrink Tubing & Sleeving
3M Heat Shrink Tubing & Sleeving3M Heat Shrink Tubing & Sleeving
3M Heat Shrink Tubing & Sleeving
 
IPSS for PCRD
IPSS for PCRDIPSS for PCRD
IPSS for PCRD
 
Api 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answersApi 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answers
 
Installation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvInstallation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kv
 
Trsv overview external
Trsv overview externalTrsv overview external
Trsv overview external
 
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...
 
Craig and Derricott Isolators & Switch Disconnectors - Isolation Equipment an...
Craig and Derricott Isolators & Switch Disconnectors - Isolation Equipment an...Craig and Derricott Isolators & Switch Disconnectors - Isolation Equipment an...
Craig and Derricott Isolators & Switch Disconnectors - Isolation Equipment an...
 

Similar a Ansi Gptc Z380.1 2009 192 467

Substation lightning protection and earthing standard(august 2019)
Substation lightning protection and earthing standard(august 2019)Substation lightning protection and earthing standard(august 2019)
Substation lightning protection and earthing standard(august 2019)Mahesh Chandra Manav
 
Electrical layout of
Electrical layout ofElectrical layout of
Electrical layout ofBhakti Stm
 
Corrosion control
Corrosion controlCorrosion control
Corrosion controlDuy Vu
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976Southern Railway
 
HA no. 2 EE182LDaet_Valdez
HA no. 2 EE182LDaet_ValdezHA no. 2 EE182LDaet_Valdez
HA no. 2 EE182LDaet_ValdezPrudenceDaet
 
2011 12-33kv tech.spec for v c b type- m2-c1-revised
2011 12-33kv tech.spec for v c b type- m2-c1-revised2011 12-33kv tech.spec for v c b type- m2-c1-revised
2011 12-33kv tech.spec for v c b type- m2-c1-revisedBasudev patra
 
METHOD OF WIRINGS.pdf
METHOD OF WIRINGS.pdfMETHOD OF WIRINGS.pdf
METHOD OF WIRINGS.pdfDonaldBohol1
 
Thiết kế đường ống trên bờ
Thiết kế đường ống trên bờThiết kế đường ống trên bờ
Thiết kế đường ống trên bờVcoi Vit
 
Thiet ke duong_ong_tren_bo
Thiet ke duong_ong_tren_boThiet ke duong_ong_tren_bo
Thiet ke duong_ong_tren_boRobinking Boley
 
An Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAn Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAli Osman Öncel
 
Fibre installation - Athene and Duffs Road Station[12].doc
Fibre installation - Athene and Duffs Road Station[12].docFibre installation - Athene and Duffs Road Station[12].doc
Fibre installation - Athene and Duffs Road Station[12].docThandabantu Magengelele
 
Specification for electrical automation and instrumentation 02
Specification for electrical automation and instrumentation  02Specification for electrical automation and instrumentation  02
Specification for electrical automation and instrumentation 02Sajeewa Lakmal
 
Cathodic Protection For Oil Wells
Cathodic Protection For Oil WellsCathodic Protection For Oil Wells
Cathodic Protection For Oil WellsAbinash Padhy
 

Similar a Ansi Gptc Z380.1 2009 192 467 (20)

Substation lightning protection and earthing standard(august 2019)
Substation lightning protection and earthing standard(august 2019)Substation lightning protection and earthing standard(august 2019)
Substation lightning protection and earthing standard(august 2019)
 
Electrical layout of
Electrical layout ofElectrical layout of
Electrical layout of
 
Corrosion control
Corrosion controlCorrosion control
Corrosion control
 
Instalaciones avionicas
Instalaciones avionicasInstalaciones avionicas
Instalaciones avionicas
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976
 
10334
1033410334
10334
 
HA no. 2 EE182LDaet_Valdez
HA no. 2 EE182LDaet_ValdezHA no. 2 EE182LDaet_Valdez
HA no. 2 EE182LDaet_Valdez
 
2011 12-33kv tech.spec for v c b type- m2-c1-revised
2011 12-33kv tech.spec for v c b type- m2-c1-revised2011 12-33kv tech.spec for v c b type- m2-c1-revised
2011 12-33kv tech.spec for v c b type- m2-c1-revised
 
KNPC Volume 3B.pdf
KNPC Volume 3B.pdfKNPC Volume 3B.pdf
KNPC Volume 3B.pdf
 
METHOD OF WIRINGS.pdf
METHOD OF WIRINGS.pdfMETHOD OF WIRINGS.pdf
METHOD OF WIRINGS.pdf
 
Safety for wiring methods
Safety for wiring methodsSafety for wiring methods
Safety for wiring methods
 
Thiết kế đường ống trên bờ
Thiết kế đường ống trên bờThiết kế đường ống trên bờ
Thiết kế đường ống trên bờ
 
Thiet ke duong_ong_tren_bo
Thiet ke duong_ong_tren_boThiet ke duong_ong_tren_bo
Thiet ke duong_ong_tren_bo
 
An Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAn Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara Sea
 
Fibre installation - Athene and Duffs Road Station[12].doc
Fibre installation - Athene and Duffs Road Station[12].docFibre installation - Athene and Duffs Road Station[12].doc
Fibre installation - Athene and Duffs Road Station[12].doc
 
Eat 105 Chapter 3
Eat 105  Chapter 3Eat 105  Chapter 3
Eat 105 Chapter 3
 
Mechanical
Mechanical Mechanical
Mechanical
 
Specification for electrical automation and instrumentation 02
Specification for electrical automation and instrumentation  02Specification for electrical automation and instrumentation  02
Specification for electrical automation and instrumentation 02
 
Cp1
Cp1Cp1
Cp1
 
Cathodic Protection For Oil Wells
Cathodic Protection For Oil WellsCathodic Protection For Oil Wells
Cathodic Protection For Oil Wells
 

Más de trorro

Gas Tite Flash Shield Product
Gas Tite Flash Shield ProductGas Tite Flash Shield Product
Gas Tite Flash Shield Producttrorro
 
Ansi Gptc Z380.1 2009 192 467
Ansi Gptc Z380.1   2009 192 467Ansi Gptc Z380.1   2009 192 467
Ansi Gptc Z380.1 2009 192 467trorro
 
Code Question
Code QuestionCode Question
Code Questiontrorro
 
Dca Commentary 2003
Dca Commentary 2003Dca Commentary 2003
Dca Commentary 2003trorro
 
Gas Pipe Becomes Grounding Electrode
Gas Pipe Becomes Grounding ElectrodeGas Pipe Becomes Grounding Electrode
Gas Pipe Becomes Grounding Electrodetrorro
 
Bonded Vs. Grounding
Bonded Vs. GroundingBonded Vs. Grounding
Bonded Vs. Groundingtrorro
 
Bonding Wire Connection
Bonding Wire ConnectionBonding Wire Connection
Bonding Wire Connectiontrorro
 
Placing The Bonding Clamp
Placing The Bonding ClampPlacing The Bonding Clamp
Placing The Bonding Clamptrorro
 
NJ DCA Commentary
NJ DCA CommentaryNJ DCA Commentary
NJ DCA Commentarytrorro
 
Outside Gas Meter
Outside Gas MeterOutside Gas Meter
Outside Gas Metertrorro
 
Irc Bonding Diagram
Irc Bonding DiagramIrc Bonding Diagram
Irc Bonding Diagramtrorro
 
Gas Pipe Becomes An Equipment Ground
Gas Pipe Becomes An Equipment GroundGas Pipe Becomes An Equipment Ground
Gas Pipe Becomes An Equipment Groundtrorro
 
Ifcg 2009
Ifcg 2009Ifcg 2009
Ifcg 2009trorro
 
Gas Meter With Dielectric Union
Gas Meter With Dielectric UnionGas Meter With Dielectric Union
Gas Meter With Dielectric Uniontrorro
 
Irc Commentary
Irc CommentaryIrc Commentary
Irc Commentarytrorro
 

Más de trorro (16)

Gas Tite Flash Shield Product
Gas Tite Flash Shield ProductGas Tite Flash Shield Product
Gas Tite Flash Shield Product
 
Ansi Gptc Z380.1 2009 192 467
Ansi Gptc Z380.1   2009 192 467Ansi Gptc Z380.1   2009 192 467
Ansi Gptc Z380.1 2009 192 467
 
Code Question
Code QuestionCode Question
Code Question
 
Dca Commentary 2003
Dca Commentary 2003Dca Commentary 2003
Dca Commentary 2003
 
Gas Pipe Becomes Grounding Electrode
Gas Pipe Becomes Grounding ElectrodeGas Pipe Becomes Grounding Electrode
Gas Pipe Becomes Grounding Electrode
 
Bonded Vs. Grounding
Bonded Vs. GroundingBonded Vs. Grounding
Bonded Vs. Grounding
 
Bonding Wire Connection
Bonding Wire ConnectionBonding Wire Connection
Bonding Wire Connection
 
Placing The Bonding Clamp
Placing The Bonding ClampPlacing The Bonding Clamp
Placing The Bonding Clamp
 
NJ DCA Commentary
NJ DCA CommentaryNJ DCA Commentary
NJ DCA Commentary
 
Outside Gas Meter
Outside Gas MeterOutside Gas Meter
Outside Gas Meter
 
Irc Bonding Diagram
Irc Bonding DiagramIrc Bonding Diagram
Irc Bonding Diagram
 
Gas Pipe Becomes An Equipment Ground
Gas Pipe Becomes An Equipment GroundGas Pipe Becomes An Equipment Ground
Gas Pipe Becomes An Equipment Ground
 
NFGC
NFGCNFGC
NFGC
 
Ifcg 2009
Ifcg 2009Ifcg 2009
Ifcg 2009
 
Gas Meter With Dielectric Union
Gas Meter With Dielectric UnionGas Meter With Dielectric Union
Gas Meter With Dielectric Union
 
Irc Commentary
Irc CommentaryIrc Commentary
Irc Commentary
 

Ansi Gptc Z380.1 2009 192 467

  • 1. GPTC GUIDE FOR GAS TRANSMISSION AND §192.465 DISTRIBUTION PIPING SYSTEMS: 2009 Edition SUBPART I (6) Cracks in gouges. (7) Coating defects. (b) No individual in-line inspection tool is universally applicable for the identification, measurement, and assessment of every type of anomaly. Tool selection and performance may be dependent upon the following parameters. (1) Type and size of anomalies to be detected. (2) Desired data resolution and sizing accuracy of anomalies. (3) Length of pipe to be inspected. (4) Ability to couple tool to pipe wall. (5) Desired tool speed. (6) Physical condition of the pipeline. (i) Internal cleanliness. (ii) Pipe wall deformations. (iii) Change in pipe wall or grade. 10.4 Reference. See guide material under §192.150. §192.467 External corrosion control: Electrical isolation. [Effective Date: 09/05/78] (a) Each buried or submerged pipeline must be electrically isolated from other underground metallic structures, unless the pipeline and the other structures are electrically interconnected and cathodically protected as a single unit. (b) One or more insulating devices must be installed where electrical isolation of a portion of a pipeline is necessary to facilitate the application of corrosion control. (c) Except for unprotected copper inserted in ferrous pipe, each pipeline must be electrically isolated from metallic casings that are a part of the underground system. However, if isolation is not achieved because it is impractical, other measures must be taken to minimize corrosion of the pipeline inside the casing. (d) Inspection and electrical tests must be made to assure that electrical isolation is adequate. (e) An insulating device may not be installed in an area where a combustible atmosphere is anticipated unless precautions are taken to prevent arcing. (f) Where a pipeline is located in close proximity to electrical transmission tower footings, ground cables or counterpoise, or in other areas where fault currents or unusual risk of lightning may be anticipated, it must be provided with protection against damage due to fault currents or lightning, and protective measures must also be taken at insulating devices. [Issued by Amdt. 192-4, 36 FR 12297, June 30, 1971; Amdt. 192-33, 43 FR 39389, Sept. 5, 1978] GUIDE MATERIAL 1 ELECTRICAL ISOLATION (§192.467(a), (b), and (c)) 1.1 Insulating devices. (§192.467(a) and (b)) Insulating devices may consist of insulating flange assemblies (see guide material under §192.147), unions or couplings, or fabricated insulating joints. These devices should be properly rated for temperature, pressure, and dielectric strength. Typical locations where electrical insulating devices should be considered include the following. Addendum 5, November 2010 181
  • 2. GPTC GUIDE FOR GAS TRANSMISSION AND §192.467 DISTRIBUTION PIPING SYSTEMS: 2009 Edition SUBPART I (a) At supporting pipe stanchions, bridge structures, tunnel enclosures, piling, and reinforced concrete foundations where electrical contact would preclude effective cathodic protection (CP). It may be necessary to electrically isolate the piping from such a structure, or the piping and structure from adjacent underground piping. (b) At metallic curb boxes and valve enclosures. These should be designed, fabricated and installed in such a manner that electrical isolation from the piping system will be maintained. (c) Where a pipe enters a building through a metallic wall sleeve and where it is intended to maintain electrical isolation between the sleeve and the pipe. To accomplish this, insulating spacers should be used. (d) At river weights, pipeline anchors, and metallic reinforcement in weight coatings. These should be electrically isolated from the carrier pipe and installed so that coating damage will not occur. (e) Points at which facilities change ownership, such as meter stations and well heads. (f) Connections to main line piping systems such as gathering or distribution system laterals. (g) Inlet and outlet piping of inline measuring or pressure regulating stations or both. (h) Compressor or pumping stations, either in the suction and discharge piping or in the main line immediately upstream and downstream of the station. (i) In stray current areas. (j) At the termination of service line connections and entrance piping to prevent electrical continuity with other metallic systems. 1.2 Casings. (§192.467(c)) (a) New installations. (1) Spacers and sealing. All new construction of cased metallic pipelines should provide for the installation of insulating type casing spacers or other suitable means to prevent physical contact between the carrier pipe and casing. The ends of the casing may be sealed with a non-conductive sealing method to prevent mud, silt, and water from entering the annular space between the casing and the carrier pipe. It may be necessary to fill this annular space with a non-conductive type casing filler to ensure continued isolation in those installations where end seals alone may not be sufficient to resist the entrance of water. (2) Joining. Lengths of casing should be joined by a full weld, or other type of joint that will provide an adequate seal against water entrance. Any holes in the casing should be closed by welding, or otherwise sealed. (3) Insertion. Care should be taken during installation to reduce the possibility of electrical shorts. The carrier pipe should be as straight as practical. The internal diameter of the casing should be adequate to ensure physical clearance from the carrier pipe. The carrier pipe should be carefully inspected and all coating damage repaired. Care should be taken during insertion of the carrier pipe. To prevent damage to the coating and spacer, the casing should be clear of any mud, water, or debris prior to insertion of the carrier pipe. When existing buried pipe is being used as the casing, steps should be taken to ensure that the casing pipe is free of weld protrusions and other obstructions that might cause jamming of the carrier pipe during insertion. Where insulating type casing spacers are used, one should be installed as close as practical to each end of the casing. Vent connections, when required, should be installed prior to the insertion of the carrier pipe to preclude the possibility of damage to the carrier pipe. (b) Existing installations. Where there is an indication on existing installations that corrosion is occurring on the carrier pipe or where a CP installation is rendered inadequate as a result of low resistance between the casing and carrier pipe, practical measures to help ensure adequate corrosion protection on the pipeline may consist of one or more of the following. (1) Filling the annular space between the carrier pipe and casing with a non-conductive filler. (2) Applying additional CP to the pipe. (3) In some cases where the carrier pipe is electrically shorted to the casing, it may be practical to expose the ends of the casing and physically realign the carrier pipe to give enough clearance for inserting electric insulating material in sheet form between the casing and carrier pipe. The feasibility of safely moving the carrier pipe to clear a short should be determined prior to performing the work. See 4 of the guide material under §192.703. Addendum 5, November 2010 182
  • 3. GPTC GUIDE FOR GAS TRANSMISSION AND §192.467 DISTRIBUTION PIPING SYSTEMS: 2009 Edition SUBPART I 2 INSPECTION AND TESTING (§192.467(d)) The required monitoring of CP systems and the evaluation of such test data is generally sufficient to ensure that electrical isolation is adequate on cathodically protected piping. However, specific electrical tests on insulating devices should be made where deemed necessary to ensure the adequacy of electrical isolation and to pinpoint operational problems on CP systems. 3 COMBUSTIBLE ATMOSPHERE (§192.467(e)) (a) Precautions to prevent arcing may be taken by installing galvanic anode type grounding cells or commercial lightning or fault arrestors across the insulating devices. (b) Where lightning arrestors are installed across insulating devices within a building or other confined space anticipated to have a combustible atmosphere, the physical installation of the lightning arrestors should be made outside the confined space. Electrical conductors of adequate size should be installed from the insulating point to the lightning arrestors. 4 PROTECTION OF INSULATING DEVICES (§192.467(f)) It is recommended that the operator make a study in collaboration with the electric company on the common problems of corrosion and electrolysis, taking into consideration the following factors. (a) The possibility of the pipeline carrying either unbalanced line currents or fault currents. (b) The possibility of lightning or fault currents inducing voltages sufficient to puncture pipe coatings or pipe. (c) CP of the pipeline, including the location of ground beds. (This is particularly important if the electric line is carried on steel towers.) (d) Bonding connections that exist between the pipeline and the overhead electric system at the following. (1) The steel tower footing; (2) The buried grounding facility; or (3) The ground wire. (e) Protection of insulating joints in the pipeline against induced voltages or currents resulting from lightning strikes. This can be obtained by: (1) Connecting buried sacrificial anodes to the pipe near the insulating joints; (2) Bridging the pipeline insulator with a spark-gap; or (3) Other effective means. (f) Cable connections from insulating devices to lightning and fault current arrestors should be short, direct, and of a size suitable for short-term, high current loading. (g) The electrical properties of nonwelded joints. (Where the objective is to ensure electrical continuity, it may be achieved by using fittings manufactured for this purpose or by bonding the mechanical joints in an approved manner. Conversely, if an insulating joint is required, a device manufactured to perform this function should be used. In either case, these fittings should be installed in accordance with the manufacturer's instructions.) 5 REFERENCES (a) NACE RP0177, "Mitigation of Alternating Current and Lightning Effects on Metallic Structures and Corrosion Control Systems." (b) NACE RP0200, "Steel-Cased Pipeline Practices." 183