   Write a Curriculum Vita (CV) to present to the
    employers at the coming ZU Job Fair .
   Make sure to include:
    ◦ Your personal data including your photo, whenever
      possible.
    ◦ Show your academic progress.
    ◦ Show your interest in Civil Engineering.
    ◦ Explain your future goals in this career.
    ◦ Explain why you should be selected.
   Hint: Search the internet on how to write a resume.



                                           4/9/2013       3
 By the end of this part of lecture, you will:
1. Differentiate between Construction
   Management and Construction Project
   Management.
2. Discuss Needs for Management in
   Construction.
3. Define Management.
4. Know parties involved in construction and their
   role.
5. Discuss Types of Construction Projects.
6. Discuss Types of Construction Companies.
7. Define Project Cycle.
8. Discuss Project Delivery Systems.



                                       4/9/2013      4
1.    What are the Methods of contractor selection
2.    What are the types of construction contracts?
3.    Define the following:
     a) Project delivery system - Markup - Profit - Risk -
        Subcontractor
4.    What are the steps of:
     a) Tendering process ?
     b) Estimating project cost?
5.    What is the difference between Bid bond and Contract
      bond?
6.    What is the difference between direct and indirect cost?
7.    What is the difference between Lowest bid and Lowest
      responsible bid?
8.    What is the difference between Balanced bid and
      Unbalanced bid?


                                                      4/9/2013   5
Management

                   Engineering

                     Science
   Planning
   Organizing
   Commanding
   Coordinating
   Controlling

                                 4/9/2013   6





               
               
           ◦
           ◦
           ◦
           ◦



4/9/2013           7



               
           ◦
           ◦
           ◦




4/9/2013           8

           
           

           




4/9/2013       9
   Client / owner
   Contractor
   Designer / consultant

Others:
 Project manager
 Users
 Public authorities




                            4/9/2013   10
Owner        
             
             
             
             
             
             
             
             



  4/9/2013       11
Designer        
                
                
                
                
                
                
                




     4/9/2013       12
Contractor        
                  
                  
                  
                  
                  
                  




       4/9/2013       13
   Residential
              -      -     40-45
   Nonresidential
         -       -       25-30
                                            -
   Engineering
    -    -      -    -     20-

   Industrial
          -          -     5-


                                 4/9/2013       14
.1


           .2


           .3


           .4


           .5




4/9/2013        15
 Concept
 Design
 Bidding/Procurement
 Construction
 Startup
 Utilization




                        4/9/2013   16
Factors affect the selection of PDS:
 Past practices, traditions, and experience;
 The advice of consultants;
 Funding sources and constraints;
 The effective use of staff and working capital;
 The interests of other project stakeholders.




                                      4/9/2013      17
   Design/Bid/Build (DBB)
   Design/Build (DB)
   Design/Build/Operate/Maintain (DBOM)
   Design/Build/Finance (DBF)
   Build/Operate/Transfer (BOT)
   Build/Own/Operate/Transfer (BOOT)
   Build/Own/Operate (BOO)
   Construction Management (CM)



                                    4/9/2013   18
4/9/2013   19

Más contenido relacionado

Destacado (20)

Columns rajeevan sir
Columns rajeevan sirColumns rajeevan sir
Columns rajeevan sir
 
Ch 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisalCh 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisal
 
Ch 6 construction progress control
Ch 6 construction progress controlCh 6 construction progress control
Ch 6 construction progress control
 
P resources
P resourcesP resources
P resources
 
P introduction
P introductionP introduction
P introduction
 
Cm exercise 8
Cm exercise 8Cm exercise 8
Cm exercise 8
 
Ch 2 planning and scheduling
Ch 2 planning and schedulingCh 2 planning and scheduling
Ch 2 planning and scheduling
 
Cm exercise 2
Cm exercise 2Cm exercise 2
Cm exercise 2
 
P scheduling
P schedulingP scheduling
P scheduling
 
Emad cv
Emad cvEmad cv
Emad cv
 
P overview
P overviewP overview
P overview
 
Session 4 gdas pmp study group presentation
Session 4   gdas pmp study group presentationSession 4   gdas pmp study group presentation
Session 4 gdas pmp study group presentation
 
Cm exercise 6
Cm exercise 6Cm exercise 6
Cm exercise 6
 
Contract
ContractContract
Contract
 
Cm exercise 3
Cm exercise 3Cm exercise 3
Cm exercise 3
 
P project finance
P project financeP project finance
P project finance
 
P repetitive
P repetitiveP repetitive
P repetitive
 
Cm exercise 7
Cm exercise 7Cm exercise 7
Cm exercise 7
 
P planning
P planningP planning
P planning
 
Cm exercise 5
Cm exercise 5Cm exercise 5
Cm exercise 5
 

Similar a 1.introduction

7-vcc-how-to-design-for-manufacture-and-assembly (1).pdf
7-vcc-how-to-design-for-manufacture-and-assembly (1).pdf7-vcc-how-to-design-for-manufacture-and-assembly (1).pdf
7-vcc-how-to-design-for-manufacture-and-assembly (1).pdf
SushmaNln
 
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdfCCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
ChassyTesoro1
 
Harita Techserv_Corporate Profile
Harita Techserv_Corporate ProfileHarita Techserv_Corporate Profile
Harita Techserv_Corporate Profile
Omkar Nagvenkar
 
Key success factors selling OpenERP. François Pietquin, OpenERP
Key success factors selling OpenERP. François Pietquin, OpenERPKey success factors selling OpenERP. François Pietquin, OpenERP
Key success factors selling OpenERP. François Pietquin, OpenERP
Odoo
 
Pilot Study on Lean Manufacturing Implementation
Pilot Study on Lean Manufacturing ImplementationPilot Study on Lean Manufacturing Implementation
Pilot Study on Lean Manufacturing Implementation
Redza Amin
 

Similar a 1.introduction (20)

Continuous Delivery: Rapid and Reliable Releases with DevOps Practices
Continuous Delivery: Rapid and Reliable Releases with DevOps PracticesContinuous Delivery: Rapid and Reliable Releases with DevOps Practices
Continuous Delivery: Rapid and Reliable Releases with DevOps Practices
 
Project Manager versus Product Manager.
Project Manager versus Product Manager.Project Manager versus Product Manager.
Project Manager versus Product Manager.
 
Quill SigDoc 2013
Quill SigDoc 2013Quill SigDoc 2013
Quill SigDoc 2013
 
Aleks Baltovski
Aleks BaltovskiAleks Baltovski
Aleks Baltovski
 
Spiral model
Spiral modelSpiral model
Spiral model
 
Open implementation practice for wide-scale e-Portfolio use #ALTC2013
Open implementation practice for wide-scale e-Portfolio use #ALTC2013Open implementation practice for wide-scale e-Portfolio use #ALTC2013
Open implementation practice for wide-scale e-Portfolio use #ALTC2013
 
DONG CoRep Program
DONG CoRep ProgramDONG CoRep Program
DONG CoRep Program
 
GOOCH_PRE-QUALIFICATION_PROFILE.pdf
GOOCH_PRE-QUALIFICATION_PROFILE.pdfGOOCH_PRE-QUALIFICATION_PROFILE.pdf
GOOCH_PRE-QUALIFICATION_PROFILE.pdf
 
Being Architect
Being ArchitectBeing Architect
Being Architect
 
Bpmppt
BpmpptBpmppt
Bpmppt
 
Introduction to lean
Introduction to leanIntroduction to lean
Introduction to lean
 
7-vcc-how-to-design-for-manufacture-and-assembly (1).pdf
7-vcc-how-to-design-for-manufacture-and-assembly (1).pdf7-vcc-how-to-design-for-manufacture-and-assembly (1).pdf
7-vcc-how-to-design-for-manufacture-and-assembly (1).pdf
 
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdfCCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
 
Greg Labbe: quality control issues in housing construction
Greg Labbe: quality control issues in housing constructionGreg Labbe: quality control issues in housing construction
Greg Labbe: quality control issues in housing construction
 
Harita Techserv_Corporate Profile
Harita Techserv_Corporate ProfileHarita Techserv_Corporate Profile
Harita Techserv_Corporate Profile
 
Application Archaeology: Accelerating App Modernization at DICK’S Sporting Goods
Application Archaeology: Accelerating App Modernization at DICK’S Sporting GoodsApplication Archaeology: Accelerating App Modernization at DICK’S Sporting Goods
Application Archaeology: Accelerating App Modernization at DICK’S Sporting Goods
 
Continuous Delivery: Rapid and Reliable Releases with DevOps Practices
Continuous Delivery: Rapid and Reliable Releases with DevOps PracticesContinuous Delivery: Rapid and Reliable Releases with DevOps Practices
Continuous Delivery: Rapid and Reliable Releases with DevOps Practices
 
Key success factors selling OpenERP. François Pietquin, OpenERP
Key success factors selling OpenERP. François Pietquin, OpenERPKey success factors selling OpenERP. François Pietquin, OpenERP
Key success factors selling OpenERP. François Pietquin, OpenERP
 
Pilot Study on Lean Manufacturing Implementation
Pilot Study on Lean Manufacturing ImplementationPilot Study on Lean Manufacturing Implementation
Pilot Study on Lean Manufacturing Implementation
 
Ishwar PROJECT REPORT
Ishwar PROJECT REPORTIshwar PROJECT REPORT
Ishwar PROJECT REPORT
 

Más de Tu Nguyen, PMP®,PMI-RMP® (16)

Session 10 gdas pmp study group presentation
Session 10   gdas pmp study group presentationSession 10   gdas pmp study group presentation
Session 10 gdas pmp study group presentation
 
Session 2 gdas pmp study group presentation
Session 2   gdas pmp study group presentationSession 2   gdas pmp study group presentation
Session 2 gdas pmp study group presentation
 
Node
NodeNode
Node
 
Cash flow
Cash flowCash flow
Cash flow
 
Bar chart
Bar chartBar chart
Bar chart
 
Arrow computation
Arrow computationArrow computation
Arrow computation
 
Arrow
ArrowArrow
Arrow
 
Administration
AdministrationAdministration
Administration
 
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
 
Time cost-control
Time cost-controlTime cost-control
Time cost-control
 
Resources
ResourcesResources
Resources
 
Pert
PertPert
Pert
 
Organization
OrganizationOrganization
Organization
 
Ch 3 contract strategy
Ch 3 contract strategyCh 3 contract strategy
Ch 3 contract strategy
 
Ch 1 organization of construction projects
Ch 1 organization of construction projectsCh 1 organization of construction projects
Ch 1 organization of construction projects
 
Ch 5 estimating and tendering
Ch 5 estimating and tenderingCh 5 estimating and tendering
Ch 5 estimating and tendering
 

Último

What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...
srcw2322l101
 
00971508021841 حبوب الإجهاض في دبي | أبوظبي | الشارقة | السطوة |❇ ❈ ((![© ر
00971508021841 حبوب الإجهاض في دبي | أبوظبي | الشارقة | السطوة |❇ ❈ ((![©  ر00971508021841 حبوب الإجهاض في دبي | أبوظبي | الشارقة | السطوة |❇ ❈ ((![©  ر
00971508021841 حبوب الإجهاض في دبي | أبوظبي | الشارقة | السطوة |❇ ❈ ((![© ر
nafizanafzal
 
Shots fired Budget Presentation.pdf12312
Shots fired Budget Presentation.pdf12312Shots fired Budget Presentation.pdf12312
Shots fired Budget Presentation.pdf12312
LR1709MUSIC
 
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg Pfizer
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg PfizerJual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg Pfizer
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg Pfizer
Pusat Herbal Resmi BPOM
 
Constitution of Company Article of Association
Constitution of Company Article of AssociationConstitution of Company Article of Association
Constitution of Company Article of Association
seri bangash
 
#Mtp-Kit Prices » Qatar. Doha (+27737758557) Abortion Pills For Sale In Doha,...
#Mtp-Kit Prices » Qatar. Doha (+27737758557) Abortion Pills For Sale In Doha,...#Mtp-Kit Prices » Qatar. Doha (+27737758557) Abortion Pills For Sale In Doha,...
#Mtp-Kit Prices » Qatar. Doha (+27737758557) Abortion Pills For Sale In Doha,...
drm1699
 

Último (20)

Exploring-Pipe-Flanges-Applications-Types-and-Benefits.pptx
Exploring-Pipe-Flanges-Applications-Types-and-Benefits.pptxExploring-Pipe-Flanges-Applications-Types-and-Benefits.pptx
Exploring-Pipe-Flanges-Applications-Types-and-Benefits.pptx
 
PitchBook’s Guide to VC Funding for Startups
PitchBook’s Guide to VC Funding for StartupsPitchBook’s Guide to VC Funding for Startups
PitchBook’s Guide to VC Funding for Startups
 
Inside the Black Box of Venture Capital (VC)
Inside the Black Box of Venture Capital (VC)Inside the Black Box of Venture Capital (VC)
Inside the Black Box of Venture Capital (VC)
 
Stages of Startup Funding - An Explainer
Stages of Startup Funding - An ExplainerStages of Startup Funding - An Explainer
Stages of Startup Funding - An Explainer
 
What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...
 
Pitch Deck Teardown: Goodcarbon's $5.5m Seed deck
Pitch Deck Teardown: Goodcarbon's $5.5m Seed deckPitch Deck Teardown: Goodcarbon's $5.5m Seed deck
Pitch Deck Teardown: Goodcarbon's $5.5m Seed deck
 
00971508021841 حبوب الإجهاض في دبي | أبوظبي | الشارقة | السطوة |❇ ❈ ((![© ر
00971508021841 حبوب الإجهاض في دبي | أبوظبي | الشارقة | السطوة |❇ ❈ ((![©  ر00971508021841 حبوب الإجهاض في دبي | أبوظبي | الشارقة | السطوة |❇ ❈ ((![©  ر
00971508021841 حبوب الإجهاض في دبي | أبوظبي | الشارقة | السطوة |❇ ❈ ((![© ر
 
wagamamaLab presentation @MIT 20240509 IRODORI
wagamamaLab presentation @MIT 20240509 IRODORIwagamamaLab presentation @MIT 20240509 IRODORI
wagamamaLab presentation @MIT 20240509 IRODORI
 
Moradia Isolada com Logradouro; Detached house with patio in Penacova
Moradia Isolada com Logradouro; Detached house with patio in PenacovaMoradia Isolada com Logradouro; Detached house with patio in Penacova
Moradia Isolada com Logradouro; Detached house with patio in Penacova
 
MichaelStarkes_UncutGemsProjectSummary.pdf
MichaelStarkes_UncutGemsProjectSummary.pdfMichaelStarkes_UncutGemsProjectSummary.pdf
MichaelStarkes_UncutGemsProjectSummary.pdf
 
Series A Fundraising Guide (Investing Individuals Improving Our World) by Accion
Series A Fundraising Guide (Investing Individuals Improving Our World) by AccionSeries A Fundraising Guide (Investing Individuals Improving Our World) by Accion
Series A Fundraising Guide (Investing Individuals Improving Our World) by Accion
 
Unlocking Growth The Power of Outsourcing for CPA Firms
Unlocking Growth The Power of Outsourcing for CPA FirmsUnlocking Growth The Power of Outsourcing for CPA Firms
Unlocking Growth The Power of Outsourcing for CPA Firms
 
Shots fired Budget Presentation.pdf12312
Shots fired Budget Presentation.pdf12312Shots fired Budget Presentation.pdf12312
Shots fired Budget Presentation.pdf12312
 
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdfInnomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
 
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg Pfizer
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg PfizerJual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg Pfizer
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg Pfizer
 
Constitution of Company Article of Association
Constitution of Company Article of AssociationConstitution of Company Article of Association
Constitution of Company Article of Association
 
#Mtp-Kit Prices » Qatar. Doha (+27737758557) Abortion Pills For Sale In Doha,...
#Mtp-Kit Prices » Qatar. Doha (+27737758557) Abortion Pills For Sale In Doha,...#Mtp-Kit Prices » Qatar. Doha (+27737758557) Abortion Pills For Sale In Doha,...
#Mtp-Kit Prices » Qatar. Doha (+27737758557) Abortion Pills For Sale In Doha,...
 
Top^Clinic ^%[+27785538335__Safe*Women's clinic//Abortion Pills In Harare
Top^Clinic ^%[+27785538335__Safe*Women's clinic//Abortion Pills In HarareTop^Clinic ^%[+27785538335__Safe*Women's clinic//Abortion Pills In Harare
Top^Clinic ^%[+27785538335__Safe*Women's clinic//Abortion Pills In Harare
 
How Do Venture Capitalists Make Decisions?
How Do Venture Capitalists Make Decisions?How Do Venture Capitalists Make Decisions?
How Do Venture Capitalists Make Decisions?
 
stock price prediction using machine learning
stock price prediction using machine learningstock price prediction using machine learning
stock price prediction using machine learning
 

1.introduction

  • 1. Ahmed Elyamany, PhD October 24/27, 2010 4/9/2013 1
  • 2. • • • • • • • • • • • • 4/9/2013 2
  • 3. Write a Curriculum Vita (CV) to present to the employers at the coming ZU Job Fair .  Make sure to include: ◦ Your personal data including your photo, whenever possible. ◦ Show your academic progress. ◦ Show your interest in Civil Engineering. ◦ Explain your future goals in this career. ◦ Explain why you should be selected.  Hint: Search the internet on how to write a resume. 4/9/2013 3
  • 4.  By the end of this part of lecture, you will: 1. Differentiate between Construction Management and Construction Project Management. 2. Discuss Needs for Management in Construction. 3. Define Management. 4. Know parties involved in construction and their role. 5. Discuss Types of Construction Projects. 6. Discuss Types of Construction Companies. 7. Define Project Cycle. 8. Discuss Project Delivery Systems. 4/9/2013 4
  • 5. 1. What are the Methods of contractor selection 2. What are the types of construction contracts? 3. Define the following: a) Project delivery system - Markup - Profit - Risk - Subcontractor 4. What are the steps of: a) Tendering process ? b) Estimating project cost? 5. What is the difference between Bid bond and Contract bond? 6. What is the difference between direct and indirect cost? 7. What is the difference between Lowest bid and Lowest responsible bid? 8. What is the difference between Balanced bid and Unbalanced bid? 4/9/2013 5
  • 6. Management Engineering Science  Planning  Organizing  Commanding  Coordinating  Controlling 4/9/2013 6
  • 7.   ◦ ◦ ◦ ◦ 4/9/2013 7
  • 8.  ◦ ◦ ◦ 4/9/2013 8
  • 9.    4/9/2013 9
  • 10. Client / owner  Contractor  Designer / consultant Others:  Project manager  Users  Public authorities 4/9/2013 10
  • 11. Owner          4/9/2013 11
  • 12. Designer         4/9/2013 12
  • 13. Contractor        4/9/2013 13
  • 14. Residential - - 40-45  Nonresidential - - 25-30 -  Engineering - - - - 20-  Industrial - - 5- 4/9/2013 14
  • 15. .1 .2 .3 .4 .5 4/9/2013 15
  • 16.  Concept  Design  Bidding/Procurement  Construction  Startup  Utilization 4/9/2013 16
  • 17. Factors affect the selection of PDS:  Past practices, traditions, and experience;  The advice of consultants;  Funding sources and constraints;  The effective use of staff and working capital;  The interests of other project stakeholders. 4/9/2013 17
  • 18. Design/Bid/Build (DBB)  Design/Build (DB)  Design/Build/Operate/Maintain (DBOM)  Design/Build/Finance (DBF)  Build/Operate/Transfer (BOT)  Build/Own/Operate/Transfer (BOOT)  Build/Own/Operate (BOO)  Construction Management (CM) 4/9/2013 18
  • 19. 4/9/2013 19