SlideShare una empresa de Scribd logo
1 de 16
Descargar para leer sin conexión
Resources
        Management



             Resources Management
What a resource?

         Any thing that is used by an activity to get the work done,

         such as: Material, Equipment, Labor, Money, …..

         Resources can be classified as:

             Consumable (Money, Material,……)

             Non Consumable (Labor, Equipment,…)




04/11/2006                     Emad Elbeltagi                          2




                                                                           1
Resources Management
Duration-Driven Schedule

       All CPM scheduling techniques are duration driven schedules

       Basic units: activities, durations, relationships

       Assumes resources are available whenever needed

       Also, resources can be classified as:

             Key or constrained resources (Skilled labor, Equipment,……)

             Secondary or non-constrained resources (Labor, …)

             General resources, used by all activities

04/11/2006                       Emad Elbeltagi                           3




             Resources Management
  Resource aggregation or Resource loading

             The summation, on a period-by-period basis, of the

             resources required to complete all activities based on the

             schedule carried out in the previous stage

             The results are usually shown graphically as a histogram

             A separate graph will be required for each resource




04/11/2006                       Emad Elbeltagi                           4




                                                                              2
Resources Management
Resource aggregation or Resource loading

         Consider the following activities


      Activity        Duration (Weeks)             Resources (units/week)


             A               2
             B               3
             C               2                     Shown in the histogram
             D               5
             E               2



             Resource limit = 10 units /week


04/11/2006                        Emad Elbeltagi                                5




                 Resources Management
Resource aggregation or Resource loading




                                                                        Resource limit



04/11/2006                        Emad Elbeltagi                                6




                                                                                         3
Resources Management
 Resource aggregation or Resource loading




 04/11/2006                               Emad Elbeltagi                                7




              Resources Management
   Problems Associated with Resource
              Resource Fluctuation (Resource leveling)
              Resource Over allocation (Resource Scheduling)

    Resource                                      Resource


Resource
  limit



                                       Time                                           Time
           Resource profile with                       Less hiring and firing
           high resource fluctuation                  (More stable work conditions)
           (High hiring and firing)




 04/11/2006                               Emad Elbeltagi                                8




                                                                                             4
Resources Management
 Methods for Resolving Resource conflicts (Problems)
              Optimization Models (Utilize optimization techniques):
                 Linear programming models
                 Advantages: Provide optimum solution
                 Limitations: Cannot be applied to large problems

              Heuristic Models (Utilize rule of thumb based on experience):
                 Heuristic or rules of thumb
                 Advantages: Can be applied to large problems
                 Limitations: Do not provide optimum solution




 04/11/2006                        Emad Elbeltagi                       9




              Resources Management
Resource Leveling (Smoothing)
Unconstrained resource scheduling (Constrained time)

   Resource Leveling

              Resource unconstrained (No limits on resources)

              Time (Project completion) constrained; project duration not
              be delayed

              Reduce the difference between the peaks and the valleys

              Average resource usage

              The objective is to smooth the use of the resources to
              avoid the resource fluctuation

 04/11/2006                        Emad Elbeltagi                       10




                                                                              5
Resources Management
Resource Leveling (Smoothing)




04/11/2006            Emad Elbeltagi       11




             Resources Management
Resource Leveling (Smoothing)
 Minimum Moment Algorithm = ∑ Yi * Yi /2




04/11/2006            Emad Elbeltagi       12




                                                6
Resources Management
Resource Leveling (Smoothing)
 Heuristic Method Procedure

             Prepare a complete activity schedule

             Draw a bar chart based on ES timings

             Draw the FF as dashed line beside the upper side of the bar
             and the TF beside the lower side

             Put the resource usage in each bar of the related activity

             Critical activities to be drawn first (do not move them)

             Aggregate the resources in each time period


04/11/2006                          Emad Elbeltagi                           13




              Resources Management
Resource Leveling (Smoothing)
 Procedure

             Calculate the total usage of resources = ∑ unit period usage

             Calculate the average resource usage = ∑ usage / utilization
             period

             Shift non-critical activities within their FF first, then their TF to
             decrease the peaks and raise the valleys

             Revise the activities float

             Aggregate the resources in each time period


04/11/2006                          Emad Elbeltagi                           14




                                                                                     7
Resources Management
Resource Leveling (Example)
 Example
                                                                   Resource
      Activity     Duration (Weeks)           Predecessors
                                                                 (units/week)
         A                    0                      -                  0
         B                    2                      1                  0
         C                    5                      1                  2
         D                    3                      1                  2
         E                    2                      2                  1
         F                    6                      2                  2
         G                    6                      3                  3
         H                    6                      4                  1
         I                    4                      4                  0
         J                    2                    5, 6                 4
         K                    7                    6, 7                 2
         L                    3                    2, 8                 2
         M                    2                   2, 8, 9               4
         N                    2               10, 11, 12, 13            0


04/11/2006                        Emad Elbeltagi                                15




             Resources Management
Resource Leveling (Example)
                                  2     4
                                   E (2)
                                  14 16


                    0     2       2     8          8    10
                     B (2)         F (6)            J (2)
                    3     5       5    11          16 18


         0     0    0     5       5    11          11 18       18 20
          A (0)      C (5)         G (6)            K (7)       N (2)
         0     0    0     5       5    11          11 18       18 20


                    0     3       3     9          9    12
                     D (3)         H (6)            L (3)
                    6     9       9    15          15 18


                                  3       7        9    11
                                    I (4)           M (2)
                                  12 16            16 18
04/11/2006                        Emad Elbeltagi                                16




                                                                                     8
Resources Management
Resource Leveling (Example)

  Activity                     ES                                  EF                      FF             TF

     A                          0                                   0                       0               0
     B                          0                                   2                       0               3
     C                          0                                   5                       0               0
     D                          0                                   3                       0               6
     E                          2                                   4                       4              12
     F                          2                                   8                       0               3
     G                          5                                  11                       0               0
     H                          3                                   9                       0               6
     I                          3                                   7                       2               9
     J                          8                                  10                       8               8
     K                         11                                  18                       0               0
     L                          9                                  12                       6               6
     M                          9                                  11                       7               7
     N                         18                                  20                       0               0



04/11/2006                                                      Emad Elbeltagi                                         17




             Resources Management
Resource Leveling (Example)
      0 1     2     3      4    5      6        7       8       9 10 11 12 13 14 15 16 17 18 19 20
                  C, 2
                                                            G, 3
                                                                                         K, 2
                                                                                                        N, 0

         B, 0
           D, 2
                    E, 1
                                    F, 2
                                           H, 1
                                    I, 0
                                                                J, 4
                                                                       L, 2
                                                                   M, 4

         4 4 7           6 5 6              6       6       8      13 9 4        2   2    2 2   2   2          ∑= 90




04/11/2006                                                      Emad Elbeltagi                                         18




                                                                                                                            9
Resources Management
    Resource Leveling (Example)
         14
         13
         12
         11
         10
          9
          8
          7
          6
          5
          4
          3
          2
          1
          0
               1     2        3       4 5                6      7       8 9 10 11 12 13 14 15 16 17 18 19 20




      04/11/2006                                                          Emad Elbeltagi                                     19




                    Resources Management
      Resource Leveling (Example)
              0 1    2        3       4       5        6     7      8     9 10 11 12 13 14 15 16 17 18 19 20
                         C, 2
                                                                        G, 3
                                                                                                   K, 2
                                                                                                              N, 0

               B, 0
                 D, 2
                           E, 1
                                                  F, 2
                                                         H, 1
                                                  I, 0
                                                                          J, 4
                                                                                 L, 2
                                                                               M, 4

               4 4        7       6       5        6         6 6 8 13 9 4                  2   2    22 2  2          ∑= 90
M (7 days)                                                           -4 -4                          +4 +4
              4 4         7       6       5       6          6 6 8 9 5 4                2 2 2 2 6 6
J (6 days)                                                       -4 -4                        +4 +4
              4 4         7       6       5        6         6 6 4 5 5 4                 2 2 6 6 6 6
L (2 days)                                                          -2 -2               +2 +2
              4 4         7       6       5        6         6 6 4 3 3 4                4 4 6 6 6 6
      04/11/2006                                                          Emad Elbeltagi                                     20




                                                                                                                                  10
Resources Management
     Resource Leveling (Example)
              0 1    2     3      4   5      6      7    8        9 10 11 12 13 14 15 16 17 18 19 20
                         C, 2
                                                             G, 3
                                                                                 K, 2
                                                                                                    N, 0

               B, 0
                 D, 2
                           E, 1
                                          F, 2
                                                 H, 1
                                          I, 0
                                                               J, 4
                                                                        L, 2
                                                                    M, 4

               4 4  7 6 5 6                        6 6        4     3
                                                                4 4 6    3 4            6   6   6          ∑= 90
E (10 days)        -1 -1                                       +1 +1
              4 4 6 5 5 6                         6 6 4 3 3 4 5 5 6                     6   6   6
H (2 days)            -1 -1                              +1 +1
              4 4 6 4 4 6                         6 6 4 4 4 4 5 5 6                     6   6   6
F (1 days)        -2                                  +2
              4 4 4 4 4 6                         6 6 6 4 4 4 5 5 6                     6   6   6
     04/11/2006                                                Emad Elbeltagi                                      21




                    Resources Management
    Resource Leveling (Example)
         7

         6

         5

         4

         3

         2

         1

         0
               1    2      3      4   5      6      7    8        9 10 11 12 13 14 15 16 17 18 19 20




     04/11/2006                                                Emad Elbeltagi                                      22




                                                                                                                        11
Resources Management
Resource Scheduling
Constrained resource scheduling (Unconstrained time)

Resource Scheduling

       Constrained Resources

       Unconstrained project completion; project time may be delayed

       Reduce the resource usage to be less than the resource availability

       The objective is to meet the resources limits



 04/11/2006                     Emad Elbeltagi                                23




              Resources Management
Resource Scheduling
        R
        2        A
        2        B
        1        C
                                                         Resource limit = 2
        1        D
        2        E
                        2   2   4   4   1    1   2   2

        R
        2        A
        2        B
        1        C
        1        D
        2        E
                        2   2   2   2   1   1    2   2   2   2



 04/11/2006                     Emad Elbeltagi                                24




                                                                                   12
Resources Management
Resource Scheduling


Is there is a way to prioritize activities

That compete for the limited resources

        so that the net project delay is

                          minimized?


 04/11/2006                     Emad Elbeltagi                      25




              Resources Management
Resource Scheduling
Resource Scheduling Rules of Thumb

         Many rules have been experimented with

         Least TF were found to be most effective

         Least LS has the same effect as the least TF and doesn’t

         require network recalculations

         In case of a tie use least TF




 04/11/2006                     Emad Elbeltagi                      26




                                                                         13
Resources Management
Resource Scheduling
 Procedure

             Prepare a complete activity schedule

             Aggregate the daily resource demand

             If demand greater than available then determine activities
             compete for resources

             Prioritize these activities based on their LS

             Allocate resources to some activities and delay the others

             Put your solution in table format


04/11/2006                          Emad Elbeltagi                           27




              Resources Management
Resource Scheduling (Example)

                                                     Resource (units/week)
   Activity      Duration (Weeks)    Predecessors
                                                      R1≤8         R2 ≤1

      A                 6                  -            3            0
      B                 4                  -            6            1
      C                 2                  -            4            0
      D                 8                 A             0            1
      E                 4                 D             4            1
      F                10                 B             0            1
      G                16                 B             4            0
      H                 8                 F             2            0
      I                 6                E, H           4            1
      J                 6                 C             5            1
      K                10                G, J           2            0




04/11/2006                          Emad Elbeltagi                           28




                                                                                  14
Resources Management
Resource Scheduling (Example)
                            0     4        4    12            12 16
                             A (4)          D (8)              E (4)
                            10 14          14 22              22 26
                             3, 0           0, 1                 4, 1
                                           6   16             16 24            24 30
                                           F (10)              H (8)             I (6)
                                           8   18             18 26            26 32
                                               0, 1              2, 0           4, 1

         0      0           0     6        6   22                              22 32        32 32
         Start (0)           B (6)         G (16)                               K (10)      End (0)
         0      0           0     6        6   22                              22 32        32 32
                             6, 1              4, 0                             2, 0
                            0     2        2      8
                             C (2)           J (6)
                            14 16          16 22
                             4, 0           5, 1




04/11/2006                                 Emad Elbeltagi                                         29




 Current        Eligible            Resources                       Earliest                Finish
                                                      Duration                   Decision
  Time         Activities       R1≤8     R2 ≤1                        LS                    Time
    0                B              6       1             6             0       Start         6
                     A              3       0             4             10      Delay         -
                     C              4       0             2             14      Delay         -
    6                G              4      0             16             6       Start        22
                     F              0      1             10             8       Start        16
                     A              3      0              4             10      Start        10
                     C              4      0              2             14      Delay         -
    10               G              4      0             16             -       Continue     22
                     F              0      1             10             -       Continue     16
                     C              4      0              2             14      Start        12
                     D              0      1              8             14      Delay         -
    12               G              4      0             16             -       Continue     22
                     F              0      1             10             -       Continue     16
                     D              0      1              8             14      Delay         -
                     J              5      0              6             16      Delay         -
    16               G              4      0             16             -       Continue     22
                     D              0      1              8             14      Start        24
                     J              5      1              6             16      Delay         -
                     H              2      0              8             18      Start        24




                                                                                                       15
Current    Eligible     Resources                Earliest               Finish
                                      Duration               Decision
 Time     Activities   R1≤8   R2 ≤1                LS                   Time
  22         D         0        1         8         -       Continue     24
             H         2        0         8         -       Continue     24
             J         5        1         6         16      Delay         -

  24         J          5      1          6         14      Start        30
             E          4      1          4         22      Delay         -


  30         E         4       1          4        22       Start        34
             K         2       0         10        22       Start        40


  34         K         2       0         10        -        Continue     40
             I         2       0         6        26         Start       40




                                                                                 16

Más contenido relacionado

Destacado (20)

Contract
ContractContract
Contract
 
P scheduling
P schedulingP scheduling
P scheduling
 
P introduction
P introductionP introduction
P introduction
 
Ch 6 construction progress control
Ch 6 construction progress controlCh 6 construction progress control
Ch 6 construction progress control
 
P overview
P overviewP overview
P overview
 
P project finance
P project financeP project finance
P project finance
 
P repetitive
P repetitiveP repetitive
P repetitive
 
Ch 2 planning and scheduling
Ch 2 planning and schedulingCh 2 planning and scheduling
Ch 2 planning and scheduling
 
P planning
P planningP planning
P planning
 
Cm exercise 5
Cm exercise 5Cm exercise 5
Cm exercise 5
 
Cm exercise 1
Cm exercise 1Cm exercise 1
Cm exercise 1
 
Cm exercise 4
Cm exercise 4Cm exercise 4
Cm exercise 4
 
Administration
AdministrationAdministration
Administration
 
Cash flow
Cash flowCash flow
Cash flow
 
2.tendering
2.tendering2.tendering
2.tendering
 
Ch 3 contract strategy
Ch 3 contract strategyCh 3 contract strategy
Ch 3 contract strategy
 
Session 8 gdas pmp study group presentation
Session 8   gdas pmp study group presentationSession 8   gdas pmp study group presentation
Session 8 gdas pmp study group presentation
 
1.introduction
1.introduction1.introduction
1.introduction
 
Overview
OverviewOverview
Overview
 
Session 2 gdas pmp study group presentation
Session 2   gdas pmp study group presentationSession 2   gdas pmp study group presentation
Session 2 gdas pmp study group presentation
 

Más de Tu Nguyen, PMP®,PMI-RMP® (18)

4.contracting
4.contracting4.contracting
4.contracting
 
3.estimating
3.estimating3.estimating
3.estimating
 
Session 7 gdas pmp study group presentation
Session 7   gdas pmp study group presentationSession 7   gdas pmp study group presentation
Session 7 gdas pmp study group presentation
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
Session 10 gdas pmp study group presentation
Session 10   gdas pmp study group presentationSession 10   gdas pmp study group presentation
Session 10 gdas pmp study group presentation
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
 
Node
NodeNode
Node
 
Bar chart
Bar chartBar chart
Bar chart
 
Arrow computation
Arrow computationArrow computation
Arrow computation
 
Arrow
ArrowArrow
Arrow
 
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
 
Time cost-control
Time cost-controlTime cost-control
Time cost-control
 
Resources
ResourcesResources
Resources
 
Pert
PertPert
Pert
 
Organization
OrganizationOrganization
Organization
 
Ch 1 organization of construction projects
Ch 1 organization of construction projectsCh 1 organization of construction projects
Ch 1 organization of construction projects
 
Ch 5 estimating and tendering
Ch 5 estimating and tenderingCh 5 estimating and tendering
Ch 5 estimating and tendering
 

Resources Management Techniques

  • 1. Resources Management Resources Management What a resource? Any thing that is used by an activity to get the work done, such as: Material, Equipment, Labor, Money, ….. Resources can be classified as: Consumable (Money, Material,……) Non Consumable (Labor, Equipment,…) 04/11/2006 Emad Elbeltagi 2 1
  • 2. Resources Management Duration-Driven Schedule All CPM scheduling techniques are duration driven schedules Basic units: activities, durations, relationships Assumes resources are available whenever needed Also, resources can be classified as: Key or constrained resources (Skilled labor, Equipment,……) Secondary or non-constrained resources (Labor, …) General resources, used by all activities 04/11/2006 Emad Elbeltagi 3 Resources Management Resource aggregation or Resource loading The summation, on a period-by-period basis, of the resources required to complete all activities based on the schedule carried out in the previous stage The results are usually shown graphically as a histogram A separate graph will be required for each resource 04/11/2006 Emad Elbeltagi 4 2
  • 3. Resources Management Resource aggregation or Resource loading Consider the following activities Activity Duration (Weeks) Resources (units/week) A 2 B 3 C 2 Shown in the histogram D 5 E 2 Resource limit = 10 units /week 04/11/2006 Emad Elbeltagi 5 Resources Management Resource aggregation or Resource loading Resource limit 04/11/2006 Emad Elbeltagi 6 3
  • 4. Resources Management Resource aggregation or Resource loading 04/11/2006 Emad Elbeltagi 7 Resources Management Problems Associated with Resource Resource Fluctuation (Resource leveling) Resource Over allocation (Resource Scheduling) Resource Resource Resource limit Time Time Resource profile with Less hiring and firing high resource fluctuation (More stable work conditions) (High hiring and firing) 04/11/2006 Emad Elbeltagi 8 4
  • 5. Resources Management Methods for Resolving Resource conflicts (Problems) Optimization Models (Utilize optimization techniques): Linear programming models Advantages: Provide optimum solution Limitations: Cannot be applied to large problems Heuristic Models (Utilize rule of thumb based on experience): Heuristic or rules of thumb Advantages: Can be applied to large problems Limitations: Do not provide optimum solution 04/11/2006 Emad Elbeltagi 9 Resources Management Resource Leveling (Smoothing) Unconstrained resource scheduling (Constrained time) Resource Leveling Resource unconstrained (No limits on resources) Time (Project completion) constrained; project duration not be delayed Reduce the difference between the peaks and the valleys Average resource usage The objective is to smooth the use of the resources to avoid the resource fluctuation 04/11/2006 Emad Elbeltagi 10 5
  • 6. Resources Management Resource Leveling (Smoothing) 04/11/2006 Emad Elbeltagi 11 Resources Management Resource Leveling (Smoothing) Minimum Moment Algorithm = ∑ Yi * Yi /2 04/11/2006 Emad Elbeltagi 12 6
  • 7. Resources Management Resource Leveling (Smoothing) Heuristic Method Procedure Prepare a complete activity schedule Draw a bar chart based on ES timings Draw the FF as dashed line beside the upper side of the bar and the TF beside the lower side Put the resource usage in each bar of the related activity Critical activities to be drawn first (do not move them) Aggregate the resources in each time period 04/11/2006 Emad Elbeltagi 13 Resources Management Resource Leveling (Smoothing) Procedure Calculate the total usage of resources = ∑ unit period usage Calculate the average resource usage = ∑ usage / utilization period Shift non-critical activities within their FF first, then their TF to decrease the peaks and raise the valleys Revise the activities float Aggregate the resources in each time period 04/11/2006 Emad Elbeltagi 14 7
  • 8. Resources Management Resource Leveling (Example) Example Resource Activity Duration (Weeks) Predecessors (units/week) A 0 - 0 B 2 1 0 C 5 1 2 D 3 1 2 E 2 2 1 F 6 2 2 G 6 3 3 H 6 4 1 I 4 4 0 J 2 5, 6 4 K 7 6, 7 2 L 3 2, 8 2 M 2 2, 8, 9 4 N 2 10, 11, 12, 13 0 04/11/2006 Emad Elbeltagi 15 Resources Management Resource Leveling (Example) 2 4 E (2) 14 16 0 2 2 8 8 10 B (2) F (6) J (2) 3 5 5 11 16 18 0 0 0 5 5 11 11 18 18 20 A (0) C (5) G (6) K (7) N (2) 0 0 0 5 5 11 11 18 18 20 0 3 3 9 9 12 D (3) H (6) L (3) 6 9 9 15 15 18 3 7 9 11 I (4) M (2) 12 16 16 18 04/11/2006 Emad Elbeltagi 16 8
  • 9. Resources Management Resource Leveling (Example) Activity ES EF FF TF A 0 0 0 0 B 0 2 0 3 C 0 5 0 0 D 0 3 0 6 E 2 4 4 12 F 2 8 0 3 G 5 11 0 0 H 3 9 0 6 I 3 7 2 9 J 8 10 8 8 K 11 18 0 0 L 9 12 6 6 M 9 11 7 7 N 18 20 0 0 04/11/2006 Emad Elbeltagi 17 Resources Management Resource Leveling (Example) 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 C, 2 G, 3 K, 2 N, 0 B, 0 D, 2 E, 1 F, 2 H, 1 I, 0 J, 4 L, 2 M, 4 4 4 7 6 5 6 6 6 8 13 9 4 2 2 2 2 2 2 ∑= 90 04/11/2006 Emad Elbeltagi 18 9
  • 10. Resources Management Resource Leveling (Example) 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 04/11/2006 Emad Elbeltagi 19 Resources Management Resource Leveling (Example) 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 C, 2 G, 3 K, 2 N, 0 B, 0 D, 2 E, 1 F, 2 H, 1 I, 0 J, 4 L, 2 M, 4 4 4 7 6 5 6 6 6 8 13 9 4 2 2 22 2 2 ∑= 90 M (7 days) -4 -4 +4 +4 4 4 7 6 5 6 6 6 8 9 5 4 2 2 2 2 6 6 J (6 days) -4 -4 +4 +4 4 4 7 6 5 6 6 6 4 5 5 4 2 2 6 6 6 6 L (2 days) -2 -2 +2 +2 4 4 7 6 5 6 6 6 4 3 3 4 4 4 6 6 6 6 04/11/2006 Emad Elbeltagi 20 10
  • 11. Resources Management Resource Leveling (Example) 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 C, 2 G, 3 K, 2 N, 0 B, 0 D, 2 E, 1 F, 2 H, 1 I, 0 J, 4 L, 2 M, 4 4 4 7 6 5 6 6 6 4 3 4 4 6 3 4 6 6 6 ∑= 90 E (10 days) -1 -1 +1 +1 4 4 6 5 5 6 6 6 4 3 3 4 5 5 6 6 6 6 H (2 days) -1 -1 +1 +1 4 4 6 4 4 6 6 6 4 4 4 4 5 5 6 6 6 6 F (1 days) -2 +2 4 4 4 4 4 6 6 6 6 4 4 4 5 5 6 6 6 6 04/11/2006 Emad Elbeltagi 21 Resources Management Resource Leveling (Example) 7 6 5 4 3 2 1 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 04/11/2006 Emad Elbeltagi 22 11
  • 12. Resources Management Resource Scheduling Constrained resource scheduling (Unconstrained time) Resource Scheduling Constrained Resources Unconstrained project completion; project time may be delayed Reduce the resource usage to be less than the resource availability The objective is to meet the resources limits 04/11/2006 Emad Elbeltagi 23 Resources Management Resource Scheduling R 2 A 2 B 1 C Resource limit = 2 1 D 2 E 2 2 4 4 1 1 2 2 R 2 A 2 B 1 C 1 D 2 E 2 2 2 2 1 1 2 2 2 2 04/11/2006 Emad Elbeltagi 24 12
  • 13. Resources Management Resource Scheduling Is there is a way to prioritize activities That compete for the limited resources so that the net project delay is minimized? 04/11/2006 Emad Elbeltagi 25 Resources Management Resource Scheduling Resource Scheduling Rules of Thumb Many rules have been experimented with Least TF were found to be most effective Least LS has the same effect as the least TF and doesn’t require network recalculations In case of a tie use least TF 04/11/2006 Emad Elbeltagi 26 13
  • 14. Resources Management Resource Scheduling Procedure Prepare a complete activity schedule Aggregate the daily resource demand If demand greater than available then determine activities compete for resources Prioritize these activities based on their LS Allocate resources to some activities and delay the others Put your solution in table format 04/11/2006 Emad Elbeltagi 27 Resources Management Resource Scheduling (Example) Resource (units/week) Activity Duration (Weeks) Predecessors R1≤8 R2 ≤1 A 6 - 3 0 B 4 - 6 1 C 2 - 4 0 D 8 A 0 1 E 4 D 4 1 F 10 B 0 1 G 16 B 4 0 H 8 F 2 0 I 6 E, H 4 1 J 6 C 5 1 K 10 G, J 2 0 04/11/2006 Emad Elbeltagi 28 14
  • 15. Resources Management Resource Scheduling (Example) 0 4 4 12 12 16 A (4) D (8) E (4) 10 14 14 22 22 26 3, 0 0, 1 4, 1 6 16 16 24 24 30 F (10) H (8) I (6) 8 18 18 26 26 32 0, 1 2, 0 4, 1 0 0 0 6 6 22 22 32 32 32 Start (0) B (6) G (16) K (10) End (0) 0 0 0 6 6 22 22 32 32 32 6, 1 4, 0 2, 0 0 2 2 8 C (2) J (6) 14 16 16 22 4, 0 5, 1 04/11/2006 Emad Elbeltagi 29 Current Eligible Resources Earliest Finish Duration Decision Time Activities R1≤8 R2 ≤1 LS Time 0 B 6 1 6 0 Start 6 A 3 0 4 10 Delay - C 4 0 2 14 Delay - 6 G 4 0 16 6 Start 22 F 0 1 10 8 Start 16 A 3 0 4 10 Start 10 C 4 0 2 14 Delay - 10 G 4 0 16 - Continue 22 F 0 1 10 - Continue 16 C 4 0 2 14 Start 12 D 0 1 8 14 Delay - 12 G 4 0 16 - Continue 22 F 0 1 10 - Continue 16 D 0 1 8 14 Delay - J 5 0 6 16 Delay - 16 G 4 0 16 - Continue 22 D 0 1 8 14 Start 24 J 5 1 6 16 Delay - H 2 0 8 18 Start 24 15
  • 16. Current Eligible Resources Earliest Finish Duration Decision Time Activities R1≤8 R2 ≤1 LS Time 22 D 0 1 8 - Continue 24 H 2 0 8 - Continue 24 J 5 1 6 16 Delay - 24 J 5 1 6 14 Start 30 E 4 1 4 22 Delay - 30 E 4 1 4 22 Start 34 K 2 0 10 22 Start 40 34 K 2 0 10 - Continue 40 I 2 0 6 26 Start 40 16