Project Management
3-1
Outline
• GLOBAL COMPANY PROFILE:
BECHTEL GROUP
• THE IMPORTANCE OF PROJECT
MANAGEMENT
• PROJECT PLANNING
– The Project Manager
– Work Breakdown Structure
• PROJECT SCHEDULING
• PROJECT CONTROLLING
3-2
Outline - Continued
• PROJECT MANAGEMENT
TECHNIQUES: PERT AND CPM
– The Framework of PERT and CPM
– Network Diagrams and Approaches
– Activity on Node Example
– Determining the Project Schedule
• Forward Pass
• Backward Pass
• Calculating Slack Time and Identifying the
Critical Path(s)
3-3
Outline - Continued
– Variability in Activity Times
• Three Time Estimates in PERT
• Probability of Project Completion
• Cost-Time Tradeoffs and Project
Crashing
• A Critique of PERT and CPM
• Visual PERT/CPM Computer
Program Practice
3-4
Learning Objectives
When you complete this chapter, you
should be able to :
Identify or Define:
– Work breakdown structure
– Critical path
– AOA and AON Networks
– Forward and Backward Passes
– Variability in Activity Times
3-5
Learning Objectives – Cont..
When you complete this chapter, you
should be able to :
Describe or Explain:
– The role of the project manager
– Program evaluation and review technique
(PERT)
– Critical path method (CPM)
– Crashing a project
– The Use of MS Project
3-6
Bechtel – Case Study
• Asked by Kuwait to begin rebuilding
after Desert Storm
• 650 wells ablaze, others uncapped
• No water, electricity, food or facilities
• Land mines! Bombs! Grenades!
• Many fires inaccessible because of oil-
covered roads
3-7
Bechtel
• Project required:
– Storage, docking, and warehousing
facilities at Dubai
– 125,000 tons of equipment and supplies
– 150 kilometers of pipeline capable of
delivering 20,000,000 gallons of water per
day to the fire site
– more than 200 lagoons with 1,000,000
gals of seawater
3-8
Bechtel Other Projects
• Building 26 massive distribution centers in just two
years for the internet company Webvan Group
• Constructing 30 high-security data centers
worldwide for Equinix, Inc.
• Building and running a rail line between London
and the Channel Tunnel ($4.6 billion)
• Developing an oil pipeline from the Caspian Sea
region to Russia ($850 million)
• Expanding the Dubai Airport in the UAE ($600
million), and the Miami Airport in Florida ($2 billion)
3-9
Bechtel Other Projects –
Cont.
• Building liquid natural gas plants in Yemen $2
billion) and in Trinidad, West Indies ($1 billion)
• Building a new subway for Athens, Greece ($2.6
billion)
• Constructing a natural gas pipeline in Thailand
($700 million)
• Building a highway to link the north and south of
Croatia ($303 million)
3-10
Strategic Importance of PM
• Bechtel Kuwait Project:
– 8,000 workers
– 1,000 construction professionals
– 100 medical personnel
– 2 helicopter evacuation teams
– 6 full-service dining halls
– 27,000 meals per day
– 40 bed field hospital
3-11
• Microsoft Windows XP Project:
– hundreds of programmers
– millions of lines of code
– millions of dollars cost
• Ford Redesign of Mustang Project:
– 450 member project team
– Cost $700-million
– 25% faster and 30% cheaper than
comparable project at Ford
Strategic Importance of PM
3-12
Project Characteristics
• Single unit
• Many related activities
• Difficult production planning and
inventory control
• General purpose equipment
• High labor skills
3-13
An Example
• Building construction
© 1995 Corel Corp.
3-14
An Example
• Research project
© 1995
Corel Corp. 3-15
Project Management
• Project management is the discipline of carefully
projecting or planning, organizing, motivating and
controlling resources to achieve specific goals and
meet specific success criteria.
• A project is a temporary endeavour designed to
produce a unique product, service or result with a
defined beginning and end (usually time-
constrained, and often constrained by funding
or deliverables) undertaken to meet unique goals
and objectives, typically to bring about beneficial
change or added value.
3-16
The Traditional
Approach
• A traditional phased approach identifies a sequence of steps to
be completed.
• Typical development phases of an engineering project
– initiation
– planning and design
– execution and construction
– monitoring and controlling systems
– completion and finish point
3-17
Management of Large Projects
• Planning - goal setting, project
definition, team organization
• Scheduling - relating people, money,
and supplies to specific activities and
activities to one and other
• Controlling - monitoring resources,
costs, quality, and budgets; revising
plans and shifting resources to meet
time and cost demands
3-18
Planning
Objectives
Resources
Work break-
down schedule
Organization
Scheduling
Project
activities
Start & end
times
Network
Controlling
Monitor, compare,
revise, action
Project Management Activities
3-19
Project Organization
Works Best When
• Work can be defined with a specific
goal and deadline
• The job is unique or somewhat
unfamiliar to the existing organization
• The work contains complex interrelated
tasks requiring specialized skills
• The project is temporary but critical to
the organization
3-20
Project Planning, Scheduling,
and Controlling
Project Planning
1. Setting goals
2. Defining the project
3. Tying needs into timed project
activities
4. Organizing the team
Project Scheduling
1. Tying resources to specific
activities
2. Relating activities to each other
3. Updating and revising on a
regular basis
Time/cost estimates
Budgets
Engineering diagrams
Cash flow charts
Material availability details
CPM/PERT
Gantt charts
Milestone charts
Cash flow schedules
Project Controlling
1. Monitoring resources, costs, quality,
and budgets
2. Revising and changing plans
3. Shifting resources to meet demands
Reports
• budgets
• delayed activities
• slack activities
Before Project During Project
3-21
Project Planning, Scheduling,
and Controlling
3-22
Project Planning
• Establishing objectives
• Defining project
• Creating work breakdown
structure
• Determining resources
• Forming organization
© 1995 Corel Corp.
3-23
Project Organization
• Often temporary structure
• Uses specialists from entire
company
• Headed by project manager
– Coordinates activities
– Monitors schedule
& costs
• Permanent
structure called
‘matrix organization’
Acct.
Eng. Eng.
Mkt.
Mgr.
3-24
A Sample Project Organization
Sales
President
Finance
Human
Resources
Engineering
Quality
Control
Production
Technician
Test
Engineer
Propulsion
Engineer
Physiologist
Project
Manager
Psychologist
Structural
Engineer
Inspection
Technician
Technician
Project 1
Project 2
Project
Manager
3-25
A Sample Project Organization
Sales Finance
Human
Resources
Engineering
Quality
Control
Production
Test
Engineer
Propulsion
Engineer
Technician
Project 1
Project 2
Project
Manager
Technician
Project
Manager
Structural
Engineer
Inspection
Technician
President
3-26
Mkt Oper Eng Fin
Project 1
Project 2
Project 3
Project 4
 
   
 

Matrix Organization
3-27
Role of Project Manager
Project Plan
and Schedule
Revisions and
Updates
Project
Manager
Project
Team
Top
Management
Resources
Performance
Reports
Information
regarding times,
costs, problems,
delays Feedback Loop
3-28
Work Breakdown Structure
1. Project
2. Major tasks in the project
3. Subtasks in the major tasks
4. Activities (or work packages) to be
completed
3-29
J
F
M
A
M
J
J
Month
Activity
Design
Build
Test
PERT
Project Scheduling
• Identifying
precedence
relationships
• Sequencing activities
• Determining activity
times & costs
• Estimating material
& worker
requirements
• Determining critical
activities 3-30
Purposes of Project Scheduling
• Shows the relationship of each activity
to others and to the whole project.
• Identifies the precedence relationships
among activities.
• Encourages the setting of realistic time
and cost estimates for each activity.
• Helps make better use of people,
money, and material resources by
identifying critical bottlenecks in the
project.
3-31
Project Management Techniques
• Gantt chart
• Critical Path Method (CPM)
• Program Evaluation &
Review Technique (PERT)
3-32
J F M A M J J
Time Period
Activity
Design
Build
Test
Gantt Chart
3-33
Service Activities for A Delta Jet
During a 60 Minute Layover
3-34
Project Control Reports
• Detailed cost breakdowns for each task
• Total program labor curves
• Cost distribution tables
• Functional cost and hour summaries
• Raw materials and expenditure
forecasts
• Variance reports
• Time analysis reports
• Work status reports
3-35
PERT and CPM
• Network techniques
• Developed in 1950’s
– CPM by DuPont for chemical plants (1957)
– PERT by Booz, Allen & Hamilton with the
U.S. Navy, for Polaris missile (1958)
• Consider precedence relationships and
interdependencies
• Each uses a different estimate of activity
times
3-36
• Is the project on schedule, ahead of
schedule, or behind schedule?
• Is the project over or under cost budget?
• Are there enough resources available to
finish the project on time?
• If the project must be finished in less than
the scheduled amount of time, what is the
way to accomplish this at least cost?
Questions Which May Be
Addressed by PERT & CPM
3-37
Six Steps Common to PERT & CPM
1. Define the project and prepare the work
breakdown structure,
2. Develop relationships among the activities.
(Decide which activities must precede and which
must follow others.)
3. Draw the network connecting all of the activities
4. Assign time and/or cost estimates to each activity
5. Compute the longest time path through the
network. This is called the critical path
6. Use the network to help plan, schedule, monitor,
and control the project
3-38
A Comparison of AON and
AOA Network Conventions
3-39
Milwaukee General Hospital’s
Activities and Predecessors
Activity Description Immediate
Predecessors
A Build internal components -
B Modify roof and floor -
C Construct collection stack A
D Pour concrete and install frame A, B
E Build high-temperature burner C
F Install pollution control system C
G Install air pollution device D, E
H Inspect and test F, G
3-40
AON Network for Milwaukee
General Hospital
Start
A
B
C
D
F
F
G
H
Arrows show
precedence
relationships
3-41
1
3
2 4
5
6 7
H
Inspect/Test
G
Install pollution
control device
D
Pour concrete/
Install frame
B
Modify
roof/floor
C
Construct
stack
F
Install controls
E
Buildburner
AOA Network (With Dummy
Activities) for Milwaukee General
A
Buildinternal
components
Dummy
Activity
3-42
Critical Path Analysis
• Provides activity information
– Earliest (ES) & latest (LS) start
– Earliest (EF) & latest (LF) finish
– Slack (S): Allowable delay
• Identifies critical path
– Longest path in network
– Shortest time project can be completed
– Any delay on critical path activities
delays project
– Critical path activities have 0 slack
3-43
Earliest Start & Finish Steps
• Begin at starting event and work forward
• ES = 0 for starting activities
– ES is earliest start
• EF = ES + Activity time
– EF is earliest finish
• ES = Maximum EF of all predecessors for
non-starting activities
3-44
Latest Start and Finish Steps
• Begin at ending event and work
backward
• LF = Maximum EF for ending activities
– LF is latest finish; EF is earliest finish
• LS = LF - Activity time
– LS is latest start
• LF = Minimum LS of all successors for
non-ending activities
3-45
Latest Start and Finish Steps
Latest
Finish
ES
LS
EF
LF
Earliest
Finish
Latest
Start
Earliest
Start
Activity
Name
Activity
Duration
3-46
Critical Path for
Milwaukee General Hospital
Start
A
B
C
D
F
F
G
H
Arrows show
precedence
relationships
3-47
AON Network for Milwaukee
Hospital Includes Critical Path
Slack=0
Start
A
B
C
D
F
F
G
H
H
13
13
2
15
15
H
G
8
8
5
13
13
H
F
4
10
3
7
13
H
C
2
2
2
4
4
H
E
4
4
4
8
8
H
D
3
4
4
7
8
H
B
0
1
3
3
4
H
A
0
0
2
2
2
H
0
0
0
0
0
Slack=0 Slack=0
Slack=0
Slack=0
Slack=6
Slack=1Slack=1
Start
3-48
Gantt Chart
Earliest Start and Finish
Milwaukee General HospitalMilwaukee General Hospital
A Build internal components
B Modify roof and floor
C Construct collection stack
D Pour concrete and install
frame
E Build high-temperature
burner
F Install pollution control
system
G Install air pollution device
H Inspect and test
1 2 3 4 5 6 7 8 9 10 1112 13 1415 16
3-49
Gantt Chart
Latest Start and Finish
Milwaukee General HospitalMilwaukee General Hospital
A Build internal components
B Modify roof and floor
C Construct collection stack
D Pour concrete and install
frame
E Build high-temperature
burner
F Install pollution control
system
G Install air pollution device
H Inspect and test
1 2 3 4 5 6 7 8 9 10 1112 13 1415 16
3-50
1-2 Fdn & frame
1-3 Buy shrubs
2-3 Roof
2-4 Interior work
3-4 Landscape
4 5 6 7 8 9
1
0
1
1
1
2321Activity
Build House Project
Gantt Chart
Latest Start and Finish
3-51
PERT Activity Times
• 3 time estimates
– Optimistic times (a)
– Most-likely time (m)
– Pessimistic time (b)
• Follow beta distribution
• Expected time: t = (a + 4m + b)/6
• Variance of times: v = (b - a)2
/6

3-52
Project Times
• Expected project time
(T)
– Sum of critical path
activity times, t
• Project variance (V)
– Sum of critical path
activity variances, v
Used to obtain
probability of project
completion!
3-53
PERT Probability Example
You’re a project planner for
General Dynamics.
A submarine project has an
expected completion time
of 40 weeks, with a
standard deviation of 5
weeks. What is the
probability of finishing the
sub in 50 weeks or less?
3-54
T = 40
s = 5
50 X
NormalNormal
DistributionDistribution
Z
X T
=
-
=
-
=
s
50 40
5
2 0.
mz = 0
sZ = 1
Z2.0
Standardized NormalStandardized Normal
DistributionDistribution
Converting to Standardized
Variable
3-55
mz = 0
s Z = 1
Z2.0
Z .00 .01
0.0 .50000 .50399
: : : :
2.0 .97725 .97784 .97831
2.1 .98214 .98257 .98300
Standardized Normal ProbabilityStandardized Normal Probability
Table (Portion)Table (Portion)
Probabilities in bodyProbabilities in body
Obtaining the Probability
.02
.50798
.97725
3-56
Variability of Completion
Time for Noncritical Paths
• Variability of times for activities on
noncritical paths must be considered
when finding the probability of finishing
in a specified time.
• Variation in noncritical activity may
cause change in critical path.
3-57
Factors to Consider when Crashing
• The amount by which an activity is
crashed is, in fact, permissible.
• Taken together, the shortened activity
durations will enable one to finish the
project by the due date.
• The total cost of crashing is as small as
possible.
3-58
Steps in Project Crashing
• Compute the crash cost per time period. For
crash costs assumed linear over time:
• Using current activity times, find the critical path
• If there is only one critical path, then select the
activity on this critical path that (a) can still be
crashed, and (b) has the smallest crash cost per
period. Note that a single activity may be
common to more than one critical path
• Update all activity times.
)Crash timetime(Normal
costNormalcost(Crash
periodpercostCrash
−
−
=
3-59
Crash and Normal Times and
Costs for Activity B
3-60
Cost-Time Curves Used in
Crashing Analysis
3-61
Advantages of PERT/CPM
• Especially useful when scheduling and controlling
large projects.
• Straightforward concept and not mathematically
complex.
• Graphical networks aid perception of relationships
among project activities.
• Critical path & slack time analyses help pinpoint
activities that need to be closely watched.
• Project documentation and graphics point out who
is responsible for various activities.
• Applicable to a wide variety of projects.
• Useful in monitoring schedules and costs.
3-62
Limitations of PERT/CPM
• Assumes clearly defined, independent,
& stable activities
• Specified precedence relationships
• Activity times (PERT) follow
beta distribution
• Subjective time estimates
• Over-emphasis on critical path
3-63
Thank You
3-64

Más contenido relacionado

La actualidad más candente

An Introduction to Project Management
An Introduction to Project Management An Introduction to Project Management
An Introduction to Project Management Krishna Kant
 
Lecture 1. general introduction to project management
Lecture 1. general introduction to project management Lecture 1. general introduction to project management
Lecture 1. general introduction to project management Dania Abdel-aziz
 
Project management
Project managementProject management
Project managementJay Raval
 
Project management
Project managementProject management
Project managementArsh Koul
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasMazen Zbib
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration ManagementBhuWan Khadka
 
Project Management
Project ManagementProject Management
Project ManagementMark Roman
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupTùng Trần Thanh
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementMohamed Loey
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project managementJared C. Powell
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management toolsNathan Petralia
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full courseMarten Schoonman
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Agus Suhanto
 

La actualidad más candente (20)

An Introduction to Project Management
An Introduction to Project Management An Introduction to Project Management
An Introduction to Project Management
 
Lecture 1. general introduction to project management
Lecture 1. general introduction to project management Lecture 1. general introduction to project management
Lecture 1. general introduction to project management
 
Project management
Project managementProject management
Project management
 
Project management
Project managementProject management
Project management
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
 
Project Management
Project ManagementProject Management
Project Management
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
 
project management
project managementproject management
project management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management tools
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
 
Project management
Project managementProject management
Project management
 
Project management
Project managementProject management
Project management
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6
 
Project management structures
Project management structuresProject management structures
Project management structures
 

Similar a Project management

ITFT - Project Management
ITFT - Project ManagementITFT - Project Management
ITFT - Project ManagementPooja
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersIIMSE Edu
 
Project management @ bec doms
Project management @ bec domsProject management @ bec doms
Project management @ bec domsBabasab Patil
 
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...Shanmukha S. Potti
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTSAJJAD KHUDHUR ABBAS
 
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesOm lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesvideoaakash15
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptxTecnicoItca
 
Pert cpm-1226075768298180-8 (1)
Pert cpm-1226075768298180-8 (1)Pert cpm-1226075768298180-8 (1)
Pert cpm-1226075768298180-8 (1)Jags Jagdish
 
Time management pressent
Time management pressentTime management pressent
Time management pressentiklil fairuz
 
06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 
Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptTecnicoItca
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
A partial results from a PERT analysis for a project with 50 activit.pdf
A partial results from a PERT analysis for a project with 50 activit.pdfA partial results from a PERT analysis for a project with 50 activit.pdf
A partial results from a PERT analysis for a project with 50 activit.pdfrozakashif85
 
Project management cpm-pert
Project management   cpm-pertProject management   cpm-pert
Project management cpm-pertAbu Bashar
 

Similar a Project management (20)

Unit IV-Project Management
Unit IV-Project ManagementUnit IV-Project Management
Unit IV-Project Management
 
ITFT - Project Management
ITFT - Project ManagementITFT - Project Management
ITFT - Project Management
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
 
Project management @ bec doms
Project management @ bec domsProject management @ bec doms
Project management @ bec doms
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
 
Chapter 03
Chapter 03Chapter 03
Chapter 03
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENT
 
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesOm lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptx
 
Pert cpm-1226075768298180-8 (1)
Pert cpm-1226075768298180-8 (1)Pert cpm-1226075768298180-8 (1)
Pert cpm-1226075768298180-8 (1)
 
Time management pressent
Time management pressentTime management pressent
Time management pressent
 
06 project time management
06  project time management06  project time management
06 project time management
 
Chapter 4.pptx
Chapter 4.pptxChapter 4.pptx
Chapter 4.pptx
 
Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.ppt
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
A partial results from a PERT analysis for a project with 50 activit.pdf
A partial results from a PERT analysis for a project with 50 activit.pdfA partial results from a PERT analysis for a project with 50 activit.pdf
A partial results from a PERT analysis for a project with 50 activit.pdf
 
Project management cpm-pert
Project management   cpm-pertProject management   cpm-pert
Project management cpm-pert
 
Cpm pert
Cpm pertCpm pert
Cpm pert
 

Más de twilight89

Biochemistry Biochemistry and clinical pathology -NOTES
Biochemistry Biochemistry and clinical pathology -NOTESBiochemistry Biochemistry and clinical pathology -NOTES
Biochemistry Biochemistry and clinical pathology -NOTEStwilight89
 
Principle of natural justice
Principle of natural justicePrinciple of natural justice
Principle of natural justicetwilight89
 
Sri lalitha sahastranam
Sri lalitha sahastranamSri lalitha sahastranam
Sri lalitha sahastranamtwilight89
 
Pharma factory location
Pharma factory locationPharma factory location
Pharma factory locationtwilight89
 
grammatical_vs_lexical_stress
grammatical_vs_lexical_stressgrammatical_vs_lexical_stress
grammatical_vs_lexical_stresstwilight89
 
Phone calls d os and don'ts
Phone calls d os and don'tsPhone calls d os and don'ts
Phone calls d os and don'tstwilight89
 
RURAL MARKETING
RURAL MARKETINGRURAL MARKETING
RURAL MARKETINGtwilight89
 
Managerial economics
Managerial economicsManagerial economics
Managerial economicstwilight89
 
Perpective management
Perpective managementPerpective management
Perpective managementtwilight89
 
Marketing text book
Marketing text bookMarketing text book
Marketing text booktwilight89
 

Más de twilight89 (11)

Biochemistry Biochemistry and clinical pathology -NOTES
Biochemistry Biochemistry and clinical pathology -NOTESBiochemistry Biochemistry and clinical pathology -NOTES
Biochemistry Biochemistry and clinical pathology -NOTES
 
Principle of natural justice
Principle of natural justicePrinciple of natural justice
Principle of natural justice
 
Sri lalitha sahastranam
Sri lalitha sahastranamSri lalitha sahastranam
Sri lalitha sahastranam
 
Pharma factory location
Pharma factory locationPharma factory location
Pharma factory location
 
grammatical_vs_lexical_stress
grammatical_vs_lexical_stressgrammatical_vs_lexical_stress
grammatical_vs_lexical_stress
 
Phone calls d os and don'ts
Phone calls d os and don'tsPhone calls d os and don'ts
Phone calls d os and don'ts
 
RURAL MARKETING
RURAL MARKETINGRURAL MARKETING
RURAL MARKETING
 
Cost sheet
Cost sheetCost sheet
Cost sheet
 
Managerial economics
Managerial economicsManagerial economics
Managerial economics
 
Perpective management
Perpective managementPerpective management
Perpective management
 
Marketing text book
Marketing text bookMarketing text book
Marketing text book
 

Último

Unraveling the Mystery of the Hinterkaifeck Murders.pptx
Unraveling the Mystery of the Hinterkaifeck Murders.pptxUnraveling the Mystery of the Hinterkaifeck Murders.pptx
Unraveling the Mystery of the Hinterkaifeck Murders.pptxelizabethella096
 
Brand experience Peoria City Soccer Presentation.pdf
Brand experience Peoria City Soccer Presentation.pdfBrand experience Peoria City Soccer Presentation.pdf
Brand experience Peoria City Soccer Presentation.pdftbatkhuu1
 
Moving beyond multi-touch attribution - DigiMarCon CanWest 2024
Moving beyond multi-touch attribution - DigiMarCon CanWest 2024Moving beyond multi-touch attribution - DigiMarCon CanWest 2024
Moving beyond multi-touch attribution - DigiMarCon CanWest 2024Richard Ingilby
 
BDSM⚡Call Girls in Sector 144 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 144 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 144 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 144 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Google 3rd-Party Cookie Deprecation [Update] + 5 Best Strategies
Google 3rd-Party Cookie Deprecation [Update] + 5 Best StrategiesGoogle 3rd-Party Cookie Deprecation [Update] + 5 Best Strategies
Google 3rd-Party Cookie Deprecation [Update] + 5 Best StrategiesSearch Engine Journal
 
Five Essential Tools for International SEO - Natalia Witczyk - SearchNorwich 15
Five Essential Tools for International SEO - Natalia Witczyk - SearchNorwich 15Five Essential Tools for International SEO - Natalia Witczyk - SearchNorwich 15
Five Essential Tools for International SEO - Natalia Witczyk - SearchNorwich 15SearchNorwich
 
How to Leverage Behavioral Science Insights for Direct Mail Success
How to Leverage Behavioral Science Insights for Direct Mail SuccessHow to Leverage Behavioral Science Insights for Direct Mail Success
How to Leverage Behavioral Science Insights for Direct Mail SuccessAggregage
 
Aryabhata I, II of mathematics of both.pptx
Aryabhata I, II of mathematics of both.pptxAryabhata I, II of mathematics of both.pptx
Aryabhata I, II of mathematics of both.pptxtegevi9289
 
BDSM⚡Call Girls in Sector 128 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 128 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 128 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 128 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
What is Google Search Console and What is it provide?
What is Google Search Console and What is it provide?What is Google Search Console and What is it provide?
What is Google Search Console and What is it provide?riteshhsociall
 
Enjoy Night⚡Call Girls Dlf City Phase 4 Gurgaon >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Dlf City Phase 4 Gurgaon >༒8448380779 Escort ServiceEnjoy Night⚡Call Girls Dlf City Phase 4 Gurgaon >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Dlf City Phase 4 Gurgaon >༒8448380779 Escort ServiceDelhi Call girls
 
Brighton SEO April 2024 - The Good, the Bad & the Ugly of SEO Success
Brighton SEO April 2024 - The Good, the Bad & the Ugly of SEO SuccessBrighton SEO April 2024 - The Good, the Bad & the Ugly of SEO Success
Brighton SEO April 2024 - The Good, the Bad & the Ugly of SEO SuccessVarn
 
Digital-Marketing-Into-by-Zoraiz-Ahmad.pptx
Digital-Marketing-Into-by-Zoraiz-Ahmad.pptxDigital-Marketing-Into-by-Zoraiz-Ahmad.pptx
Digital-Marketing-Into-by-Zoraiz-Ahmad.pptxZACGaming
 

Último (20)

Unraveling the Mystery of the Hinterkaifeck Murders.pptx
Unraveling the Mystery of the Hinterkaifeck Murders.pptxUnraveling the Mystery of the Hinterkaifeck Murders.pptx
Unraveling the Mystery of the Hinterkaifeck Murders.pptx
 
Brand experience Peoria City Soccer Presentation.pdf
Brand experience Peoria City Soccer Presentation.pdfBrand experience Peoria City Soccer Presentation.pdf
Brand experience Peoria City Soccer Presentation.pdf
 
Moving beyond multi-touch attribution - DigiMarCon CanWest 2024
Moving beyond multi-touch attribution - DigiMarCon CanWest 2024Moving beyond multi-touch attribution - DigiMarCon CanWest 2024
Moving beyond multi-touch attribution - DigiMarCon CanWest 2024
 
BDSM⚡Call Girls in Sector 144 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 144 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 144 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 144 Noida Escorts >༒8448380779 Escort Service
 
Google 3rd-Party Cookie Deprecation [Update] + 5 Best Strategies
Google 3rd-Party Cookie Deprecation [Update] + 5 Best StrategiesGoogle 3rd-Party Cookie Deprecation [Update] + 5 Best Strategies
Google 3rd-Party Cookie Deprecation [Update] + 5 Best Strategies
 
BUY GMAIL ACCOUNTS PVA USA IP INDIAN IP GMAIL
BUY GMAIL ACCOUNTS PVA USA IP INDIAN IP GMAILBUY GMAIL ACCOUNTS PVA USA IP INDIAN IP GMAIL
BUY GMAIL ACCOUNTS PVA USA IP INDIAN IP GMAIL
 
No Cookies No Problem - Steve Krull, Be Found Online
No Cookies No Problem - Steve Krull, Be Found OnlineNo Cookies No Problem - Steve Krull, Be Found Online
No Cookies No Problem - Steve Krull, Be Found Online
 
Five Essential Tools for International SEO - Natalia Witczyk - SearchNorwich 15
Five Essential Tools for International SEO - Natalia Witczyk - SearchNorwich 15Five Essential Tools for International SEO - Natalia Witczyk - SearchNorwich 15
Five Essential Tools for International SEO - Natalia Witczyk - SearchNorwich 15
 
How to Leverage Behavioral Science Insights for Direct Mail Success
How to Leverage Behavioral Science Insights for Direct Mail SuccessHow to Leverage Behavioral Science Insights for Direct Mail Success
How to Leverage Behavioral Science Insights for Direct Mail Success
 
Aryabhata I, II of mathematics of both.pptx
Aryabhata I, II of mathematics of both.pptxAryabhata I, II of mathematics of both.pptx
Aryabhata I, II of mathematics of both.pptx
 
Brand Strategy Master Class - Juntae DeLane
Brand Strategy Master Class - Juntae DeLaneBrand Strategy Master Class - Juntae DeLane
Brand Strategy Master Class - Juntae DeLane
 
BDSM⚡Call Girls in Sector 128 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 128 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 128 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 128 Noida Escorts >༒8448380779 Escort Service
 
Top 5 Breakthrough AI Innovations Elevating Content Creation and Personalizat...
Top 5 Breakthrough AI Innovations Elevating Content Creation and Personalizat...Top 5 Breakthrough AI Innovations Elevating Content Creation and Personalizat...
Top 5 Breakthrough AI Innovations Elevating Content Creation and Personalizat...
 
What is Google Search Console and What is it provide?
What is Google Search Console and What is it provide?What is Google Search Console and What is it provide?
What is Google Search Console and What is it provide?
 
Enjoy Night⚡Call Girls Dlf City Phase 4 Gurgaon >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Dlf City Phase 4 Gurgaon >༒8448380779 Escort ServiceEnjoy Night⚡Call Girls Dlf City Phase 4 Gurgaon >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Dlf City Phase 4 Gurgaon >༒8448380779 Escort Service
 
How to Create a Social Media Plan Like a Pro - Jordan Scheltgen
How to Create a Social Media Plan Like a Pro - Jordan ScheltgenHow to Create a Social Media Plan Like a Pro - Jordan Scheltgen
How to Create a Social Media Plan Like a Pro - Jordan Scheltgen
 
Foundation First - Why Your Website and Content Matters - David Pisarek
Foundation First - Why Your Website and Content Matters - David PisarekFoundation First - Why Your Website and Content Matters - David Pisarek
Foundation First - Why Your Website and Content Matters - David Pisarek
 
Brighton SEO April 2024 - The Good, the Bad & the Ugly of SEO Success
Brighton SEO April 2024 - The Good, the Bad & the Ugly of SEO SuccessBrighton SEO April 2024 - The Good, the Bad & the Ugly of SEO Success
Brighton SEO April 2024 - The Good, the Bad & the Ugly of SEO Success
 
SEO Master Class - Steve Wiideman, Wiideman Consulting Group
SEO Master Class - Steve Wiideman, Wiideman Consulting GroupSEO Master Class - Steve Wiideman, Wiideman Consulting Group
SEO Master Class - Steve Wiideman, Wiideman Consulting Group
 
Digital-Marketing-Into-by-Zoraiz-Ahmad.pptx
Digital-Marketing-Into-by-Zoraiz-Ahmad.pptxDigital-Marketing-Into-by-Zoraiz-Ahmad.pptx
Digital-Marketing-Into-by-Zoraiz-Ahmad.pptx
 

Project management

  • 2. Outline • GLOBAL COMPANY PROFILE: BECHTEL GROUP • THE IMPORTANCE OF PROJECT MANAGEMENT • PROJECT PLANNING – The Project Manager – Work Breakdown Structure • PROJECT SCHEDULING • PROJECT CONTROLLING 3-2
  • 3. Outline - Continued • PROJECT MANAGEMENT TECHNIQUES: PERT AND CPM – The Framework of PERT and CPM – Network Diagrams and Approaches – Activity on Node Example – Determining the Project Schedule • Forward Pass • Backward Pass • Calculating Slack Time and Identifying the Critical Path(s) 3-3
  • 4. Outline - Continued – Variability in Activity Times • Three Time Estimates in PERT • Probability of Project Completion • Cost-Time Tradeoffs and Project Crashing • A Critique of PERT and CPM • Visual PERT/CPM Computer Program Practice 3-4
  • 5. Learning Objectives When you complete this chapter, you should be able to : Identify or Define: – Work breakdown structure – Critical path – AOA and AON Networks – Forward and Backward Passes – Variability in Activity Times 3-5
  • 6. Learning Objectives – Cont.. When you complete this chapter, you should be able to : Describe or Explain: – The role of the project manager – Program evaluation and review technique (PERT) – Critical path method (CPM) – Crashing a project – The Use of MS Project 3-6
  • 7. Bechtel – Case Study • Asked by Kuwait to begin rebuilding after Desert Storm • 650 wells ablaze, others uncapped • No water, electricity, food or facilities • Land mines! Bombs! Grenades! • Many fires inaccessible because of oil- covered roads 3-7
  • 8. Bechtel • Project required: – Storage, docking, and warehousing facilities at Dubai – 125,000 tons of equipment and supplies – 150 kilometers of pipeline capable of delivering 20,000,000 gallons of water per day to the fire site – more than 200 lagoons with 1,000,000 gals of seawater 3-8
  • 9. Bechtel Other Projects • Building 26 massive distribution centers in just two years for the internet company Webvan Group • Constructing 30 high-security data centers worldwide for Equinix, Inc. • Building and running a rail line between London and the Channel Tunnel ($4.6 billion) • Developing an oil pipeline from the Caspian Sea region to Russia ($850 million) • Expanding the Dubai Airport in the UAE ($600 million), and the Miami Airport in Florida ($2 billion) 3-9
  • 10. Bechtel Other Projects – Cont. • Building liquid natural gas plants in Yemen $2 billion) and in Trinidad, West Indies ($1 billion) • Building a new subway for Athens, Greece ($2.6 billion) • Constructing a natural gas pipeline in Thailand ($700 million) • Building a highway to link the north and south of Croatia ($303 million) 3-10
  • 11. Strategic Importance of PM • Bechtel Kuwait Project: – 8,000 workers – 1,000 construction professionals – 100 medical personnel – 2 helicopter evacuation teams – 6 full-service dining halls – 27,000 meals per day – 40 bed field hospital 3-11
  • 12. • Microsoft Windows XP Project: – hundreds of programmers – millions of lines of code – millions of dollars cost • Ford Redesign of Mustang Project: – 450 member project team – Cost $700-million – 25% faster and 30% cheaper than comparable project at Ford Strategic Importance of PM 3-12
  • 13. Project Characteristics • Single unit • Many related activities • Difficult production planning and inventory control • General purpose equipment • High labor skills 3-13
  • 14. An Example • Building construction © 1995 Corel Corp. 3-14
  • 15. An Example • Research project © 1995 Corel Corp. 3-15
  • 16. Project Management • Project management is the discipline of carefully projecting or planning, organizing, motivating and controlling resources to achieve specific goals and meet specific success criteria. • A project is a temporary endeavour designed to produce a unique product, service or result with a defined beginning and end (usually time- constrained, and often constrained by funding or deliverables) undertaken to meet unique goals and objectives, typically to bring about beneficial change or added value. 3-16
  • 17. The Traditional Approach • A traditional phased approach identifies a sequence of steps to be completed. • Typical development phases of an engineering project – initiation – planning and design – execution and construction – monitoring and controlling systems – completion and finish point 3-17
  • 18. Management of Large Projects • Planning - goal setting, project definition, team organization • Scheduling - relating people, money, and supplies to specific activities and activities to one and other • Controlling - monitoring resources, costs, quality, and budgets; revising plans and shifting resources to meet time and cost demands 3-18
  • 19. Planning Objectives Resources Work break- down schedule Organization Scheduling Project activities Start & end times Network Controlling Monitor, compare, revise, action Project Management Activities 3-19
  • 20. Project Organization Works Best When • Work can be defined with a specific goal and deadline • The job is unique or somewhat unfamiliar to the existing organization • The work contains complex interrelated tasks requiring specialized skills • The project is temporary but critical to the organization 3-20
  • 21. Project Planning, Scheduling, and Controlling Project Planning 1. Setting goals 2. Defining the project 3. Tying needs into timed project activities 4. Organizing the team Project Scheduling 1. Tying resources to specific activities 2. Relating activities to each other 3. Updating and revising on a regular basis Time/cost estimates Budgets Engineering diagrams Cash flow charts Material availability details CPM/PERT Gantt charts Milestone charts Cash flow schedules Project Controlling 1. Monitoring resources, costs, quality, and budgets 2. Revising and changing plans 3. Shifting resources to meet demands Reports • budgets • delayed activities • slack activities Before Project During Project 3-21
  • 23. Project Planning • Establishing objectives • Defining project • Creating work breakdown structure • Determining resources • Forming organization © 1995 Corel Corp. 3-23
  • 24. Project Organization • Often temporary structure • Uses specialists from entire company • Headed by project manager – Coordinates activities – Monitors schedule & costs • Permanent structure called ‘matrix organization’ Acct. Eng. Eng. Mkt. Mgr. 3-24
  • 25. A Sample Project Organization Sales President Finance Human Resources Engineering Quality Control Production Technician Test Engineer Propulsion Engineer Physiologist Project Manager Psychologist Structural Engineer Inspection Technician Technician Project 1 Project 2 Project Manager 3-25
  • 26. A Sample Project Organization Sales Finance Human Resources Engineering Quality Control Production Test Engineer Propulsion Engineer Technician Project 1 Project 2 Project Manager Technician Project Manager Structural Engineer Inspection Technician President 3-26
  • 27. Mkt Oper Eng Fin Project 1 Project 2 Project 3 Project 4          Matrix Organization 3-27
  • 28. Role of Project Manager Project Plan and Schedule Revisions and Updates Project Manager Project Team Top Management Resources Performance Reports Information regarding times, costs, problems, delays Feedback Loop 3-28
  • 29. Work Breakdown Structure 1. Project 2. Major tasks in the project 3. Subtasks in the major tasks 4. Activities (or work packages) to be completed 3-29
  • 30. J F M A M J J Month Activity Design Build Test PERT Project Scheduling • Identifying precedence relationships • Sequencing activities • Determining activity times & costs • Estimating material & worker requirements • Determining critical activities 3-30
  • 31. Purposes of Project Scheduling • Shows the relationship of each activity to others and to the whole project. • Identifies the precedence relationships among activities. • Encourages the setting of realistic time and cost estimates for each activity. • Helps make better use of people, money, and material resources by identifying critical bottlenecks in the project. 3-31
  • 32. Project Management Techniques • Gantt chart • Critical Path Method (CPM) • Program Evaluation & Review Technique (PERT) 3-32
  • 33. J F M A M J J Time Period Activity Design Build Test Gantt Chart 3-33
  • 34. Service Activities for A Delta Jet During a 60 Minute Layover 3-34
  • 35. Project Control Reports • Detailed cost breakdowns for each task • Total program labor curves • Cost distribution tables • Functional cost and hour summaries • Raw materials and expenditure forecasts • Variance reports • Time analysis reports • Work status reports 3-35
  • 36. PERT and CPM • Network techniques • Developed in 1950’s – CPM by DuPont for chemical plants (1957) – PERT by Booz, Allen & Hamilton with the U.S. Navy, for Polaris missile (1958) • Consider precedence relationships and interdependencies • Each uses a different estimate of activity times 3-36
  • 37. • Is the project on schedule, ahead of schedule, or behind schedule? • Is the project over or under cost budget? • Are there enough resources available to finish the project on time? • If the project must be finished in less than the scheduled amount of time, what is the way to accomplish this at least cost? Questions Which May Be Addressed by PERT & CPM 3-37
  • 38. Six Steps Common to PERT & CPM 1. Define the project and prepare the work breakdown structure, 2. Develop relationships among the activities. (Decide which activities must precede and which must follow others.) 3. Draw the network connecting all of the activities 4. Assign time and/or cost estimates to each activity 5. Compute the longest time path through the network. This is called the critical path 6. Use the network to help plan, schedule, monitor, and control the project 3-38
  • 39. A Comparison of AON and AOA Network Conventions 3-39
  • 40. Milwaukee General Hospital’s Activities and Predecessors Activity Description Immediate Predecessors A Build internal components - B Modify roof and floor - C Construct collection stack A D Pour concrete and install frame A, B E Build high-temperature burner C F Install pollution control system C G Install air pollution device D, E H Inspect and test F, G 3-40
  • 41. AON Network for Milwaukee General Hospital Start A B C D F F G H Arrows show precedence relationships 3-41
  • 42. 1 3 2 4 5 6 7 H Inspect/Test G Install pollution control device D Pour concrete/ Install frame B Modify roof/floor C Construct stack F Install controls E Buildburner AOA Network (With Dummy Activities) for Milwaukee General A Buildinternal components Dummy Activity 3-42
  • 43. Critical Path Analysis • Provides activity information – Earliest (ES) & latest (LS) start – Earliest (EF) & latest (LF) finish – Slack (S): Allowable delay • Identifies critical path – Longest path in network – Shortest time project can be completed – Any delay on critical path activities delays project – Critical path activities have 0 slack 3-43
  • 44. Earliest Start & Finish Steps • Begin at starting event and work forward • ES = 0 for starting activities – ES is earliest start • EF = ES + Activity time – EF is earliest finish • ES = Maximum EF of all predecessors for non-starting activities 3-44
  • 45. Latest Start and Finish Steps • Begin at ending event and work backward • LF = Maximum EF for ending activities – LF is latest finish; EF is earliest finish • LS = LF - Activity time – LS is latest start • LF = Minimum LS of all successors for non-ending activities 3-45
  • 46. Latest Start and Finish Steps Latest Finish ES LS EF LF Earliest Finish Latest Start Earliest Start Activity Name Activity Duration 3-46
  • 47. Critical Path for Milwaukee General Hospital Start A B C D F F G H Arrows show precedence relationships 3-47
  • 48. AON Network for Milwaukee Hospital Includes Critical Path Slack=0 Start A B C D F F G H H 13 13 2 15 15 H G 8 8 5 13 13 H F 4 10 3 7 13 H C 2 2 2 4 4 H E 4 4 4 8 8 H D 3 4 4 7 8 H B 0 1 3 3 4 H A 0 0 2 2 2 H 0 0 0 0 0 Slack=0 Slack=0 Slack=0 Slack=0 Slack=6 Slack=1Slack=1 Start 3-48
  • 49. Gantt Chart Earliest Start and Finish Milwaukee General HospitalMilwaukee General Hospital A Build internal components B Modify roof and floor C Construct collection stack D Pour concrete and install frame E Build high-temperature burner F Install pollution control system G Install air pollution device H Inspect and test 1 2 3 4 5 6 7 8 9 10 1112 13 1415 16 3-49
  • 50. Gantt Chart Latest Start and Finish Milwaukee General HospitalMilwaukee General Hospital A Build internal components B Modify roof and floor C Construct collection stack D Pour concrete and install frame E Build high-temperature burner F Install pollution control system G Install air pollution device H Inspect and test 1 2 3 4 5 6 7 8 9 10 1112 13 1415 16 3-50
  • 51. 1-2 Fdn & frame 1-3 Buy shrubs 2-3 Roof 2-4 Interior work 3-4 Landscape 4 5 6 7 8 9 1 0 1 1 1 2321Activity Build House Project Gantt Chart Latest Start and Finish 3-51
  • 52. PERT Activity Times • 3 time estimates – Optimistic times (a) – Most-likely time (m) – Pessimistic time (b) • Follow beta distribution • Expected time: t = (a + 4m + b)/6 • Variance of times: v = (b - a)2 /6  3-52
  • 53. Project Times • Expected project time (T) – Sum of critical path activity times, t • Project variance (V) – Sum of critical path activity variances, v Used to obtain probability of project completion! 3-53
  • 54. PERT Probability Example You’re a project planner for General Dynamics. A submarine project has an expected completion time of 40 weeks, with a standard deviation of 5 weeks. What is the probability of finishing the sub in 50 weeks or less? 3-54
  • 55. T = 40 s = 5 50 X NormalNormal DistributionDistribution Z X T = - = - = s 50 40 5 2 0. mz = 0 sZ = 1 Z2.0 Standardized NormalStandardized Normal DistributionDistribution Converting to Standardized Variable 3-55
  • 56. mz = 0 s Z = 1 Z2.0 Z .00 .01 0.0 .50000 .50399 : : : : 2.0 .97725 .97784 .97831 2.1 .98214 .98257 .98300 Standardized Normal ProbabilityStandardized Normal Probability Table (Portion)Table (Portion) Probabilities in bodyProbabilities in body Obtaining the Probability .02 .50798 .97725 3-56
  • 57. Variability of Completion Time for Noncritical Paths • Variability of times for activities on noncritical paths must be considered when finding the probability of finishing in a specified time. • Variation in noncritical activity may cause change in critical path. 3-57
  • 58. Factors to Consider when Crashing • The amount by which an activity is crashed is, in fact, permissible. • Taken together, the shortened activity durations will enable one to finish the project by the due date. • The total cost of crashing is as small as possible. 3-58
  • 59. Steps in Project Crashing • Compute the crash cost per time period. For crash costs assumed linear over time: • Using current activity times, find the critical path • If there is only one critical path, then select the activity on this critical path that (a) can still be crashed, and (b) has the smallest crash cost per period. Note that a single activity may be common to more than one critical path • Update all activity times. )Crash timetime(Normal costNormalcost(Crash periodpercostCrash − − = 3-59
  • 60. Crash and Normal Times and Costs for Activity B 3-60
  • 61. Cost-Time Curves Used in Crashing Analysis 3-61
  • 62. Advantages of PERT/CPM • Especially useful when scheduling and controlling large projects. • Straightforward concept and not mathematically complex. • Graphical networks aid perception of relationships among project activities. • Critical path & slack time analyses help pinpoint activities that need to be closely watched. • Project documentation and graphics point out who is responsible for various activities. • Applicable to a wide variety of projects. • Useful in monitoring schedules and costs. 3-62
  • 63. Limitations of PERT/CPM • Assumes clearly defined, independent, & stable activities • Specified precedence relationships • Activity times (PERT) follow beta distribution • Subjective time estimates • Over-emphasis on critical path 3-63

Notas del editor

  1. It may be helpful here to ask students to compare the effort they believe necessary to manage this project to the effort they believe required to actually perform the physical tasks. Total cost might be a useful unit of comparison. One might expect the management cost to run 10% - 20% of the total.
  2. It is helpful here to provide an expanded discussion of the activities.
  3. A useful project management technique must contribute in all areas.
  4. Students should be asked to explain why these requirements are appropriate.
  5. If students have been assigned a term project, this material can be covered early in the semester and the students asked to develop a plan for their project.
  6. This may be a good time to look, at least briefly, at alternative organizational structures. Certainly hierarchical and matrix structures should be examined. The role of information technology in each of the alternatives should be examined. The following several slides illustrate various organizational structures.
  7. How does the structure of the project organization compare with the typical structure of the larger organization?
  8. How does the structure of the project organization compare with the typical structure of the larger organization?
  9. Given that a project is something the firm is relatively unfamiliar with, how does one go about determining the appropriate costs and times? You might point out that specifying the beginning and end points for an activity is often a difficult task. Work breakdown may be the most difficult aspect of many projects.
  10. You might point out to students that there are those who claim that the real benefit of using project management tools comes from the planning and organizing effort, not the actual management of the tasks during the project.
  11. As you discuss the various project scheduling techniques, you should include at least: - the basic assumptions of the technique - problems typically encountered in applying it - the nature of the effort required to keep the tool current - sources of problems - the nature of the decisions supported by the tool - the nature of the management effort and cost associated with using the tool.
  12. What circumstances lead the two organizations to develop different, yet similar tools for the management of complex projects? In your discussion of PERT/CPM, you should probably note that PERT helps us identify critical tasks/activities and look at the probability of completing the project by a given date; CPM helps us analyze the cost/time tradeoffs possible if we need to speed the project up.
  13. This and the next several slides illustrate the definitions of terms appropriate to critical path analysis. There are many opportunities for good managers to truly manage a project once they have a PERT network established. For instance, sub-contractors know early start and late start times and the managers know the activities on the critical path upon which to focus effort.
  14. This and the following slide illustrate the translation of Early and Late Start and Finish time to Gantt charts.
  15. This and the following slide illustrate the translation of Early and Late Start and Finish time to Gantt charts.
  16. In your discussion of activity times, you should probably at least make note of the difference between “most likely” and “average” or “ expected” completion times.
  17. There are those that argue that the Polaris could not have been built without the use of project management techniques (PERT).
  18. Another issue with respect to the use of PERT/CPM is the cost and amount of management time required to keep the system up to date.