SlideShare una empresa de Scribd logo
1 de 23
Descargar para leer sin conexión
© 2014 Uptime Institute
Low Complexity + Low Cost = High Availability
Keith Klesner, PE
Vice President, Strategic Accounts
Uptime Institute
Driven by Business, IT Strategy, and Customers
Multitude of Data Center Design Criteria
§  Availability
§  Location
§  Connectivity
§  Scalability
§  Energy Efficiency with 100% Availability
§  Innovation
Many Data Centers 100% Uptime is an Expectation
Simple and Cost-Effective Designs Lead to Uptime
Data Center Solutions
2
Uptime Institute Data and Analysis:
§  Historically vast majority of outages are caused by human error
§  In 2011 redundancy and staffing led to 67% of saves (outages
prevented)
§  Operational Sustainability reviews of dozens of live data centers in the
past 3 years
Certain Design Solutions Increase the Chance
for Human Error while other Designs Reduce the Risk
and Allow for Saves
Why Do Failures Occur?
3
Start With The End In Mind
Uptime Institute research and field experience confirms
§  Data center operations start before the conceptual design
phase of the project process
§  Data center operations continue to serve as the source of
continuity for knowledge management and transition to
production
Why an Operations Focus?
§  Increase return on investment
§  Increase uptime
§  Increase data center efficiency
§  Reduce costs
§  Reduce risks
4
Typical Construction Plan
Precon/Planning
Design
Construction
Commissioning
Turnover
Close out project
Scramble to get operations management program in place
Uptime Institute’s
Integrated Capital Project Plan
Starts with the end in mind…
and prepares customers from the beginning to maintain
and operate a data center beginning at turnover
5
Uptime Institute
Highly Operable Engineering Solution?
•  Fuel Control, Pumping, and
Filtration Room
•  2(N+1) Pumps
•  Complex Design was Initially
Built Incorrectly
•  Operating Valves Required
Climbing on and over Piping
7
Highly Operable Engineering Solution
•  20,000-liter Engine Generator
Belly Tank
•  Engine Generator within
Enclosure is Directly on top of
Belly Tank
•  No Additional Piping or Fuel
Pumps Required
8
Traits of Simplicity
§  Immediately understood architecture
•  2N Topology versus Isolated Redundant
•  Well marked A and B Systems
§  Avoid reliance and over provisioning of ATSs or STSs
§  Limit Complex Building Automation Systems
Allow for
§  Reduced operator error
§  Clear operations during emergency (allows for saves)
§  Reduced cording error
Simple Solutions
9
Simplicity in Practice
11
Design Example: 3 to Make 2 Option
•  Allows the UPSs and PDUs to be loaded at maximum of 66.6%
•  Requires strict management of loads and connections
12
Design Example: 2N Option
•  Allows the UPSs and PDUs to be loaded at maximum of 50%
•  Easiest layout to manage loads and connections
13
§  Is the design characteristic a proven performance
enhancement?
§  Does the design characteristic increase exposure to
human error?
Designers, Owners and Operators must be able
to answer the following:
14
“Right sized” for Load
§  Key equipment designed around major components
•  UPS, Engine Generators, and Chillers/Mechanical Cooling
§  Phased build out to truly allow for “pay-as-you-grow”
but without impacting the critical load
§  Modern equipment offers efficient performance across the load profile
Avoid Overspending
§  Over provisioning of ATSs and STSs
§  Excessive Redundancy at transformation layer
§  Too many system ties
Cost-Effective Solutions
15
Utilize Proven Technology
§  Early adopters pay a price penalty
§  Outage costs exceed incremental savings from new or
leading edge technology
Low Maintenance Systems
§  Lifecycle Cost - Purchase price not the only consideration
•  Operations/energy cost
•  Maintenance requirements
•  Lifespan and overhaul timelines
Offer Resource Availability
§  Critical spare parts
§  Local, experienced technicians
Cost-Effective Solutions
16
Proposed Electrical Solution
17
Onsite Power Generation
§  N+R systems where R= 1 or 2 have proven effective
§  1500 to 2000 kW Diesel EGs provide the most kW per dollar
UPS Systems
§  2N configuration has proven most reliable preventing costly outages
§  Allow for high efficiency across a load profile of 10-50%
§  Most have proven ability to handle a step load
§  1000 to 1200 kW static UPS systems provide the most kW per dollar
Critical Distribution
§  2N UPS allows for independent critical distribution to IT devices
Mechanical System
§  Designed to fit within EG balance of power and climate conditions
§  N+R systems where R= 1 or 2 have proven effective
Example of a Cost Effective Solution
18
Simplified Electrical Solution
G
UPS System
Computer Room Cooling
House Power
Chilled Water Plant
Main Distribution
UPS System
Computer Room Cooling
House Power
Chilled Water Plant
U
A
A
A
A
B
B
B
Mech Distribution A
Mech Distribution B
Main Distribution B
A
B
G
Critical Distribution Bus A
Critical Distribution Bus B
Side “A”
Side “B”
19
§  Scenario – Data Center w/Legacy Chilled Water with CRAHs or CRACs
§  Goal – Improve Efficiency of CRAHs/CRACs
§  Options – Replace or Retrofit with VFD or Electronically Commutated
Fan Assembly (EC)
Cost Effective Example - CRAC/CRAH Retrofit
20
Neither options change capacity of the cooling unit
Both technologies proven
Both options require control modification
Cost
•  Initial cost lower on VFD upgrade using existing
squirrel cage fans
•  EC fans offer improved fan performance
•  EC fan retrofit has significantly reduced maintenance
Result – EC fan assembly had 20-50% reduced
fan energy, reduced maintenance and reduced
maintenance related risk
CRAC/CRAH Retrofit - Analysis
21
Low Complexity and Low Cost may lead to high
availability
§  Start with the End In Mind
§  New yet proven technologies are efficient and may
be cost effective
Reduced complexity, simplifies the design
and lowers component count,
lowers cost and reduces the risk of human error
Summary
22
For more information contact:
Keith Klesner
UIwebinars@uptimeinstitute.com
720.214.6634
Questions?
© 2014 Uptime Institute23

Más contenido relacionado

La actualidad más candente

Combined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWCombined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NW
melanie_bissonnette
 

La actualidad más candente (20)

Monitoring Based Commissioning - A Must in The World of High Energy Efficiency
Monitoring Based Commissioning - A Must in The World of High Energy EfficiencyMonitoring Based Commissioning - A Must in The World of High Energy Efficiency
Monitoring Based Commissioning - A Must in The World of High Energy Efficiency
 
Resume1a
Resume1aResume1a
Resume1a
 
Transforming data into sustained energy performance
Transforming data into sustained energy performanceTransforming data into sustained energy performance
Transforming data into sustained energy performance
 
Combined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWCombined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NW
 
Implementing Hot and Cold Air Containment in Existing Data Centers
Implementing Hot and Cold Air Containment in Existing Data CentersImplementing Hot and Cold Air Containment in Existing Data Centers
Implementing Hot and Cold Air Containment in Existing Data Centers
 
Emerson Energy Logic
Emerson Energy LogicEmerson Energy Logic
Emerson Energy Logic
 
Air Flow Presentation 0218
Air Flow  Presentation 0218Air Flow  Presentation 0218
Air Flow Presentation 0218
 
Air Flow Presentation Pdf
Air Flow  Presentation PdfAir Flow  Presentation Pdf
Air Flow Presentation Pdf
 
Data Center Cooling Design - Datacenter-serverroom
Data Center Cooling Design - Datacenter-serverroomData Center Cooling Design - Datacenter-serverroom
Data Center Cooling Design - Datacenter-serverroom
 
How Green Is Your Data Center
How Green Is Your Data CenterHow Green Is Your Data Center
How Green Is Your Data Center
 
Data Center Cooling Strategies
Data Center Cooling StrategiesData Center Cooling Strategies
Data Center Cooling Strategies
 
Improving your PUE while consolidating into an existing live data center
Improving your PUE while consolidating into an existing live data centerImproving your PUE while consolidating into an existing live data center
Improving your PUE while consolidating into an existing live data center
 
Data Center Power Strategies
Data Center Power StrategiesData Center Power Strategies
Data Center Power Strategies
 
Centralized Management, Controlled Savings
Centralized Management, Controlled SavingsCentralized Management, Controlled Savings
Centralized Management, Controlled Savings
 
Data Center Server Rack Strategies
Data Center Server Rack StrategiesData Center Server Rack Strategies
Data Center Server Rack Strategies
 
Extending the Life of Existing Switchgear
Extending the Life of Existing SwitchgearExtending the Life of Existing Switchgear
Extending the Life of Existing Switchgear
 
Ever Green Dc
Ever Green DcEver Green Dc
Ever Green Dc
 
Retrocommissioning Gets Results
Retrocommissioning Gets ResultsRetrocommissioning Gets Results
Retrocommissioning Gets Results
 
Energy Management Impact on Distributed Control Systems (DCS) in Industrial E...
Energy Management Impact on Distributed Control Systems (DCS) in Industrial E...Energy Management Impact on Distributed Control Systems (DCS) in Industrial E...
Energy Management Impact on Distributed Control Systems (DCS) in Industrial E...
 
DCD_FOCUS on POWER Article
DCD_FOCUS on POWER ArticleDCD_FOCUS on POWER Article
DCD_FOCUS on POWER Article
 

Destacado

The_Future_of_Data-Centres_-_Prof._Ian_Bitterlin_Emerson
The_Future_of_Data-Centres_-_Prof._Ian_Bitterlin_EmersonThe_Future_of_Data-Centres_-_Prof._Ian_Bitterlin_Emerson
The_Future_of_Data-Centres_-_Prof._Ian_Bitterlin_Emerson
Johann Hendry
 
Tier Stanadard Operational-Sustainability
Tier Stanadard Operational-SustainabilityTier Stanadard Operational-Sustainability
Tier Stanadard Operational-Sustainability
Johann Hendry
 

Destacado (9)

Uptime Institute 2015 Industry Survey
Uptime Institute 2015 Industry SurveyUptime Institute 2015 Industry Survey
Uptime Institute 2015 Industry Survey
 
Avoid wasting time and money procuring and implementing dcim
Avoid wasting time and money procuring and implementing dcimAvoid wasting time and money procuring and implementing dcim
Avoid wasting time and money procuring and implementing dcim
 
Buyer beware
Buyer bewareBuyer beware
Buyer beware
 
Cisco Connected Grid Solutions
Cisco Connected Grid SolutionsCisco Connected Grid Solutions
Cisco Connected Grid Solutions
 
The_Future_of_Data-Centres_-_Prof._Ian_Bitterlin_Emerson
The_Future_of_Data-Centres_-_Prof._Ian_Bitterlin_EmersonThe_Future_of_Data-Centres_-_Prof._Ian_Bitterlin_Emerson
The_Future_of_Data-Centres_-_Prof._Ian_Bitterlin_Emerson
 
Start With The End In Mind
Start With The End In MindStart With The End In Mind
Start With The End In Mind
 
Tier Stanadard Operational-Sustainability
Tier Stanadard Operational-SustainabilityTier Stanadard Operational-Sustainability
Tier Stanadard Operational-Sustainability
 
Is your data center on the verge of a crisis?
Is your data center on the verge of a crisis?Is your data center on the verge of a crisis?
Is your data center on the verge of a crisis?
 
Commissioning services for substation and power plants
Commissioning services for substation and power plantsCommissioning services for substation and power plants
Commissioning services for substation and power plants
 

Similar a Low Complexity + Low Cost = High Availability

6dec2011 - Power Back-up_1
6dec2011 - Power Back-up_16dec2011 - Power Back-up_1
6dec2011 - Power Back-up_1
Agora Group
 
Evaluation of standby power system architectures
Evaluation of standby power system architecturesEvaluation of standby power system architectures
Evaluation of standby power system architectures
michaeljmack
 
E source energy managers conf 4 24-13-final
E source energy managers conf 4 24-13-finalE source energy managers conf 4 24-13-final
E source energy managers conf 4 24-13-final
josh whitney
 
Data Center PUE Reconsidered
Data Center PUE Reconsidered Data Center PUE Reconsidered
Data Center PUE Reconsidered
Raritan
 

Similar a Low Complexity + Low Cost = High Availability (20)

Aged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptxAged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptx
 
Going Modular? Lessons learned from 500 modular data center implementations
Going Modular?  Lessons learned from 500 modular data center implementations Going Modular?  Lessons learned from 500 modular data center implementations
Going Modular? Lessons learned from 500 modular data center implementations
 
PUE Reconsidered
PUE ReconsideredPUE Reconsidered
PUE Reconsidered
 
6dec2011 - Power Back-up_1
6dec2011 - Power Back-up_16dec2011 - Power Back-up_1
6dec2011 - Power Back-up_1
 
Green power for the futuree
Green power for the futureeGreen power for the futuree
Green power for the futuree
 
High Performance Buildings: Meeting Operational Expectations with Constrained...
High Performance Buildings: Meeting Operational Expectations with Constrained...High Performance Buildings: Meeting Operational Expectations with Constrained...
High Performance Buildings: Meeting Operational Expectations with Constrained...
 
Retrofit, build, or go cloud/colo? Choosing your best direction
Retrofit, build, or go cloud/colo?  Choosing your best directionRetrofit, build, or go cloud/colo?  Choosing your best direction
Retrofit, build, or go cloud/colo? Choosing your best direction
 
Retrofit, build, or go cloud/colo? Choosing your best direction
Retrofit, build, or go cloud/colo?  Choosing your best directionRetrofit, build, or go cloud/colo?  Choosing your best direction
Retrofit, build, or go cloud/colo? Choosing your best direction
 
Green & Beyond: Data Center Actions to Increase Business Responsiveness and R...
Green & Beyond: Data Center Actions to Increase Business Responsiveness and R...Green & Beyond: Data Center Actions to Increase Business Responsiveness and R...
Green & Beyond: Data Center Actions to Increase Business Responsiveness and R...
 
Upgrading data centres beyond planned capacity
Upgrading data centres beyond planned capacityUpgrading data centres beyond planned capacity
Upgrading data centres beyond planned capacity
 
Umit hw6
Umit hw6Umit hw6
Umit hw6
 
Evaluation of standby power system architectures
Evaluation of standby power system architecturesEvaluation of standby power system architectures
Evaluation of standby power system architectures
 
E source energy managers conf 4 24-13-final
E source energy managers conf 4 24-13-finalE source energy managers conf 4 24-13-final
E source energy managers conf 4 24-13-final
 
Data Center PUE Reconsidered
Data Center PUE Reconsidered Data Center PUE Reconsidered
Data Center PUE Reconsidered
 
Steve hammond nrel
Steve hammond nrelSteve hammond nrel
Steve hammond nrel
 
Hacking the Conventional Data Center Infrastructure
Hacking the Conventional  Data Center InfrastructureHacking the Conventional  Data Center Infrastructure
Hacking the Conventional Data Center Infrastructure
 
axisCONSERVE4.0
axisCONSERVE4.0axisCONSERVE4.0
axisCONSERVE4.0
 
Data Center UPS System Upgrade
Data Center UPS System UpgradeData Center UPS System Upgrade
Data Center UPS System Upgrade
 
Faronics Power Save
Faronics Power SaveFaronics Power Save
Faronics Power Save
 
Top 10 Products That Save Money - David McDougall, EnerNOC
Top 10 Products That Save Money - David McDougall, EnerNOCTop 10 Products That Save Money - David McDougall, EnerNOC
Top 10 Products That Save Money - David McDougall, EnerNOC
 

Último

Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
Nauman Safdar
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
allensay1
 

Último (20)

Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck Template
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTSDurg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTSJAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
 
WheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond InsightsWheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond Insights
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
 
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableBerhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
 

Low Complexity + Low Cost = High Availability

  • 1. © 2014 Uptime Institute Low Complexity + Low Cost = High Availability Keith Klesner, PE Vice President, Strategic Accounts Uptime Institute
  • 2. Driven by Business, IT Strategy, and Customers Multitude of Data Center Design Criteria §  Availability §  Location §  Connectivity §  Scalability §  Energy Efficiency with 100% Availability §  Innovation Many Data Centers 100% Uptime is an Expectation Simple and Cost-Effective Designs Lead to Uptime Data Center Solutions 2
  • 3. Uptime Institute Data and Analysis: §  Historically vast majority of outages are caused by human error §  In 2011 redundancy and staffing led to 67% of saves (outages prevented) §  Operational Sustainability reviews of dozens of live data centers in the past 3 years Certain Design Solutions Increase the Chance for Human Error while other Designs Reduce the Risk and Allow for Saves Why Do Failures Occur? 3
  • 4. Start With The End In Mind Uptime Institute research and field experience confirms §  Data center operations start before the conceptual design phase of the project process §  Data center operations continue to serve as the source of continuity for knowledge management and transition to production Why an Operations Focus? §  Increase return on investment §  Increase uptime §  Increase data center efficiency §  Reduce costs §  Reduce risks 4
  • 5. Typical Construction Plan Precon/Planning Design Construction Commissioning Turnover Close out project Scramble to get operations management program in place Uptime Institute’s Integrated Capital Project Plan Starts with the end in mind… and prepares customers from the beginning to maintain and operate a data center beginning at turnover 5
  • 7. Highly Operable Engineering Solution? •  Fuel Control, Pumping, and Filtration Room •  2(N+1) Pumps •  Complex Design was Initially Built Incorrectly •  Operating Valves Required Climbing on and over Piping 7
  • 8. Highly Operable Engineering Solution •  20,000-liter Engine Generator Belly Tank •  Engine Generator within Enclosure is Directly on top of Belly Tank •  No Additional Piping or Fuel Pumps Required 8
  • 9. Traits of Simplicity §  Immediately understood architecture •  2N Topology versus Isolated Redundant •  Well marked A and B Systems §  Avoid reliance and over provisioning of ATSs or STSs §  Limit Complex Building Automation Systems Allow for §  Reduced operator error §  Clear operations during emergency (allows for saves) §  Reduced cording error Simple Solutions 9
  • 10.
  • 12. Design Example: 3 to Make 2 Option •  Allows the UPSs and PDUs to be loaded at maximum of 66.6% •  Requires strict management of loads and connections 12
  • 13. Design Example: 2N Option •  Allows the UPSs and PDUs to be loaded at maximum of 50% •  Easiest layout to manage loads and connections 13
  • 14. §  Is the design characteristic a proven performance enhancement? §  Does the design characteristic increase exposure to human error? Designers, Owners and Operators must be able to answer the following: 14
  • 15. “Right sized” for Load §  Key equipment designed around major components •  UPS, Engine Generators, and Chillers/Mechanical Cooling §  Phased build out to truly allow for “pay-as-you-grow” but without impacting the critical load §  Modern equipment offers efficient performance across the load profile Avoid Overspending §  Over provisioning of ATSs and STSs §  Excessive Redundancy at transformation layer §  Too many system ties Cost-Effective Solutions 15
  • 16. Utilize Proven Technology §  Early adopters pay a price penalty §  Outage costs exceed incremental savings from new or leading edge technology Low Maintenance Systems §  Lifecycle Cost - Purchase price not the only consideration •  Operations/energy cost •  Maintenance requirements •  Lifespan and overhaul timelines Offer Resource Availability §  Critical spare parts §  Local, experienced technicians Cost-Effective Solutions 16
  • 18. Onsite Power Generation §  N+R systems where R= 1 or 2 have proven effective §  1500 to 2000 kW Diesel EGs provide the most kW per dollar UPS Systems §  2N configuration has proven most reliable preventing costly outages §  Allow for high efficiency across a load profile of 10-50% §  Most have proven ability to handle a step load §  1000 to 1200 kW static UPS systems provide the most kW per dollar Critical Distribution §  2N UPS allows for independent critical distribution to IT devices Mechanical System §  Designed to fit within EG balance of power and climate conditions §  N+R systems where R= 1 or 2 have proven effective Example of a Cost Effective Solution 18
  • 19. Simplified Electrical Solution G UPS System Computer Room Cooling House Power Chilled Water Plant Main Distribution UPS System Computer Room Cooling House Power Chilled Water Plant U A A A A B B B Mech Distribution A Mech Distribution B Main Distribution B A B G Critical Distribution Bus A Critical Distribution Bus B Side “A” Side “B” 19
  • 20. §  Scenario – Data Center w/Legacy Chilled Water with CRAHs or CRACs §  Goal – Improve Efficiency of CRAHs/CRACs §  Options – Replace or Retrofit with VFD or Electronically Commutated Fan Assembly (EC) Cost Effective Example - CRAC/CRAH Retrofit 20
  • 21. Neither options change capacity of the cooling unit Both technologies proven Both options require control modification Cost •  Initial cost lower on VFD upgrade using existing squirrel cage fans •  EC fans offer improved fan performance •  EC fan retrofit has significantly reduced maintenance Result – EC fan assembly had 20-50% reduced fan energy, reduced maintenance and reduced maintenance related risk CRAC/CRAH Retrofit - Analysis 21
  • 22. Low Complexity and Low Cost may lead to high availability §  Start with the End In Mind §  New yet proven technologies are efficient and may be cost effective Reduced complexity, simplifies the design and lowers component count, lowers cost and reduces the risk of human error Summary 22
  • 23. For more information contact: Keith Klesner UIwebinars@uptimeinstitute.com 720.214.6634 Questions? © 2014 Uptime Institute23