Reconstruction in Chile




                                      Julio Poblete
                                          Architect, MAUD
                                                   Partner
                          DUPLA_Urban Design an d Planning
                                        jpoblete@dupla.cl
Contents

-The Disaster and the Reconstruction Plan

- DUPLA Reconstruction Work

-Challenges and Lessons Learned
General Figures
25-Mar   370.000 Initial Assesment of HOUSES DAMAGED OR DESTROYED

27-Ago   285.500 FAMILIES REGISTERED IN THE REGISTRY OF VICTIMS

27-Sep   220.000 FAMILIES ELIGIBLE FOR GOVERNMENT ASSISTANCE
Managing Emergency: ALDEAS
By July 2010 almost 80.000 emergency houses were constructed in the 6 affected regions .
       More than 70.000 of these homes were built in the same places where the victims lived.




4.350 families had no land to build the EH, so that 107 emergency camps - Aldeas - were located




Families living in Aldeas represent less than 5.3% of the total of families living in a emergency

houses after the earthquake.
Housing Program
Housing Program main challenge:
disperse damage




                                  TALCA
                                  Damage Maping
                                  31.07.2010
Reconstruction in the owner’s site
•Respect the right of families to choose their solution.
•The construction in the owner’s site allows to recognize their own roots
•Is an invitation to innovation and more competition in the industry
•Greater transparency, participation
• Highest standards of quality and performance
•Bank of More than 200 models pre-designed and certified by Housing Ministery
Housing EXPO for pre-designed homes
Housing Program


Demand organization to achieve critical mass for
industrialized homes in remote areas

19,000 dollar-subsidy (once and not
refundable) for a 50 sq. meter home, including
reconnecting to sewage, water supply and
electricity.
Common Scenario for Rural Areas


Original Home                     New Home   Emergency Solution
Risk Mitigation for Tsumani Areas

• Risk Studies were conducted form Regions VI to IX + Tsunami risk simulations
• 25 Master Plans of Coastline were completed in 6 months.
   Cobquecura     Dichato           Tumbes        Lo Rojas




                                                                       Cocholgue

                            Llico   Tubul                    Quidico   I. Sta. María




     Coliumo
Urban Rehabilitation and Reconstruction
2 Master Plans for main inland cities
25 Master Plans developed for main coastal cities
100 Regeneration Plans developed for mid-size cities, towns, and villages
 Heritage Recovery Plans developed for 180 historic preservation districts
How is Housing Program progressing?
  Subsidies




  Buildings under Construction/Repairing




  Finished
DUPLA Reconstruction Work:

-Reconstruction Plan for the city of Talca
-Special Housing Program for Talca’s Historic District
-Design Guidelines por Mid-Density Projects
-Land Pooling Proposal for Mixed Income Projects.
TALCA




        260 KM.
        520 KM.




                        Population:   238.000 people
                  Daily Commuters:     40.000 people
City Historic Center Severely Damaged




                                          _3600 damaged properties
                                            _ 1700 to be demolished

                                        _ 90 hectares will be available for
                                                            redevelopment
Main Comercial District Destroyed




                                    80% of Heritage with
                                    considerable damage
Continous Facades no longer define the Street nor Public Space
Master Plan_ Improve Conectivity

                                                                             10
                                                               11
                                                                    9                                 1. Costanera Río Claro
                                                                                                      2. Aperturas hacia la Costanera
                                                                                                          (4)
                                        2   11                                                        3. Extensión Diagonal hacia
                            1       2                                                                     Costanera
                                                                                      9
                                                 12                                                   4. Costanera Piduco Sur
                        2                                                                             5. Extensión Carlos Schor
                                                                        15
                    2                                 14                                              6. Extensión 26 Sur
                                                13                                            a
                                                                                                      7. Costanera El Cajón Sur
                            3                                                                         8. Circunvalación 30 Oriente
                                                                                                  9   9. Circunvalación 17 Norte
                                                                                                      10. 20 Norte
                                                                                                      11. Canal de la Luz
                                                                                                      12. 1 Oriente / 9 O – 11 O
                                4
                                                                                                      13. Extensión Diagonal Pencahue
                5                                                                                     14. Extensión Av. Lircay
                                                                                                      15. Conexión 11 Oriente
                                                                                                  8
        1                                                                                             EXPROPIACIONES
                                                                                                      Av. Lircay / 8 N – 9 N
                                            4
                                                                                                      Nuevos accesos (Enlaces ruta 5)

                                                                                                      a. Circunvalación 17 Norte
            6                                                                     4
                                                                                                      b. Costanera Piduco Sur
                                                                                          b




    7                                                                                     8
                                                           7
Master Plan_ Recover and define a Public Space Network

                               4
                                                 Public Space

                                                 PARQUES PÚBLICOS
                                                 1. Parque Río Claro
                  1                              2. Forestación Cerro La Virgen
                               a                 3. Mejoramiento Estero
                                                    Piduco
                                                 4. Mejoramiento Estero Baeza
       2

                                                 CORREDORES
                      b                          SEMIPEATONALES
                                                 a. Par 4 O y 5O
                                                 b. Par 1S – 1N – Diagonal
                                   b

                                                 MEJORAMIENTO DEL
                           a
                                                 ESPACIO PÚBLICO
                                                 i. 12 N /Av. Lircay-
                                                      Circunvalación
                           3                     ii. Av. Lircay / 12 N – 9N
                                                 iii. 11 Oriente / 4 N – 8 S
                                                 iv. 12 Oriente / 2 N – 8 S
                                                 v. 1 Norte / 12 O – 14 O
                                                 vi. 1 Sur / 11 O- 12 O
                                                 vii. 3 Sur / 12 O – 15 O
And a different approach for housing program




 Tipology adapted to lot shape and measures
 Apaptive Model: space for densifying and/or adding sq. meters
Before




After
With Urban DNA: 1+1=3
Urban Image, Redefine Public Space, Reinforce Identity.
300 houses under construction (30% of all destroyed within historic distric)
Design Guidelines for Mid Density Projects
Goverment adopted them and called for proposals
Imagen Objetivo Densificación con Comercio
Land Readjustment for Inclusionary Housing Projects
(Proposal by DUPLA + Lincoln Institute of Land Policy + Catholic University Public
Policy Program)
Challenges / Lessons Learned / Things to Do

1.   Improving Communication with Municipalities and Supporting Local
     Capacities.

2.   Balance Transparency with Efficiency: Asking sometimes is enemy of Doing

3.   Build Common Indicators for evaluating reconstruction

4.   Switch to a NOT Business as usual model: Call for Home Builders and
     Contractors to be more flexible.

5.   Strengthen opportunities for community involvement : Lack of Community
     Organization and Weak Empowerment

6.   Timely Implementation of special /ad-hoc measures vs. over reacting
     (reinvent all)

7.   Master Plan Initiatives linked to National Budget and Regular Public
     Investment Programs: design a new pipeline for project’s approval and
     funding
Reconstruction in Chile
Thanks to ULI
Thanks to EBSA (my client and generous donor)
Thanks…




                                                            Julio Poblete
                                                      Architect, MAUD / Partner
                                                DUPLA_Urban Design an d Planning
                                                              jpoblete@dupla.cl

Más contenido relacionado

Más de Virtual ULI

Michael smith, Urban Environments Built on Innovative Thinking
Michael smith, Urban Environments Built on Innovative ThinkingMichael smith, Urban Environments Built on Innovative Thinking
Michael smith, Urban Environments Built on Innovative Thinking
Virtual ULI
 

Más de Virtual ULI (20)

Will balthrope, Multifamily Development Today
Will balthrope, Multifamily Development TodayWill balthrope, Multifamily Development Today
Will balthrope, Multifamily Development Today
 
Spencer stuart, Multifamily Development Today
Spencer stuart, Multifamily Development TodaySpencer stuart, Multifamily Development Today
Spencer stuart, Multifamily Development Today
 
Peter porraro, Multifamily Development Today
Peter porraro, Multifamily Development TodayPeter porraro, Multifamily Development Today
Peter porraro, Multifamily Development Today
 
Timothy mc entee, Multifamily Development Today
Timothy mc entee, Multifamily Development TodayTimothy mc entee, Multifamily Development Today
Timothy mc entee, Multifamily Development Today
 
Marc goldstein, Building Capital Stacks in Today's Market
Marc goldstein, Building Capital Stacks in Today's MarketMarc goldstein, Building Capital Stacks in Today's Market
Marc goldstein, Building Capital Stacks in Today's Market
 
Jeffrey bijur, Building Capital Stacks in Today's Market
Jeffrey bijur, Building Capital Stacks in Today's MarketJeffrey bijur, Building Capital Stacks in Today's Market
Jeffrey bijur, Building Capital Stacks in Today's Market
 
Perry reader, What Is the Recipe for Community Development-Let's Stir the Pot
Perry reader, What Is the Recipe for Community Development-Let's Stir the PotPerry reader, What Is the Recipe for Community Development-Let's Stir the Pot
Perry reader, What Is the Recipe for Community Development-Let's Stir the Pot
 
Jack cecil, What Is the Recipe for Community Development-Let's Stir the Pot
Jack cecil, What Is the Recipe for Community Development-Let's Stir the PotJack cecil, What Is the Recipe for Community Development-Let's Stir the Pot
Jack cecil, What Is the Recipe for Community Development-Let's Stir the Pot
 
Don whyte, What Is the Recipe for Community Development-Let's Stir the Pot
Don whyte, What Is the Recipe for Community Development-Let's Stir the PotDon whyte, What Is the Recipe for Community Development-Let's Stir the Pot
Don whyte, What Is the Recipe for Community Development-Let's Stir the Pot
 
Andy cohen, Rethinking Office
Andy cohen, Rethinking OfficeAndy cohen, Rethinking Office
Andy cohen, Rethinking Office
 
Martha o'mara, Rethinking Office
Martha o'mara, Rethinking OfficeMartha o'mara, Rethinking Office
Martha o'mara, Rethinking Office
 
Tom caputo, Repositioning and Restructuring Retail
Tom caputo, Repositioning and Restructuring RetailTom caputo, Repositioning and Restructuring Retail
Tom caputo, Repositioning and Restructuring Retail
 
Robert grossman, Repositioning and Restructuring Retail
Robert grossman, Repositioning and Restructuring RetailRobert grossman, Repositioning and Restructuring Retail
Robert grossman, Repositioning and Restructuring Retail
 
Michael carroll, Repositioning and Restructuring Retail
Michael carroll, Repositioning and Restructuring RetailMichael carroll, Repositioning and Restructuring Retail
Michael carroll, Repositioning and Restructuring Retail
 
Anthony chang, Making ULI Work for you
Anthony chang, Making ULI Work for youAnthony chang, Making ULI Work for you
Anthony chang, Making ULI Work for you
 
Michael smith, Urban Environments Built on Innovative Thinking
Michael smith, Urban Environments Built on Innovative ThinkingMichael smith, Urban Environments Built on Innovative Thinking
Michael smith, Urban Environments Built on Innovative Thinking
 
Urban Environments Built on Innovative Thinking
Urban Environments Built on Innovative ThinkingUrban Environments Built on Innovative Thinking
Urban Environments Built on Innovative Thinking
 
Ron kimble, Urban Environments Built on Innovative Thinking
Ron kimble, Urban Environments Built on Innovative ThinkingRon kimble, Urban Environments Built on Innovative Thinking
Ron kimble, Urban Environments Built on Innovative Thinking
 
Cats: Issues/Challenges for the Future
Cats: Issues/Challenges for the FutureCats: Issues/Challenges for the Future
Cats: Issues/Challenges for the Future
 
South Corridor Development Summary
South Corridor Development SummarySouth Corridor Development Summary
South Corridor Development Summary
 

Último

EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
Earley Information Science
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
Joaquim Jorge
 

Último (20)

Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdf
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 

Reconstruction in Chile (Corinne Packard) - ULI fall meeting - 102711

  • 1. Reconstruction in Chile Julio Poblete Architect, MAUD Partner DUPLA_Urban Design an d Planning jpoblete@dupla.cl
  • 2. Contents -The Disaster and the Reconstruction Plan - DUPLA Reconstruction Work -Challenges and Lessons Learned
  • 3.
  • 4.
  • 5.
  • 6. General Figures 25-Mar 370.000 Initial Assesment of HOUSES DAMAGED OR DESTROYED 27-Ago 285.500 FAMILIES REGISTERED IN THE REGISTRY OF VICTIMS 27-Sep 220.000 FAMILIES ELIGIBLE FOR GOVERNMENT ASSISTANCE
  • 7. Managing Emergency: ALDEAS By July 2010 almost 80.000 emergency houses were constructed in the 6 affected regions . More than 70.000 of these homes were built in the same places where the victims lived. 4.350 families had no land to build the EH, so that 107 emergency camps - Aldeas - were located Families living in Aldeas represent less than 5.3% of the total of families living in a emergency houses after the earthquake.
  • 9. Housing Program main challenge: disperse damage TALCA Damage Maping 31.07.2010
  • 10. Reconstruction in the owner’s site •Respect the right of families to choose their solution. •The construction in the owner’s site allows to recognize their own roots •Is an invitation to innovation and more competition in the industry •Greater transparency, participation • Highest standards of quality and performance •Bank of More than 200 models pre-designed and certified by Housing Ministery
  • 11. Housing EXPO for pre-designed homes
  • 12. Housing Program Demand organization to achieve critical mass for industrialized homes in remote areas 19,000 dollar-subsidy (once and not refundable) for a 50 sq. meter home, including reconnecting to sewage, water supply and electricity.
  • 13. Common Scenario for Rural Areas Original Home New Home Emergency Solution
  • 14. Risk Mitigation for Tsumani Areas • Risk Studies were conducted form Regions VI to IX + Tsunami risk simulations • 25 Master Plans of Coastline were completed in 6 months. Cobquecura Dichato Tumbes Lo Rojas Cocholgue Llico Tubul Quidico I. Sta. María Coliumo
  • 15. Urban Rehabilitation and Reconstruction 2 Master Plans for main inland cities 25 Master Plans developed for main coastal cities 100 Regeneration Plans developed for mid-size cities, towns, and villages  Heritage Recovery Plans developed for 180 historic preservation districts
  • 16. How is Housing Program progressing? Subsidies Buildings under Construction/Repairing Finished
  • 17. DUPLA Reconstruction Work: -Reconstruction Plan for the city of Talca -Special Housing Program for Talca’s Historic District -Design Guidelines por Mid-Density Projects -Land Pooling Proposal for Mixed Income Projects.
  • 18. TALCA 260 KM. 520 KM. Population: 238.000 people Daily Commuters: 40.000 people
  • 19. City Historic Center Severely Damaged _3600 damaged properties _ 1700 to be demolished _ 90 hectares will be available for redevelopment
  • 20. Main Comercial District Destroyed 80% of Heritage with considerable damage
  • 21. Continous Facades no longer define the Street nor Public Space
  • 22. Master Plan_ Improve Conectivity 10 11 9 1. Costanera Río Claro 2. Aperturas hacia la Costanera (4) 2 11 3. Extensión Diagonal hacia 1 2 Costanera 9 12 4. Costanera Piduco Sur 2 5. Extensión Carlos Schor 15 2 14 6. Extensión 26 Sur 13 a 7. Costanera El Cajón Sur 3 8. Circunvalación 30 Oriente 9 9. Circunvalación 17 Norte 10. 20 Norte 11. Canal de la Luz 12. 1 Oriente / 9 O – 11 O 4 13. Extensión Diagonal Pencahue 5 14. Extensión Av. Lircay 15. Conexión 11 Oriente 8 1 EXPROPIACIONES Av. Lircay / 8 N – 9 N 4 Nuevos accesos (Enlaces ruta 5) a. Circunvalación 17 Norte 6 4 b. Costanera Piduco Sur b 7 8 7
  • 23. Master Plan_ Recover and define a Public Space Network 4 Public Space PARQUES PÚBLICOS 1. Parque Río Claro 1 2. Forestación Cerro La Virgen a 3. Mejoramiento Estero Piduco 4. Mejoramiento Estero Baeza 2 CORREDORES b SEMIPEATONALES a. Par 4 O y 5O b. Par 1S – 1N – Diagonal b MEJORAMIENTO DEL a ESPACIO PÚBLICO i. 12 N /Av. Lircay- Circunvalación 3 ii. Av. Lircay / 12 N – 9N iii. 11 Oriente / 4 N – 8 S iv. 12 Oriente / 2 N – 8 S v. 1 Norte / 12 O – 14 O vi. 1 Sur / 11 O- 12 O vii. 3 Sur / 12 O – 15 O
  • 24.
  • 25. And a different approach for housing program Tipology adapted to lot shape and measures Apaptive Model: space for densifying and/or adding sq. meters
  • 27. With Urban DNA: 1+1=3 Urban Image, Redefine Public Space, Reinforce Identity.
  • 28. 300 houses under construction (30% of all destroyed within historic distric)
  • 29. Design Guidelines for Mid Density Projects Goverment adopted them and called for proposals
  • 31. Land Readjustment for Inclusionary Housing Projects (Proposal by DUPLA + Lincoln Institute of Land Policy + Catholic University Public Policy Program)
  • 32. Challenges / Lessons Learned / Things to Do 1. Improving Communication with Municipalities and Supporting Local Capacities. 2. Balance Transparency with Efficiency: Asking sometimes is enemy of Doing 3. Build Common Indicators for evaluating reconstruction 4. Switch to a NOT Business as usual model: Call for Home Builders and Contractors to be more flexible. 5. Strengthen opportunities for community involvement : Lack of Community Organization and Weak Empowerment 6. Timely Implementation of special /ad-hoc measures vs. over reacting (reinvent all) 7. Master Plan Initiatives linked to National Budget and Regular Public Investment Programs: design a new pipeline for project’s approval and funding
  • 33. Reconstruction in Chile Thanks to ULI Thanks to EBSA (my client and generous donor) Thanks… Julio Poblete Architect, MAUD / Partner DUPLA_Urban Design an d Planning jpoblete@dupla.cl