SlideShare una empresa de Scribd logo
1 de 35
ENVIRONMENT IMPACT ASSESMENT OF
NAVI MUMBAI AIRPORT

Vivekanand P. Moril
2012JEN2119
PROJECT


Total area earmarked for airport development is
2054 Ha. consisting of 1615 Ha. as airport zone
and remaining for off-site infrastructure, such as;
diversion & training of rivers, approach road,
railways, interchanges and utility lines, etc.



The entire area of the airport zone falls in Raigad
District in Panvel & Uran Tahasil covering its 16
villages.
Selection of Alternative Sites
The analysis of alternative sites is done based on
following two methods.
 1) SWOT (Strength, Weakness, Opportunity &
Threat) Analysis
 2) Site Sensitivity Analysis


 The

overall score is worked out on the basis of site
sensitivity index for different parameters and
integration of total impact is worked out &
categorized as below-
Categorisation Criteria












Overall scale Level of Environmental Impact
750-1000
Very high
600-750
High
450-600
Moderate
300-450
Low
Less than 300
Very low
After comparison the scores were added.
The Rewas-Mandwa score is 773.95.(Environmental
Impact is Very High).
Navi Mumbai score is 498.69. (Environmental Impact
is Moderate).
Study Area
The study area around airport falling within the
radius of 10Kms. The study area is further
extended upto 20 km. as fringe area.
 The core area covers the area within the radius of
10km, in which all the scoped environmental
parameters is studied to understand the
magnitude of impact.
 In the remaining area i.e. fringe area places of
historical
importance,
aesthetic,
cultural
including environmentally sensitive area is
studied.

Identification
and
Evaluation
and
Development of Impact & Mitigation Options


Flow Diagram
Impact Identification


To help in / ease the impact evaluation process,
the various activities of the NMIA which can have
an impact on environment have been classified
into four stages namely:



I. NMIA location



II. NMIA project design



III. NMIA construction phase



IV. NMIA operation phase
1.1 NMIA Location : Activity, Impact &
Mitigation
1.1.1 Activity


Removal of Mangroves & Biodiversity

1.1.2 Impacts


With the project intervention, these mangroves (though in
degraded form) will be totally lost forever. A total of
161.5 Ha of mangroves will be lost due to the project.

1.1.3 Mitigation
CIDCO has planned to take up approx. 350 Ha. of plantation
of mangroves against 161.5 Ha. loss.
1.2 NMIA Location : Activities, Impact & Mitigation
1.2.1 Activity


Tree Clearance

1.2.2 Impact


There is no forest in the project site area, though there are naturally
growing trees/plants/vegetation in the area. Most of the vegetation of
trees in and around the villages are planted fruiting trees like mango,
jamun, jackfruit, guava, custard apple etc. and the wood yielding trees
like teak, etc. The ornamental trees, bamboos and palms also have
been planted and/or maintained by the villagers.



This project will result in loss of all vegetation in the project site.
1.2 NMIA Location : Activities, Impact & Mitigation
1.2.3 Mitigation


With respect to the trees from the displaced villages,
CIDCO will take up the task of replanting the trees in their
areas where they are carrying out developmental
activities or along the highways.
1.3 NMIA Location : Activities, Impact
& Mitigation
1.3.1 Activity


Roads and Infrastructure

1.3.2 Impacts


The over concretization resulting in increase in
temperature during the day time and summer time along
the roads.



Diversion of agricultural land leading to issues of land use
change and food security.
1.3 NMIA Location : Activities, Impact &
Mitigation
1.3.3 Mitigation


Compensatory vegetation and plantation programme will be
undertaken within the airport area in the mandatory space.



The entire plantation undertaken will be non-fruit bearing so as
to reduce any bird mishaps during the operation phase.
1.4 NMIA Location : Activities, Impact
& Mitigation
1.4.1 Activity


Railways Infrastructure

1.4.2 Impacts


The loss of mangroves & vegetation.



Diversion of agricultural land leading to issues of land use
change and food security.
1.5 NMIA Location : Activity, Impact &
Mitigation
1.5.1 Activity
 Rehabilitation of the displaced villagers
1.5.2 Impacts
 Ten settlements belonging to seven villages are required to be resettled
away from the project site. Approx 15000 people will be affected due to
the project.
 Development of basic infrastructure such as water supply, electricity,
sewerage, roads, social infrastructure etc. shall be required.
1.5.3 Mitigation
 Land will be provided to displaced villagers.
 CIDCO has assumed a proactive role towards the mitigation of the social
impacts by the rehabilitation.
1.6 NMIA Location : Activity, Impact &
Mitigation
1.6.1 Activity


Archeological / Cultural / Historic Sites

1.6.2 Impacts


The fringe area study falling between 10 to 20 km. radius,
revealed that there are 3 places of historic importance, aesthetic,
cultural including sensitive area namely the Elephanta Caves,
Karnala Bird Sanctuary and Matheran Eco-sensitive Zone.
1.6 NMIA Location : Activity, Impact &
Mitigation
1.6.3

Mitigation



The Elephanta Caves is about 13.5 km from site. The position of aircraft during
takeoff/landing/missed approach, would be more than 700 m.



The Karnala Bird sanctuary is about 12.5 km from site. The position of
aircraft during takeoff/landing/missed approach, would be more than 750
m.



The Karnala Bird sanctuary is about 11 km from site. The position of
aircraft during takeoff/landing/missed approach, would be more than 500
m.



During operation phase, proper flight directions can be provided so as to
avoid flying over any of these sites.
1.7 NMIA Location : Activity, Impact &
Mitigation
1.7.1 Activity


Residential Facilities

1.7.2 Impacts


300 Ha. Area is required for the housing needs of workers.
This housing needs to be supported by all the requisite
social and cultural facilities.



Additional load on water and energy would have to be
met.
2.1 NMIA Project Design – Activity,
Impact & Mitigation
2.1.1 Activity


Training of Gadhi River, Diversion of Ulve River

2.1.2 Impacts


The impacts of channelization on the aquatic community
mainly arise due to channel excavation, dredging, clearing and
removal of vegetation.



Siltation affects aquatic vegetation by increasing the turbidity
of water.



Loss and reduction in the number of organisms.
2.1 NMIA Project Design – Activity, Impact &
Mitigation
2.1.3 Mitigation






The channelization activities are designed to keep flow
characteristics as close to natural flow.
In order to minimize the above impacts of
dredging/channelization, proper route alignment will be
selected and the dredging and excavation will be done in
stages maintaining the water flow. This operation will result
in minimum impact on siltation/turbidity on aquatic
community.
Contamination of estuarine body would occur mostly during
the construction phase due to resuspension of sediments or
dust from construction site, both of which are temporary.
2.2 NMIA Project Design – Activity,
Impact & Mitigation
2.2.1 Activity


Hill Cutting (Quarrying / Blasting)

2.2.2 Impacts


Generation of heavy quantity of dust which raises the SPM
levels in the vicinity.



Noise levels also will increase occasionally. Houses around the
site (if any) may feel the intense acoustic waves.



Affects aquatic vegetation by increasing the turbidity of water.



Loss and reduction in the number of organisms.
2.2.3 Mitigation


The excavated material/construction debris would be used for land
development of marshy land in the project site area. This would result in
change of land use pattern apart from the dust generated and increased
noise & air pollution (SPM levels) in the vicinity.



Hi-tech equipment will be used for controlled blasting excavation and
hauling of materials which will generate minimal noise as well as dust. This
aspect will be covered as a tender condition.



Best engineering practices and modern technologies producing minimum
noise would be maintained during the blasting.



Blasting should be well planned with large numbers being fired infrequently
than a few blasts daily.



No blasting will be carried out at night.



Before controlled blasting, the surrounding villages will be alerted and the
villagers and domestic animals will be offered safe place away from the
project site.
2.3 NMIA Project Design – Activity,
Impact & Mitigation
2.3.1 Activity


Shifting of Extra
undergrounding

High

Tension

(EHT)

Line

by

2.3.2 Impacts


There are 4 Extra High Tension Lines existing in the Airport
Operational Area and in the surroundings which are
required to be rerouted either over-head or underground
by cables.
2.4 NMIA Project Design – Activity,
Impact & Mitigation
2.4.1


Activity

Reclamation of marshy lands (For a safe grade level varying from RL
7.0 to RL 8.5. by cutting of hills and reclaiming the land.)

2.4.2

Impacts



Creek recoursing would take place on existing land cover.



The studies indicate marginal rise in the water levels in the Panvel
creek reach along the proposed airport boundary.



Along the Ulwe creek however, the rise in the water levels will be
slightly over 1.5 m due to recourse channel along the longer route
with flatter slope.
3.1 NMIA Construction Phase – Activity,
Impact, & Mitigation
3.1.1 Activity


Employment, Migration and Settlement

3.1.2 Impacts


Due to migratory workers lot of stress in the area surrounding the
project in terms of water requirement, power, increased
ecological footprint, increased requirement for health and
educational facilities and changes in the land use pattern and
local culture.
3.2 NMIA Construction Phase – Activity,
Impact & Mitigation
3.2.1 Activity


Siting of construction camp for construction

3.2.2 Impacts


Lack of Sewerage and Sewage Treatment Facilities could lead to
water pollution



Misuse of local ecological resources like forests for firewood which would
result in destruction of vegetation in the surrounding area,



Improper handling of solid waste generated could lead to unhygienic
condition.



Use of biomass fuel for cooking would lead to indoor air pollution in the
camp and fire hazard.
3.2.3 Mitigation


Safe and secure construction camp area will be provided for the
migrant laborers during the construction period. At the camp
site, the contractors will be directed to make adequate
arrangements for water supply, sanitation and cooking fuels to
the laborers.



The construction site will be provided with sufficient and suitable
toilet facilities for workers to allow proper standards of hygiene.



Adequate firefighting arrangement would be maintained by the
contractor during the construction phase



During the operation phase, high level of fire – fighting
equipments with adequate water and foam facility would be
maintained as per the stipulated ICAO standards.
3.3 NMIA Construction Phase – Activity,
Impact & Mitigation
3.3.1 Activity
 Construction Activity
3.3.2 Impacts
 loading/unloading of different materials and its transportation
particularly through the unpaved sections may result in spillage of
material/oil and hence contaminates the soil and groundwater and also
raise the ambient SPM levels.
 Noise Pollution
3.3.3 Mitigation
 A thick green belt should be planned all around the project site to
mitigate noise and vibrations to the nearby settlements. The
identification of species/plants should be made based on the botanical
studies.
3.4 NMIA Construction Phase – Activity,
Impact & Mitigation
3.4.1 Activity
 Safety of Workers
3.4.2 Impacts
 Wide level of hazards arising due to the blasting activity,
reclaiming activity, construction of various components of
the project. Use of heavy equipment, high levels of dust
and noise aggravate the issues of health and safety of the
workers.
4.1 NMIA Operation Phase – Activity,
Impact & Mitigation
4.1.1 Activity


Operation of Airport

4.1.2 Impact


Emissions from Aircrafts



Noise from Aircrafts

4.1.3 Mitigation


Natural and artificial noise barriers may be considered for
critical locations.



Emissions from aircrafts are under the limit.
4.2 NMIA Operation Phase – Activity,
Impact & Mitigation
4.2.1 Activity


Surface Traffic

4.2.2 Impact


The emission from surface traffic.(Within the prescribed limit)



Surface traffic noise exceeds the prescribed limit

4.2.3 Mitigation


Aerobridges would be used for passenger transportation.



However surface transport for other ground services would still
happen with use of fuel efficient vehicles.
4.3 NMIA Operation Phase – Activity,
Impact & Mitigation
4.3.1 Activity
 Employment, Migration & Settlement
4.3.2 Impact
 Migration into the surrounding area would be permanent nature. This
would lead to a lot of stress in the area surrounding the project in
terms of water requirement, power, increased ecological footprint,
increased requirement for health and educational facilities and
changes in the land use pattern and local culture.
4.3.3 Mitigation
 As CIDCO has been carrying out developmental activities in the
surrounding area, it is quite competent to absorb the load arising out
of such an activity.
POSITIVE IMPACTS


Project will facilitate the fast movement of men and materials,
thereby fostering trade and commerce.



Supports employment generation. Around 11 lakh direct jobs and
4 lakhs indirect jobs due to this project.



Pressure on other airport at Shantacruz will be eased.



Offers increased accessibility, which in turn fuels the tourism
sector which causes more money flows into the local economy.



Raising the standard of living of people in the region, having a
positive impact on National economy.



It will handle 60 million passenger per year.
THANK YOU

Más contenido relacionado

La actualidad más candente

Urban Villages of Delhi: Case study Kotla Mubarakpur
Urban Villages of Delhi: Case study Kotla MubarakpurUrban Villages of Delhi: Case study Kotla Mubarakpur
Urban Villages of Delhi: Case study Kotla MubarakpurJoel Michael
 
Elements of city plan 3 unit
Elements of city plan 3 unitElements of city plan 3 unit
Elements of city plan 3 unitSumanta Das
 
EIA for development projects
EIA for development projectsEIA for development projects
EIA for development projectsAnchal Garg
 
EIA an introduction - Case study wrt Coastal development & Aquaculture
EIA an introduction - Case study wrt Coastal development & AquacultureEIA an introduction - Case study wrt Coastal development & Aquaculture
EIA an introduction - Case study wrt Coastal development & AquacultureKANTHARAJAN GANESAN
 
EIA report presentation
EIA report presentationEIA report presentation
EIA report presentationsujit roy
 
Multiple nuclei model (Town Planning)
Multiple nuclei  model (Town Planning)Multiple nuclei  model (Town Planning)
Multiple nuclei model (Town Planning)S.m. Atik
 
Quarry Restoration case studies
Quarry Restoration case studiesQuarry Restoration case studies
Quarry Restoration case studiesWill Williams
 
Jaipur master plan review
Jaipur master plan reviewJaipur master plan review
Jaipur master plan reviewvikashsaini78
 
Review of Development Plans/ Master Plans of selected cities of India.
Review of Development Plans/ Master Plans of selected cities of India.Review of Development Plans/ Master Plans of selected cities of India.
Review of Development Plans/ Master Plans of selected cities of India.KARTHICK KRISHNA
 
Bhubaneswar an ideal capital city
Bhubaneswar   an ideal capital cityBhubaneswar   an ideal capital city
Bhubaneswar an ideal capital cityRajesh Kolli
 
Environmental impact assessment case study
Environmental impact assessment case studyEnvironmental impact assessment case study
Environmental impact assessment case studyKundan Sanap
 
Bhopal city planning
Bhopal city planningBhopal city planning
Bhopal city planningsonika patel
 
Architecture and town planning _Unit 3_SPPU_Town planning and various levels ...
Architecture and town planning _Unit 3_SPPU_Town planning and various levels ...Architecture and town planning _Unit 3_SPPU_Town planning and various levels ...
Architecture and town planning _Unit 3_SPPU_Town planning and various levels ...Shrikant Kate
 
KERALA TOWN AND COUNTRY PLANNING ACT, 2016
KERALA TOWN AND COUNTRY PLANNING ACT, 2016KERALA TOWN AND COUNTRY PLANNING ACT, 2016
KERALA TOWN AND COUNTRY PLANNING ACT, 2016Tulika Kumar
 
EIA PRESENTATION ON NARMDA RIVER
EIA PRESENTATION ON NARMDA RIVEREIA PRESENTATION ON NARMDA RIVER
EIA PRESENTATION ON NARMDA RIVERvikas rahangdale
 
Copy of sustainable urban development ppt presentation
Copy of sustainable urban development   ppt presentationCopy of sustainable urban development   ppt presentation
Copy of sustainable urban development ppt presentationAr. Mukunda K.S
 

La actualidad más candente (20)

Nirvana hills project-Case Study
Nirvana hills project-Case StudyNirvana hills project-Case Study
Nirvana hills project-Case Study
 
Urban Villages of Delhi: Case study Kotla Mubarakpur
Urban Villages of Delhi: Case study Kotla MubarakpurUrban Villages of Delhi: Case study Kotla Mubarakpur
Urban Villages of Delhi: Case study Kotla Mubarakpur
 
Elements of city plan 3 unit
Elements of city plan 3 unitElements of city plan 3 unit
Elements of city plan 3 unit
 
EIA for development projects
EIA for development projectsEIA for development projects
EIA for development projects
 
EIA OF DAM: DURGAWATI RESERVIOR
EIA OF DAM: DURGAWATI RESERVIOREIA OF DAM: DURGAWATI RESERVIOR
EIA OF DAM: DURGAWATI RESERVIOR
 
EIA an introduction - Case study wrt Coastal development & Aquaculture
EIA an introduction - Case study wrt Coastal development & AquacultureEIA an introduction - Case study wrt Coastal development & Aquaculture
EIA an introduction - Case study wrt Coastal development & Aquaculture
 
EIA report presentation
EIA report presentationEIA report presentation
EIA report presentation
 
Multiple nuclei model (Town Planning)
Multiple nuclei  model (Town Planning)Multiple nuclei  model (Town Planning)
Multiple nuclei model (Town Planning)
 
Quarry Restoration case studies
Quarry Restoration case studiesQuarry Restoration case studies
Quarry Restoration case studies
 
Jaipur master plan review
Jaipur master plan reviewJaipur master plan review
Jaipur master plan review
 
Review of Development Plans/ Master Plans of selected cities of India.
Review of Development Plans/ Master Plans of selected cities of India.Review of Development Plans/ Master Plans of selected cities of India.
Review of Development Plans/ Master Plans of selected cities of India.
 
Bhubaneswar an ideal capital city
Bhubaneswar   an ideal capital cityBhubaneswar   an ideal capital city
Bhubaneswar an ideal capital city
 
Environmental impact assessment case study
Environmental impact assessment case studyEnvironmental impact assessment case study
Environmental impact assessment case study
 
Garden city
Garden city Garden city
Garden city
 
Bhopal city planning
Bhopal city planningBhopal city planning
Bhopal city planning
 
Ecocity
EcocityEcocity
Ecocity
 
Architecture and town planning _Unit 3_SPPU_Town planning and various levels ...
Architecture and town planning _Unit 3_SPPU_Town planning and various levels ...Architecture and town planning _Unit 3_SPPU_Town planning and various levels ...
Architecture and town planning _Unit 3_SPPU_Town planning and various levels ...
 
KERALA TOWN AND COUNTRY PLANNING ACT, 2016
KERALA TOWN AND COUNTRY PLANNING ACT, 2016KERALA TOWN AND COUNTRY PLANNING ACT, 2016
KERALA TOWN AND COUNTRY PLANNING ACT, 2016
 
EIA PRESENTATION ON NARMDA RIVER
EIA PRESENTATION ON NARMDA RIVEREIA PRESENTATION ON NARMDA RIVER
EIA PRESENTATION ON NARMDA RIVER
 
Copy of sustainable urban development ppt presentation
Copy of sustainable urban development   ppt presentationCopy of sustainable urban development   ppt presentation
Copy of sustainable urban development ppt presentation
 

Destacado

Eia Of Navi Mumbai International Airport (Nmia
Eia Of Navi Mumbai International Airport (NmiaEia Of Navi Mumbai International Airport (Nmia
Eia Of Navi Mumbai International Airport (NmiaKetan Wadodkar
 
legal aspects of navi mumbai international airport
legal aspects  of navi mumbai international airportlegal aspects  of navi mumbai international airport
legal aspects of navi mumbai international airporttwinkle Chhadwa
 
Environment Impact Assessment
Environment Impact Assessment Environment Impact Assessment
Environment Impact Assessment Istiak Asif
 
Chhatrapati Shivaji International Airport, Mumbai - Terminal 2
Chhatrapati Shivaji International Airport, Mumbai - Terminal 2Chhatrapati Shivaji International Airport, Mumbai - Terminal 2
Chhatrapati Shivaji International Airport, Mumbai - Terminal 2Mitesh Gupta
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentNigel Gardner
 
Airport Expansion - Challenges
Airport Expansion - ChallengesAirport Expansion - Challenges
Airport Expansion - ChallengesHusain Baqer
 
Singapore free trade agreements
Singapore free trade agreementsSingapore free trade agreements
Singapore free trade agreementsdebtcollecction
 
Signage design for Mumbai International & Domestic Airport
Signage design for Mumbai International & Domestic AirportSignage design for Mumbai International & Domestic Airport
Signage design for Mumbai International & Domestic Airportparul_gupta
 
BasicAirportOperation - TerminalFacilities&Care
BasicAirportOperation - TerminalFacilities&CareBasicAirportOperation - TerminalFacilities&Care
BasicAirportOperation - TerminalFacilities&CareAiDY
 
Mitigation of environmental issues of Aviation
Mitigation of environmental issues of AviationMitigation of environmental issues of Aviation
Mitigation of environmental issues of AviationAkanksha Singh
 
ICWES15 - Rules for the Povision of Earthquake Resistance in Small Buildings ...
ICWES15 - Rules for the Povision of Earthquake Resistance in Small Buildings ...ICWES15 - Rules for the Povision of Earthquake Resistance in Small Buildings ...
ICWES15 - Rules for the Povision of Earthquake Resistance in Small Buildings ...Engineers Australia
 
Djibouti lake assal salt_project_eia_report_nov 2008
Djibouti lake assal salt_project_eia_report_nov 2008Djibouti lake assal salt_project_eia_report_nov 2008
Djibouti lake assal salt_project_eia_report_nov 2008Parti Djibouti
 
Topic 6 air pollution, sources and impacts
Topic 6 air pollution, sources and impactsTopic 6 air pollution, sources and impacts
Topic 6 air pollution, sources and impactsDebbie-Ann Hall
 
Mumbai airport branding - Airport Media (CSI Airport)
Mumbai airport branding  - Airport Media (CSI Airport)Mumbai airport branding  - Airport Media (CSI Airport)
Mumbai airport branding - Airport Media (CSI Airport)Organized Outdoor
 
Law presentation
Law presentationLaw presentation
Law presentationRachit Shiv
 

Destacado (20)

Eia Of Navi Mumbai International Airport (Nmia
Eia Of Navi Mumbai International Airport (NmiaEia Of Navi Mumbai International Airport (Nmia
Eia Of Navi Mumbai International Airport (Nmia
 
legal aspects of navi mumbai international airport
legal aspects  of navi mumbai international airportlegal aspects  of navi mumbai international airport
legal aspects of navi mumbai international airport
 
Environment Impact Assessment
Environment Impact Assessment Environment Impact Assessment
Environment Impact Assessment
 
Chhatrapati Shivaji International Airport, Mumbai - Terminal 2
Chhatrapati Shivaji International Airport, Mumbai - Terminal 2Chhatrapati Shivaji International Airport, Mumbai - Terminal 2
Chhatrapati Shivaji International Airport, Mumbai - Terminal 2
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)
 
MARKETING MANAGEMENT - JEANS
MARKETING MANAGEMENT - JEANSMARKETING MANAGEMENT - JEANS
MARKETING MANAGEMENT - JEANS
 
Airport Expansion - Challenges
Airport Expansion - ChallengesAirport Expansion - Challenges
Airport Expansion - Challenges
 
Singapore free trade agreements
Singapore free trade agreementsSingapore free trade agreements
Singapore free trade agreements
 
EIA repot for Airport
EIA repot for AirportEIA repot for Airport
EIA repot for Airport
 
Signage design for Mumbai International & Domestic Airport
Signage design for Mumbai International & Domestic AirportSignage design for Mumbai International & Domestic Airport
Signage design for Mumbai International & Domestic Airport
 
BasicAirportOperation - TerminalFacilities&Care
BasicAirportOperation - TerminalFacilities&CareBasicAirportOperation - TerminalFacilities&Care
BasicAirportOperation - TerminalFacilities&Care
 
Mitigation of environmental issues of Aviation
Mitigation of environmental issues of AviationMitigation of environmental issues of Aviation
Mitigation of environmental issues of Aviation
 
ICWES15 - Rules for the Povision of Earthquake Resistance in Small Buildings ...
ICWES15 - Rules for the Povision of Earthquake Resistance in Small Buildings ...ICWES15 - Rules for the Povision of Earthquake Resistance in Small Buildings ...
ICWES15 - Rules for the Povision of Earthquake Resistance in Small Buildings ...
 
Djibouti lake assal salt_project_eia_report_nov 2008
Djibouti lake assal salt_project_eia_report_nov 2008Djibouti lake assal salt_project_eia_report_nov 2008
Djibouti lake assal salt_project_eia_report_nov 2008
 
Ryan khargar, navi mumbai
Ryan khargar, navi mumbaiRyan khargar, navi mumbai
Ryan khargar, navi mumbai
 
EIA-Final-Report (1)
EIA-Final-Report (1)EIA-Final-Report (1)
EIA-Final-Report (1)
 
Topic 6 air pollution, sources and impacts
Topic 6 air pollution, sources and impactsTopic 6 air pollution, sources and impacts
Topic 6 air pollution, sources and impacts
 
Mumbai airport branding - Airport Media (CSI Airport)
Mumbai airport branding  - Airport Media (CSI Airport)Mumbai airport branding  - Airport Media (CSI Airport)
Mumbai airport branding - Airport Media (CSI Airport)
 
Law presentation
Law presentationLaw presentation
Law presentation
 

Similar a Environment impact assessment of navi mumbai airport

Green infrastructure foundation for climate resilience Mekong
Green infrastructure foundation for climate resilience MekongGreen infrastructure foundation for climate resilience Mekong
Green infrastructure foundation for climate resilience MekongWater, Land and Ecosystems (WLE)
 
F1 b forest road
F1 b forest roadF1 b forest road
F1 b forest roadpcntc
 
Fohh, planning for the future, tpb 19.5.14
Fohh, planning for the future, tpb 19.5.14Fohh, planning for the future, tpb 19.5.14
Fohh, planning for the future, tpb 19.5.14Kelly Chan
 
IRJET- Environmental Impact Assessment on Quarry
IRJET-  	  Environmental Impact Assessment on QuarryIRJET-  	  Environmental Impact Assessment on Quarry
IRJET- Environmental Impact Assessment on QuarryIRJET Journal
 
Snowy Hydro Engineering Management Final
Snowy Hydro Engineering Management FinalSnowy Hydro Engineering Management Final
Snowy Hydro Engineering Management FinalBrady Lockwood
 
Unit V - EIA case studies pertaining to Infrastructure Projects.pptx
Unit V - EIA case studies pertaining to Infrastructure Projects.pptxUnit V - EIA case studies pertaining to Infrastructure Projects.pptx
Unit V - EIA case studies pertaining to Infrastructure Projects.pptxssuser65cc68
 
Jamuna Bridge & A Successful EIA-Malthus.pptx
Jamuna Bridge & A Successful EIA-Malthus.pptxJamuna Bridge & A Successful EIA-Malthus.pptx
Jamuna Bridge & A Successful EIA-Malthus.pptxMd. Mahmudor Rahman
 
Kuttanadu Concreate Bandu
Kuttanadu Concreate  BanduKuttanadu Concreate  Bandu
Kuttanadu Concreate BanduKSSP
 
Factor considered for Environment Impact assessment (EIA) in legal procedure ...
Factor considered for Environment Impact assessment (EIA) in legal procedure ...Factor considered for Environment Impact assessment (EIA) in legal procedure ...
Factor considered for Environment Impact assessment (EIA) in legal procedure ...Himanshu Goyal
 
LESCO- EIA report
LESCO- EIA reportLESCO- EIA report
LESCO- EIA reportAsh Hassan
 

Similar a Environment impact assessment of navi mumbai airport (20)

Lgu services amp
Lgu services ampLgu services amp
Lgu services amp
 
Pnacp687
Pnacp687Pnacp687
Pnacp687
 
Green infrastructure foundation for climate resilience Mekong
Green infrastructure foundation for climate resilience MekongGreen infrastructure foundation for climate resilience Mekong
Green infrastructure foundation for climate resilience Mekong
 
F1 b forest road
F1 b forest roadF1 b forest road
F1 b forest road
 
Fohh, planning for the future, tpb 19.5.14
Fohh, planning for the future, tpb 19.5.14Fohh, planning for the future, tpb 19.5.14
Fohh, planning for the future, tpb 19.5.14
 
Environmental Impact Assessment in Water Resources Projects
Environmental Impact Assessment in Water Resources ProjectsEnvironmental Impact Assessment in Water Resources Projects
Environmental Impact Assessment in Water Resources Projects
 
Green infrastructure as a foundation for climate resilience and sustainabilit...
Green infrastructure as a foundation for climate resilience and sustainabilit...Green infrastructure as a foundation for climate resilience and sustainabilit...
Green infrastructure as a foundation for climate resilience and sustainabilit...
 
IRJET- Environmental Impact Assessment on Quarry
IRJET-  	  Environmental Impact Assessment on QuarryIRJET-  	  Environmental Impact Assessment on Quarry
IRJET- Environmental Impact Assessment on Quarry
 
Snowy Hydro Engineering Management Final
Snowy Hydro Engineering Management FinalSnowy Hydro Engineering Management Final
Snowy Hydro Engineering Management Final
 
EIA Project
EIA ProjectEIA Project
EIA Project
 
Unit V - EIA case studies pertaining to Infrastructure Projects.pptx
Unit V - EIA case studies pertaining to Infrastructure Projects.pptxUnit V - EIA case studies pertaining to Infrastructure Projects.pptx
Unit V - EIA case studies pertaining to Infrastructure Projects.pptx
 
Jamuna Bridge & A Successful EIA-Malthus.pptx
Jamuna Bridge & A Successful EIA-Malthus.pptxJamuna Bridge & A Successful EIA-Malthus.pptx
Jamuna Bridge & A Successful EIA-Malthus.pptx
 
Kuttanadu Concreate Bandu
Kuttanadu Concreate  BanduKuttanadu Concreate  Bandu
Kuttanadu Concreate Bandu
 
PIC 2 Display Boards
PIC 2 Display BoardsPIC 2 Display Boards
PIC 2 Display Boards
 
Factor considered for Environment Impact assessment (EIA) in legal procedure ...
Factor considered for Environment Impact assessment (EIA) in legal procedure ...Factor considered for Environment Impact assessment (EIA) in legal procedure ...
Factor considered for Environment Impact assessment (EIA) in legal procedure ...
 
LESCO- EIA report
LESCO- EIA reportLESCO- EIA report
LESCO- EIA report
 
Trans-boundary Issues
Trans-boundary IssuesTrans-boundary Issues
Trans-boundary Issues
 
Aoc sediment update_part2
Aoc sediment update_part2Aoc sediment update_part2
Aoc sediment update_part2
 
Presentation 3: Impact Assessment Findings
Presentation 3: Impact Assessment FindingsPresentation 3: Impact Assessment Findings
Presentation 3: Impact Assessment Findings
 
To Mine or Not to Mine
To Mine or Not to MineTo Mine or Not to Mine
To Mine or Not to Mine
 

Último

Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsTop 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsRoshan Dwivedi
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024The Digital Insurer
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 

Último (20)

Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsTop 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 

Environment impact assessment of navi mumbai airport

  • 1. ENVIRONMENT IMPACT ASSESMENT OF NAVI MUMBAI AIRPORT Vivekanand P. Moril 2012JEN2119
  • 2. PROJECT  Total area earmarked for airport development is 2054 Ha. consisting of 1615 Ha. as airport zone and remaining for off-site infrastructure, such as; diversion & training of rivers, approach road, railways, interchanges and utility lines, etc.  The entire area of the airport zone falls in Raigad District in Panvel & Uran Tahasil covering its 16 villages.
  • 3. Selection of Alternative Sites The analysis of alternative sites is done based on following two methods.  1) SWOT (Strength, Weakness, Opportunity & Threat) Analysis  2) Site Sensitivity Analysis   The overall score is worked out on the basis of site sensitivity index for different parameters and integration of total impact is worked out & categorized as below-
  • 4. Categorisation Criteria          Overall scale Level of Environmental Impact 750-1000 Very high 600-750 High 450-600 Moderate 300-450 Low Less than 300 Very low After comparison the scores were added. The Rewas-Mandwa score is 773.95.(Environmental Impact is Very High). Navi Mumbai score is 498.69. (Environmental Impact is Moderate).
  • 5.
  • 6.
  • 7. Study Area The study area around airport falling within the radius of 10Kms. The study area is further extended upto 20 km. as fringe area.  The core area covers the area within the radius of 10km, in which all the scoped environmental parameters is studied to understand the magnitude of impact.  In the remaining area i.e. fringe area places of historical importance, aesthetic, cultural including environmentally sensitive area is studied. 
  • 8. Identification and Evaluation and Development of Impact & Mitigation Options  Flow Diagram
  • 9. Impact Identification  To help in / ease the impact evaluation process, the various activities of the NMIA which can have an impact on environment have been classified into four stages namely:  I. NMIA location  II. NMIA project design  III. NMIA construction phase  IV. NMIA operation phase
  • 10. 1.1 NMIA Location : Activity, Impact & Mitigation 1.1.1 Activity  Removal of Mangroves & Biodiversity 1.1.2 Impacts  With the project intervention, these mangroves (though in degraded form) will be totally lost forever. A total of 161.5 Ha of mangroves will be lost due to the project. 1.1.3 Mitigation CIDCO has planned to take up approx. 350 Ha. of plantation of mangroves against 161.5 Ha. loss.
  • 11. 1.2 NMIA Location : Activities, Impact & Mitigation 1.2.1 Activity  Tree Clearance 1.2.2 Impact  There is no forest in the project site area, though there are naturally growing trees/plants/vegetation in the area. Most of the vegetation of trees in and around the villages are planted fruiting trees like mango, jamun, jackfruit, guava, custard apple etc. and the wood yielding trees like teak, etc. The ornamental trees, bamboos and palms also have been planted and/or maintained by the villagers.  This project will result in loss of all vegetation in the project site.
  • 12. 1.2 NMIA Location : Activities, Impact & Mitigation 1.2.3 Mitigation  With respect to the trees from the displaced villages, CIDCO will take up the task of replanting the trees in their areas where they are carrying out developmental activities or along the highways.
  • 13. 1.3 NMIA Location : Activities, Impact & Mitigation 1.3.1 Activity  Roads and Infrastructure 1.3.2 Impacts  The over concretization resulting in increase in temperature during the day time and summer time along the roads.  Diversion of agricultural land leading to issues of land use change and food security.
  • 14. 1.3 NMIA Location : Activities, Impact & Mitigation 1.3.3 Mitigation  Compensatory vegetation and plantation programme will be undertaken within the airport area in the mandatory space.  The entire plantation undertaken will be non-fruit bearing so as to reduce any bird mishaps during the operation phase.
  • 15. 1.4 NMIA Location : Activities, Impact & Mitigation 1.4.1 Activity  Railways Infrastructure 1.4.2 Impacts  The loss of mangroves & vegetation.  Diversion of agricultural land leading to issues of land use change and food security.
  • 16. 1.5 NMIA Location : Activity, Impact & Mitigation 1.5.1 Activity  Rehabilitation of the displaced villagers 1.5.2 Impacts  Ten settlements belonging to seven villages are required to be resettled away from the project site. Approx 15000 people will be affected due to the project.  Development of basic infrastructure such as water supply, electricity, sewerage, roads, social infrastructure etc. shall be required. 1.5.3 Mitigation  Land will be provided to displaced villagers.  CIDCO has assumed a proactive role towards the mitigation of the social impacts by the rehabilitation.
  • 17. 1.6 NMIA Location : Activity, Impact & Mitigation 1.6.1 Activity  Archeological / Cultural / Historic Sites 1.6.2 Impacts  The fringe area study falling between 10 to 20 km. radius, revealed that there are 3 places of historic importance, aesthetic, cultural including sensitive area namely the Elephanta Caves, Karnala Bird Sanctuary and Matheran Eco-sensitive Zone.
  • 18. 1.6 NMIA Location : Activity, Impact & Mitigation 1.6.3 Mitigation  The Elephanta Caves is about 13.5 km from site. The position of aircraft during takeoff/landing/missed approach, would be more than 700 m.  The Karnala Bird sanctuary is about 12.5 km from site. The position of aircraft during takeoff/landing/missed approach, would be more than 750 m.  The Karnala Bird sanctuary is about 11 km from site. The position of aircraft during takeoff/landing/missed approach, would be more than 500 m.  During operation phase, proper flight directions can be provided so as to avoid flying over any of these sites.
  • 19. 1.7 NMIA Location : Activity, Impact & Mitigation 1.7.1 Activity  Residential Facilities 1.7.2 Impacts  300 Ha. Area is required for the housing needs of workers. This housing needs to be supported by all the requisite social and cultural facilities.  Additional load on water and energy would have to be met.
  • 20. 2.1 NMIA Project Design – Activity, Impact & Mitigation 2.1.1 Activity  Training of Gadhi River, Diversion of Ulve River 2.1.2 Impacts  The impacts of channelization on the aquatic community mainly arise due to channel excavation, dredging, clearing and removal of vegetation.  Siltation affects aquatic vegetation by increasing the turbidity of water.  Loss and reduction in the number of organisms.
  • 21. 2.1 NMIA Project Design – Activity, Impact & Mitigation 2.1.3 Mitigation    The channelization activities are designed to keep flow characteristics as close to natural flow. In order to minimize the above impacts of dredging/channelization, proper route alignment will be selected and the dredging and excavation will be done in stages maintaining the water flow. This operation will result in minimum impact on siltation/turbidity on aquatic community. Contamination of estuarine body would occur mostly during the construction phase due to resuspension of sediments or dust from construction site, both of which are temporary.
  • 22. 2.2 NMIA Project Design – Activity, Impact & Mitigation 2.2.1 Activity  Hill Cutting (Quarrying / Blasting) 2.2.2 Impacts  Generation of heavy quantity of dust which raises the SPM levels in the vicinity.  Noise levels also will increase occasionally. Houses around the site (if any) may feel the intense acoustic waves.  Affects aquatic vegetation by increasing the turbidity of water.  Loss and reduction in the number of organisms.
  • 23. 2.2.3 Mitigation  The excavated material/construction debris would be used for land development of marshy land in the project site area. This would result in change of land use pattern apart from the dust generated and increased noise & air pollution (SPM levels) in the vicinity.  Hi-tech equipment will be used for controlled blasting excavation and hauling of materials which will generate minimal noise as well as dust. This aspect will be covered as a tender condition.  Best engineering practices and modern technologies producing minimum noise would be maintained during the blasting.  Blasting should be well planned with large numbers being fired infrequently than a few blasts daily.  No blasting will be carried out at night.  Before controlled blasting, the surrounding villages will be alerted and the villagers and domestic animals will be offered safe place away from the project site.
  • 24. 2.3 NMIA Project Design – Activity, Impact & Mitigation 2.3.1 Activity  Shifting of Extra undergrounding High Tension (EHT) Line by 2.3.2 Impacts  There are 4 Extra High Tension Lines existing in the Airport Operational Area and in the surroundings which are required to be rerouted either over-head or underground by cables.
  • 25. 2.4 NMIA Project Design – Activity, Impact & Mitigation 2.4.1  Activity Reclamation of marshy lands (For a safe grade level varying from RL 7.0 to RL 8.5. by cutting of hills and reclaiming the land.) 2.4.2 Impacts  Creek recoursing would take place on existing land cover.  The studies indicate marginal rise in the water levels in the Panvel creek reach along the proposed airport boundary.  Along the Ulwe creek however, the rise in the water levels will be slightly over 1.5 m due to recourse channel along the longer route with flatter slope.
  • 26. 3.1 NMIA Construction Phase – Activity, Impact, & Mitigation 3.1.1 Activity  Employment, Migration and Settlement 3.1.2 Impacts  Due to migratory workers lot of stress in the area surrounding the project in terms of water requirement, power, increased ecological footprint, increased requirement for health and educational facilities and changes in the land use pattern and local culture.
  • 27. 3.2 NMIA Construction Phase – Activity, Impact & Mitigation 3.2.1 Activity  Siting of construction camp for construction 3.2.2 Impacts  Lack of Sewerage and Sewage Treatment Facilities could lead to water pollution  Misuse of local ecological resources like forests for firewood which would result in destruction of vegetation in the surrounding area,  Improper handling of solid waste generated could lead to unhygienic condition.  Use of biomass fuel for cooking would lead to indoor air pollution in the camp and fire hazard.
  • 28. 3.2.3 Mitigation  Safe and secure construction camp area will be provided for the migrant laborers during the construction period. At the camp site, the contractors will be directed to make adequate arrangements for water supply, sanitation and cooking fuels to the laborers.  The construction site will be provided with sufficient and suitable toilet facilities for workers to allow proper standards of hygiene.  Adequate firefighting arrangement would be maintained by the contractor during the construction phase  During the operation phase, high level of fire – fighting equipments with adequate water and foam facility would be maintained as per the stipulated ICAO standards.
  • 29. 3.3 NMIA Construction Phase – Activity, Impact & Mitigation 3.3.1 Activity  Construction Activity 3.3.2 Impacts  loading/unloading of different materials and its transportation particularly through the unpaved sections may result in spillage of material/oil and hence contaminates the soil and groundwater and also raise the ambient SPM levels.  Noise Pollution 3.3.3 Mitigation  A thick green belt should be planned all around the project site to mitigate noise and vibrations to the nearby settlements. The identification of species/plants should be made based on the botanical studies.
  • 30. 3.4 NMIA Construction Phase – Activity, Impact & Mitigation 3.4.1 Activity  Safety of Workers 3.4.2 Impacts  Wide level of hazards arising due to the blasting activity, reclaiming activity, construction of various components of the project. Use of heavy equipment, high levels of dust and noise aggravate the issues of health and safety of the workers.
  • 31. 4.1 NMIA Operation Phase – Activity, Impact & Mitigation 4.1.1 Activity  Operation of Airport 4.1.2 Impact  Emissions from Aircrafts  Noise from Aircrafts 4.1.3 Mitigation  Natural and artificial noise barriers may be considered for critical locations.  Emissions from aircrafts are under the limit.
  • 32. 4.2 NMIA Operation Phase – Activity, Impact & Mitigation 4.2.1 Activity  Surface Traffic 4.2.2 Impact  The emission from surface traffic.(Within the prescribed limit)  Surface traffic noise exceeds the prescribed limit 4.2.3 Mitigation  Aerobridges would be used for passenger transportation.  However surface transport for other ground services would still happen with use of fuel efficient vehicles.
  • 33. 4.3 NMIA Operation Phase – Activity, Impact & Mitigation 4.3.1 Activity  Employment, Migration & Settlement 4.3.2 Impact  Migration into the surrounding area would be permanent nature. This would lead to a lot of stress in the area surrounding the project in terms of water requirement, power, increased ecological footprint, increased requirement for health and educational facilities and changes in the land use pattern and local culture. 4.3.3 Mitigation  As CIDCO has been carrying out developmental activities in the surrounding area, it is quite competent to absorb the load arising out of such an activity.
  • 34. POSITIVE IMPACTS  Project will facilitate the fast movement of men and materials, thereby fostering trade and commerce.  Supports employment generation. Around 11 lakh direct jobs and 4 lakhs indirect jobs due to this project.  Pressure on other airport at Shantacruz will be eased.  Offers increased accessibility, which in turn fuels the tourism sector which causes more money flows into the local economy.  Raising the standard of living of people in the region, having a positive impact on National economy.  It will handle 60 million passenger per year.