Activity ID Activity Name Original
Duration
Remaining
Duration
Schedule %
Complete
Start Finish Resources
Bridge ProjectBridge Project 358d 341d 0% 14-Dec-16 08:00 AM A 22-Mar-18 04:00 PM
Identify the problemIdentify the problem 15d 0d 0% 14-Dec-16 08:00 AM A 02-Jan-17 03:00 PM A
A1000 start of project 0d 0d 0% 14-Dec-16 08:00 AM A 14-Dec-16 08:00 AM A
A1010 analyse the purpose of bridge 10d 0d 0% 14-Dec-16 08:00 AM A 27-Dec-16 09:00 AM A Desing engineer, Anaylzer, Site Engineer, Project E
A1030 analyse the load (capacity) of the bridge 13d 0d 0% 14-Dec-16 08:00 AM A 30-Dec-16 12:00 PM A Design Engineer, Anaylzer, Site Engineer, Project E
A1020 discussion among engineers, contractors 5d 0d 0% 27-Dec-16 09:00 AM A 02-Jan-17 03:00 PM A Anaylzer, Site Engineer, Project Engineer
Determine constraintsDetermine constraints 25d 21d 0% 30-Dec-16 12:00 PM A 01-Feb-17 10:00 AM
A1040 analyse the material used for constructin 4d 0d 0% 30-Dec-16 12:00 PM A 04-Jan-17 05:00 PM A Design Engineer, Welder, Anaylzer, Site Engineer,
A1050 prepare the rough sketch 7d 7d 0% 04-Jan-17 05:00 PM 13-Jan-17 03:00 PM Anaylzer, Site Engineer
A1060 estimate the cost 7d 0d 0% 13-Jan-17 03:00 PM A 20-Jan-17 05:00 PM A Desing engineer, Anaylzer, Site engineer, Project E
A1070 prepare the schedule 14d 14d 0% 13-Jan-17 03:00 PM 01-Feb-17 10:00 AM Desing engineer, Anaylzer, Site Engineer, Project E
Analyse of designAnalyse of design 33d 29d 0% 01-Feb-17 10:00 AM A 15-Mar-17 05:00 PM
A1080 analyse the span 7d 0d 0% 01-Feb-17 10:00 AM A 11-Feb-17 06:00 PM A Desing engineer, Anaylzer, Site Engineer, Project E
A1100 analyse the material 5d 0d 5h 0% 06-Feb-17 03:00 PM A 07-Feb-17 10:00 AM Desing engineer, Welder, Anaylzer, Site Engineer,
A1090 according to the span decide the type pof bridge7d 0d 7h 0% 10-Feb-17 08:00 AM A 11-Feb-17 02:00 PM Desing engineer, Anaylzer, Site Engineer
A1120 prepare the drawings 5d 0d 8h 0% 10-Feb-17 08:00 AM A 10-Feb-17 04:30 PM Desing engineer, Anaylzer, Project Engineer, labou
A1110 determine the strenght, market appeal of hte material7d 0d 7h 0% 18-Feb-17 04:00 PM A 20-Feb-17 02:00 PM Welder, Anaylzer, Site engineer, Masonry
A1130 prepare the model 5d 0d 8h 0% 28-Feb-17 02:00 PM A 01-Mar-17 11:30 AM Desing engineer, Anaylzer, Project Engineer, Labou
A1140 calculate teh bridge will carry the loads 7d 7d 0% 07-Mar-17 09:00 AM 15-Mar-17 05:00 PM Welder, Anaylzer, Project Engineer, labour
Design RefineementDesign Refineement 14d 3d 0% 15-Mar-17 05:00 PM A 28-Mar-17 06:00 PM
A1150 analyse & select the bridge type 7d 1d 4h 0% 15-Mar-17 05:00 PM A 27-Mar-17 10:00 AM Welder, Anaylzer, Project Engineer, Plumber, Maso
A1160 analyse the calculations 7d 1d 4h 0% 24-Mar-17 03:00 PM A 27-Mar-17 10:00 AM Desing engineer, Welder, Anaylzer, Masonry
A1180 anlayse & corrects the calculatieons 7d 1d 8h 0% 24-Mar-17 03:00 PM A 27-Mar-17 02:30 PM Desing engineer, Welder, Project Engineer
A1170 verify the calculations 5d 1d 0% 27-Mar-17 05:00 PM A 28-Mar-17 06:00 PM Welder, Anaylzer, Masonry, Plumber
Implement PlanImplement Plan 72d 62d 2h 0% 03-Apr-17 12:00 PM A 22-Jun-17 02:00 PM
A1190 after planning get approval 30d 7d 5h 0% 03-Apr-17 12:00 PM A 12-Apr-17 04:00 PM Welder, Anaylzer, site engineer, Project Engineer
A1200 outlien the construction 7d 1d 8h 0% 11-May-17 04:00 PM A 13-May-17 03:30 PM Welder, Anaylzer, Site Engineer, Labour
A1210 install temporary power 4d 1d 0% 20-May-17 02:00 PM A 22-May-17 03:00 PM Welder, Anaylzer, Site Engineer, Carpenter, Labour
A1220 install temporary water services 5d 1d 3h 0% 26-May-17 08:00 AM A 27-May-17 11:30 AM Welder, Anaylzer, Site Engineer, Project Engineer,
A1230 set up site office 7d 2d 1h 0% 01-Jun-17 02:00 PM A 03-Jun-17 05:00 PM Welder, Anaylzer, Site Engineer, Masonry, Painter,
A1240 arrange the machinery 7d 2d 1h 0% 08-Jun-17 09:00 AM A 10-Jun-17 12:00 PM Welder, Anaylzer, Site Engineer, Masonry, Carpent
A1250 implement the blueprint model with dimension14d 4d 2h 0% 16-Jun-17 05:00 PM A 22-Jun-17 02:00 PM Desing engineer, Welder, Plumber, labour, Anaylze
building project... Classic Schedule Layout 11-Jan-17 01:21 PM
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 1 of 4 TASK filter: All Activities
© Oracle Corporation
Budgeted Total
Cost
Total
Float
$113,656.80 0d
$2,096.14
$0.00
aylzer, Site Engineer, Project Engineer$676.17
aylzer, Site Engineer, Project Engineer$1,158.72
er, Project Engineer $261.25
$3,093.50 0d
elder, Anaylzer, Site Engineer, Project Engineer, Masory, Carpenter, Plumber, labour$823.70
er $236.66 0d
aylzer, Site engineer, Project Engineer$699.23
aylzer, Site Engineer, Project Engineer$1,333.91 0d
$4,053.97 0d
aylzer, Site Engineer, Project Engineer$753.01
lder, Anaylzer, Site Engineer, Masonry, Carpenter, Plumber, Labour$972.77 5d
aylzer, Site Engineer $344.23
aylzer, Project Engineer, labour $161.36 9d
e engineer, Masonry $720.74 0d
aylzer, Project Engineer, Labour, Plumber$445.66 0d
oject Engineer, labour $656.20 0d
$2,030.06 0d
oject Engineer, Plumber, Masonry$634.68
lder, Anaylzer, Masonry $430.29 0d
lder, Project Engineer $580.90 0d
sonry, Plumber $384.19 0d
$8,318.04 0d
e engineer, Project Engineer $2,147.95 0d
e Engineer, Labour $623.92 0d
e Engineer, Carpenter, Labour, Plumber$682.32 0d
e Engineer, Project Engineer, Masonry, Plumber, labour$883.64 0d
e Engineer, Masonry, Painter, Plumber, labour$1,161.79 0d
e Engineer, Masonry, Carpenter, Plumber, Labour$1,032.70 0d
lder, Plumber, labour, Anaylzer$1,785.71 0d
04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28
December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
02-Jan-17 03:00 PM A, Identify the problem
start of project
analyse the purpose of bridge
analyse the load (capacity) of the bridge
discussion among engineers, contractors
01-Feb-17 10:00 AM, Determine constraints
analyse the material used for constructin
prepare the rough sketch
estimate the cost
prepare the schedule
15-Mar-17 05:00 PM, Analyse of design
analyse the span
analyse the material
according to the span decide the type pof bridge
prepare the drawings
determine the strenght, market appeal of hte material
prepare the model
calculate teh bridge will carry the loads
28-Mar-17 06:00 PM, Design Refineement
analyse & select the bridge type
analyse the calculations
anlayse & corrects the calculatieons
verify the calculations
after planning get approval
outlien the construction
install temporary powe
install temporary w
set up site o
arrang
building project... Classic Schedule Layout 11-Jan-17 01:21 PM
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 2 of 4 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name Original
Duration
Remaining
Duration
Schedule %
Complete
Start Finish Resources
ConstructionConstruction 79d 77d 10h 0% 05-Jul-17 12:00 PM A 14-Oct-17 08:30 AM
A1260 after get approvall make as a documetn 30d 12d 0% 05-Jul-17 12:00 PM A 20-Jul-17 04:00 PM Welder, Site Engineer, Anaylzer, Project Engineer,
A1270 prepare an agreement for contractor 15d 6d 0% 05-Jul-17 12:00 PM A 13-Jul-17 09:00 AM Desing engineer, Welder, Anaylzer, Carpenter, labo
A1280 stablizing the ground 10d 4d 0% 25-Jul-17 09:00 AM A 29-Jul-17 02:00 PM Welder, Anaylzer, Carpenter, Plumber, Labour, Bull
A1290 excavation 10d 4d 0% 07-Aug-17 10:00 AM A 11-Aug-17 03:00 PM Site Engineer, Labour, Sand, Bull dozer, Motor Gra
A1300 construct bridge pier 14d 6d 3h 0% 19-Aug-17 11:00 AM A 28-Aug-17 11:00 AM Masory, Carpenter, Plumber, Labour, Sand, Cemen
A1310 curing the pier 14d 7d 0% 06-Sep-17 05:00 PM A 15-Sep-17 03:00 PM Welder, Site Engineer, Project Engineer, Masonry,
A1320 build pier cap 14d 8d 4h 0% 09-Sep-17 09:00 AM A 20-Sep-17 12:00 PM Site Engineer, Masory, Cement, labour, Sand, Moto
A1330 construction of beams 7d 5d 3h 0% 27-Sep-17 03:00 PM A 04-Oct-17 12:30 PM Welder, Site Engineer, Project Engineer, Masory, C
A1340 construct bridge deck 7d 5d 10h 0% 06-Oct-17 12:00 PM A 14-Oct-17 08:30 AM Welder, Site Engineer, Masory, Carpenter, labour, S
Pre stressed ConcretePre stressed Concrete 57d 57d 0% 16-Oct-17 10:00 AM A 28-Dec-17 02:00 PM
A1350 rolls of post tensioning cables 7d 7d 0% 16-Oct-17 10:00 AM 24-Oct-17 06:00 PM Welder, site engineer, Carpenter, Plumber, labour,
A1360 Pulling anchors for post tensioning cables 14d 14d 0% 25-Oct-17 08:00 AM 11-Nov-17 02:00 PM Welder, Site Engineer, Masonry, Plumber, labour, S
A1370 post-tensinoing cables stripped for placement in pulling anchors14d 14d 0% 25-Oct-17 08:00 AM 11-Nov-17 02:00 PM Welder, Project Engineer, Masonry, Carpenter, Plu
A1380 Positioined post tensioning cables 14d 14d 0% 11-Nov-17 02:00 PM 30-Nov-17 09:00 AM Welder, Masory, Carpenter, Plumber, labour
A1390 post-tensioning cable ends extending from conctete slab18d 18d 0% 30-Nov-17 09:00 AM 23-Dec-17 09:00 AM Welder, Site Engineer, Masonry, Plumber, labour
A1400 Post tensioning cable ends extending from concrete cables14d 2d 1h 0% 30-Nov-17 09:00 AM A 02-Dec-17 12:00 PM Welder, Site Engineer, Masonry, Carpenter, Painte
A1410 Hydraulic jack for tensioning cables 7d 7d 0% 18-Dec-17 03:00 PM 27-Dec-17 12:00 PM Welder, Site Engineer, Carpenter, Plumber, labour
A1420 cable conduits in formwork 7d 7d 0% 19-Dec-17 04:00 PM 28-Dec-17 02:00 PM Welder, Site Engineer, Masory, Carpenter, labour, P
Final StepFinal Step 41d 41d 0% 28-Dec-17 02:00 PM 20-Feb-18 09:00 AM
A1430 build abutment 14d 14d 0% 28-Dec-17 02:00 PM 16-Jan-18 09:00 AM Desing engineer, Welder, Anaylzer, Project Engine
A1440 insert the pre-stressed conctete 14d 14d 0% 16-Jan-18 09:00 AM 02-Feb-18 03:00 PM Welder, labour, Carpenter
A1460 expansion joint 14d 14d 0% 01-Feb-18 02:00 PM 20-Feb-18 09:00 AM Site engineer, Carpenter, labour
A1450 build barrier 7d 7d 0% 02-Feb-18 03:00 PM 12-Feb-18 12:00 PM Site engineer, Masory, Carpenter, labour
Testing & InspectionTesting & Inspection 24d 24d 0% 20-Feb-18 09:00 AM 22-Mar-18 04:00 PM
A1470 apply actual load 2d 2d 0% 20-Feb-18 09:00 AM 22-Feb-18 11:00 AM Anaylzer, Project Engineer, Site engineer, Carpente
A1480 using device to test 7d 7d 0% 22-Feb-18 11:00 AM 03-Mar-18 09:00 AM Anaylzer, Project Engineer, Carpenter, labour, Site
A1490 prepare a document 15d 15d 0% 03-Mar-18 09:00 AM 22-Mar-18 04:00 PM Desing engineer, Anaylzer, Project Engineer
A1500 fiinsh of project 0d 0d 0% 22-Mar-18 04:00 PM 22-Mar-18 04:00 PM
building projectbuilding project 0d 0d 0%
building project... Classic Schedule Layout 11-Jan-17 01:21 PM
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 3 of 4 TASK filter: All Activities
© Oracle Corporation
Budgeted Total
Cost
Total
Float
$66,467.87 0d
r, Anaylzer, Project Engineer, Plumber, Labour$5,486.23 0d
lder, Anaylzer, Carpenter, labour$1,936.32 0d
rpenter, Plumber, Labour, Bull dozer$1,429.19 0d
r, Sand, Bull dozer, Motor Grader$3,964.84 0d
lumber, Labour, Sand, Cement$6,949.23 0d
r, Project Engineer, Masonry, Carpenter, Plumber, labour, Cement, Sand$13,932.87 0d
y, Cement, labour, Sand, Motor Grader, plumber$17,664.85 0d
r, Project Engineer, Masory, Cement, Painter, Plumber, labour, Sand, Motor Grader, Carpenter$7,821.64 0d
r, Masory, Carpenter, labour, Sand, Cement, Motor Grader, Painter$7,282.70 0d
$18,940.97 0d
r, Carpenter, Plumber, labour, Sand$1,626.30 0d
r, Masonry, Plumber, labour, Sand$2,366.61 0d
neer, Masonry, Carpenter, Plumber, labour, Sand$6,303.79 0d
penter, Plumber, labour $1,419.97 0d
r, Masonry, Plumber, labour $2,932.14 0d
r, Masonry, Carpenter, Painter, Plumber, labour$2,431.15 0d
r, Carpenter, Plumber, labour $753.01 0d
r, Masory, Carpenter, labour, Project Engineer$1,108.00 0d
$6,770.65 0d
lder, Anaylzer, Project Engineer, Masonry, Carpenter, Painter, labour, Cement$3,704.82 0d
enter $1,419.97 0d
nter, labour $839.07 0d
y, Carpenter, labour $806.80 0d
$1,885.60 0d
gineer, Site engineer, Carpenter, labour, Masory$390.34 0d
gineer, Carpenter, labour, Site engineer$1,043.46 0d
aylzer, Project Engineer $451.81 0d
$0.00 0d
$0.00 0d
04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28
December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
building project... Classic Schedule Layout 11-Jan-17 01:21 PM
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 4 of 4 TASK filter: All Activities
© Oracle Corporation

Más contenido relacionado

Similar a Bridge project

HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityRoumik Mukherjee
 
49700707 t9085-estimate-blank
49700707 t9085-estimate-blank49700707 t9085-estimate-blank
49700707 t9085-estimate-blankimaduddin91
 
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...Rodger McKinley
 
ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)Jamal Nelson, CCM
 
Equipment Arrival Status.pptx
Equipment Arrival Status.pptxEquipment Arrival Status.pptx
Equipment Arrival Status.pptxMehmanNasibov1
 
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Ahmed Mehrem
 
MPR OCT-22 PPT COMBINE.pptx
MPR OCT-22 PPT COMBINE.pptxMPR OCT-22 PPT COMBINE.pptx
MPR OCT-22 PPT COMBINE.pptxSuyogJungare
 
Water pipe Lines Progress Planned Vs actual.pptx
Water pipe Lines  Progress Planned Vs actual.pptxWater pipe Lines  Progress Planned Vs actual.pptx
Water pipe Lines Progress Planned Vs actual.pptxDILIP KUMAR M.Tech (ACT)
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...yang lu
 
HFO Diesel Power Plant Erection Case Studies
HFO Diesel Power Plant Erection Case StudiesHFO Diesel Power Plant Erection Case Studies
HFO Diesel Power Plant Erection Case StudiesBerr Industry
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Allan Leyte
 
SAMPLE PROJECT P6 PROFESSIONAL R16.2
SAMPLE PROJECT P6 PROFESSIONAL R16.2SAMPLE PROJECT P6 PROFESSIONAL R16.2
SAMPLE PROJECT P6 PROFESSIONAL R16.2Aqeel Imran
 
MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1Eko Untung
 

Similar a Bridge project (20)

01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
 
49700707 t9085-estimate-blank
49700707 t9085-estimate-blank49700707 t9085-estimate-blank
49700707 t9085-estimate-blank
 
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
 
2014-B36-D01
2014-B36-D012014-B36-D01
2014-B36-D01
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)
 
Equipment Arrival Status.pptx
Equipment Arrival Status.pptxEquipment Arrival Status.pptx
Equipment Arrival Status.pptx
 
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
 
MPR OCT-22 PPT COMBINE.pptx
MPR OCT-22 PPT COMBINE.pptxMPR OCT-22 PPT COMBINE.pptx
MPR OCT-22 PPT COMBINE.pptx
 
Water pipe Lines Progress Planned Vs actual.pptx
Water pipe Lines  Progress Planned Vs actual.pptxWater pipe Lines  Progress Planned Vs actual.pptx
Water pipe Lines Progress Planned Vs actual.pptx
 
200040 CSJ.pdf
200040 CSJ.pdf200040 CSJ.pdf
200040 CSJ.pdf
 
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
 
W15 Weekly Report RME
W15 Weekly Report RMEW15 Weekly Report RME
W15 Weekly Report RME
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
 
HFO Diesel Power Plant Erection Case Studies
HFO Diesel Power Plant Erection Case StudiesHFO Diesel Power Plant Erection Case Studies
HFO Diesel Power Plant Erection Case Studies
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016
 
SAMPLE PROJECT P6 PROFESSIONAL R16.2
SAMPLE PROJECT P6 PROFESSIONAL R16.2SAMPLE PROJECT P6 PROFESSIONAL R16.2
SAMPLE PROJECT P6 PROFESSIONAL R16.2
 
MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1
 

Más de Vivek John

Jigs and fixture_pnuematically operated
Jigs and fixture_pnuematically operatedJigs and fixture_pnuematically operated
Jigs and fixture_pnuematically operatedVivek John
 
double acting cylinder-hydraulic circuit desgin
double acting cylinder-hydraulic circuit desgindouble acting cylinder-hydraulic circuit desgin
double acting cylinder-hydraulic circuit desginVivek John
 
Vivek Primavera
Vivek PrimaveraVivek Primavera
Vivek PrimaveraVivek John
 
PROCESS CHART-SAMPLE
PROCESS CHART-SAMPLEPROCESS CHART-SAMPLE
PROCESS CHART-SAMPLEVivek John
 
Calculation for Compressor Table
Calculation for Compressor TableCalculation for Compressor Table
Calculation for Compressor TableVivek John
 

Más de Vivek John (6)

Jigs and fixture_pnuematically operated
Jigs and fixture_pnuematically operatedJigs and fixture_pnuematically operated
Jigs and fixture_pnuematically operated
 
double acting cylinder-hydraulic circuit desgin
double acting cylinder-hydraulic circuit desgindouble acting cylinder-hydraulic circuit desgin
double acting cylinder-hydraulic circuit desgin
 
Vivek Primavera
Vivek PrimaveraVivek Primavera
Vivek Primavera
 
PROCESS CHART-SAMPLE
PROCESS CHART-SAMPLEPROCESS CHART-SAMPLE
PROCESS CHART-SAMPLE
 
JB 11 M
JB 11 MJB 11 M
JB 11 M
 
Calculation for Compressor Table
Calculation for Compressor TableCalculation for Compressor Table
Calculation for Compressor Table
 

Bridge project

  • 1. Activity ID Activity Name Original Duration Remaining Duration Schedule % Complete Start Finish Resources Bridge ProjectBridge Project 358d 341d 0% 14-Dec-16 08:00 AM A 22-Mar-18 04:00 PM Identify the problemIdentify the problem 15d 0d 0% 14-Dec-16 08:00 AM A 02-Jan-17 03:00 PM A A1000 start of project 0d 0d 0% 14-Dec-16 08:00 AM A 14-Dec-16 08:00 AM A A1010 analyse the purpose of bridge 10d 0d 0% 14-Dec-16 08:00 AM A 27-Dec-16 09:00 AM A Desing engineer, Anaylzer, Site Engineer, Project E A1030 analyse the load (capacity) of the bridge 13d 0d 0% 14-Dec-16 08:00 AM A 30-Dec-16 12:00 PM A Design Engineer, Anaylzer, Site Engineer, Project E A1020 discussion among engineers, contractors 5d 0d 0% 27-Dec-16 09:00 AM A 02-Jan-17 03:00 PM A Anaylzer, Site Engineer, Project Engineer Determine constraintsDetermine constraints 25d 21d 0% 30-Dec-16 12:00 PM A 01-Feb-17 10:00 AM A1040 analyse the material used for constructin 4d 0d 0% 30-Dec-16 12:00 PM A 04-Jan-17 05:00 PM A Design Engineer, Welder, Anaylzer, Site Engineer, A1050 prepare the rough sketch 7d 7d 0% 04-Jan-17 05:00 PM 13-Jan-17 03:00 PM Anaylzer, Site Engineer A1060 estimate the cost 7d 0d 0% 13-Jan-17 03:00 PM A 20-Jan-17 05:00 PM A Desing engineer, Anaylzer, Site engineer, Project E A1070 prepare the schedule 14d 14d 0% 13-Jan-17 03:00 PM 01-Feb-17 10:00 AM Desing engineer, Anaylzer, Site Engineer, Project E Analyse of designAnalyse of design 33d 29d 0% 01-Feb-17 10:00 AM A 15-Mar-17 05:00 PM A1080 analyse the span 7d 0d 0% 01-Feb-17 10:00 AM A 11-Feb-17 06:00 PM A Desing engineer, Anaylzer, Site Engineer, Project E A1100 analyse the material 5d 0d 5h 0% 06-Feb-17 03:00 PM A 07-Feb-17 10:00 AM Desing engineer, Welder, Anaylzer, Site Engineer, A1090 according to the span decide the type pof bridge7d 0d 7h 0% 10-Feb-17 08:00 AM A 11-Feb-17 02:00 PM Desing engineer, Anaylzer, Site Engineer A1120 prepare the drawings 5d 0d 8h 0% 10-Feb-17 08:00 AM A 10-Feb-17 04:30 PM Desing engineer, Anaylzer, Project Engineer, labou A1110 determine the strenght, market appeal of hte material7d 0d 7h 0% 18-Feb-17 04:00 PM A 20-Feb-17 02:00 PM Welder, Anaylzer, Site engineer, Masonry A1130 prepare the model 5d 0d 8h 0% 28-Feb-17 02:00 PM A 01-Mar-17 11:30 AM Desing engineer, Anaylzer, Project Engineer, Labou A1140 calculate teh bridge will carry the loads 7d 7d 0% 07-Mar-17 09:00 AM 15-Mar-17 05:00 PM Welder, Anaylzer, Project Engineer, labour Design RefineementDesign Refineement 14d 3d 0% 15-Mar-17 05:00 PM A 28-Mar-17 06:00 PM A1150 analyse & select the bridge type 7d 1d 4h 0% 15-Mar-17 05:00 PM A 27-Mar-17 10:00 AM Welder, Anaylzer, Project Engineer, Plumber, Maso A1160 analyse the calculations 7d 1d 4h 0% 24-Mar-17 03:00 PM A 27-Mar-17 10:00 AM Desing engineer, Welder, Anaylzer, Masonry A1180 anlayse & corrects the calculatieons 7d 1d 8h 0% 24-Mar-17 03:00 PM A 27-Mar-17 02:30 PM Desing engineer, Welder, Project Engineer A1170 verify the calculations 5d 1d 0% 27-Mar-17 05:00 PM A 28-Mar-17 06:00 PM Welder, Anaylzer, Masonry, Plumber Implement PlanImplement Plan 72d 62d 2h 0% 03-Apr-17 12:00 PM A 22-Jun-17 02:00 PM A1190 after planning get approval 30d 7d 5h 0% 03-Apr-17 12:00 PM A 12-Apr-17 04:00 PM Welder, Anaylzer, site engineer, Project Engineer A1200 outlien the construction 7d 1d 8h 0% 11-May-17 04:00 PM A 13-May-17 03:30 PM Welder, Anaylzer, Site Engineer, Labour A1210 install temporary power 4d 1d 0% 20-May-17 02:00 PM A 22-May-17 03:00 PM Welder, Anaylzer, Site Engineer, Carpenter, Labour A1220 install temporary water services 5d 1d 3h 0% 26-May-17 08:00 AM A 27-May-17 11:30 AM Welder, Anaylzer, Site Engineer, Project Engineer, A1230 set up site office 7d 2d 1h 0% 01-Jun-17 02:00 PM A 03-Jun-17 05:00 PM Welder, Anaylzer, Site Engineer, Masonry, Painter, A1240 arrange the machinery 7d 2d 1h 0% 08-Jun-17 09:00 AM A 10-Jun-17 12:00 PM Welder, Anaylzer, Site Engineer, Masonry, Carpent A1250 implement the blueprint model with dimension14d 4d 2h 0% 16-Jun-17 05:00 PM A 22-Jun-17 02:00 PM Desing engineer, Welder, Plumber, labour, Anaylze building project... Classic Schedule Layout 11-Jan-17 01:21 PM Actual Work Remaining Work Critical Remaining ... Milestone Page 1 of 4 TASK filter: All Activities © Oracle Corporation
  • 2. Budgeted Total Cost Total Float $113,656.80 0d $2,096.14 $0.00 aylzer, Site Engineer, Project Engineer$676.17 aylzer, Site Engineer, Project Engineer$1,158.72 er, Project Engineer $261.25 $3,093.50 0d elder, Anaylzer, Site Engineer, Project Engineer, Masory, Carpenter, Plumber, labour$823.70 er $236.66 0d aylzer, Site engineer, Project Engineer$699.23 aylzer, Site Engineer, Project Engineer$1,333.91 0d $4,053.97 0d aylzer, Site Engineer, Project Engineer$753.01 lder, Anaylzer, Site Engineer, Masonry, Carpenter, Plumber, Labour$972.77 5d aylzer, Site Engineer $344.23 aylzer, Project Engineer, labour $161.36 9d e engineer, Masonry $720.74 0d aylzer, Project Engineer, Labour, Plumber$445.66 0d oject Engineer, labour $656.20 0d $2,030.06 0d oject Engineer, Plumber, Masonry$634.68 lder, Anaylzer, Masonry $430.29 0d lder, Project Engineer $580.90 0d sonry, Plumber $384.19 0d $8,318.04 0d e engineer, Project Engineer $2,147.95 0d e Engineer, Labour $623.92 0d e Engineer, Carpenter, Labour, Plumber$682.32 0d e Engineer, Project Engineer, Masonry, Plumber, labour$883.64 0d e Engineer, Masonry, Painter, Plumber, labour$1,161.79 0d e Engineer, Masonry, Carpenter, Plumber, Labour$1,032.70 0d lder, Plumber, labour, Anaylzer$1,785.71 0d 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 02-Jan-17 03:00 PM A, Identify the problem start of project analyse the purpose of bridge analyse the load (capacity) of the bridge discussion among engineers, contractors 01-Feb-17 10:00 AM, Determine constraints analyse the material used for constructin prepare the rough sketch estimate the cost prepare the schedule 15-Mar-17 05:00 PM, Analyse of design analyse the span analyse the material according to the span decide the type pof bridge prepare the drawings determine the strenght, market appeal of hte material prepare the model calculate teh bridge will carry the loads 28-Mar-17 06:00 PM, Design Refineement analyse & select the bridge type analyse the calculations anlayse & corrects the calculatieons verify the calculations after planning get approval outlien the construction install temporary powe install temporary w set up site o arrang building project... Classic Schedule Layout 11-Jan-17 01:21 PM Actual Work Remaining Work Critical Remaining ... Milestone Page 2 of 4 TASK filter: All Activities © Oracle Corporation
  • 3. Activity ID Activity Name Original Duration Remaining Duration Schedule % Complete Start Finish Resources ConstructionConstruction 79d 77d 10h 0% 05-Jul-17 12:00 PM A 14-Oct-17 08:30 AM A1260 after get approvall make as a documetn 30d 12d 0% 05-Jul-17 12:00 PM A 20-Jul-17 04:00 PM Welder, Site Engineer, Anaylzer, Project Engineer, A1270 prepare an agreement for contractor 15d 6d 0% 05-Jul-17 12:00 PM A 13-Jul-17 09:00 AM Desing engineer, Welder, Anaylzer, Carpenter, labo A1280 stablizing the ground 10d 4d 0% 25-Jul-17 09:00 AM A 29-Jul-17 02:00 PM Welder, Anaylzer, Carpenter, Plumber, Labour, Bull A1290 excavation 10d 4d 0% 07-Aug-17 10:00 AM A 11-Aug-17 03:00 PM Site Engineer, Labour, Sand, Bull dozer, Motor Gra A1300 construct bridge pier 14d 6d 3h 0% 19-Aug-17 11:00 AM A 28-Aug-17 11:00 AM Masory, Carpenter, Plumber, Labour, Sand, Cemen A1310 curing the pier 14d 7d 0% 06-Sep-17 05:00 PM A 15-Sep-17 03:00 PM Welder, Site Engineer, Project Engineer, Masonry, A1320 build pier cap 14d 8d 4h 0% 09-Sep-17 09:00 AM A 20-Sep-17 12:00 PM Site Engineer, Masory, Cement, labour, Sand, Moto A1330 construction of beams 7d 5d 3h 0% 27-Sep-17 03:00 PM A 04-Oct-17 12:30 PM Welder, Site Engineer, Project Engineer, Masory, C A1340 construct bridge deck 7d 5d 10h 0% 06-Oct-17 12:00 PM A 14-Oct-17 08:30 AM Welder, Site Engineer, Masory, Carpenter, labour, S Pre stressed ConcretePre stressed Concrete 57d 57d 0% 16-Oct-17 10:00 AM A 28-Dec-17 02:00 PM A1350 rolls of post tensioning cables 7d 7d 0% 16-Oct-17 10:00 AM 24-Oct-17 06:00 PM Welder, site engineer, Carpenter, Plumber, labour, A1360 Pulling anchors for post tensioning cables 14d 14d 0% 25-Oct-17 08:00 AM 11-Nov-17 02:00 PM Welder, Site Engineer, Masonry, Plumber, labour, S A1370 post-tensinoing cables stripped for placement in pulling anchors14d 14d 0% 25-Oct-17 08:00 AM 11-Nov-17 02:00 PM Welder, Project Engineer, Masonry, Carpenter, Plu A1380 Positioined post tensioning cables 14d 14d 0% 11-Nov-17 02:00 PM 30-Nov-17 09:00 AM Welder, Masory, Carpenter, Plumber, labour A1390 post-tensioning cable ends extending from conctete slab18d 18d 0% 30-Nov-17 09:00 AM 23-Dec-17 09:00 AM Welder, Site Engineer, Masonry, Plumber, labour A1400 Post tensioning cable ends extending from concrete cables14d 2d 1h 0% 30-Nov-17 09:00 AM A 02-Dec-17 12:00 PM Welder, Site Engineer, Masonry, Carpenter, Painte A1410 Hydraulic jack for tensioning cables 7d 7d 0% 18-Dec-17 03:00 PM 27-Dec-17 12:00 PM Welder, Site Engineer, Carpenter, Plumber, labour A1420 cable conduits in formwork 7d 7d 0% 19-Dec-17 04:00 PM 28-Dec-17 02:00 PM Welder, Site Engineer, Masory, Carpenter, labour, P Final StepFinal Step 41d 41d 0% 28-Dec-17 02:00 PM 20-Feb-18 09:00 AM A1430 build abutment 14d 14d 0% 28-Dec-17 02:00 PM 16-Jan-18 09:00 AM Desing engineer, Welder, Anaylzer, Project Engine A1440 insert the pre-stressed conctete 14d 14d 0% 16-Jan-18 09:00 AM 02-Feb-18 03:00 PM Welder, labour, Carpenter A1460 expansion joint 14d 14d 0% 01-Feb-18 02:00 PM 20-Feb-18 09:00 AM Site engineer, Carpenter, labour A1450 build barrier 7d 7d 0% 02-Feb-18 03:00 PM 12-Feb-18 12:00 PM Site engineer, Masory, Carpenter, labour Testing & InspectionTesting & Inspection 24d 24d 0% 20-Feb-18 09:00 AM 22-Mar-18 04:00 PM A1470 apply actual load 2d 2d 0% 20-Feb-18 09:00 AM 22-Feb-18 11:00 AM Anaylzer, Project Engineer, Site engineer, Carpente A1480 using device to test 7d 7d 0% 22-Feb-18 11:00 AM 03-Mar-18 09:00 AM Anaylzer, Project Engineer, Carpenter, labour, Site A1490 prepare a document 15d 15d 0% 03-Mar-18 09:00 AM 22-Mar-18 04:00 PM Desing engineer, Anaylzer, Project Engineer A1500 fiinsh of project 0d 0d 0% 22-Mar-18 04:00 PM 22-Mar-18 04:00 PM building projectbuilding project 0d 0d 0% building project... Classic Schedule Layout 11-Jan-17 01:21 PM Actual Work Remaining Work Critical Remaining ... Milestone Page 3 of 4 TASK filter: All Activities © Oracle Corporation
  • 4. Budgeted Total Cost Total Float $66,467.87 0d r, Anaylzer, Project Engineer, Plumber, Labour$5,486.23 0d lder, Anaylzer, Carpenter, labour$1,936.32 0d rpenter, Plumber, Labour, Bull dozer$1,429.19 0d r, Sand, Bull dozer, Motor Grader$3,964.84 0d lumber, Labour, Sand, Cement$6,949.23 0d r, Project Engineer, Masonry, Carpenter, Plumber, labour, Cement, Sand$13,932.87 0d y, Cement, labour, Sand, Motor Grader, plumber$17,664.85 0d r, Project Engineer, Masory, Cement, Painter, Plumber, labour, Sand, Motor Grader, Carpenter$7,821.64 0d r, Masory, Carpenter, labour, Sand, Cement, Motor Grader, Painter$7,282.70 0d $18,940.97 0d r, Carpenter, Plumber, labour, Sand$1,626.30 0d r, Masonry, Plumber, labour, Sand$2,366.61 0d neer, Masonry, Carpenter, Plumber, labour, Sand$6,303.79 0d penter, Plumber, labour $1,419.97 0d r, Masonry, Plumber, labour $2,932.14 0d r, Masonry, Carpenter, Painter, Plumber, labour$2,431.15 0d r, Carpenter, Plumber, labour $753.01 0d r, Masory, Carpenter, labour, Project Engineer$1,108.00 0d $6,770.65 0d lder, Anaylzer, Project Engineer, Masonry, Carpenter, Painter, labour, Cement$3,704.82 0d enter $1,419.97 0d nter, labour $839.07 0d y, Carpenter, labour $806.80 0d $1,885.60 0d gineer, Site engineer, Carpenter, labour, Masory$390.34 0d gineer, Carpenter, labour, Site engineer$1,043.46 0d aylzer, Project Engineer $451.81 0d $0.00 0d $0.00 0d 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017 building project... Classic Schedule Layout 11-Jan-17 01:21 PM Actual Work Remaining Work Critical Remaining ... Milestone Page 4 of 4 TASK filter: All Activities © Oracle Corporation