CHAPTER 3
PROJECT MANAGEMENT
THE ESSENCE OF PROJECT MANAGEMENT
“First, have a definite, clear practical ideal; a goal, an objective. Second, have the necessary means to achieve your ends; wisdom, money, materials, and methods. Third, adjust all your means to that end.”
—Aristotle, ancient Greek philosopher and scientist
THE BBC DIGITAL MEDIA INITIATIVE
In 2007, the British Broadcasting Corporation (BBC) launched the Digital Media Initiative, an IT project meant to digitize media production and media asset management across the organization. Originally estimated at a cost of £80 million ($128 million), DMI was intended to introduce a tape- less workflow—from raw footage to finished programs—and give BBC staff immediate desktop access to the entire BBC archive. It was predicted that the DMI would save the company 2.5 percent in media production costs per hour, bringing a return of £100 million ($160 million) by 2015. In 2008, the BBC awarded the contract to Siemens, its long-time technology partner; however, that partnership broke down in 2009, with neither company taking direct responsibility for the failure. Rather, the two companies issued a statement saying, “The media environment has changed a great deal since the DMI project began, and both organizations have been in discussions about the way forward. The BBC and Siemens have reached an agreement that allows the BBC to complete the
Chapter 3
project in-house.” DMI was dubbed the “Don’t Mention It” project and delegated to the BBC’s chief
62
technical architect and executive producer.
Once in-house, however, DMI ran into a series of obstacles. Behind schedule, the IT team struggled to get end users to commit to firm project requirements and priorities. “Throughout the project, the team informed me that the biggest single challenge facing the project was the changes to requirements requested by the business,” said the former chief technology officer John Linwood. The result was a constantly fluctuating project scope.
In addition, the technology team sought to adopt an agile development approach, so that the software would be produced bit-by-bit, with the business units exploring each incremental release as it was developed. Linwood claims, however, that the business units did not want to take the time to test the releases. Eventually, the IT team simply developed major system components with minimal business unit testing. Meanwhile, the project was falling further and further behind sched- ule. In addition, the BBC did not assign anyone the responsibility or the authority to oversee the adoption of the program by the business units, depriving the DMI of effective project integration management. Because the transition from tape-based production and asset management to digital production and asset management necessitated a significant shift in work processes, management of the adoption and integration of the DMI into business units was essential.
In May 2013, the B.
Measures of Central Tendency: Mean, Median and Mode
CHAPTER 3PROJECT MANAGEMENTT.docx
1. CHAPTER 3
PROJECT MANAGEMENT
THE ESSENCE OF PROJECT MANAGEMENT
“First, have a definite, clear practical ideal; a goal, an
objective. Second, have the necessary means to achieve your
ends; wisdom, money, materials, and methods. Third, adjust all
your means to that end.”
—Aristotle, ancient Greek philosopher and scientist
THE BBC DIGITAL MEDIA INITIATIVE
In 2007, the British Broadcasting Corporation (BBC) launched
the Digital Media Initiative, an IT project meant to digitize
media production and media asset management across the
organization. Originally estimated at a cost of £80 million
($128 million), DMI was intended to introduce a tape- less
2. workflow—from raw footage to finished programs—and give
BBC staff immediate desktop access to the entire BBC archive.
It was predicted that the DMI would save the company 2.5
percent in media production costs per hour, bringing a return of
£100 million ($160 million) by 2015. In 2008, the BBC awarded
the contract to Siemens, its long-time technology partner;
however, that partnership broke down in 2009, with neither
company taking direct responsibility for the failure. Rather, the
two companies issued a statement saying, “The media
environment has changed a great deal since the DMI project
began, and both organizations have been in discussions about
the way forward. The BBC and Siemens have reached an
agreement that allows the BBC to complete the
Chapter 3
project in-house.” DMI was dubbed the “Don’t Mention It”
project and delegated to the BBC’s chief
62
technical architect and executive producer.
Once in-house, however, DMI ran into a series of obstacles.
Behind schedule, the IT team struggled to get end users to
commit to firm project requirements and priorities. “Throughout
the project, the team informed me that the biggest single
challenge facing the project was the changes to requirements
requested by the business,” said the former chief technology
officer John Linwood. The result was a constantly fluctuating
project scope.
In addition, the technology team sought to adopt an agile
development approach, so that the software would be produced
3. bit-by-bit, with the business units exploring each incremental
release as it was developed. Linwood claims, however, that the
business units did not want to take the time to test the releases.
Eventually, the IT team simply developed major system
components with minimal business unit testing. Meanwhile, the
project was falling further and further behind sched- ule. In
addition, the BBC did not assign anyone the responsibility or
the authority to oversee the adoption of the program by the
business units, depriving the DMI of effective project
integration management. Because the transition from tape-based
production and asset management to digital production and asset
management necessitated a significant shift in work processes,
management of the adoption and integration of the DMI into
business units was essential.
In May 2013, the BBC announced that it was scrapping the
entire DMI project and firing its chief technology officer. In
January 2014, the National Audit Office (NAO) of the United
Kingdom released an in-depth report on the project, which was
originally intended to include seven parts: an archive database,
a virtual warehouse for storing audio and video content,
production tools, pro- duction reporting, a music reporting
system, a media infrastructure that would allow the files to
Project Management
move freely among the BBC staff, and enterprise services. Of
these seven parts, only the music reporting system had been
successfully built and deployed. According to the NAO report,
DMI cost
£98.4 million ($157 million), took six years, and left the BBC
relying on its original tape-based production and asset
managing system.
63
4. L E A R N I N G O B J E C T I V E S
As you read this chapter, ask yourself:
What is project management, and what are the key elements of
an effective project management process?
How can an effective project management process improve the
likelihood of project success?
This chapter clarifies the importance of project management and
outlines a tried and proven process for successful project
management.
WHY MANAGERS MUST UNDERSTAND PROJECT
MANAGEMENT
Projects are the way that much of an organization’s work gets
done. No matter what the industry and no matter whether the
organization is a for-profit company or a nonprofit
organization—large or small, multinational or local—good
project management is a positive force that enables your
organization to get results from its efforts.
Unfortunately, IT-related projects are not always successful.
The Standish Group has been tracking the success rate of IT
projects for over 20 years, and although the success rate has
improved over time due to improved methods, training, and
tools, roughly
61 percent of all IT projects failed or faced major challenges
such as lateness, budget overruns, and lack of required
features.1 The Project Management Institute also found a gap
between what organizations should be doing—aligning projects
to the organization’s strategy—and what they are able to
accomplish. The result is that 44 percent of strategic initiatives
are unsuccessful.2 This chapter provides information and
guidance that will help you avoid failed and challenged
5. information technology projects.
Researchers Gary Hamel and C.K. Prahalad defined the term
core competency to mean something that a firm can do well and
that provides customer benefits, is hard for competitors to
imitate, and can be leveraged widely to many products and
markets.3 Today, many organizations recognize project
management as one of their core compe- tencies and see their
ability to manage projects better as a way to achieve an edge
over
Chapter 3
64
competitors and deliver greater value to shareholders and
customers. As a result, they spend considerable effort
identifying potential project managers and then training and
developing them. For many managers, their ability to manage
projects effectively is a key to their success within an
organization.
WHAT IS A PROJECT?
A project is a temporary endeavor undertaken to create a
unique product, service, or result. Each project attempts to
achieve specific business objectives and is
subject to certain constraints, such as total cost and completion
date. As previously discussed, organizations must always make
clear connections among business
objectives, goals, and projects; also, projects must be consistent
with business
strategies. For example, an organization may have a business
6. objective to improve customer service by offering a consistently
high level of service that exceeds custo- mers’ expectations.
Initiating a project to reduce costs in the customer service
area by eliminating all but essential services would be
inconsistent with this business objective.
At any point in time, an organization may have dozens or even
hundreds of active projects aimed at accomplishing a wide
range of results. Projects are different from operational
activities, which are repetitive activities performed over and
over again.
Projects are not repetitive; they come to a definite end once
the project objectives are met or the project is cancelled.
Projects come in all sizes and levels of complexity, as you can
see from the following examples:
A senior executive led a project to integrate two organizations
following a corporate merger.
A consumer goods company executed a project to launch a
new product. An operations manager led a project to outsource
part of a firm’s operations to a contract manufacturer.
A hospital executed a project to load an app on physicians’
smartphones that would enable them to access patient data
anywhere.
A computer software manufacturer completed a project to
improve the scheduling of help desk technicians and reduce the
time on hold for callers to its telephone support services.
A staff assistant led a project to plan the annual sales meeting.
A manager completed a project to enter her departmental budget
into a pre- formatted spreadsheet template.
Project Variables
Five highly interrelated parameters define a project—scope,
cost, time, quality, and user expectations. If any one of these
parameters changes for a project, there must be a corresponding
change in one or more of the other parameters. A brief
discussion of these parameters follows.
7. Scope
Project Management
Project scope is a definition of which tasks are and which tasks
are not included in a project. Project scope is a key determinant
of the other project factors and must carefully
be defined to ensure that a project meets its essential objectives.
In general, the larger the
65
scope of the project, the more difficult it is to meet cost,
schedule, quality, and stake- holder expectations.
For example, the California Case Management System was a
major IT project intended to automate court operations for the
state of California with a common system across the state that
would replace 70 different legacy systems. At the start of the
project, planners expected the system to cost $260 million.
Court officials terminated the project after spending $500
million on the effort. Today, it is estimated that the project
would have cost nearly $2 billion if it had run to completion.
While a variety of factors contrib- uted to this waste of
resources, one primary cause was inadequate control of the
project scope, with some 102 changes in requirements and scope
approved over the life of the project.4
Cost
The cost of a project includes all the capital, expenses, and
internal cross-charges associ- ated with the project’s buildings,
operation, maintenance, and support. Capital is money spent to
purchase assets that appear on the organization’s balance sheet
and are depreci- ated over the life of the asset. Capital items
typically have a useful life of at least several years. A building,
8. office equipment, computer hardware, and network equipment
are examples of capital assets. Computer software also can be
classified as a capital item if it costs more than $1000 per unit,
has a useful life exceeding one year, and is not used for
research and development.
Expense items are nondepreciable items that are consumed
shortly after they are purchased. Typical expenses associated
with an IT-related project include the use of out- side labor or
consultants, travel, and training. Software that does not meet
the criteria to be classified as a capital item is classified as an
expense item.
Many organizations use a system of internal cross-charges to
account for the cost of employees assigned to a project. For
example, the fully loaded cost (salary, benefits, and overhead)
of a manager might be set at $120,000 per year. The sponsoring
organization’s budget is cross-charged this amount for each
manager who works full time on the project. (The sponsoring
business unit is the business unit most affected by the project
and the one whose budget will cover the project costs.) So, if a
manager works at a 75 percent level of effort on a project for
five months, the cross-charge is $120,000 0.75 5/12
$37,500. The rationale behind cross-charging is to enable sound
economic decisions about whether employees should be
assigned to project work or to operational activities. If
employees are assigned to a project, cross-charging helps
organizations determine which project makes the most economic
sense.
Organizations have different processes and mechanisms for
budgeting and controlling each of the three types of costs:
capital, expense, and internal cross-charge. Money from the
budget for one type of cost cannot be used to pay for an item
associated with another type of cost. Thus, a project with a
large amount of capital remaining in its budget cannot
Chapter 3
9. 66
use the available dollars to pay for an expense item even if the
expense budget is overspent.
Table 3-1 summarizes and classifies various types of common
costs associated with an IT-related project.
Time
The timing of a project is frequently a critical constraint. For
example, in most organiza- tions, projects that involve finance
and accounting must be scheduled to avoid any conflict with
operations associated with the closing of end-of-quarter books.
Often, projects must be completed by a certain date to meet an
important business goal or a government mandate.
CGI, a Canadian consulting, systems integration, outsourcing,
and solutions company was awarded a $36 million contract in
December 2012 to build the Vermont Health Con- nect state
health exchange.5 Work on the project quickly fell behind
schedule—with CGI failing to meet more than half of
Vermont’s 21 performance deadlines—so the state and CGI
entered into an amended $84 million contract in August 2013 to
complete the proj- ect.6 The Vermont Health Connect site
launched in October 2013 as required to meet American
Affordable Care Act mandates, but with serious deficiencies.
Users were unable to edit their information, and the site did not
work for small businesses. Despite calls to dump CGI after the
flawed launch, state officials decided to continue working with
CGI to complete the site. In April 2014, the state and CGI
signed off on yet another agreement
TABLE 3-1 Typical IT-related project costs
10. Development Costs
Capital Internal Cross-Charge Expense
Employee-related expenses
Employees’ effort
X
Travel-related expenses
X
Training-related expenses
X
Contractor and consultant charges
X
IT-related capital and expenses
Software licenses (software purchases that qualify as a capital
expense)
X
Software licenses (software that does not qualify as a capital
expense)
11. X
Computing hardware devices
X
Network hardware devices
X
Data entry equipment
X
Total development costs
X
X
X
Project Management
that set a new schedule for delivering missing functionality and
included financial penal- ties for missed deadlines.7 When CGI
failed to meet a May deadline for enabling users to edit their
information, the state extended the deadline again—without
assessing any pen- alties.8 CGI failed to meet the revised
deadline, and in August 2014, the state fired CGI and
announced it would transition the remaining work to a new
contractor. In the end, Vermont paid CGI $66.7 million for
completed work on the $84 million contract.9, 10 CGI was
replaced by Optum, a healthcare technology company based in
Minnesota that is owned by UnitedHealth Group, the nation’s
largest health insurer.11
67
12. W H A T W O U L D Y O U D O ?
You are the Optum project leader taking over responsibility for
implementing the Vermont Health Connect state health
exchange. Your manager has just sent you a text asking you if
you think it necessary to debrief Vermont state officials on what
caused the project with CGI to spiral out of control. How do
you reply?
Quality
The quality of a project can be defined as the degree to which
the project meets the needs of its users. The quality of a project
that delivers an IT-related system may be defined in terms of
the system’s functionality, features, system outputs,
performance, reliability, and maintainability. For example,
Apple sold an astounding 10 million of its new iPhone 6 and
iPhone 6 Plus models in the first few days they were available.
Unfortunately, the new iPhones had both hardware and software
problems that caused the devices to fail to meet users’
functionality and performance expectations. Apple’s new
mobile operating system iOS 8 for the devices came without
promised apps that used a health and fitness feature called
HealthKit. In addition, it turned out that the iPhone 6 Plus was
too pliable, with some users complaining that the phone bent
when sitting in their pockets for extended periods. Then when
Apple released an iOS 8 update aimed at fixing the HealthKit
problem, some users complained the update had caused their
iPhones to lose the ability to make phone calls.12 Failure to
meet users’ functionality and performance needs detracted from
the initial introduction of the new iPhone 6.
User Expectations
As a project begins, stakeholders will form expectations—or
will already have expectations— about how the project will be
conducted and how it will affect them. For example, based on
13. previous project experience, the end users of a new IT system
may expect that they will have no involvement with the system
until it is time for them to be trained. However, the project
manager may follow a more interactive development process
that requires users to help define system requirements, evaluate
system options, try out system prototypes, develop user docu-
mentation, and define and conduct the user acceptance test.
As another example, end users may expect to participate in
weekly project status meetings to hear progress reports
firsthand. However, the project manager may not have
Chapter 3
68
considered involving them in the status meetings or may not
even be planning weekly meetings.
Both examples illustrate the significant differences in
expectations that can exist between stakeholders and project
members. It is critical to a project’s success to identify
expectations of key stakeholders and team members; if there are
differences, they must be resolved to avoid future problems and
misunderstandings.
The five project parameters—scope, cost, time, quality, and
user expectations—are all closely interrelated, as shown in
Figure 3-1. For example, if the time allowed to complete the
project is decreased, it may require an increase in project costs,
a reduction in project quality and scope, and a change of
expectations among the project stakeholders, as shown in Figure
3-2.
15. Scientific activity, on the other hand, involves following
defined routines and exacting adherence to laws. Under these
definitions, part of project management can be considered an
art, because project managers must apply intuitive skills that
vary from project to project and even from team member to
team member. The “art” of project management also involves
salesmanship and psychology in convincing others of the need
to change and that this project is right to do.
Project management is also part science because it uses time-
proven, repeatable processes and techniques to achieve project
goals. Thus, one challenge to successful project management is
recognizing when to act as an artist and rely on one’s own
instinct, versus when to act as a scientist and apply fundamental
project management principles and practices. The following
section covers the nine areas associated with the science of
project management.
PROJECT MANAGEMENT KNOWLEDGE AREAS
According to the Project Management Institute, project
managers must coordinate nine areas of expertise: scope, time,
cost, quality, human resources, communications, risk,
procurement, and integration as shown in Figure 3-3.
18. scope changes can be reviewed and the project team can decide
which, if any, of the changes will be implemented and when.
Often, it is cheaper to initiate one project to implement
numerous related changes than to start several independent
projects. A follow-
on project can then be considered to implement the
recommended changes. The scope,
71
cost, schedule, and benefits of the project must be determined to
ensure that it is well defined and worth doing.
If the project team has decided to allow scope changes during
the project, then time and effort must be allowed to assess how
the scope change will affect the interrelated project variables of
cost, schedule, quality, and expectations. This impact on the
project must be weighed against the benefits of implementing
the scope change, and the team must decide whether to
implement the scope change. Of course, there may be
alternatives for implementing a particular scope change, and the
pros and cons must be weighed for each. The time required just
to research scope changes can add considerable cost and time
to the original project. Each scope change should be approved
formally or rejected by the project manager and key
stakeholders.
Time Management
Time management includes defining an achievable completion
date that is acceptable to the project stakeholders, developing a
workable project schedule, and ensuring the timely completion
of the project. Successful project time management requires
identifying spe- cific tasks that project team members and/or
other resources must complete; sequencing these tasks, taking
into account any task dependencies or firm deadlines;
estimating the amount of resources required to complete each
task, including people, material, and equipment; estimating the
19. elapsed time to complete each task; analyzing all this data to
create a project schedule; and controlling and managing changes
to the project schedule.
The bigger the project, the more likely that poor planning will
lead to significant problems. Well-managed projects use
effective planning tools and techniques, including schedules,
milestones, and deadlines. A project schedule identifies the
project activities that must be completed, the expected start and
end dates, and what resources are assigned to each task. A
project schedule is needed to complete a project by a defined
deadline, avoid rework, and ensure that people know what to do
and when to do it. A project milestone is a critical date for
completing a major part of the project, such as program design,
coding, testing, and release (for a programming project). The
project deadline is the date the entire project should be
completed and operational—when the organization can expect to
begin to reap the benefits of the project.
In a systems development project, each activity is assigned an
earliest start time and an earliest finish time. Each activity is
also allocated slack time, which is the amount of time an
activity can be delayed without delaying the entire project. The
critical path of a project consists of all activities that, if
delayed, would delay the entire project. These activities have
zero slack time. Any problems with critical path activities will
cause pro- blems for the entire project. To ensure that critical
path activities are completed on time, project managers use
certain approaches and tools such as GanttProject, Microsoft
Project, ProjectLibre, or Webplanner to help compute these
critical project attributes.
Although the steps of systems development seem
straightforward, larger projects can become complex, requiring
hundreds or thousands of separate activities. For these systems
Chapter 3
20. 72
development efforts, formal project management methods and
tools are essential. A formal- ized approach called Program
Evaluation and Review Technique (PERT) creates three time
estimates for an activity: shortest possible time, most likely
time, and longest possible time. A formula is then applied to
determine a single PERT time estimate. A Gantt chart is a
graphical tool used for planning, monitoring, and coordinating
projects; it is essentially a grid that lists activities and
deadlines. Each time a task is completed, a marker such as a
darkened line is placed in the proper grid cell to indicate the
completion of a task.
The development of a work breakdown structure is a critical
activity needed for effective time management. A work
breakdown structure (WBS) is an outline of the work to be done
to complete the project. You start by breaking the project into
various stages or groups of activities that need to be performed.
Then, you identify the tasks associated with each project stage.
A task typically requires a week or less to complete and
produces a specific deliverable—tangible output like a
flowchart or end-user training plan. Then the tasks within each
stage are sequenced. Finally, any predecessor tasks are
identified—these are tasks that must be completed before a later
task can begin. For example, the testing of a unit of program
code cannot begin until the program has been coded, compiled,
and debugged. Next you must determine how long each task
in the WBS will take.
Thus, building a WBS allows you to look at the project in great
detail to get a complete picture of all the work that must be
performed. Development of a WBS is another approach to
defining the scope of a project—work not included in the WBS
21. is outside the scope of the project.
Table 3-2 shows a sample WBS for a project whose goal is to
establish a wireless network in a warehouse and install RFID
scanning equipment on forklift trucks for the tracking of
inventory. The three phases of the project in Table 3-2 are
“Define Ware- house Network,” “Configure Forklift Trucks,”
and “Test Warehouse Network.” Figure 3-5 shows the
associated schedule in the form of a Gantt chart, with each bar
in the chart indicating the start and end dates of each major
activity (heavy black lines) and task (lighter lines).
Cost Management
Cost management includes developing and managing the project
budget. This area involves resource planning, cost estimating,
cost budgeting, and cost control. As previously discussed, a
separate budget must be established for each of the three types
of costs— capital, expense, and internal cross-charge—and
money in one budget cannot be spent to pay for another type of
cost.
One approach to cost estimating uses the WBS to estimate all
costs (capital, expense, and cross-charge) associated with the
completion of each task. This approach can require a fair
amount of detailed work, such as determining the hourly rate of
each resource assigned to the task and multiplying by the hours
the resource will work on the task, estimating the cost per unit
for supplies and multiplying that by the number of units
required, and so on. If possible, the people who will complete
the tasks should be allowed to estimate the time duration and
associated costs. This approach helps them to better understand
the tasks they are expected to complete, gives them some degree
of control
Project Management
TABLE 3-2 Work breakdown structure
Predecessor
23. 5
7
Configure forklift trucks
19d
5/06/16
6/01/16
8
Order RFID scanners for trucks
12d
5/06/16
5/23/16
9
Install RFID scanners on trucks
5d
5/24/16
5/30/16
8
10
Test RFID scanners
2d
5/31/16
6/01/16
9
11
Test warehouse network
28d
5/06/16
6/14/16
12
Develop test plan
2d
5/06/16
5/09/16
26. Define warehouse network
3
Conduct survey
$2400
4
Order RF equipment
$9000
5
Install RF equipment
$7800
6
Test RF equipment
$ 960
7
Configure forklift trucks
8
Order RFID scanners for trucks
$12,500
9
Install RFID scanners on trucks
27. $2400
10
Test RFID scanners
$1200
11
Test warehouse network
$ 960
12
Develop test plan
13
Conduct test
$1440
TOTAL Costs
$21,500
$10,200
$6960
Project Management
As an example, suppose that a company plans to implement a
new software package for its accounts payable process. The
company must spend $150,000 on computer hard- ware (capital)
and pay the software vendor $20,000 for its time and effort to
implement
28. the software (expense). The vendor must also be paid $125,000
for the software package
75
license (capital). In addition, one business manager will spend
six months full time leading the implementation effort. Six
months’ worth of the fully loaded cost of the manager (say,
$120,000 per year) must be charged to the cross-charge budget
of the accounting organi- zation. The cross-charge is a total of
$60,000.
W H A T W O U L D Y O U D O ?
The new warehouse inventory control system will use the
recently installed wireless net- work and RFID scanning
equipment mounted on forklift trucks to track inventory in the
warehouse. You have been holding off meeting with the project
team to develop a sched- ule and cost estimate because three
key members of the five-person project team are not available
to meet until late next week. The CFO is on the phone with you.
She needs dates, effort estimates, and dollar estimates to
complete the capital and staffing forecast for next year and
ensure there will be a budget for this project. What do you say?
Quality Management
Quality management ensures that the project will meet the needs
for which it was undertaken. This process involves quality
planning, quality assurance, and quality control. Quality
planning involves determining which quality standards are
relevant to the project and determining how they will be met.
Quality assurance involves evaluating the progress of the
project on an ongoing basis to ensure that it meets the identified
quality standards. Quality control involves checking project
results to ensure that they meet identified qual- ity standards.
When it comes to developing IT-related systems, the source of
29. the majority of defects uncovered in system testing can be
traced back to an error in specifying requirements.
Thus, most organizations put a heavy emphasis on accurately
capturing and documenting system requirements and carefully
managing changes in user requirements over the course of the
project. A useful checklist for assessing the validity of system
requirements includes the following questions:13
Does the requirement describe something actually needed by the
customer? Is the requirement correctly defined?
Is the requirement consistent with other requirements? Is the
requirement defined completely?
Is the requirement verifiable (testable)?
Is the requirement traceable back to a user need?
Hewlett Packard’s Quality Center, Jama from Jama Software,
and Innoslate from Sys- tems and Proposal Engineering
Company are three examples of requirements management
software.
76
Chapter 3
Human Resource Management
Human resource management is about making the most effective
use of the people involved with the project. It includes
organizational planning, staff acquisition, and team
development. The project manager must be able to build a
project team staffed with peo- ple with the right mix of skills
and experience and then train, develop, coach, and moti- vate
them to perform effectively on the project.
30. The project manager may be assigned all members of the team,
or may have the lux- ury of selecting all or some team members.
Team members should be selected based on their skills in the
technology needed for the project, their understanding of the
business area affected by the project, their expertise in a
specific area of the project, and their ability to work well on a
team. Often, compromises must be made. For example, the best
available subject matter expert may not work well with others,
which becomes an addi- tional challenge for the project
manager.
Experienced project managers have learned that forming an
effective team to accom- plish a difficult goal is a challenge in
itself. For the team to reach high levels of perfor- mance, it
takes considerable effort and a willingness to change on the part
of the entire team. A useful model to describe how teams
develop and evolve is the forming-
storming-norming-performing model, which was first proposed
by Bruce Tuckman (see Figure 3-7).14
During the forming stage, the team meets to learn about the
project, agrees on basic goals, and begins to work on project
tasks. Team members are on their best behavior and try to be
pleasant to one another while avoiding any conflict or
disagreement. Team members work independently of one
another and focus on their role or tasks without understanding
what others are attempting to do. The team’s project manager in
the for- mation stage tends to be highly directive and tells
members what needs to be done. If the team remains in this
stage, it is unlikely to perform well, and it will never develop
break- through solutions to problems or effectively solve a
conflicting set of priorities and constraints.
The team has moved into the storming stage when it recognizes
that differences of opinion exist among team members and
allows these ideas to compete for consideration.
32. become interdepen- dent on one another and have developed an
effective decision-making process that does not require the
project manager. Dissent is expected, and the team has
developed an effective process to ensure that everyone’s ideas
and opinions are heard. Work is done quickly and with high
quality. Problems that once seemed unsolvable now have
“obvious” solutions. The team’s effectiveness is much more
than the sum of the individual members’ contributions. The
project manager encourages participative decision making, with
the team members making most of the decisions.
No matter what stage a team is operating in, it commonly will
revert to less advanced stages in the model when confronted
with major changes in the work to be done, a change in project
leadership, or substantial changes in the team’s makeup. The
project manager and business managers must recognize and
consider this important dynamic when con- templating project
changes.
Another key aspect of human resource management is getting
the project team and the sponsoring business unit to take equal
responsibility for making the project a success. The project
team members must realize that on their own they cannot
possibly make the project a success. They must ensure that the
business managers and end users become deeply involved in the
project and take an active role. The project team must actively
involve the end users, provide information for them to make
wise choices, and insist on their participation in major
decisions. The business unit must remain engaged in the proj-
ect, challenge recommendations, ask questions, and weigh
options. It cannot simply sit back and “let the project happen to
them.” Key users need to be identified as part of the project
team with responsibility for developing and reviewing
deliverables. Indeed, some organizations require that the project
manager come from the sponsoring business unit. Other
organizations assign co-project managers to IT-related
projects—one from the IT organization and one from the
business unit.
33. In addition to the development team, each project should have a
project steering team, made up of senior managers representing
the business and IT organizations, to provide guid- ance and
support to the project. The number of members on the steering
team should be
Chapter 3
78
limited (three to five) to simplify the decision-making process
and ease the effort to schedule a quorum of these busy
executives. The project manager and select members of the
development team should meet with the steering team on an as-
needed basis, typically at the end of each project phase or every
few months. The three key members of the steering team
include the project champion who is a well-respected manager
with a passion to see the project succeed and who removes
barriers to the project success; the project sponsor who is a
senior manager from the business unit most affected by the
project and who ensures the project will indeed meet the needs
of his or her organization; and the IT manager who ensures
proper IT staffing for the project and ensures the project uses
approved technology and vendors. These roles are further
explained in Figure 3-8 and outlined in Table 3-4.
Many projects also draw on key resources who are not assigned
to the project team but who provide valuable input and advice.
A subject matter expert is someone who pro- vides knowledge
and expertise in a particular aspect important to the project. For
exam- ple, an accounting system project may seek advice from a
member of the internal auditing group in defining the mandatory
35. Ensures project is staffed with appropriate IT staff
Convinces other senior man- agers of the project’s merits to
gain their approval to fund and staff it
Ensures that the project solution is truly workable and
consistent with business and end-user requirements
Ensures technology and vendors suggested for inclusion in the
project are consistent with IT strategy
Acts as a vocal and visible champion for the project to gain the
support of others
Works to overcome resistance to change and prepare the organi-
zation to embrace the new system and way of doing things
Identifies and removes barriers to project success
Identifies workers from business unit to be assigned on a full-
or part-time basis to project
Resolves any issues outside the control of the project manager
Provides advice and counsel to the project team
Keeps informed of major project activities and developments
Has final approval of all requests for changes in project scope,
budget, and schedule
Signs off on approvals to proceed to each succeeding project
phase
36. 79
In preparing a communications plan, the project manager should
recognize that the various stakeholders have different
information needs in the project. A useful tool for identifying
and documenting these needs is the stakeholder analysis matrix
37. shown in Table 3-5. This matrix identifies the interests of the
stakeholders, their information needs, and important facts for
managing communications with the champion, sponsor, project
team members, and key end users who are associated with the
project. The project manager should include his or her manager
in this analysis. Based on analysis of this data, the preferred
form and frequency of communication is identified for each
stakeholder.
Chapter 3
80
TABLE 3-5 Sample stakeholder analysis matrix
Key Stakeholders
Ray Boaz
Klem Kiddlehopper
John Smith
Forklift Drivers
Organization
Project champion and VP of supply chain
Project sponsor and warehouse manager
Experienced forklift driver
15 different drivers
Useful facts
Very persuasive Trusted by CEO
Risk taker, very aggressive
38. Will push this through, no matter what
Has driven fork- lift truck for five years
Well respected by peers
Not highly moti- vated to make project a success
Level of interest
High
High
Medium
Low
Level of influence
High
Medium
High
Low
Suggestions on managing relationship
Demands respect, somewhat formal
Speak in business terms, never get technical; no surprises!
Poor listener, forgets details
Put it in writing
Must keep John enthusiastic about project
Don’t ignore
Attend occa- sional shift change-over meeting
Information needs
ROI, budget, and schedule
Schedule and potential opera- tional conflicts
Schedule, especially timing of training
Schedule, especially tim- ing of training
Safety and pro- ductivity issues
Safety issues
Information medium, format, and timing
Biweekly face- to-face meeting
Weekly email newsletter
Biweekly face- to-face
39. Newsletter
Catch-as-catch can
Brief updates at weekly depart- ment meeting
If the project team is unable to recruit either a project champion
or sponsor, the problem may be that management does not see
clearly that the benefits of the project outweigh its costs, or that
the project appears to run counter to organizational goals and
strategies. A potential project without either a champion or a
sponsor is highly unlikely to get the needed resources, and for
good reason. No project should be started without both a
champion and a sponsor.
Risk Management
“Things will go wrong, and at the worst possible time,”
according to a variation of Murphy’s Law, a popular adage.
Project risk is an uncertain event or condition that, if it occurs,
has a positive or a negative effect on a project objective. Known
risks are risks that can be identified and analyzed. For example,
in creating a new IT-related system that includes the acquisition
of new computing and/or networking hardware, a known risk
might be that the hardware will take longer than expected to
arrive at the installation site. If the hardware is delayed by
several weeks, it could have a negative effect on the project
completion date. Countermeasures can be defined to avoid some
known risks entirely, and
Project Management
contingency plans can be developed to address unavoidable
known risks if they occur. Of course, some risks simply cannot
be anticipated.
A hallmark of experienced project managers is that they follow
a deliberate and sys-
tematic process of risk management to identify, analyze, and
40. manage project risks. Having
81
identified potential risks, they make plans to avoid them
entirely. When an unavoidable risk occurs and becomes an
issue, the project team has already defined an alternative course
of action to minimize the impact on the project. They waste no
time executing the backup plan. Unknown risks cannot be
managed directly; however, an experienced project manager will
build some contingency into the project budget and schedule to
allow for their occurrence.
While inexperienced project managers realize that things may
go wrong, they fail to identify and address known risks and do
not build in contingencies for unknown risks. Thus, they are
often unsure of what to do, at least temporarily, when a project
setback occurs. In their haste to react to a risk, they may not
implement the best course of action.
The project manager needs to lead a rigorous effort to identify
all risks associated with the project. The project team, business
managers, and end users should participate in the effort. These
resources can include seasoned project managers and members
of the orga- nization’s risk management department. After each
risk is identified and defined, as shown in Table 3-6, the group
should attempt to classify the risk by the probability that it will
occur and the impact on the project if the risk does occur. Both
the probability and the impact can be classified as high,
medium, or low, as shown in the example in Table 3-7.
TABLE 3-6 Identification of project risks
Risk Example
R1
The required new servers arrive at the installation site more
than two weeks late.
R2
Business pressures make key end users unavailable to develop
the user acceptance test by the date it is needed.
41. R3
Business pressures make end users unavailable during time
scheduled for training.
R4
One or more end-user computers have insufficient memory or
CPU capacity to run the new software efficiently (or at all).
Rn
….
TABLE 3-7 Example of an assessment of project risks
Impact on Project
Low Medium High
Probability risk occurs
High Medium
Low
R10
R5, R6
R2, R3
Rn
R1
R8,
R11
R7,
R9
R4
42. Dark High risk/high impact; risk management plan is
needed
Lightest Medium or high risk and impact; risk management
plan recommended Lighter Low or medium risk and impact;
risk management plan not needed
Chapter 3
82
The project team then needs to consider which risks need to be
addressed with some sort of risk management plan. Generally,
the team can ignore risks with a low probability of occur- rence
and low potential impact. Risks with a high probability of
occurrence and a high poten- tial impact need to have a risk
owner assigned. The risk owner is responsible for developing a
risk management strategy and monitoring the project to
determine if the risk is about to occur or has occurred. One
strategy is to take steps to avoid the risk altogether, while
another is to develop a backup plan. The risk management plan
can be documented as shown in Table 3-8.
One of the biggest risks associated with a project is that
considerable time, energy, and resources might be consumed
with little value to show in return. To avoid this poten- tial risk,
an organization must ensure that a strong rationale exists for
completing a proj- ect. The project must have a direct link to an
organizational strategy and goal, as shown in Figure 3-9. In this
example, assume that an organization has been losing sales
because of customer dissatisfaction. It has set an objective of
improving customer service, with a goal of increasing the
retention rate of existing customers. The organization has
43. defined one of its key strategies as improving customer service
to world-class levels. A project that is consistent with this
strategy and that can deliver results to achieve this goal is
clearly aligned with the organization’s objectives.
Objective—Improve customer service.
Goal—Reduce customer turnover from 25 percent per year to 10
percent by June 2017 by responding to 95 percent of customers’
inquiries within 90 seconds, with less than 5 percent callbacks
about the same problem.
Strategy—Improve customer service to world-class levels.
Project—Implement a state-of-the-art customer call center with
“24/7” availability and a well-trained staff.
TABLE 3-8 Risk management plan
Risk
Description
Risk Owner
Risk Strategy
Current Status
R2
Business pressures
Jon Andersen,
Try to avoid this
Key users have been
make key end users
manager of end
problem by starting
identified and have
unavailable to
users in the busi-
development of the
started developing the
44. develop the user
ness area
user acceptance test
test.
acceptance test by
three weeks earlier
the deadline.
than originally
planned. Monitor
progress carefully.
R3
Business pressures
Jon Andersen,
Try to avoid this pro-
Three of four temporary
make end users
manager of end
blem by hiring and
workers have been
45. unavailable during
users in the busi-
training four tempor-
hired. Their training is
the time scheduled
ness area
ary workers to fill in
scheduled to begin next
for training.
for end users as they
week.
participate in training.
R1
The required new
Alice Fields, team
Set a firm delivery
The contract with the
servers arrive at the
member responsi-
deadline with the
penalty clause has been
installation site
ble for hardware
vendor, with a sub-
signed by the vendor, who
more than two
46. acquisition
stantial dollar penalty
agrees to provide a ship-
weeks late.
for each day that the
ment status update each
equipment is late.
Tuesday and Friday.
Project Management
83
48. 84
includes tracking and documenting the provider’s performance,
managing contract changes, and taking any necessary corrective
actions.
Contract closure—This process completes and settles terms of
any contracts, including resolving any open items.
The make-or-buy decision is a key decision made during the
plan purchase and acquisition process. The make-or-buy
decision involves comparing the pros and cons of in-house
production versus outsourcing of a given product or service. In
addition to cost, two key factors to consider in this decision are
(1) “Do we have a sufficient number of employees with the
skills and experience required to deliver the product or service
at an acceptable level of quality and within the required
deadlines?” (2) “Are we willing to invest the management time,
energy, and money required to identify, recruit, train, develop,
and manage people with the skills to do this kind of work?”
Outsourcing is discussed further in Chapter 4.
A contract is a legally binding agreement that defines the terms
and conditions of the buyer–provider relationship, including
who is authorized to do what, who holds what responsibilities,
costs and terms of payment, remedies in case of breach of
contract, and the process for revising the contract. Contract
types fall into three main categories:
Fixed-price contract—With this type of contract, the buyer and
provider agree to a total fixed price for a well-defined product
or service. For example, the purchase of a large number of
laptop computers with specified capabili- ties and features
frequently involves a fixed-price contract.
Cost-reimbursable contract—This type of contract requires
paying the pro- vider an amount that covers the provider’s
actual costs plus an additional amount or percentage for profit.
Three common types of cost-reimbursable contracts exist. In a
49. cost-plus-fee or cost-plus-percentage of cost contract, the
provider is reimbursed for all allowable costs and receives a
percentage of the costs as a fee. In a cost-plus-fixed-fee
contract, the provider is reim- bursed for all allowable costs and
receives a fixed fee. In a cost-
plus-incentive-fee contract, the provider is reimbursed for all
allowable costs. In addition, a predetermined fee is paid if the
provider achieves specified performance objectives—for
example, the provider’s hardware must be received, installed,
and operational by a specific date. In such con- tracts, buyers
run the risk of paying more for the work but are rewarded by
having their objectives met or exceeded. Providers run the risk
of reduced profits if they fail to deliver, but can be rewarded for
superior performance. Time and material contract—Under this
type of contract, the buyer pays the pro- vider for both the time
and materials required to complete the contract. The con- tract
includes an agreed-upon hourly rate and unit price for the
various materials to be used. The exact number of hours and
precise quantity of each material are not known, however. Thus,
the true value of the contract is not defined when the contract is
approved. If not managed carefully, time and material contracts
actu- ally can motivate suppliers to extend projects to maximize
their fees.
Poor procurement management can result in serious project
problems and even a project’s outright cancellation.
Project Integration Management
Project Management
Project integration management is perhaps the most important
knowledge area because it requires the assimilation of all eight
other project management knowledge areas. Project
integration management requires the coordination of all
50. appropriate people, resources,
85
plans, and efforts to complete a project successfully. Project
integration management comprises seven project management
processes:
1. Developing the project charter that formally recognizes the
existence of the project, outlines the project objectives and how
they will be met, lists key assumptions, and identifies major
roles and responsibilities.
2. Developing a preliminary project scope statement to define
and gain consen- sus about the work to be done. Over the life of
the project, the scope state- ment will become fuller and more
detailed.
3. Developing the project management plan that describes the
overall scope, schedule, and budget for the project. This plan
coordinates all subsequent project planning efforts and is used
in the execution and control of the project.
4. Directing and managing project execution by following the
project management plan.
5. Monitoring and controlling the project work to meet the
project’s perfor- mance objectives. This process requires
regularly measuring effort and expenditures against the project
tasks, recognizing when significant devia- tions occur from the
schedule or budget, and taking corrective action to regain
alignment with the plan.
6. Performing integrated change control by managing changes
over the course of the project that can affect its scope, schedule,
and/or cost.
7. Closing the project successfully by gaining stakeholder and
customer accep- tance of the final product, closing all budgets
and purchase orders after con- firming that final disbursements
have been made, and capturing knowledge from the project that
may prove useful for future projects.
As an example of a firm that excels in project integration
management, consider Atos, an international IT services
51. company that employs 76,300 workers in more than 52
countries, with 2013 annual revenue of €8.6 billion ($11.0
billion). The firm successfully delivered the information
technology systems that enabled the smooth running of the
Sochi 2014 Olympic Games in Russia. Atos had the primary
responsibility for project integration, consulting, sys- tems
integration, operations management, information security, and
software applications development for the games. Through its
experience with previous Olympics (Atos has been the
Worldwide IT partner for the Olympic Games, both winter and
summer, since Salt Lake City in 2002), Atos has developed an
effective project management process. The firm spent over four
years configuring, testing, and retesting some 10,000 pieces of
equipment deployed to 30 different venues. Atos coordinated
the work of hundreds of subcontractors to deliver a reliable IT
infrastructure and IT services in support of one of the world’s
widely viewed sporting events. The Sochi project was
coordinated so that custom software, thousands of workstations
and laptops, tens of thousands of phones, hundreds of servers,
and multiple operations centers and data centers all operated
together effectively and efficiently.15
The manager’s checklist in Table 3-9 provides a set of
recommended actions for business managers to improve the
success rate of their organization’s projects. The appropriate
answer to each question is yes.
Chapter 3
TABLE 3-9 A manager’s checklist
Recommended Action
Yes
No
52. Are project scope, cost, time, quality, and user expectations
treated as highly interrelated variables—in other words,
changing one affects the others?
Is an internal cross-charge system used to account for the cost
of employees assigned to a project?
Is the project scope well defined and managed?
Is a detailed work breakdown structure prepared to define the
project schedule and cost?
Is the project’s estimated cost well defined and controlled?
Is the project team performing quality planning, quality assur-
ance, and quality control?
Is there a heavy emphasis on defining user requirements?
Does the project manager take action to form and maintain an
effective working team?
53. Do the project team and sponsoring organization take equal
responsibility for the success of the project?
Have a project champion and project sponsor been identified for
the project?
Has a communications plan for all key stakeholders been
defined for the project?
Has the project manager followed a deliberate and systematic
process of risk management to identify, analyze, and manage
project risks?
Is it clear that a strong rationale exists for doing the project?
Does the project have a direct link to an organizational strategy
and goal?
Is a process in place to manage project procurement?
Has responsibility for the seven project integration management
processes been defined?
54. Are the seven project integration management processes being
performed?
86
KEY TERMS
communications management core competency
cost management
cost-reimbursable contract critical path
fixed-price contract
forming-storming-
norming-performing model functional decomposition Gantt
Chart
human resource management make-or-buy decision predecessor
tasks
process
procurement management
CHAPTER SUMMARY
55. Program Evaluation and Review Technique (PERT)
project
project champion project deadline
project integration management project management
project milestone project risk project schedule project scope
project sponsor
project stakeholders project steering team quality
Project Management
quality assurance quality control quality management quality
planning
87
risk management risk owner
scope management slack time
sponsoring business unit subject matter expert technical
resource
time and material contract time management
work breakdown structure (WBS)
Roughly 61 percent of all IT projects are challenged or failed.
About 44 percent of all strategic initiatives are unsuccessful.
Today, many organizations have recognized project management
as one of their core competencies.
Organizations must always make clear connections among
business objectives, goals, strategies, and projects.
A project is a temporary endeavor undertaken to create a unique
product, service, or result.
Five highly interrelated parameters define a project—scope,
cost, time, quality, and user expectations. If any one of these
project parameters is changed, there must be a corre- sponding
change in one or more of the other parameters.
56. Project scope is the definition of which work is and which work
is not included in a project.
The cost of a project includes all the capital, expenses, and
internal cross-charges associ- ated with the project’s buildings,
operation, maintenance, and support.
The timing of a project is frequently a critical constraint.
Quality of a project can be defined as the degree to which the
project meets the needs of its users.
Project management is the application of knowledge, skills, and
techniques to project activ- ities to meet project requirements.
Project managers must attempt to deliver a solution that meets
specific scope, cost, time, and quality goals while managing the
expectations of the project stakeholders—the people involved in
the project or those affected by its outcome.
88
Chapter 3
According to the Project Management Institute, project
managers must coordinate nine areas of expertise, including
scope, time, cost, quality, human resources, communica- tions,
risk, procurement, and integration.
Scope management includes defining the work that must be
done as part of the project and then controlling the work to stay
within the agreed-upon scope.
Functional decomposition is a technique frequently used to
define the scope of an infor- mation system by identifying the
business processes it will affect.
Time management includes defining an achievable completion
57. date that is acceptable to the project stakeholders, developing a
workable project schedule, and ensuring the timely completion
of the project.
Cost management includes developing and managing the project
budget.
Quality management ensures that the project will meet the needs
for which it was undertaken.
Human resource management is about making the most effective
use of the people involved in the project.
The forming-storming-norming-performing model describes
how teams form and evolve.
Each project should have a project steering team—made up of
senior managers representing the business and IT
organizations—to provide guidance and support to the project.
Three key members of the steering team are the project
champion, project sponsor, and IT manager.
Communications management involves the generation,
collection, dissemination, and storage of project information in
a timely and effective manner.
Risk management is a process that attempts to identify, analyze,
and manage project risks. Experienced project managers follow
a deliberate and systematic process of risk management to avoid
risks or minimize their negative impact on a project.
Procurement management involves acquiring goods and/or
services for the project from sources outside the organization.
Project integration management is a critical knowledge area of
project management that involves chartering, scoping, planning,
executing, monitoring and controlling, change control, and
project closing.
DISCUSSION QUESTIONS
1. Do research online to find the success rate of IT projects
compared to all types of organiza- tional projects. Which has
the higher success rate? Why do you think that this is so?
58. 2. What is meant by the scope of a project? How can the scope
of a project be defined?
3. Distinguish between the role of the project champion and the
role of the project sponsor. Is one more important to the success
of a project than the other?
4. Present an argument of why organizations should not include
internal cross-charges in evalu- ating the economic desirability
of projects. Now present an argument of why they should. What
is your final position on the use of cross-charges?
5. What is the difference between quality assurance and quality
control?
Project Management
6. Describe three specific actions that the ideal project sponsor
should take to ensure the success of a project.
7. Is there a difference between project time management and
personal time management? Can
someone be “good” at one but not the other? Explain your
answer.
89
8. Discuss the team dynamics for a highly effective (or
ineffective) team of which you were a member. Can you explain
why the team performed so well (or poorly) using the forming-
storming-norming-performing model?
9. What sort of behaviors would indicate that the business
organization is not fully engaged in a project and instead is
looking to the project team to make the project a success? What
is the danger with this attitude?
10. Identify some of the challenges of performing project
integration management on a project in which team members are
distributed globally and cannot physically meet in one location.
How might these challenges be overcome?
11. Imagine that you are hiring a firm to complete a large but
59. undetermined amount of project work for your firm. Which form
of contract would you prefer and why?
12. How would you respond to a project team member who feels
that risk management is a waste of time because the future
cannot be predicted? Instead, this person prefers to react to pro-
blems as they occur.
ACTION NEEDED
1. You are on the phone with the project sponsor of a project
you are managing. He informs you that he accepted the role
reluctantly and now, two months into this eight-month project,
he is considering withdrawing as project sponsor. He does not
see the need for this role and is extremely busy with his other
responsibilities. How do you respond?
2. You and a small group of managers from the sponsoring
organization have just completed defining the scope, schedule,
and cost for an important project in your firm. You estimate that
the project will take 12 people about 10 months and cost just
over $2.5 million. You just received an email from your
manager insisting that the project schedule be shortened by
three months because senior management is impatient for the
improvements this project is expected to deliver. He promises to
“free up” four additional resources within the next month or so
to be assigned to your project. How do you respond?
3. You are surprised when your project team “pushes back” on
your request for them to schedule a full-day offsite to work with
you to develop a risk management plan. They state that they are
simply too busy to afford time for this activity. And besides,
they feel that if something unfore- seen occurs, it is your
responsibility to react to it. How do you respond to your team?
WEB-BASED CASE
BBC Digital Media Initiative Revisited
The National Audit Office (NAO) scrutinizes public spending in
the United Kingdom. Its memoran- dum on the BBC’s DMI
project reported on several key findings. First, the in-house
60. team was
90
Chapter 3
severely challenged by the fact that the project was already 18
months behind schedule when they began work on the project.
Second, the technology team issued releases throughout the
project that did not meet end-user expectations and eroded
confidence in the project. Third, the BBC focused more on the
technological development rather than on encouraging
organization-wide changes in workflow that would encourage
adoption. Finally, the NAO concluded, the DMI lacked
governance arrangements for the scale, risk, and complexity of
the project.
Do research online to identify the capabilities of digital asset
management software. What are the top rated digital asset
management software products? Who uses this software?
Given the NAO’s findings and what you discover about
available off-the-shelf products, would it have been wiser for
the BBC to adopt a collection of these existing products? What
actions would be necessary to gain the cooperation of the
business units to incorporate this collection of products into
their work processes?
CASE STUDY
Webcor: Building Buy-In in the Brick-and-Mortar Business
61. Founded in 1971, Webcor Builders is one of the largest
construction companies in California and one of the largest
green construction companies in the United States. Committed
to innovative practices, Webcor has gained considerable
attention due to its award-winning construction, historic
restoration, and seismic renovation work. As Webcor expanded
from multifamily residences to com- mercial offices, interiors,
retail, public works, parking structures, and federal, education,
and health- care facilities, the company opened offices first in
San Francisco, and then in San Diego, Los Angeles, and
Alameda. Its merger with the large Japanese construction firm
Obayashi positioned the company to reach customers along the
Pacific Rim, with a new office in Honolulu.
Along with developing innovations in building materials and
methods, Webcor has leveraged cutting-edge information
technologies—in an industry that is often slow to consider,
accept, and adopt IT advances. As early as 1984, Webcor
integrated the Apple desktop into its work process. In 2011,
Webcor made a significant commitment to virtual design and
construction in its public sector building projects. Adopting
Vico Software’s 5D Virtual Construction application allowed
Webcor to estimate costs, schedule projects, and manage
projects with increased efficiency. With this software, Webcor
can take its customers through a series of what-if scenarios that
allow them to make key design decisions from the start. Frank
Haase, Director of Virtual Building at Webcor, explains, “We
have amassed a knowledge base of real data—from past projects
and from our subcontractors—that when combined with the
integrated 5D approach gives us an unprecedented planning and
management capability on all projects. The precise information
derived from this approach, both in preconstruction planning
and in ongoing construction operations, helps us to resolve
issues early and to make prompt fact-based decisions.” Using
the software, Webcor can also predict the scheduling and cost
impact of changes that occur throughout building design and
construction.
62. The big question many observers asked was, “How did Webcor
Builders manage to persuade its workforce to adopt the new
technologies?” The decision to adopt the system involved fairly
high risks, given the potential resistance of its end users. As
Vince Sarrubi, Webcor CIO, explained the complexity of the
challenge, “Blue collar industries tend to focus on completing
tasks, meeting deadlines, and doing what they know how to do
best to minimize time loss. New technologies
Project Management
mean changes to physical work practices, which could mean
missing a deadline. These workers live in the physical world
and have been manually practicing their art for years. There’s a
mentality of ‘head down and nose to the grindstone gets the
work done’ and ‘if it ain’t broke, don’t fix it.’ ”
So, how did Webcor achieve this success? First, Sarrubi is not
alone in leading the call for
91
innovative IT utilization within the company. Webcor cites
innovation as one of its strengths, and its top management has
been firmly committed to technological innovation. Company
CEO Andy Ball spearheaded the virtual construction project. He
insists, “Change is never easy, and it has an emotional toll and
it has a financial toll. Initially, it has a reduction in productivity
in order to have a significant gain in productivity. So all of
these things sort of work against change, but if you don’t
embrace it and you don’t move forward, you’re just going to
move backward and fall off the back because it occurs every
day.” The management of Webcor understands the risks and
advan- tage of innovation and is fully invested in seeing it
through.
With the firm backing of the top management team, Sarrubi has
used two tactics to persuade his blue-collar workforce to adopt
63. technological innovation. First, Sarrubi searches for and hires
what he calls technology “cheerleaders,” young college
graduates who are more collaborative and who have embraced
technology from their early years as a means of producing
higher quality work in less time. “Once older workers see a
‘greenhorn’—a new construction worker—using tech- nology to
manage a job, the older, senior superintendents begin to see the
benefits of the technol- ogy and start to hop on the wagon,”
Sarrubi confides. This strategy successfully persuaded older
employees to adopt Box, a cloud-based storage platform for the
company’s architectural drawings and financial documents.
Cloud technology has facilitated low-cost collaboration and
electronic document management for both Webcor and its
subcontractors. For a small fee, workers can use the Box
application and an iPad to access drawings and 3-D models,
report problems, submit inspections, and notify all stakeholders
of issues or changes.
Sarrubi recalls how Webcor adopted Box technology: “Our
enterprise adoption of Box grew out of a trial at one job site and
just took off, caught fire, adoption-wise…. All of a sudden,
what started as a small group test project grew into almost one
hundred Box users within a few weeks. The match that lit the
Box fuse was word-of-mouth employee testimonials within the
company.”
In addition to his cheerleader approach, Sarrubi also makes sure
that working with the new technology is “as easy as using
Amazon.” Cost, scalability, and return-on-investment are
important factors the company considers when making IT
decisions, but end-user preference is also a big factor in what
technologies the company adopts. When deciding between
different technology solutions, Sarrubi tells Webcor’s top
management to “slip on the user’s boots and walk a mile.” That
he feels will lead to the best IT choice.
Discussion Questions
1. How has Webcor used technology to support project
management in the construction field?
64. 2. List the main lessons IT managers can learn from Webcor
Builders about the successful adop- tion of new technologies.
3. Webcor bought an application called PlanGrid to mark up
construction blueprints on iPads. PlanGrid can be used when the
workers are offline and later syncs up with files on the Box
platform. Webcor frequently follows this approach of buying
applications and then building application programming
interfaces (APIs) to connect these programs to its main
enterprise systems. What are the advantages and disadvantages
of this IT development process?
92
Chapter 3
4. How might developing whole IT systems themselves, rather
than adopting already developed solutions and integrating them
using APIs, change Webcor’s ability to encourage IT adoption?
5. What obstacles do companies face when developing
customized IT systems themselves? Under what circumstances
does it make sense?
Sources: Webcor Builders, www.webcor.com, accessed October
5, 2014; “Webcor
Builders Standardizes on Vico Office for Virtual Construction,”
Vico Software, June 9, 2011, www
.vicosoftware.com/0/webcor-builders-standardizes-on-vico-
office-for-virtual-construction/tabid/250240
/Default.aspx; Florentine, Sharon, “Construction Company CIO
Builds a Better Business with the Cloud,” CIO, August 1, 2014,
www.cio.com/article/2459507/leadership-
65. management/construction
-company-cio-builds-a-better-business-with-the-cloud.html;
“Webcore Builders Named as 2014 Contractor of the Year,”
Market Watch—PR Newswire, August 6, 2014,
www.marketwatch.com
/story/webcor-builders-named-as-2014-contractor-of-the-year-
2014-08-06; Geron, Tomio, “Webcor Moves Construction
Industry to the Cloud,” Forbes, August 21, 2013,
www.forbes.com/sites
/tomiogeron/2013/08/21/webcor-moves-construction-industry-
to-the-cloud/; Green, Laura, “Andy Ball Leads Webcor Builders
into a New Age of Construction,” Smart Business, September 1,
2011, www.sbnonline.com/article/andy-ball-leads-webcor-
builders-into-a-new-age-of-construction/.
NOTES
Sources for the opening vignette:
Rushton, Katherine, “BBC Ditches Siemens from £80m DMI
Scheme,” BBC, December 10, 2009, www
.broadcastnow.co.uk/news/broadcasters/bbc-ditches-siemens-
from-80m-dmi-scheme/5008953. article; Glick, Bryan, “The
BBC DMI Project—What Went Wrong?” ComputerWeekly.com,
February 5, 2014,
www.computerweekly.com/news/2240213773/The-BBC-DMI-
project-what-went-wrong; Glick, Bryan, “Lack of Business and
IT Engagement Led to BBC DMI Failure, Say MPs,”
ComputerWeekly.com, April 10, 2014,
www.computerweekly.com/news/2240217918/Lack-of
-business-and-IT-engagement-led-to-BBC-DMI-project-being-a-
complete-failure-say-MPs; “Digital Media Initiative,
Memorandum prepared by the Comptroller and Auditor General
presented to the BBC Trust, National Audit Office, British
Broadcasting Corporation—Digital Media Initiative,” January
2014, www.nao.org.uk/wp-content/uploads/2015/01/BBC-
66. Digital-Media-Initiative.pdf.
1 “CHAOS Manifesto 2013; Think Big, Act Small,” The
Standish Group, www.versionone.com
/assets/img/files/CHAOSManifesto2013.pdf, accessed June 11,
2014.
2 “PMI’s Pulse of the Profession,” Project Management
Institute, www.pmi.org/Learning/Pulse
.aspx, accessed September 20, 2014.
3 Hamel, Gary and Prahalad, C.K., “The Core Competence of
the Corporation,” Harvard Business Review, Volume 68, no. 3,
pages 79–93, May–June 1990.
4 Krigsman, Michael, “California Abandons $2 Billion Court
Management System,” Zdnet, April
2, 2012, www.zdnet.com/blog/projectfailures/california-
abandons-2-billion-court-management
-system/15363.
5 Brino, Anthony, “CGI to Build Vermont’s HIX,” Government
Health IT, December 20, 2012,
www.govhealthit.com/news/vermont-sign-hix-it-contract-cgi.
6 Stein, Andrew, “Builder of State’s Health Care Exchange
Misses Key Deadlines,” vtdigger.org, September 27, 2013,
http://vtdigger.org/2013/09/27/builder-states-health-care-
exchange
-misses-key-deadliness/.
Project Management
7 Goswami, Neal, “State, CGI Sign Amended Contract with
New Timetable and Penalties,”
Vermont Press Bureau, April 3, 2014,
www.vermontpressbureau.com/state-cgi-sign-amended
-contract-with-new-timeline-and-penalties/.
8 True, Morgan, “CGI Misses Vermont Health Connect
Deadline Again,” VermontBiz, May 21, 2014,
www.vermontbiz.com/news/may/cgi-misses-vermont-health-
connect-deadline-again.
67. 93
9 Remsen, Nancy, “Health Site Contractor Misses Deadline,
Again,” Burlington Free Press, June
10, 2014,
www.burlingtonfreepress.com/story/news/local/2014/06/06/heal
th-site-contractor
-misses-deadline/10090537/.
10 Parker, Bruce, “Vermont Fires Creator of Its ‘Unacceptable,’
Glitchy ObamaCare Site,” Fox News, August 5, 2014,
www.foxnews.com/politics/2014/08/05/vermont-fires-creator-its
-unacceptable-glitchy-obamacare-site/.
11 Browning, Lynnley, “Thanks for Nothing: Obamacare
Website Bunglers Fired,” Newsweek, August 6, 2014,
www.newsweek.com/thanks-nothing-obamacare-website-
bunglers-fired
-263205.
12 Fitzpatrick, Alex, “Apple Has an iPhone Headache, but It
Won’t Last Long,” Time, September 24, 2014,
http://time.com/3426561/apple-iphone-6-plus-ios-8-problems/.
13 Brown, James, “6 Things to Remember When Projects Spiral
Out of Control,” SAP Community
Network, September 27, 2013, http://scn.sap.com/community/it-
management/blog/2013
/09/27/6-things-to-remember-when-projects-spiral-out-of-
control.
14 Tuckman, Bruce, “Developmental Sequence in Small
Groups,” Psychological Bulletin, Volume 63, pages 384–389,
1965.
15 “Lead Integrator Atos Successfully Completes Delivery of
World’s Biggest IT Sports Contract for
Sochi 2014 Games,” Atos, February