SAP Solution Manager
Change Request Management
Using Urgent Correction with Change Request Management
http://www.linkedin.com/in/solutionmanager
Wenceslao Lacaze
2. Change Request Management – Urgent Correction Lifecycle Management
Table of Contents
Author Bio Versioning .......................................................................................................................................................3
Author Bio ..............................................................................................................................................................................3
Landscape Preparation: ....................................................................................................................................................4
Users Preparation: ..............................................................................................................................................................4
Project Preparation.............................................................................................................................................................4
Cycle overview......................................................................................................................................................................5
Create the Change Request .........................................................................................................................................5
Aprove the Change Request........................................................................................................................................7
Start the corrections ......................................................................................................................................................8
Release the modifictation to test ........................................................................................................................... 11
Start the Testing Phase.............................................................................................................................................. 12
Release to Production ................................................................................................................................................ 14
Confirm the Correction.............................................................................................................................................. 15
Complete the Cycle...................................................................................................................................................... 16
See the log....................................................................................................................................................................... 17
SAP-SOLMAN-CHARM-UrgentCorrection-v2.0.doc Page 2 of 18
3. Change Request Management – Urgent Correction Lifecycle Management
Author Bio Versioning
Version Change Date
1.0 Original 10/06/2008
2.0 Webpage Link. 23/06/2008
Author Bio
My name is Wenceslao Lacaze and I’ve been working as a SAP basis
Administrator and Solution Manager Consultant for the last 8 years.
I’m a Techno-Functional SAP Solution Manager Subject Matter Expert (SME), I
Design, Build and Implement the product using “Run Sap” Methodology.
I have developed a very extended experience with medium and large scaled
SAP installations in several (multi)national environments.
I am based in Argentina, but work all around the World.
I work directly for clients or via an agency.
I do speak Spanish, Italian and English fluently.
You can contact me at:
Email: wlacaze@gmail.com
http://www.linkedin.com/in/solutionmanager
You can found more papers at :
http://wlacaze.googlepages.com/home
SAP-SOLMAN-CHARM-UrgentCorrection-v2.0.doc Page 3 of 18
4. Change Request Management – Urgent Correction Lifecycle Management
Landscape Preparation:
For this Demo we use 3 client inside Solution Manager
801 Development
802 Quality
803 Productive
Users Preparation:
We create 5 diferent users and profiles
Creates and confirm the Change Request
Categorizes, Approve and monitors Change Request.
Implements a change, and hands it over to the Tester
Test changes and ajust the Change Document Status
Manages and coordinates software logistics
Project Preparation
We create a project and 1 Maintenace cycle
SAP-SOLMAN-CHARM-UrgentCorrection-v2.0.doc Page 4 of 18
5. Change Request Management – Urgent Correction Lifecycle Management
Cycle overview
Create the Change Request
The Requester logon to SM and run the transaction CRMD_ORDER.
Click in the Button “Urgent Correction”, if you don’t have add manually in “Extra Settings
Specific Push Button 1 = SDHF
SAP-SOLMAN-CHARM-UrgentCorrection-v2.0.doc Page 5 of 18
6. Change Request Management – Urgent Correction Lifecycle Management
This is the Main Change Request Window.
For create a Urgent Correction you need to identify some information:
• Description
• Change Manager
• It Operator
• Current Processor
• Ibase/Component
• Description of Change
• Reason of Change
• Effect on the System
Then Save
SAP-SOLMAN-CHARM-UrgentCorrection-v2.0.doc Page 6 of 18
7. Change Request Management – Urgent Correction Lifecycle Management
Aprove the Change Request
The Change Manager logon to the system and run the transaction CRM_DNO_MONITOR
The system show all the Transaction open, The Change Manager (CHM) double click over the
transacion 80000163.
The system show this warning.
The CHANGE MANAGER read the Urgent correction document and select if Approve or Withdraw
the document, in this sample we aprove putting the document in “In Development” the task.
SAP-SOLMAN-CHARM-UrgentCorrection-v2.0.doc Page 7 of 18
8. Change Request Management – Urgent Correction Lifecycle Management
When the CHANGE MANAGERsave, the system create 2 transport in the development system, 1
for Customizing, 1 for Workbench, SOLUTION MANAGER ask for the Request Owner, Short
description and the Task Employee,(Ussualy the developer)
When we save, the document status change to “In Development”.
Start the corrections
Tthe Developer logon to SOLUTION MANAGER and open the Urgent Correction 8000000163.
Inside the Tasklist select “Logon to System”
Inside the Development system(SMR-801) , the developer make some change and Save.
SAP-SOLMAN-CHARM-UrgentCorrection-v2.0.doc Page 8 of 18
9. Change Request Management – Urgent Correction Lifecycle Management
Make a Change
The Satellite System (SM4-801) ask for a request,
SAP-SOLMAN-CHARM-UrgentCorrection-v2.0.doc Page 9 of 18
10. Change Request Management – Urgent Correction Lifecycle Management
The Developer select the request SM4K900047 Created for CHMANAGER with the TASK
SMK4900048 for DEVELOPER
Then the Developer release his Task SM4K900048 , You can see that the TASK is for user
Developer and the Transport if for user Chmanager.
Then the Developer return to Solution Manager and in “Test Instruction” put the task for the
Tester
SAP-SOLMAN-CHARM-UrgentCorrection-v2.0.doc Page 10 of 18
11. Change Request Management – Urgent Correction Lifecycle Management
Release the modifictation to test
Then the Change Manager go to the TASKLIST and set “Release Transport Requests”.
The system show the Transport request for select the releated. (1 for Customizing and 1 for
Workbench)
SAP-SOLMAN-CHARM-UrgentCorrection-v2.0.doc Page 11 of 18
12. Change Request Management – Urgent Correction Lifecycle Management
The Change Manager Select “Pass Correction to Test to move the Urgent Correction to QA
Solution Manager in automatic way start the import in QA
Start the Testing Phase
The Tester logon to Solution Manager and open the Urgent Correction 800000163 and Read the
Test Instrucction , then use the TASKLIST for connect to the TEST system.
SAP-SOLMAN-CHARM-UrgentCorrection-v2.0.doc Page 12 of 18
13. Change Request Management – Urgent Correction Lifecycle Management
In the TEST System check the value modificated before.
The Tester return to Solution Manager and write the Test Report, then in the TASKLIST select
“Confirm Successful Test”
SAP-SOLMAN-CHARM-UrgentCorrection-v2.0.doc Page 13 of 18
14. Change Request Management – Urgent Correction Lifecycle Management
Release to Production
The Change Manager logon in Solution Manager and in the TASKLIST select “Released for
Production”
The IT Operator logon to Solution Manager and in the TASKLIST select “Import Correction to
Production System”.
The System start the import
SAP-SOLMAN-CHARM-UrgentCorrection-v2.0.doc Page 14 of 18
15. Change Request Management – Urgent Correction Lifecycle Management
Confirm the Correction
The REQUESTER logon in SOLUTION MANAGER and in the TASKLIST Select “Logon to System” to
logon in the productive enviroment for check the modification.
In the Productive enviroment check the values.
The Requester return to Solution Manager and select “Confirm Correction” in the TASKLIST
SAP-SOLMAN-CHARM-UrgentCorrection-v2.0.doc Page 15 of 18
16. Change Request Management – Urgent Correction Lifecycle Management
Complete the Cycle
The CHANGE MANAGERselect in the TASKLIST “Complete Correction”
SOLUTION MANAGER Show a warning for complete the Urgent Correction
SOLUTION MANAGER show the check of all the Task List.
SAP-SOLMAN-CHARM-UrgentCorrection-v2.0.doc Page 16 of 18
17. Change Request Management – Urgent Correction Lifecycle Management
Now the Urgent Correction is in Status Completed.
See the log
Solution Manager create a log for all the task during the change management cycle.
Full Text
General Note REQUESTER 04.11.2007 15:34:19
Task list created in SAP Change Manager
Task list H000000022 created in SAP Change Manager
Description of Change REQUESTER 04.11.2007 15:42:15
Update T005A
Reason for Change REQUESTER 04.11.2007 15:47:57
Update the information in Table T005A for TAX
Effect on System(s) REQUESTER 04.11.2007 15:52:39
Work with old information
General Note CHMANAGER 04.11.2007 15:57:23
The status was set to the value 'In Development'
General Note CHMANAGER 04.11.2007 16:10:15
Requests SM4K900045 SM4K900047 created
Test Instruction DEVELOPER 04.11.2007 16:22:56
Logon and Check the Table T005A
General Note DEVELOPER 04.11.2007 16:25:38
Imported into subsequent system started
The status was set to the value 'To Be Tested'
Test Instruction DEVELOPER 04.11.2007 16:32:00
See the content of T005A with SM30
Test Report TESTER 04.11.2007 16:32:00
The test was OK
General Note TESTER 04.11.2007 16:32:00
The status was set to the value 'Successfully Tested'
SAP-SOLMAN-CHARM-UrgentCorrection-v2.0.doc Page 17 of 18
18. Change Request Management – Urgent Correction Lifecycle Management
General Note CCHMANAGER 04.11.2007 16:38:03
The status was set to the value 'Authorized for Import'
General Note ITOPERATOR 04.11.2007 16:40:47
Import into production system started
The status was set to the value 'Production'
General Note REQUESTER 04.11.2007 16:45:21
The status was set to the value 'Confirmed'
General Note CHMANAGER 04.11.2007 16:48:22
Task list H000000022 in the SAP Change Manager Completed
SAP-SOLMAN-CHARM-UrgentCorrection-v2.0.doc Page 18 of 18