Passive Fire Protection
Design and Application
CONCEPTS OF FIRE SAFETY
1 EVACUATION
2 PASSIVE CONTAINMENT
3 ACTIVE INTERVENTION
4 ACCESS FOR FIRE FIGHTING AND RESCUE
• 134 – designation of purpose group
• 136 – limits of compartment sizes
• 137 & 138 - compartment floors
• 140 – separation of fire risk areas
• 215 – vertical compartment wall
• 5th
Schedule
UBBL
Compartmentation
• 5th
Schedule
Usage / purpose group limits of dimensions
Hotel / III Height > 28m
Floor area : 2000m2
Volume : 5500m3
Office / IV Height > 28m
Floor area : no limit
Volume : no limit
Shops / V Floor area : 2000m2
Volume : 7000m3
Basement Car Park / VIII Floor area : no limit
Volume : 21,000m3
4,000m2
11,000m3
4,000m2
14,000m3
42,000m3
* UBBL Clause 136 : with Automatic Sprinklers : limits shall be x 2
1800m2 / flr
40000m2 / flr
40,000m2 / flr ( 160,000m2 total )
UBBL 137
Compartment
Floors
UBBL 137
Compartment
Floors
UBBL 138(d)
Compartment floor
UBBL 215
Vertical separation
Shop compartment limit 4,000m2 14,000m3
Compartment A
Compartment B
No limits if
At least 60% area are shops
Less than 280m2 each
Compartment C
Basement compartment volume limit 42,000m2
Compartment A
Compartment B
Compartment C
Separation of vertical ‘shaft’
Compartment D
• 165 – measurements of travel distance
• 166 – minimum 2 separate exits
• 167 – storey exits
• 171 – horizontal exit
• 174 – storey exit to lead to final exit
• 7th
Schedule
UBBL
Exits Considerations
• 7th
Schedule
Maximum Travel Distance Occupant load capacity of exits
Dead End / w Sprinklers ( e.g Stair )
Hotel 10m / 45m 2 pax / room 45
Office 15m / 60m 10m2 per person 60
(gross)
Shops 15m / 45m street level 3m2 / pax 60
upper level 6m2 / pax 60
Basement 15m / 30m* not specified
* Basement garages limited to 30m even with sprinklers
Final exit
Exit route
horizontal exit
storey exit
Travel distance
Travel distanceTravel distance
Final exit
• Occupant load :
• Capacity of Exits :
• Exit width required :
• Total exit width required :
• ‘redundancy’ calculation :
UBBL 168, 175, 176, 177, 181
Exit capacity calculation : Hotel
2 pax X 40 rooms = 80 pax / floor (By law
175)
45 per unit (By law 176 ,7th schedule),
80/45 =1.77, say 1.8 (By law 176, 7th schedule)
1.8 X 550mm = 990mm (By law 176, 7th schedule)
round up to 2 full units (By law 177,181)
therefore, 2 X 550mm = 1100mmSay 1 staircase inaccessible,
2-1 = 1, therefore min exit width = 1100mm
• Occupant load :
• Capacity of Exits :
• Exit width required :
• Total exit width required :
• ‘redundancy’ calculation :
UBBL 168, 175, 176, 177, 181
Exit capacity calculation : Office
Gross floor area = 1800m2, 10 m2/pax,
therefore 1800/10 = 180 pax/floor
60 per unit (By law 176, 7th schedule),
180/60 = 3 (By law 176, 7th schedule)
3 X 550mm = 1650mm (By law 176,7th Sch
Say 1 staircase inaccessible, 2-
1 = 1, therefore the min exit width = 1650mm
• Occupant load :
• Capacity of Exits :
• Exit width required :
• Total exit width required :
• ‘redundancy’ calculation :
UBBL 168, 175, 176, 177, 181
Exit capacity calculation : Shopping Podium
Gross floor area = 40 000 – 4000 (Atrium) = 36
000m2, 6m2 / pax, therefore = 36 000 / 6 = 6000
pax / floor
60 per unit (By law 176, 7th schedule),
6000 / 60 = 100 (By law 176, 7th schedule)
100 X 550mm = 55 000mm (By law 176,7th schedule)
Say 1 staircase inaccessible,
14-1 = 13,
therefore the min exit width = 55 000mm/13 =
4200mm
• Occupant load :
• Capacity of Exits :
• Exit width required :
• Total exit width required :
• ‘redundancy’ calculation :
UBBL 168, 175, 176, 177, 181
Exit capacity calculation : Basement carpark
Gross floor area = 40 000, assume 2 pax/car and
40m2/car, therefore 40 000/40 = 1000 car or 2000
pax/floor
Compare 2000 to 6000 (shopping),
factor reduction = 1/3
55 000 / 3 = 18300 mm (By law 176, 7th schedule)
Say 1 staircase inaccessible,
14-1 = 13,
therefore the min exit width = 18 300mm / 13
= 1400mm
Final exit
Exit route
horizontal exit
storey exit
Final exit
250 pax
400 pax
200 pax 150 pax
300 pax
250 pax
400 pax
400 pax
400 pax
400 pax
200 pax
Exit route to discharge
direct to final exit
Basement
Exit route to discharge
direct to final exit
Travel distance
• UBBL 165
• 7th
Schedule
• Dead end
• initial travel distance before a point where an alternative path
becomes available
• Direct distance
• Stipulates that travel distance must be measured along the actual
path of travel
• Open plan
• Where an actual path of travel cannot be determined, the direct
distance can be measured as a straight line direct to the exit.
Permitted travel distance is then reduced to 2/3.
• 196, 197 - smoke lobbies, protected
lobbies
• 198, 199, 200, 201 – ventilation of stairs
• 229 – fire fighting lobbies
UBBL
Protection of stairs and lobbies
Protection of stairs and lobbies
• Protected Lobby : protected lobby separated
or isolated from fire and smoke infiltration
• Smoke Lobby : a protected lobby primarily to
isolate staircases from smoke infiltration
• ventilated lobby : protected/smoke lobby by
means of natural ventilation from outside
• Fire Fighting Access Lobby : a protected
lobby designed for fire fighting access
PROTECTED / PRESSURISED
> 45o
Room < 6 pax
UBBL 229
60m
UBBL Clause 140
Volume of building > 112,000m3 hence, island site
Hydrants to be located at max. 90m intervals
Thank you
Thank you
Thank you

Más contenido relacionado

La actualidad más candente

Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]JerotichMaswan
 
Building technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSBuilding technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSDigital Space Consultancy Ltd
 
industrialised building systems_achah
industrialised building systems_achahindustrialised building systems_achah
industrialised building systems_achahAisyah Asyikin
 
Deisgn of Fire Escapes
Deisgn of Fire EscapesDeisgn of Fire Escapes
Deisgn of Fire EscapesIshan Garg
 
Building Services Assignment 1
Building Services Assignment 1Building Services Assignment 1
Building Services Assignment 1Nur Zaas
 
Building Services
Building ServicesBuilding Services
Building ServicesEric Lai
 
Building Services Case Study
Building Services Case StudyBuilding Services Case Study
Building Services Case StudyBolin Loong
 
Fire safety guide
Fire safety guideFire safety guide
Fire safety guidesappy2shail
 
Menara Tabung Haji Case Study
Menara Tabung Haji Case StudyMenara Tabung Haji Case Study
Menara Tabung Haji Case StudyLovie Tey
 
Building Services
Building Services Building Services
Building Services Joshua Lee
 
Lift Location, Arrangement and Zoning System
Lift Location, Arrangement and Zoning SystemLift Location, Arrangement and Zoning System
Lift Location, Arrangement and Zoning Systemwan hafizuddin
 
PREFABRICATED TIMBER FRAMING SYSTEM
PREFABRICATED TIMBER FRAMING SYSTEMPREFABRICATED TIMBER FRAMING SYSTEM
PREFABRICATED TIMBER FRAMING SYSTEMFarah Sham
 
Building Service, Taylor's University Lakeside Campus //
Building Service, Taylor's University Lakeside Campus // Building Service, Taylor's University Lakeside Campus //
Building Service, Taylor's University Lakeside Campus // Lovie Tey
 
Intelligent building
Intelligent buildingIntelligent building
Intelligent buildingMohd. Ikhwan
 
B.services case-study
B.services case-studyB.services case-study
B.services case-studyClement Seong
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
IBS design proposal of apartment
IBS design proposal of apartmentIBS design proposal of apartment
IBS design proposal of apartmentJy Chong
 

La actualidad más candente (20)

Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]
 
Building technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSBuilding technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBS
 
industrialised building systems_achah
industrialised building systems_achahindustrialised building systems_achah
industrialised building systems_achah
 
Deisgn of Fire Escapes
Deisgn of Fire EscapesDeisgn of Fire Escapes
Deisgn of Fire Escapes
 
Building Services Assignment 1
Building Services Assignment 1Building Services Assignment 1
Building Services Assignment 1
 
Introduction To Building Services
Introduction To Building ServicesIntroduction To Building Services
Introduction To Building Services
 
Building Services
Building ServicesBuilding Services
Building Services
 
Building Services Case Study
Building Services Case StudyBuilding Services Case Study
Building Services Case Study
 
Fire safety guide
Fire safety guideFire safety guide
Fire safety guide
 
Menara Tabung Haji Case Study
Menara Tabung Haji Case StudyMenara Tabung Haji Case Study
Menara Tabung Haji Case Study
 
Building Services
Building Services Building Services
Building Services
 
Dry & Wet Riser Systems
Dry & Wet Riser SystemsDry & Wet Riser Systems
Dry & Wet Riser Systems
 
Lift Location, Arrangement and Zoning System
Lift Location, Arrangement and Zoning SystemLift Location, Arrangement and Zoning System
Lift Location, Arrangement and Zoning System
 
PREFABRICATED TIMBER FRAMING SYSTEM
PREFABRICATED TIMBER FRAMING SYSTEMPREFABRICATED TIMBER FRAMING SYSTEM
PREFABRICATED TIMBER FRAMING SYSTEM
 
Building Service, Taylor's University Lakeside Campus //
Building Service, Taylor's University Lakeside Campus // Building Service, Taylor's University Lakeside Campus //
Building Service, Taylor's University Lakeside Campus //
 
High rise structure & core
High rise  structure & coreHigh rise  structure & core
High rise structure & core
 
Intelligent building
Intelligent buildingIntelligent building
Intelligent building
 
B.services case-study
B.services case-studyB.services case-study
B.services case-study
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
IBS design proposal of apartment
IBS design proposal of apartmentIBS design proposal of apartment
IBS design proposal of apartment
 

Similar a Passive Fire Protection According to UBBL Malaysia

Case study in uwtc mall of tripeshwor
Case study in uwtc mall of tripeshworCase study in uwtc mall of tripeshwor
Case study in uwtc mall of tripeshworEeelsa shrestha
 
Multicomplex and Commercial Complex
Multicomplex  and Commercial ComplexMulticomplex  and Commercial Complex
Multicomplex and Commercial ComplexRemisha Maharjan
 
3-Means of Egress arabic.ppt
3-Means of Egress arabic.ppt3-Means of Egress arabic.ppt
3-Means of Egress arabic.pptJonah Reyes
 
Shopping mall case study
Shopping mall case studyShopping mall case study
Shopping mall case studyankita20111994
 
Fire safety system of Building.
Fire safety system of Building.Fire safety system of Building.
Fire safety system of Building.Integrated Design
 
Future engineering powerpoint presentation
Future engineering powerpoint presentationFuture engineering powerpoint presentation
Future engineering powerpoint presentationSteve Cartwright
 
ARCHITECTURAL LITERATURE STUDY.pdf
ARCHITECTURAL LITERATURE STUDY.pdfARCHITECTURAL LITERATURE STUDY.pdf
ARCHITECTURAL LITERATURE STUDY.pdfKumarSatyam263033
 
Bs ii-presentation
Bs ii-presentationBs ii-presentation
Bs ii-presentationLee Chun Yee
 
Case study about auditorium
Case study about auditoriumCase study about auditorium
Case study about auditoriumNilanjana Pal
 
• Part Number1910• Part TitleOccupational Safety and Healt.docx
• Part Number1910• Part TitleOccupational Safety and Healt.docx• Part Number1910• Part TitleOccupational Safety and Healt.docx
• Part Number1910• Part TitleOccupational Safety and Healt.docxoswald1horne84988
 
Euroclima presentatie
Euroclima presentatieEuroclima presentatie
Euroclima presentatiecmul
 
Euroclima general presentation
Euroclima general presentationEuroclima general presentation
Euroclima general presentationcmul
 
Provision for fire protection in high rise buildings
Provision for fire protection in high rise buildingsProvision for fire protection in high rise buildings
Provision for fire protection in high rise buildingsAarti Rani
 
IT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHA
IT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHAIT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHA
IT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHAalwayslogo
 
Advanced Design Studio 2
Advanced Design Studio 2Advanced Design Studio 2
Advanced Design Studio 2ong93
 
352967258-Standards-for-Shopping-Mall-Ppt.pdf
352967258-Standards-for-Shopping-Mall-Ppt.pdf352967258-Standards-for-Shopping-Mall-Ppt.pdf
352967258-Standards-for-Shopping-Mall-Ppt.pdfssuser111045
 

Similar a Passive Fire Protection According to UBBL Malaysia (20)

Case study in uwtc mall of tripeshwor
Case study in uwtc mall of tripeshworCase study in uwtc mall of tripeshwor
Case study in uwtc mall of tripeshwor
 
Multicomplex and Commercial Complex
Multicomplex  and Commercial ComplexMulticomplex  and Commercial Complex
Multicomplex and Commercial Complex
 
3-Means of Egress arabic.ppt
3-Means of Egress arabic.ppt3-Means of Egress arabic.ppt
3-Means of Egress arabic.ppt
 
Shopping mall case study
Shopping mall case studyShopping mall case study
Shopping mall case study
 
Fire safety system of Building.
Fire safety system of Building.Fire safety system of Building.
Fire safety system of Building.
 
Future engineering powerpoint presentation
Future engineering powerpoint presentationFuture engineering powerpoint presentation
Future engineering powerpoint presentation
 
ARCHITECTURAL LITERATURE STUDY.pdf
ARCHITECTURAL LITERATURE STUDY.pdfARCHITECTURAL LITERATURE STUDY.pdf
ARCHITECTURAL LITERATURE STUDY.pdf
 
Bs ii-presentation
Bs ii-presentationBs ii-presentation
Bs ii-presentation
 
Case study about auditorium
Case study about auditoriumCase study about auditorium
Case study about auditorium
 
• Part Number1910• Part TitleOccupational Safety and Healt.docx
• Part Number1910• Part TitleOccupational Safety and Healt.docx• Part Number1910• Part TitleOccupational Safety and Healt.docx
• Part Number1910• Part TitleOccupational Safety and Healt.docx
 
Shopping centers
Shopping centersShopping centers
Shopping centers
 
Data
DataData
Data
 
Euroclima presentatie
Euroclima presentatieEuroclima presentatie
Euroclima presentatie
 
Euroclima general presentation
Euroclima general presentationEuroclima general presentation
Euroclima general presentation
 
Provision for fire protection in high rise buildings
Provision for fire protection in high rise buildingsProvision for fire protection in high rise buildings
Provision for fire protection in high rise buildings
 
IT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHA
IT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHAIT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHA
IT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHA
 
Gamma industries
Gamma industries Gamma industries
Gamma industries
 
Advanced Design Studio 2
Advanced Design Studio 2Advanced Design Studio 2
Advanced Design Studio 2
 
352967258-Standards-for-Shopping-Mall-Ppt.pdf
352967258-Standards-for-Shopping-Mall-Ppt.pdf352967258-Standards-for-Shopping-Mall-Ppt.pdf
352967258-Standards-for-Shopping-Mall-Ppt.pdf
 
Plant layout of denim jeans manufacturing unit
Plant layout of denim jeans manufacturing unitPlant layout of denim jeans manufacturing unit
Plant layout of denim jeans manufacturing unit
 

Más de Zhao Wei Kim

ARCHITECT ACT 1967 (ACT 117) & RULES
ARCHITECT ACT 1967 (ACT 117) & RULESARCHITECT ACT 1967 (ACT 117) & RULES
ARCHITECT ACT 1967 (ACT 117) & RULESZhao Wei Kim
 
Social Culture, Arts & People Study in Johor Bahru
Social Culture, Arts & People Study in Johor BahruSocial Culture, Arts & People Study in Johor Bahru
Social Culture, Arts & People Study in Johor BahruZhao Wei Kim
 
Agri-Market Hall in Melaka - UTM M.Arch Final Thesis Design
Agri-Market Hall in Melaka - UTM M.Arch Final Thesis DesignAgri-Market Hall in Melaka - UTM M.Arch Final Thesis Design
Agri-Market Hall in Melaka - UTM M.Arch Final Thesis DesignZhao Wei Kim
 
CITY OF IMPERMANENCE & CHANGE - PAM MASTERCLASS 2016
CITY OF IMPERMANENCE & CHANGE - PAM MASTERCLASS 2016CITY OF IMPERMANENCE & CHANGE - PAM MASTERCLASS 2016
CITY OF IMPERMANENCE & CHANGE - PAM MASTERCLASS 2016Zhao Wei Kim
 
High rise Office Building Technical Design Guidelines in Malaysia
High rise Office Building Technical Design Guidelines in MalaysiaHigh rise Office Building Technical Design Guidelines in Malaysia
High rise Office Building Technical Design Guidelines in MalaysiaZhao Wei Kim
 
Contract implementation and management phase in Malaysia Construction Practice
Contract implementation and management phase in Malaysia Construction PracticeContract implementation and management phase in Malaysia Construction Practice
Contract implementation and management phase in Malaysia Construction PracticeZhao Wei Kim
 
THE DESIGN OF LOUVERS AS SHADING DEVICE & FAÇADE TREATMENT TO OPTIMIZE DAYLI...
THE DESIGN OF LOUVERS  AS SHADING DEVICE & FAÇADE TREATMENT TO OPTIMIZE DAYLI...THE DESIGN OF LOUVERS  AS SHADING DEVICE & FAÇADE TREATMENT TO OPTIMIZE DAYLI...
THE DESIGN OF LOUVERS AS SHADING DEVICE & FAÇADE TREATMENT TO OPTIMIZE DAYLI...Zhao Wei Kim
 
Malaysia's Architect Act 1967 & Architect Rules 1996 (amended 2010)
Malaysia's Architect Act 1967 & Architect Rules 1996 (amended 2010)Malaysia's Architect Act 1967 & Architect Rules 1996 (amended 2010)
Malaysia's Architect Act 1967 & Architect Rules 1996 (amended 2010)Zhao Wei Kim
 
Desire-Value-Learn, A lifelong Adventure of Ourselves
Desire-Value-Learn, A lifelong Adventure of OurselvesDesire-Value-Learn, A lifelong Adventure of Ourselves
Desire-Value-Learn, A lifelong Adventure of OurselvesZhao Wei Kim
 
Architectural & Design Issues in Urban Environment
Architectural & Design Issues in Urban Environment Architectural & Design Issues in Urban Environment
Architectural & Design Issues in Urban Environment Zhao Wei Kim
 
Inter-Farm-Market Proposal Presentation Slides - AVF Summit 2016
Inter-Farm-Market Proposal Presentation Slides - AVF Summit 2016Inter-Farm-Market Proposal Presentation Slides - AVF Summit 2016
Inter-Farm-Market Proposal Presentation Slides - AVF Summit 2016Zhao Wei Kim
 
Urban stream study
Urban stream studyUrban stream study
Urban stream studyZhao Wei Kim
 

Más de Zhao Wei Kim (13)

ARCHITECT ACT 1967 (ACT 117) & RULES
ARCHITECT ACT 1967 (ACT 117) & RULESARCHITECT ACT 1967 (ACT 117) & RULES
ARCHITECT ACT 1967 (ACT 117) & RULES
 
Social Culture, Arts & People Study in Johor Bahru
Social Culture, Arts & People Study in Johor BahruSocial Culture, Arts & People Study in Johor Bahru
Social Culture, Arts & People Study in Johor Bahru
 
Agri-Market Hall in Melaka - UTM M.Arch Final Thesis Design
Agri-Market Hall in Melaka - UTM M.Arch Final Thesis DesignAgri-Market Hall in Melaka - UTM M.Arch Final Thesis Design
Agri-Market Hall in Melaka - UTM M.Arch Final Thesis Design
 
CITY OF IMPERMANENCE & CHANGE - PAM MASTERCLASS 2016
CITY OF IMPERMANENCE & CHANGE - PAM MASTERCLASS 2016CITY OF IMPERMANENCE & CHANGE - PAM MASTERCLASS 2016
CITY OF IMPERMANENCE & CHANGE - PAM MASTERCLASS 2016
 
High rise Office Building Technical Design Guidelines in Malaysia
High rise Office Building Technical Design Guidelines in MalaysiaHigh rise Office Building Technical Design Guidelines in Malaysia
High rise Office Building Technical Design Guidelines in Malaysia
 
Contract implementation and management phase in Malaysia Construction Practice
Contract implementation and management phase in Malaysia Construction PracticeContract implementation and management phase in Malaysia Construction Practice
Contract implementation and management phase in Malaysia Construction Practice
 
THE DESIGN OF LOUVERS AS SHADING DEVICE & FAÇADE TREATMENT TO OPTIMIZE DAYLI...
THE DESIGN OF LOUVERS  AS SHADING DEVICE & FAÇADE TREATMENT TO OPTIMIZE DAYLI...THE DESIGN OF LOUVERS  AS SHADING DEVICE & FAÇADE TREATMENT TO OPTIMIZE DAYLI...
THE DESIGN OF LOUVERS AS SHADING DEVICE & FAÇADE TREATMENT TO OPTIMIZE DAYLI...
 
Malaysia's Architect Act 1967 & Architect Rules 1996 (amended 2010)
Malaysia's Architect Act 1967 & Architect Rules 1996 (amended 2010)Malaysia's Architect Act 1967 & Architect Rules 1996 (amended 2010)
Malaysia's Architect Act 1967 & Architect Rules 1996 (amended 2010)
 
Desire-Value-Learn, A lifelong Adventure of Ourselves
Desire-Value-Learn, A lifelong Adventure of OurselvesDesire-Value-Learn, A lifelong Adventure of Ourselves
Desire-Value-Learn, A lifelong Adventure of Ourselves
 
Architectural & Design Issues in Urban Environment
Architectural & Design Issues in Urban Environment Architectural & Design Issues in Urban Environment
Architectural & Design Issues in Urban Environment
 
Inter-Farm-Market Proposal Presentation Slides - AVF Summit 2016
Inter-Farm-Market Proposal Presentation Slides - AVF Summit 2016Inter-Farm-Market Proposal Presentation Slides - AVF Summit 2016
Inter-Farm-Market Proposal Presentation Slides - AVF Summit 2016
 
Urban stream study
Urban stream studyUrban stream study
Urban stream study
 
Procurement types
Procurement typesProcurement types
Procurement types
 

Último

PPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptxPPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptxRRR Chambers
 
LITERAL RULE OF INTERPRETATION - PRIMARY RULE
LITERAL RULE OF INTERPRETATION - PRIMARY RULELITERAL RULE OF INTERPRETATION - PRIMARY RULE
LITERAL RULE OF INTERPRETATION - PRIMARY RULEsreeramsaipranitha
 
一比一原版西澳大学毕业证学位证书
 一比一原版西澳大学毕业证学位证书 一比一原版西澳大学毕业证学位证书
一比一原版西澳大学毕业证学位证书SS A
 
Essentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmmEssentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmm2020000445musaib
 
一比一原版利兹大学毕业证学位证书
一比一原版利兹大学毕业证学位证书一比一原版利兹大学毕业证学位证书
一比一原版利兹大学毕业证学位证书E LSS
 
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptxCOPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptxRRR Chambers
 
INVOLUNTARY TRANSFERS Kenya school of law.pptx
INVOLUNTARY TRANSFERS Kenya school of law.pptxINVOLUNTARY TRANSFERS Kenya school of law.pptx
INVOLUNTARY TRANSFERS Kenya school of law.pptxnyabatejosphat1
 
Human Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptxHuman Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptxfilippoluciani9
 
pnp FIRST-RESPONDER-IN-CRIME-SCENEs.pptx
pnp FIRST-RESPONDER-IN-CRIME-SCENEs.pptxpnp FIRST-RESPONDER-IN-CRIME-SCENEs.pptx
pnp FIRST-RESPONDER-IN-CRIME-SCENEs.pptxPSSPRO12
 
Transferable and Non-Transferable Property.pptx
Transferable and Non-Transferable Property.pptxTransferable and Non-Transferable Property.pptx
Transferable and Non-Transferable Property.pptx2020000445musaib
 
Shubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptxShubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptxShubham Wadhonkar
 
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptxKEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptxRRR Chambers
 
Negotiable Instruments Act 1881.UNDERSTAND THE LAW OF 1881
Negotiable Instruments Act 1881.UNDERSTAND THE LAW OF 1881Negotiable Instruments Act 1881.UNDERSTAND THE LAW OF 1881
Negotiable Instruments Act 1881.UNDERSTAND THE LAW OF 1881mayurchatre90
 
IBC (Insolvency and Bankruptcy Code 2016)-IOD - PPT.pptx
IBC (Insolvency and Bankruptcy Code 2016)-IOD - PPT.pptxIBC (Insolvency and Bankruptcy Code 2016)-IOD - PPT.pptx
IBC (Insolvency and Bankruptcy Code 2016)-IOD - PPT.pptxRRR Chambers
 
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxxAudience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxxMollyBrown86
 
589308994-interpretation-of-statutes-notes-law-college.pdf
589308994-interpretation-of-statutes-notes-law-college.pdf589308994-interpretation-of-statutes-notes-law-college.pdf
589308994-interpretation-of-statutes-notes-law-college.pdfSUSHMITAPOTHAL
 
THE FACTORIES ACT,1948 (2).pptx labour
THE FACTORIES ACT,1948 (2).pptx   labourTHE FACTORIES ACT,1948 (2).pptx   labour
THE FACTORIES ACT,1948 (2).pptx labourBhavikaGholap1
 
Appeal and Revision in Income Tax Act.pdf
Appeal and Revision in Income Tax Act.pdfAppeal and Revision in Income Tax Act.pdf
Appeal and Revision in Income Tax Act.pdfPoojaGadiya1
 

Último (20)

PPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptxPPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptx
 
LITERAL RULE OF INTERPRETATION - PRIMARY RULE
LITERAL RULE OF INTERPRETATION - PRIMARY RULELITERAL RULE OF INTERPRETATION - PRIMARY RULE
LITERAL RULE OF INTERPRETATION - PRIMARY RULE
 
一比一原版西澳大学毕业证学位证书
 一比一原版西澳大学毕业证学位证书 一比一原版西澳大学毕业证学位证书
一比一原版西澳大学毕业证学位证书
 
Essentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmmEssentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmm
 
一比一原版利兹大学毕业证学位证书
一比一原版利兹大学毕业证学位证书一比一原版利兹大学毕业证学位证书
一比一原版利兹大学毕业证学位证书
 
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptxCOPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
 
INVOLUNTARY TRANSFERS Kenya school of law.pptx
INVOLUNTARY TRANSFERS Kenya school of law.pptxINVOLUNTARY TRANSFERS Kenya school of law.pptx
INVOLUNTARY TRANSFERS Kenya school of law.pptx
 
Human Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptxHuman Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptx
 
pnp FIRST-RESPONDER-IN-CRIME-SCENEs.pptx
pnp FIRST-RESPONDER-IN-CRIME-SCENEs.pptxpnp FIRST-RESPONDER-IN-CRIME-SCENEs.pptx
pnp FIRST-RESPONDER-IN-CRIME-SCENEs.pptx
 
Russian Call Girls Rohini Sector 6 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...
Russian Call Girls Rohini Sector 6 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...Russian Call Girls Rohini Sector 6 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...
Russian Call Girls Rohini Sector 6 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...
 
Transferable and Non-Transferable Property.pptx
Transferable and Non-Transferable Property.pptxTransferable and Non-Transferable Property.pptx
Transferable and Non-Transferable Property.pptx
 
Shubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptxShubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptx
 
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptxKEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
 
Negotiable Instruments Act 1881.UNDERSTAND THE LAW OF 1881
Negotiable Instruments Act 1881.UNDERSTAND THE LAW OF 1881Negotiable Instruments Act 1881.UNDERSTAND THE LAW OF 1881
Negotiable Instruments Act 1881.UNDERSTAND THE LAW OF 1881
 
IBC (Insolvency and Bankruptcy Code 2016)-IOD - PPT.pptx
IBC (Insolvency and Bankruptcy Code 2016)-IOD - PPT.pptxIBC (Insolvency and Bankruptcy Code 2016)-IOD - PPT.pptx
IBC (Insolvency and Bankruptcy Code 2016)-IOD - PPT.pptx
 
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxxAudience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
 
589308994-interpretation-of-statutes-notes-law-college.pdf
589308994-interpretation-of-statutes-notes-law-college.pdf589308994-interpretation-of-statutes-notes-law-college.pdf
589308994-interpretation-of-statutes-notes-law-college.pdf
 
THE FACTORIES ACT,1948 (2).pptx labour
THE FACTORIES ACT,1948 (2).pptx   labourTHE FACTORIES ACT,1948 (2).pptx   labour
THE FACTORIES ACT,1948 (2).pptx labour
 
Russian Call Girls Rohini Sector 7 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...
Russian Call Girls Rohini Sector 7 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...Russian Call Girls Rohini Sector 7 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...
Russian Call Girls Rohini Sector 7 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...
 
Appeal and Revision in Income Tax Act.pdf
Appeal and Revision in Income Tax Act.pdfAppeal and Revision in Income Tax Act.pdf
Appeal and Revision in Income Tax Act.pdf
 

Passive Fire Protection According to UBBL Malaysia

  • 2.
  • 3. CONCEPTS OF FIRE SAFETY 1 EVACUATION 2 PASSIVE CONTAINMENT 3 ACTIVE INTERVENTION 4 ACCESS FOR FIRE FIGHTING AND RESCUE
  • 4. • 134 – designation of purpose group • 136 – limits of compartment sizes • 137 & 138 - compartment floors • 140 – separation of fire risk areas • 215 – vertical compartment wall • 5th Schedule UBBL Compartmentation
  • 5. • 5th Schedule Usage / purpose group limits of dimensions Hotel / III Height > 28m Floor area : 2000m2 Volume : 5500m3 Office / IV Height > 28m Floor area : no limit Volume : no limit Shops / V Floor area : 2000m2 Volume : 7000m3 Basement Car Park / VIII Floor area : no limit Volume : 21,000m3 4,000m2 11,000m3 4,000m2 14,000m3 42,000m3 * UBBL Clause 136 : with Automatic Sprinklers : limits shall be x 2
  • 6. 1800m2 / flr 40000m2 / flr 40,000m2 / flr ( 160,000m2 total ) UBBL 137 Compartment Floors UBBL 137 Compartment Floors UBBL 138(d) Compartment floor UBBL 215 Vertical separation
  • 7. Shop compartment limit 4,000m2 14,000m3 Compartment A Compartment B No limits if At least 60% area are shops Less than 280m2 each Compartment C
  • 8. Basement compartment volume limit 42,000m2 Compartment A Compartment B Compartment C Separation of vertical ‘shaft’ Compartment D
  • 9. • 165 – measurements of travel distance • 166 – minimum 2 separate exits • 167 – storey exits • 171 – horizontal exit • 174 – storey exit to lead to final exit • 7th Schedule UBBL Exits Considerations
  • 10. • 7th Schedule Maximum Travel Distance Occupant load capacity of exits Dead End / w Sprinklers ( e.g Stair ) Hotel 10m / 45m 2 pax / room 45 Office 15m / 60m 10m2 per person 60 (gross) Shops 15m / 45m street level 3m2 / pax 60 upper level 6m2 / pax 60 Basement 15m / 30m* not specified * Basement garages limited to 30m even with sprinklers
  • 11. Final exit Exit route horizontal exit storey exit Travel distance Travel distanceTravel distance Final exit
  • 12. • Occupant load : • Capacity of Exits : • Exit width required : • Total exit width required : • ‘redundancy’ calculation : UBBL 168, 175, 176, 177, 181 Exit capacity calculation : Hotel 2 pax X 40 rooms = 80 pax / floor (By law 175) 45 per unit (By law 176 ,7th schedule), 80/45 =1.77, say 1.8 (By law 176, 7th schedule) 1.8 X 550mm = 990mm (By law 176, 7th schedule) round up to 2 full units (By law 177,181) therefore, 2 X 550mm = 1100mmSay 1 staircase inaccessible, 2-1 = 1, therefore min exit width = 1100mm
  • 13. • Occupant load : • Capacity of Exits : • Exit width required : • Total exit width required : • ‘redundancy’ calculation : UBBL 168, 175, 176, 177, 181 Exit capacity calculation : Office Gross floor area = 1800m2, 10 m2/pax, therefore 1800/10 = 180 pax/floor 60 per unit (By law 176, 7th schedule), 180/60 = 3 (By law 176, 7th schedule) 3 X 550mm = 1650mm (By law 176,7th Sch Say 1 staircase inaccessible, 2- 1 = 1, therefore the min exit width = 1650mm
  • 14. • Occupant load : • Capacity of Exits : • Exit width required : • Total exit width required : • ‘redundancy’ calculation : UBBL 168, 175, 176, 177, 181 Exit capacity calculation : Shopping Podium Gross floor area = 40 000 – 4000 (Atrium) = 36 000m2, 6m2 / pax, therefore = 36 000 / 6 = 6000 pax / floor 60 per unit (By law 176, 7th schedule), 6000 / 60 = 100 (By law 176, 7th schedule) 100 X 550mm = 55 000mm (By law 176,7th schedule) Say 1 staircase inaccessible, 14-1 = 13, therefore the min exit width = 55 000mm/13 = 4200mm
  • 15. • Occupant load : • Capacity of Exits : • Exit width required : • Total exit width required : • ‘redundancy’ calculation : UBBL 168, 175, 176, 177, 181 Exit capacity calculation : Basement carpark Gross floor area = 40 000, assume 2 pax/car and 40m2/car, therefore 40 000/40 = 1000 car or 2000 pax/floor Compare 2000 to 6000 (shopping), factor reduction = 1/3 55 000 / 3 = 18300 mm (By law 176, 7th schedule) Say 1 staircase inaccessible, 14-1 = 13, therefore the min exit width = 18 300mm / 13 = 1400mm
  • 16. Final exit Exit route horizontal exit storey exit Final exit 250 pax 400 pax 200 pax 150 pax 300 pax 250 pax 400 pax 400 pax 400 pax 400 pax 200 pax
  • 17. Exit route to discharge direct to final exit Basement Exit route to discharge direct to final exit
  • 18. Travel distance • UBBL 165 • 7th Schedule • Dead end • initial travel distance before a point where an alternative path becomes available • Direct distance • Stipulates that travel distance must be measured along the actual path of travel • Open plan • Where an actual path of travel cannot be determined, the direct distance can be measured as a straight line direct to the exit. Permitted travel distance is then reduced to 2/3.
  • 19.
  • 20.
  • 21. • 196, 197 - smoke lobbies, protected lobbies • 198, 199, 200, 201 – ventilation of stairs • 229 – fire fighting lobbies UBBL Protection of stairs and lobbies
  • 22. Protection of stairs and lobbies • Protected Lobby : protected lobby separated or isolated from fire and smoke infiltration • Smoke Lobby : a protected lobby primarily to isolate staircases from smoke infiltration • ventilated lobby : protected/smoke lobby by means of natural ventilation from outside • Fire Fighting Access Lobby : a protected lobby designed for fire fighting access
  • 23.
  • 25.
  • 26. > 45o Room < 6 pax
  • 28.
  • 29. 60m
  • 30. UBBL Clause 140 Volume of building > 112,000m3 hence, island site Hydrants to be located at max. 90m intervals