PLANNING
PLANNING
 Planning involves deciding in advance . . .
What is to be done ?
How it is to be done ?
What order . . . ? In order to achieve the
objectives.
 Planning aims at deciding upon future course
of action whereas schedule depicts when the
planned activities are to be carried, it puts the
plan on calendar.
PLANNING
Forecasting can be described as predicting what the future
will look like, whereas planning predicts what the future
should look like.
PLANNING
Planning for construction projects
 Planning means “looking ahead”
 Should take into consideration the past failure, present needs and
future utilities.
 Ensure proper utilization of human and material resources.
 Ensure proper arrangement of repair of machinery and
equipment.
 Flow of funds.
PRINCIPLES OF PLANNING
 Plan should provide information.
 Plan should be realistic.
Plan should be flexible.
Plan should serve as a basis for project monitoring & controlling
 Plan should be comprehensive.
5
P L A N N I N G F O R C O N S T R U C T I O N P R O J E C T S
PLANNING
ADVANTAGES OF PLANNING
1. Advantages to the Contractors
 Cost control
 Supply of labour
 Actual work
 Work Schedule
 Preconceived plan for the whole job
6
P L A N N I N G F O R C O N S T R U C T I O N P R O J E C T S
2. Advantages to the Clients
 Duration of the project
 Project Budget
PLANNING
PLANNING
PLANNING CONSTRUCTION WORK FORCE
 Manpower planning primarily focuses on determining the size of
the project work force, its structuring into functional groups and
workers teams and scheduling the manpower recruitment to match
the task requirement.
 Identify skill required, establishing productivity standards to
determine the number of workers needed to perform a given job in
the specified time, forecasting of the workers requirements for
accomplishing the project work and finally organising the planned
work force into operating work teams having assigned
programmed tasks.
PLANNING
PLANNING CONSTRUCTION MATERIALS
 Efficient material management for integrated approach covering
materials planning and programming, material purchasing, store
keeping, materials transportation and handling at the site and
disposal of surpluses.
 Provide material of right quantity, right quality, right price from
right source and at right time.
PLANNING
PLANNING CONSTRUCTION EQUIPMENT
 Production task needing equipment include excavating, handling,
transporting, filling, compacting, hoisting, concreting, precasting, plastering,
finishing, trenching and laying of pipes and cables.
 Construction equipment is indispensable in the execution of modern high
cost, time bound massive construction projects.
 Its saves manpower, which is becoming even more costly and demanding.
 It improves the productivity, quality and safety
 Acquisition of equipment ; initial heavy investment but in the whole, it adds
to profitability by reducing the overall costs, provided
it is properly planned, economically procured and effectively
managed.
PLANNING
PLANNING CONSTRUCTION COST
 A project budget reflects the financial plan of operation with specified
goals and the costs expected to be incurred for achieving these.
 The primary purpose of having a budget is to assign financial targets
and resources to each functional group so as to establish some basis
for controlling their performance and to make participants plan with
cost.
 The basis of budget is the project plan and its schedule of work.
 The budget preparation involves structuring of the project functioning
organisation into production, service and administration responsibility
centres, assigning resources with the budgeted cost
necessary to achieve the assigned goals.
 Planning in organizations and public policy is both the organizational
process of creating and maintaining a plan; and the psychological
process of thinking about the activities required to create a desired goal
on some scale.
As such, it is a fundamental property of intelligent behaviour. This thought
process is essential to the creation and refinement of a plan, or integration
of it with other plans, that is, it combines forecasting of developments with
the preparation of scenarios of how to react to them. An important, albeit
often ignored aspect of planning, is the relationship it holds with
forecasting.
PLANNING
CO-ORDINATION & INTERACTION OF THE
CONSTRUCTION TEAM
OWNER
PROJECT
MANAGER
ARCHITECTS/
CONSULTANTS
CONTRACTORMUTUAL
CO-ORDINATION
14
P L A N N I N G F O R C O N S T R U C T I O N P R O J E C T S
Client
Project sponsor
Project manager
Engineer Specialist
Design co-ordination Construction co-ordination of
supply chain
Project team
Design team leader Construction
team
QS Architect Specialist Specialist
Communication link
Contractual link
Project Structure Diagram – Executive Project Management Model
SCHEDULING
 Scheduling means putting the plan on calender basis.
 A project network shows the sequence and interdependencies of
activities, their time, duration and the earliest and the latest
completion time, but this needs to be scheduled to determine
commencement and termination dates of each activity, using
optimum resource or working with resource constraints.
 A time schedule outlines the project work programme; it is the time
table of work.
 Network scheduling methodology is suitable for all types of project.
SCHEDULE
PREPARATION OF SCHEDULE
 Project divided into number of operations.
 Sequence of these operations derived after knowing their
relationship.
 Quantity of work has to be calculated.
 By quantity of work in each operation, time required for activities
calculated.
SCHEDULE
Construction scheduling is a graphical representation which shows the
phasing rate of construction activities with the starting and completion
dates and the sequential relationship among the various activities or
operations in a project so that work can be carried out in an orderly and
effective manner.
DEFINITION OF SCHEDULING
.PREPARATION OF CONSTRUCTION SCHEDULES
The project is divided into number of operations and the
sequences of these operations can be derived after knowing their
relationship properly.
The quantity of work involved in each operation has to be
calculated.
The time required for completion of the project as well as the
different activities are to be calculated. This can be done from the
quantity of work involved and the rate of performing each work.
SCHEDULE
SCHEDULE
USES OF SCHEDULING
It gives the quantity of work involved, labour, materials and
equipment for each stage of work.
The actual progress of the work can be checked.
The project can be carried out in a systematic manner using
scheduling.
ADVANTAGES OF SCHEDULING
 By studying the schedule of any work and the many alternative
methods of execution, we can choose the best one.
 It gives a clear idea regarding the required men, materials and
equipment at different stages of the work.
 Since the starting time of each work is known, proper
arrangements and requirements can be done prior to the starting
of the work.
ADVANTAGES OF SCHEDULING
Resource utilisation is optimised.
Actual progress of the work is monitored with the actual plan.
If there is any delay, proper remedial measures can be taken to
avoid such delays.
Inter-relationship of various activities at different stages is
known; thus we will be able to fix them according to their
priority.
Total duration of the complete project is known.
METHODS OF SCHEDULING
Scheduling can be done by different methods depending on the size of the
project.
METHODSOF
SCHEDULING BAR CHARTS OR
GANTT CHARTS
MILESTONE
CHART
NETWORK
ANALYSIS
BAR CHART / GANTT CHART
A bar chart or bar graph is a chart with rectangular bars
with lengths proportional to the values that they represent.
The bars can be plotted vertically or horizontally.
BAR CHART / GANTT CHART
These types of charts were introduced by
Henry Gantt around 1900 A.D.
A bar chart consists of two co-ordinate axes - one representing the
jobs or activities to be performed and the other representing the time
elapsed.
Each bar represents one specific job or activity of the project.
The beginning and end of each bar represents the time of start and
time of finish of that activity.
The length of the bar represents the time required for the completion
of that job or activity.
The following steps are involved in preparing the bar chart
1. Divide the project into many
activities.
2. List out the activities
3. Find the inter relationship among
these activities
4. Arrange the activities in a systematic
way
5. Calculate the quantity of work and
the time required
6. Draw it according to scale
LIMITATIONS OF BAR CHARTS
(i) They can be used only for small projects.
(ii) It does not show the interdependencies between the various activities in the
project. This is a serious limitation of the bar chart.
(iii) The progress of the work in the project cannot be monitored scientifically.
(iv) Delays in the work cannot be detected.
(v) It does not indicate the critical activities of the project.
(vi) It gives some idea about the physical progress of the project, but the
financial aspect involved is not known i.e., whether the project cost is within the
estimated one or exceeded.
(vii) Bar chart cannot be used as a controlling device by the project manager to
take any timely action.
MILESTONE CHARTS
The milestone chart is a modification over the original bar chart.
In every activity, there are certain key events which are to be carried
out for the completion of the activity. Such key events are called
milestones and they are represented by a square or circle.
These events are those which can be easily identified over the main
bar representing the activity.
It has been noticed that when a particular activity represented by a bar
is very long, the details will be lacking.
 If, however, the activity is broken into a number of sub-activities or
key events, each one of which can be recognised during the progress
of the project, controlling can be done easily and also some
interrelationship between the activities established.
Milestone chart shown
The activity or Job A is divided into 4 key events or milestones, Job
B into 3 milestones and so on. Each milestone can be considered to
be a specific event along the job and is represented by a square.
FIG: MILESTONE CHART
LIMITATIONS OF MILESTONE CHART
Though controlling can be better achieved with the help of the
milestone chart, still it possesses the some deficiency as the bar
chart i.e.; the interdependencies between the milestones is not
shown.
Within an activity, the relationship between two specific milestones
is revealed by the milestone chart but the relationship between and
among milestones contained in different activities is not indicated.
A project has seven distinct activities - A, B, C, D, E, F and G which are to
be performed for its timely and successful completion. The time required
for the completion of these activities are 11, 6, 11, 8, 6, 9 and 16 units
respectively.
1. Draw a bar chart for the project.
2. Calculate the total time required to complete the project.
SOLVE:
The relationship of the activities are as follows:
1. Activities A and B can start simultaneously, since they are independent of each
other.
2. Activity C can start only when activity B is completed.
3. Activity D is independent of C. It starts earlier than C and is also completed
earlier.
4. Activity E starts only when D is completed.
5. Activity F starts when B is completed.
6. Activity G is the last activity and is dependent on the completion of D.
Fig. shows a bar chart for a project which has seven distinct activities
viz; A, B, C, D, E, F and G which are to be performed for its timely
and successful completion. The times required for the completion of
these activities are 11, 6, 11, 8, 6, 9 and 16 units of time respectively.
BAR CHART
0 5 10 15 20 25 30
A
B
C
D
E
F
G
J
O
B
A
C
T
I
V
I
T
I
E
S
T I M E ( U n i t s D a y s )
11 units
6 units
8 units
11 units
9 units
6 units
16 units
2-5-8
3-5-13 2-4-6
4-7-16 7-10-13
1 2
3 7 8
4 6
5
2
1 2
4 6
7 9
5
3
85
3
1 2
3
7
4
5
10
9
6 8 11 15
12 13
14
5 3
1
2
2
4
10
9
6
4 4 6
2 6
2
9
2

Más contenido relacionado

La actualidad más candente

Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt341741357
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of schedulingjmd2011
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Schedulingakashpadole
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Project Management and Process
Project Management and ProcessProject Management and Process
Project Management and ProcessMuhammad Rehman
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project managementJared C. Powell
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringSandeep Kumar
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network DiagramsNicola2903
 
Line of Balance
Line of BalanceLine of Balance
Line of BalanceIJMER
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost ManagementBhuWan Khadka
 

La actualidad más candente (20)

Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Project Planning & Management
Project Planning & ManagementProject Planning & Management
Project Planning & Management
 
Project Management and Process
Project Management and ProcessProject Management and Process
Project Management and Process
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoring
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Line of Balance
Line of BalanceLine of Balance
Line of Balance
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 

Similar a Project management-planning and scheduling

Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdfssuserc0e4e0
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.pptDejeneTsegaye6
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...IRJET Journal
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesSHAZEBALIKHAN1
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Managementsrinivas2036
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Schedulingijtsrd
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3POOJA UDAYAN
 
1.1b Construction (Project) Planning.ppt
1.1b Construction (Project) Planning.ppt1.1b Construction (Project) Planning.ppt
1.1b Construction (Project) Planning.pptravi590686
 
1.1c Construction Planning.ppt
1.1c Construction Planning.ppt1.1c Construction Planning.ppt
1.1c Construction Planning.pptravi590686
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1Ahmad Basim Hamza
 
Module Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docxModule Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docxgilpinleeanna
 
Construction management
Construction managementConstruction management
Construction managementAbhishekR63
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & ScheduleVîñõđ Kůmåř
 

Similar a Project management-planning and scheduling (20)

Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdf
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
 
Unit II.pptx
Unit II.pptxUnit II.pptx
Unit II.pptx
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & Techniques
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Scheduling
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
 
1.1b Construction (Project) Planning.ppt
1.1b Construction (Project) Planning.ppt1.1b Construction (Project) Planning.ppt
1.1b Construction (Project) Planning.ppt
 
PROJECT PLANNING
PROJECT PLANNINGPROJECT PLANNING
PROJECT PLANNING
 
1.1c Construction Planning.ppt
1.1c Construction Planning.ppt1.1c Construction Planning.ppt
1.1c Construction Planning.ppt
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1
 
H1303024956
H1303024956H1303024956
H1303024956
 
Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Network Analysis- CPM ppt..pptx
 
Module Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docxModule Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docx
 
Construction management
Construction managementConstruction management
Construction management
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 

Más de Aditi Garg

WORK BREAKDOWN STRUCTURE, JOB LAYOUT & LINE OF BALANCE
WORK BREAKDOWN STRUCTURE, JOB LAYOUT & LINE OF BALANCEWORK BREAKDOWN STRUCTURE, JOB LAYOUT & LINE OF BALANCE
WORK BREAKDOWN STRUCTURE, JOB LAYOUT & LINE OF BALANCEAditi Garg
 
Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdfAditi Garg
 
Project Management- introduction
Project Management- introductionProject Management- introduction
Project Management- introductionAditi Garg
 
CAT questions - verbal, logical reasoning, quantitative aptitude
CAT questions - verbal, logical reasoning, quantitative aptitudeCAT questions - verbal, logical reasoning, quantitative aptitude
CAT questions - verbal, logical reasoning, quantitative aptitudeAditi Garg
 
Re-thinking market segmentation - Marketing 101
Re-thinking market segmentation - Marketing 101Re-thinking market segmentation - Marketing 101
Re-thinking market segmentation - Marketing 101Aditi Garg
 
Cialdini and Aristotle's Models of persuasion-Apple advertisement
Cialdini and Aristotle's Models of persuasion-Apple advertisementCialdini and Aristotle's Models of persuasion-Apple advertisement
Cialdini and Aristotle's Models of persuasion-Apple advertisementAditi Garg
 
Urban economy literature study
Urban economy literature studyUrban economy literature study
Urban economy literature studyAditi Garg
 
Formal economy of Karkala Town- Urban Design Report
Formal economy of Karkala Town- Urban Design ReportFormal economy of Karkala Town- Urban Design Report
Formal economy of Karkala Town- Urban Design ReportAditi Garg
 
Material study-danpalon polycarbonate sheets
Material study-danpalon polycarbonate sheetsMaterial study-danpalon polycarbonate sheets
Material study-danpalon polycarbonate sheetsAditi Garg
 
Building study report of a residence
Building study report of a residenceBuilding study report of a residence
Building study report of a residenceAditi Garg
 
Building construction-Building detail study report
Building construction-Building detail study reportBuilding construction-Building detail study report
Building construction-Building detail study reportAditi Garg
 
Architecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliationArchitecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliationAditi Garg
 
Architecture- easements and valuations
Architecture- easements and valuationsArchitecture- easements and valuations
Architecture- easements and valuationsAditi Garg
 
Setting up architectural practice
Setting up architectural practiceSetting up architectural practice
Setting up architectural practiceAditi Garg
 
Architects professional liability
Architects professional liabilityArchitects professional liability
Architects professional liabilityAditi Garg
 
Architects act 1972 - COA
Architects act 1972 - COAArchitects act 1972 - COA
Architects act 1972 - COAAditi Garg
 
Professional practice of architects-Role of an architect (COA)
Professional practice of architects-Role of an architect (COA)Professional practice of architects-Role of an architect (COA)
Professional practice of architects-Role of an architect (COA)Aditi Garg
 

Más de Aditi Garg (17)

WORK BREAKDOWN STRUCTURE, JOB LAYOUT & LINE OF BALANCE
WORK BREAKDOWN STRUCTURE, JOB LAYOUT & LINE OF BALANCEWORK BREAKDOWN STRUCTURE, JOB LAYOUT & LINE OF BALANCE
WORK BREAKDOWN STRUCTURE, JOB LAYOUT & LINE OF BALANCE
 
Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdf
 
Project Management- introduction
Project Management- introductionProject Management- introduction
Project Management- introduction
 
CAT questions - verbal, logical reasoning, quantitative aptitude
CAT questions - verbal, logical reasoning, quantitative aptitudeCAT questions - verbal, logical reasoning, quantitative aptitude
CAT questions - verbal, logical reasoning, quantitative aptitude
 
Re-thinking market segmentation - Marketing 101
Re-thinking market segmentation - Marketing 101Re-thinking market segmentation - Marketing 101
Re-thinking market segmentation - Marketing 101
 
Cialdini and Aristotle's Models of persuasion-Apple advertisement
Cialdini and Aristotle's Models of persuasion-Apple advertisementCialdini and Aristotle's Models of persuasion-Apple advertisement
Cialdini and Aristotle's Models of persuasion-Apple advertisement
 
Urban economy literature study
Urban economy literature studyUrban economy literature study
Urban economy literature study
 
Formal economy of Karkala Town- Urban Design Report
Formal economy of Karkala Town- Urban Design ReportFormal economy of Karkala Town- Urban Design Report
Formal economy of Karkala Town- Urban Design Report
 
Material study-danpalon polycarbonate sheets
Material study-danpalon polycarbonate sheetsMaterial study-danpalon polycarbonate sheets
Material study-danpalon polycarbonate sheets
 
Building study report of a residence
Building study report of a residenceBuilding study report of a residence
Building study report of a residence
 
Building construction-Building detail study report
Building construction-Building detail study reportBuilding construction-Building detail study report
Building construction-Building detail study report
 
Architecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliationArchitecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliation
 
Architecture- easements and valuations
Architecture- easements and valuationsArchitecture- easements and valuations
Architecture- easements and valuations
 
Setting up architectural practice
Setting up architectural practiceSetting up architectural practice
Setting up architectural practice
 
Architects professional liability
Architects professional liabilityArchitects professional liability
Architects professional liability
 
Architects act 1972 - COA
Architects act 1972 - COAArchitects act 1972 - COA
Architects act 1972 - COA
 
Professional practice of architects-Role of an architect (COA)
Professional practice of architects-Role of an architect (COA)Professional practice of architects-Role of an architect (COA)
Professional practice of architects-Role of an architect (COA)
 

Último

Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Alex Marques
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementTulsiDhidhi1
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningCIToolkit
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxSaqib Mansoor Ahmed
 

Último (20)

Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing management
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for Learning
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptx
 

Project management-planning and scheduling

  • 2. PLANNING  Planning involves deciding in advance . . . What is to be done ? How it is to be done ? What order . . . ? In order to achieve the objectives.  Planning aims at deciding upon future course of action whereas schedule depicts when the planned activities are to be carried, it puts the plan on calendar.
  • 3. PLANNING Forecasting can be described as predicting what the future will look like, whereas planning predicts what the future should look like.
  • 4. PLANNING Planning for construction projects  Planning means “looking ahead”  Should take into consideration the past failure, present needs and future utilities.  Ensure proper utilization of human and material resources.  Ensure proper arrangement of repair of machinery and equipment.  Flow of funds.
  • 5. PRINCIPLES OF PLANNING  Plan should provide information.  Plan should be realistic. Plan should be flexible. Plan should serve as a basis for project monitoring & controlling  Plan should be comprehensive. 5 P L A N N I N G F O R C O N S T R U C T I O N P R O J E C T S PLANNING
  • 6. ADVANTAGES OF PLANNING 1. Advantages to the Contractors  Cost control  Supply of labour  Actual work  Work Schedule  Preconceived plan for the whole job 6 P L A N N I N G F O R C O N S T R U C T I O N P R O J E C T S
  • 7. 2. Advantages to the Clients  Duration of the project  Project Budget
  • 9. PLANNING PLANNING CONSTRUCTION WORK FORCE  Manpower planning primarily focuses on determining the size of the project work force, its structuring into functional groups and workers teams and scheduling the manpower recruitment to match the task requirement.  Identify skill required, establishing productivity standards to determine the number of workers needed to perform a given job in the specified time, forecasting of the workers requirements for accomplishing the project work and finally organising the planned work force into operating work teams having assigned programmed tasks.
  • 10. PLANNING PLANNING CONSTRUCTION MATERIALS  Efficient material management for integrated approach covering materials planning and programming, material purchasing, store keeping, materials transportation and handling at the site and disposal of surpluses.  Provide material of right quantity, right quality, right price from right source and at right time.
  • 11. PLANNING PLANNING CONSTRUCTION EQUIPMENT  Production task needing equipment include excavating, handling, transporting, filling, compacting, hoisting, concreting, precasting, plastering, finishing, trenching and laying of pipes and cables.  Construction equipment is indispensable in the execution of modern high cost, time bound massive construction projects.  Its saves manpower, which is becoming even more costly and demanding.  It improves the productivity, quality and safety  Acquisition of equipment ; initial heavy investment but in the whole, it adds to profitability by reducing the overall costs, provided it is properly planned, economically procured and effectively managed.
  • 12. PLANNING PLANNING CONSTRUCTION COST  A project budget reflects the financial plan of operation with specified goals and the costs expected to be incurred for achieving these.  The primary purpose of having a budget is to assign financial targets and resources to each functional group so as to establish some basis for controlling their performance and to make participants plan with cost.  The basis of budget is the project plan and its schedule of work.  The budget preparation involves structuring of the project functioning organisation into production, service and administration responsibility centres, assigning resources with the budgeted cost necessary to achieve the assigned goals.
  • 13.  Planning in organizations and public policy is both the organizational process of creating and maintaining a plan; and the psychological process of thinking about the activities required to create a desired goal on some scale. As such, it is a fundamental property of intelligent behaviour. This thought process is essential to the creation and refinement of a plan, or integration of it with other plans, that is, it combines forecasting of developments with the preparation of scenarios of how to react to them. An important, albeit often ignored aspect of planning, is the relationship it holds with forecasting. PLANNING
  • 14. CO-ORDINATION & INTERACTION OF THE CONSTRUCTION TEAM OWNER PROJECT MANAGER ARCHITECTS/ CONSULTANTS CONTRACTORMUTUAL CO-ORDINATION 14 P L A N N I N G F O R C O N S T R U C T I O N P R O J E C T S
  • 15. Client Project sponsor Project manager Engineer Specialist Design co-ordination Construction co-ordination of supply chain Project team Design team leader Construction team QS Architect Specialist Specialist Communication link Contractual link Project Structure Diagram – Executive Project Management Model
  • 16.
  • 18.  Scheduling means putting the plan on calender basis.  A project network shows the sequence and interdependencies of activities, their time, duration and the earliest and the latest completion time, but this needs to be scheduled to determine commencement and termination dates of each activity, using optimum resource or working with resource constraints.  A time schedule outlines the project work programme; it is the time table of work.  Network scheduling methodology is suitable for all types of project. SCHEDULE
  • 19. PREPARATION OF SCHEDULE  Project divided into number of operations.  Sequence of these operations derived after knowing their relationship.  Quantity of work has to be calculated.  By quantity of work in each operation, time required for activities calculated. SCHEDULE
  • 20. Construction scheduling is a graphical representation which shows the phasing rate of construction activities with the starting and completion dates and the sequential relationship among the various activities or operations in a project so that work can be carried out in an orderly and effective manner. DEFINITION OF SCHEDULING
  • 21. .PREPARATION OF CONSTRUCTION SCHEDULES The project is divided into number of operations and the sequences of these operations can be derived after knowing their relationship properly. The quantity of work involved in each operation has to be calculated. The time required for completion of the project as well as the different activities are to be calculated. This can be done from the quantity of work involved and the rate of performing each work. SCHEDULE
  • 22. SCHEDULE USES OF SCHEDULING It gives the quantity of work involved, labour, materials and equipment for each stage of work. The actual progress of the work can be checked. The project can be carried out in a systematic manner using scheduling.
  • 23. ADVANTAGES OF SCHEDULING  By studying the schedule of any work and the many alternative methods of execution, we can choose the best one.  It gives a clear idea regarding the required men, materials and equipment at different stages of the work.  Since the starting time of each work is known, proper arrangements and requirements can be done prior to the starting of the work.
  • 24. ADVANTAGES OF SCHEDULING Resource utilisation is optimised. Actual progress of the work is monitored with the actual plan. If there is any delay, proper remedial measures can be taken to avoid such delays. Inter-relationship of various activities at different stages is known; thus we will be able to fix them according to their priority. Total duration of the complete project is known.
  • 25. METHODS OF SCHEDULING Scheduling can be done by different methods depending on the size of the project. METHODSOF SCHEDULING BAR CHARTS OR GANTT CHARTS MILESTONE CHART NETWORK ANALYSIS
  • 26. BAR CHART / GANTT CHART A bar chart or bar graph is a chart with rectangular bars with lengths proportional to the values that they represent. The bars can be plotted vertically or horizontally.
  • 27. BAR CHART / GANTT CHART These types of charts were introduced by Henry Gantt around 1900 A.D. A bar chart consists of two co-ordinate axes - one representing the jobs or activities to be performed and the other representing the time elapsed. Each bar represents one specific job or activity of the project. The beginning and end of each bar represents the time of start and time of finish of that activity. The length of the bar represents the time required for the completion of that job or activity.
  • 28. The following steps are involved in preparing the bar chart 1. Divide the project into many activities. 2. List out the activities 3. Find the inter relationship among these activities 4. Arrange the activities in a systematic way 5. Calculate the quantity of work and the time required 6. Draw it according to scale
  • 29. LIMITATIONS OF BAR CHARTS (i) They can be used only for small projects. (ii) It does not show the interdependencies between the various activities in the project. This is a serious limitation of the bar chart. (iii) The progress of the work in the project cannot be monitored scientifically. (iv) Delays in the work cannot be detected. (v) It does not indicate the critical activities of the project. (vi) It gives some idea about the physical progress of the project, but the financial aspect involved is not known i.e., whether the project cost is within the estimated one or exceeded. (vii) Bar chart cannot be used as a controlling device by the project manager to take any timely action.
  • 30. MILESTONE CHARTS The milestone chart is a modification over the original bar chart. In every activity, there are certain key events which are to be carried out for the completion of the activity. Such key events are called milestones and they are represented by a square or circle. These events are those which can be easily identified over the main bar representing the activity. It has been noticed that when a particular activity represented by a bar is very long, the details will be lacking.  If, however, the activity is broken into a number of sub-activities or key events, each one of which can be recognised during the progress of the project, controlling can be done easily and also some interrelationship between the activities established.
  • 31. Milestone chart shown The activity or Job A is divided into 4 key events or milestones, Job B into 3 milestones and so on. Each milestone can be considered to be a specific event along the job and is represented by a square. FIG: MILESTONE CHART
  • 32. LIMITATIONS OF MILESTONE CHART Though controlling can be better achieved with the help of the milestone chart, still it possesses the some deficiency as the bar chart i.e.; the interdependencies between the milestones is not shown. Within an activity, the relationship between two specific milestones is revealed by the milestone chart but the relationship between and among milestones contained in different activities is not indicated.
  • 33. A project has seven distinct activities - A, B, C, D, E, F and G which are to be performed for its timely and successful completion. The time required for the completion of these activities are 11, 6, 11, 8, 6, 9 and 16 units respectively. 1. Draw a bar chart for the project. 2. Calculate the total time required to complete the project. SOLVE: The relationship of the activities are as follows: 1. Activities A and B can start simultaneously, since they are independent of each other. 2. Activity C can start only when activity B is completed. 3. Activity D is independent of C. It starts earlier than C and is also completed earlier. 4. Activity E starts only when D is completed. 5. Activity F starts when B is completed. 6. Activity G is the last activity and is dependent on the completion of D.
  • 34. Fig. shows a bar chart for a project which has seven distinct activities viz; A, B, C, D, E, F and G which are to be performed for its timely and successful completion. The times required for the completion of these activities are 11, 6, 11, 8, 6, 9 and 16 units of time respectively. BAR CHART 0 5 10 15 20 25 30 A B C D E F G J O B A C T I V I T I E S T I M E ( U n i t s D a y s ) 11 units 6 units 8 units 11 units 9 units 6 units 16 units
  • 36. 2 1 2 4 6 7 9 5 3 85 3
  • 37. 1 2 3 7 4 5 10 9 6 8 11 15 12 13 14 5 3 1 2 2 4 10 9 6 4 4 6 2 6 2 9 2