SlideShare una empresa de Scribd logo
1 de 34
Refrigeration
and
Air conditioning
Lesson Plan
• Vapour compression refrigeration cycle
• Components of a refrigeration system
• Pressure enthalpy chart
• superheating & sub-cooling
• Heat exchanger
• Coefficient of performance ( COP )
• System Capacity
• Direct and Indirect Expansion System
• Back Pressure Regulating valve
• Types of compressor
• Oil Separator
• Filter/Drier
• Throttling device
• Capacity control Method
Basic refrigeration cycle:
• Heat energy flows from a hot region to a cooler region.
• Vapour Compression Refrigeration System uses a circulating refrigerant
as a medium which
1) absorbs & removes heat from space to be cooled
2) rejects the heat elsewhere (cooler)
Heat energy
Refrigerant flow
cooler
Cooling
water
Cold
room
Vapour Compression System
Low Pressure Side
High Pressure Side
Liquid receiver
Expansion
valve
Compressor
Evaporator
Liquid
Condenser
Heat in
Heat out
Hot Gas
Gas
4 numbers principle components :
(1) Evaporator
(2) Compressor
(3) Condenser
(4) Expansion Valve
Vapour Compression System
Low Pressure Side
High Pressure Side
Liquid receiver
Expansion
valve
Compressor
Evaporator
Liquid
Condenser
Heat in
Heat out
Hot Gas
Gas
EVAPORATOR:
1) The evaporator coils are
located in the compartment to
be cooled.
2) The low pressure liquid
refrigerant ,after passing
through the expansion valve,
expands.
3) Takes in heat from the
surrounding and evaporates.
4) The gas is then sucked up by
the compressor.
Vapour Compression System
Low Pressure Side
High Pressure Side
Liquid receiver
Expansion
valve
Compressor
Evaporator
Liquid
Condenser
Heat in
Heat out
Hot Gas
Gas
COMPRESSOR :
1) Compresses the refrigerant
(gaseous state).
2) Raising its Temperature &
Pressure.
3) Discharges refrigerant to
Condenser.
Vapour Compression System
Low Pressure Side
High Pressure Side
Liquid receiver
Expansion
valve
Compressor
Evaporator
Liquid
Condenser
Heat in
Heat out
Hot Gas
Gas
LIQUEFACTION:
1) Hot refrigerant gas cooled in
the condenser.
2) Condensed liquid refrigerant
flows into a receiver.
3) Then liquid refrigerant flows to
the expansion valve.
Vapour Compression System
Low Pressure Side
High Pressure Side
Liquid receiver
Expansion
valve
Compressor
Evaporator
Liquid
Condenser
Heat in
Heat out
Hot Gas
Gas
EXPANSION:
1) The expansion valve acting as
a regulating valve, limits the
amount of refrigerant flowing
through.
2) Resulting in reduction of
pressure of the liquid and
expansion takes place.
P-H chart ( Pressure – Enthalpy chart )
Sub cooled
liquid
• Pressure – Absolute pressure
Unit : bar , psi
• Enthalpy – Total amount of energy
per unit weight of substance.
Unit : BTU / Lb or kJ / kg
• The lines ,saturated liquid & vapour
respectively are plots of pressure vs
enthalpy for the saturated state of a
given refrigerant.
• This chart is used to understand the
property changes that takes place in
each phase of the cycle.
Saturated liquid line
Saturated vapour
line
Superheated
region
Sub-cooled
region
Liquid –
vapour
mixture
• Enthalpy – Total amount of energy per unit
weight of substance.
Unit : BTU / Lb or kJ / kg
• Entropy – Measure of heat dispersion in a
system divided by temperature.
Unit : BTU / Lb / deg change
or kJ / kg / deg change for a
substance.
Refrigeration Cycle :
Pressure-Enthalpy graph
Ideal Refrigeration Cycle :
Pressure-Enthalpy chart
Superheated
vapour
Sub cooled liquid
Liquid vapour
mixture
Ideal Refrigeration Cycle : Pressure – Enthalpy chart
Enthalpy ( BTU / lbs or KJ / kg )
Pressure(absolute)
P1
P2
1 2
34
Refrigeration Cycle :
Pressure-Enthalpy chart
Non ideal Refrigeration Cycle : Pressure – Enthalpy chart , showing
superheating & sub cooling
Sub cooled liquid Superheated
vapour
Liquid vapour
mixture
Enthalpy ( BTU / lbs or KJ / kg )
Pressure(absolute)
1
4
2
Liquid to Vapour
Transformation in
EVAPORATOR
Throttling at
expansion
valve
Vapour to Liquid
transformation in
CONDENSER
Work done in the
compressor
Liquid vapour
mixture
superheated
Superheated
subcooling 3
Non ideal Refrigeration Cycle : Pressure – Enthalpy chart , showing superheating & sub cooling
Sub cooled liquid
Superheated vapour
Liquid vapour
mixture
Enthalpy ( BTU / lbs or KJ / kg )
Pressure(absolute)
1
34
2Liquid to Vapour
Transformation in
EVAPORATOR
Throttling at
expansion
valve
Vapour to Liquid
transformation in
CONDENSER
Work done in the
compressor
H1 H2 H3
The amount of heat that the refrigerant absorb must equal the cooling load.
(1) Refrigerant cooling load ( F ) = cooling load / ( H2 – H1)
(2) Work done by compressor = F x ( H3 – H2 )
(3) Heat rejected by condenser = F x ( H3 – H1 )
(4) Heat absorbed by evaporator = F x ( H2 – H1 )
Coefficient of Performance (COP) = heat absorbed by refrigerant / Energy required driving
compressor
= ( H2 – H1) / ( H3 – H2)
Pressure-Enthalpy chart
Pressure
( bar )
Enthalpy ( KJ / kg of refrigerant )
Liquid to Vapour
Transformation in
EVAPORATOR at -13 deg C
Vapour to Liquid
transformation in
CONDENSER at 42 deg C
Work done in the
compressor
Throttling at
expansion valve
1
4
1-2 : EVAPORATOR – extraction of heat from room
2-3 : COMPRESSOR – compression work
3-4 : CONDENSER – energy thrown to sea
4-1 : EXPANSION VALVE – throttling at the expansion valve
3
2
16
3.2
150 304 365
For each kg of refrigerant flow ,
Energy extracted from meat room : 304 - 150 = 154 KJ / kg
Work spent on compressor = 365 – 304 = 61 KJ / Kg
Coefficient of Performance ( COP ) =
Energy extracted from room / Energy spent
= 154 / 61 or 2.52
• Pressure – Enthalpy chart , of a practical
cycle (refer to page 8)
• Effects of pressure loss resulting from
friction.
Superheating & Sub-cooling
compressor
condenser
receiver
refrigerant control (expansion valve)
evaporator
Heat exchanger
Saturated liquid
Superheated suction vapour
Saturated suction
vapour
Sub cooled liquid
Improvement in cycle efficiency with a heat exchanger – as compared to another cycle where vapour is
superheated without producing any useful cooling
Page 7
Refrigeration system capacity
• Rate at which system removes heat from.
• Rate depends :
(1) mass of refrigerant circulated per unit time
(2) refrigerating effect per unit mass circulated
(undercooling increases the refrigerating effect)
Two systems employed:
• Direct Expansion System
• Indirect expansion system
aka Brine System
Direct Expansion System : Provisional Refrigeration System
Condenser
Cooling water in / out
Fan/blower
expansion valve
Solenoid
stop valve
Thermostat
Temperature
sensor
MEAT ROOM
LP pressure switch
HP pressure switch
Refrigerant
compressor
Sight glass
Drier
Evaporator
Capillarytube
: Refrigerant flow
From FISH ROOM
From VEGETABLE
ROOM
To FISH ROOM
To VEGETABLE
ROOM
Oil separator
Oil return to
compressor sump
Bulb
T1
T2
receiver
Oil pressure switch
Purging
line
LP pressure gauge
Oil pressure gauge
HP pressure gauge
Back pressure
regulating valve
Indirect Expansion (Brine System)
Condenser / Receiver
Cooling water in / out
expansion valve
Solenoid
stop valve
Thermostat
Temperature
sensor
LP pressure switch
HP pressure switch
Refrigerant
compressor
Sight glass
Drier
Evaporator
Capillarytube
: Refrigerant flow
Oil separator
Oil return to
compressor sump
Bulb
T1
T2
pump
Brine
header
tank
Secondary refrigerant
to various
compartment
Oil pressure switch
Back pressure regulating valve
• Normally fitted to higher temperature rooms, ie the vegetable room
not for the fish room or meat room.
Purpose :
• Act as system balancing diverters –
a) When all solenoid valves are opened, the valve restrict liquid flowing into the vegetable room &
therefore deliver the bulk to the colder rooms.
b) Limits the pressure drops across the expansion valve by giving a set minimum pressure in the
evaporator coil. Prevents cold air blowing directly onto delicate vegetables.
Refrigerant Compressor types:
• Reciprocating
• Rotary
• Centrifugal
• Screw
Oil Separator
Gas from
compressor
Float
Oil to
compressor
crankcase
Oil
Gas to
condenser
Internal
baffles
Page 12
Liquid-line Filter / Drier
Desiccant
(dehydrating material)
Refrigerant in Clean,dry refrigerant
Fine filter to remove small
particles
Course filter to remove
large particles
Felt pad
Drying agent : silica gel
or activated alumina
Page 13
Condenser:
• Air cooled type – up to 5 hp
• Large capacity – shell & tube type , SW
cool
• Tubes – aluminium brass (option ext. fins)
• Water velocity < 2.5 m/s minimise erosion
• Anodes – avoid corrosion non ferrous
metals
Throttling device:
• Metering of refrigerant – rate suitable to maintain
designed operating pressures at different load.
• Maintain pressure differential between HP & LP side.
The pressure of the refrigerant is reduced as it passes through the small orifice
of the throttling device. With the reduction in pressure, the corresponding
boiling point of the liquid is reduced.
Types of throttling devices:
• Hand expansion valves
• Automatic constant pressure expansion valve
• Thermostatic expansion valve
• Externally equalized expansion valve
• Pressure balancing expansion valve
• Expansion valves with centrifugal type distributors
• Flow control device for flooded evaporators
Expansion valve
• automatic expansion valve
• thermostatic expansion valve
• externally equalised thermostatic expansion va
Automatic expansion valve
Page 18
Thermostatic expansion valve
(TEV)
Page 19
External equalised thermostatic
expansion valve
Page 20
Capacity control methods
• Manual start/stop
• Speed variation
• Cylinder unloading
reciprocating compressor
• Suction side throttling
centrifugal compressor
• Inlet guide vane
centrifugal compressor
• Hot gas bypass
• Compressor in parallel
• Slide valve
Screw compressor - control
effective working length of rotor.
To maintain constant temperature, a constant pressure must be present in the
EVAPORATOR.
Ideally, the compressor should remove from the EVAPORATOR exactly the
volume of refrigerant that boils off in it. Change in loading : change in quantity
of boiling off the refrigerant.
Unloading device
Screw compressor
LOBES
DRIVE
SHAFT
Min
BYPASS
GAS OUTLET
DISCHARGE
PORT
INLET
UNLOADING
PISTON
Max
SLIDE VALVECYLINDER
NORMAL LOADING
Page 12
Screw compressor
LOBES
DRIVE
SHAFT
Min
BYPASS
GAS OUTLET
DISCHARGE
PORT
INLET
UNLOADING
PISTON
Max
SLIDE VALVECYLINDER
REDUCE LOADING

Más contenido relacionado

Más de Arafat Hossain

Más de Arafat Hossain (8)

Pump survey & line bearing
Pump survey & line bearingPump survey & line bearing
Pump survey & line bearing
 
He1
He1He1
He1
 
Directional valve
Directional valveDirectional valve
Directional valve
 
Central cooling system
Central cooling systemCentral cooling system
Central cooling system
 
4.operational faults
4.operational faults4.operational faults
4.operational faults
 
2.ozone & reffrigerant
2.ozone & reffrigerant2.ozone & reffrigerant
2.ozone & reffrigerant
 
Sg solas
Sg solasSg solas
Sg solas
 
Damages due bad weather
Damages due bad weatherDamages due bad weather
Damages due bad weather
 

Último

Electrical shop management system project report.pdf
Electrical shop management system project report.pdfElectrical shop management system project report.pdf
Electrical shop management system project report.pdfKamal Acharya
 
Diploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdfDiploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdfJNTUA
 
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdfInvolute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdfJNTUA
 
Supermarket billing system project report..pdf
Supermarket billing system project report..pdfSupermarket billing system project report..pdf
Supermarket billing system project report..pdfKamal Acharya
 
analog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptxanalog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptxKarpagam Institute of Teechnology
 
Introduction to Arduino Programming: Features of Arduino
Introduction to Arduino Programming: Features of ArduinoIntroduction to Arduino Programming: Features of Arduino
Introduction to Arduino Programming: Features of ArduinoAbhimanyu Sangale
 
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...Lovely Professional University
 
Operating System chapter 9 (Virtual Memory)
Operating System chapter 9 (Virtual Memory)Operating System chapter 9 (Virtual Memory)
Operating System chapter 9 (Virtual Memory)NareenAsad
 
Interfacing Analog to Digital Data Converters ee3404.pdf
Interfacing Analog to Digital Data Converters ee3404.pdfInterfacing Analog to Digital Data Converters ee3404.pdf
Interfacing Analog to Digital Data Converters ee3404.pdfragupathi90
 
Final DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manualFinal DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manualBalamuruganV28
 
E-Commerce Shopping using MERN Stack where different modules are present
E-Commerce Shopping using MERN Stack where different modules are presentE-Commerce Shopping using MERN Stack where different modules are present
E-Commerce Shopping using MERN Stack where different modules are presentjatinraor66
 
RM&IPR M5 notes.pdfResearch Methodolgy & Intellectual Property Rights Series 5
RM&IPR M5 notes.pdfResearch Methodolgy & Intellectual Property Rights Series 5RM&IPR M5 notes.pdfResearch Methodolgy & Intellectual Property Rights Series 5
RM&IPR M5 notes.pdfResearch Methodolgy & Intellectual Property Rights Series 5T.D. Shashikala
 
15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon15-Minute City: A Completely New Horizon
15-Minute City: A Completely New HorizonMorshed Ahmed Rahath
 
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024EMMANUELLEFRANCEHELI
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGKOUSTAV SARKAR
 
5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...archanaece3
 
Introduction to Artificial Intelligence and History of AI
Introduction to Artificial Intelligence and History of AIIntroduction to Artificial Intelligence and History of AI
Introduction to Artificial Intelligence and History of AISheetal Jain
 
Electrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission lineElectrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission lineJulioCesarSalazarHer1
 
Lesson no16 application of Induction Generator in Wind.ppsx
Lesson no16 application of Induction Generator in Wind.ppsxLesson no16 application of Induction Generator in Wind.ppsx
Lesson no16 application of Induction Generator in Wind.ppsxmichaelprrior
 
BURGER ORDERING SYSYTEM PROJECT REPORT..pdf
BURGER ORDERING SYSYTEM PROJECT REPORT..pdfBURGER ORDERING SYSYTEM PROJECT REPORT..pdf
BURGER ORDERING SYSYTEM PROJECT REPORT..pdfKamal Acharya
 

Último (20)

Electrical shop management system project report.pdf
Electrical shop management system project report.pdfElectrical shop management system project report.pdf
Electrical shop management system project report.pdf
 
Diploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdfDiploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdf
 
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdfInvolute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
 
Supermarket billing system project report..pdf
Supermarket billing system project report..pdfSupermarket billing system project report..pdf
Supermarket billing system project report..pdf
 
analog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptxanalog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptx
 
Introduction to Arduino Programming: Features of Arduino
Introduction to Arduino Programming: Features of ArduinoIntroduction to Arduino Programming: Features of Arduino
Introduction to Arduino Programming: Features of Arduino
 
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
 
Operating System chapter 9 (Virtual Memory)
Operating System chapter 9 (Virtual Memory)Operating System chapter 9 (Virtual Memory)
Operating System chapter 9 (Virtual Memory)
 
Interfacing Analog to Digital Data Converters ee3404.pdf
Interfacing Analog to Digital Data Converters ee3404.pdfInterfacing Analog to Digital Data Converters ee3404.pdf
Interfacing Analog to Digital Data Converters ee3404.pdf
 
Final DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manualFinal DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manual
 
E-Commerce Shopping using MERN Stack where different modules are present
E-Commerce Shopping using MERN Stack where different modules are presentE-Commerce Shopping using MERN Stack where different modules are present
E-Commerce Shopping using MERN Stack where different modules are present
 
RM&IPR M5 notes.pdfResearch Methodolgy & Intellectual Property Rights Series 5
RM&IPR M5 notes.pdfResearch Methodolgy & Intellectual Property Rights Series 5RM&IPR M5 notes.pdfResearch Methodolgy & Intellectual Property Rights Series 5
RM&IPR M5 notes.pdfResearch Methodolgy & Intellectual Property Rights Series 5
 
15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon15-Minute City: A Completely New Horizon
15-Minute City: A Completely New Horizon
 
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
 
5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...
 
Introduction to Artificial Intelligence and History of AI
Introduction to Artificial Intelligence and History of AIIntroduction to Artificial Intelligence and History of AI
Introduction to Artificial Intelligence and History of AI
 
Electrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission lineElectrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission line
 
Lesson no16 application of Induction Generator in Wind.ppsx
Lesson no16 application of Induction Generator in Wind.ppsxLesson no16 application of Induction Generator in Wind.ppsx
Lesson no16 application of Induction Generator in Wind.ppsx
 
BURGER ORDERING SYSYTEM PROJECT REPORT..pdf
BURGER ORDERING SYSYTEM PROJECT REPORT..pdfBURGER ORDERING SYSYTEM PROJECT REPORT..pdf
BURGER ORDERING SYSYTEM PROJECT REPORT..pdf
 

1.refrigeration

  • 2. Lesson Plan • Vapour compression refrigeration cycle • Components of a refrigeration system • Pressure enthalpy chart • superheating & sub-cooling • Heat exchanger • Coefficient of performance ( COP ) • System Capacity • Direct and Indirect Expansion System • Back Pressure Regulating valve • Types of compressor • Oil Separator • Filter/Drier • Throttling device • Capacity control Method
  • 3. Basic refrigeration cycle: • Heat energy flows from a hot region to a cooler region. • Vapour Compression Refrigeration System uses a circulating refrigerant as a medium which 1) absorbs & removes heat from space to be cooled 2) rejects the heat elsewhere (cooler) Heat energy Refrigerant flow cooler Cooling water Cold room
  • 4. Vapour Compression System Low Pressure Side High Pressure Side Liquid receiver Expansion valve Compressor Evaporator Liquid Condenser Heat in Heat out Hot Gas Gas 4 numbers principle components : (1) Evaporator (2) Compressor (3) Condenser (4) Expansion Valve
  • 5. Vapour Compression System Low Pressure Side High Pressure Side Liquid receiver Expansion valve Compressor Evaporator Liquid Condenser Heat in Heat out Hot Gas Gas EVAPORATOR: 1) The evaporator coils are located in the compartment to be cooled. 2) The low pressure liquid refrigerant ,after passing through the expansion valve, expands. 3) Takes in heat from the surrounding and evaporates. 4) The gas is then sucked up by the compressor.
  • 6. Vapour Compression System Low Pressure Side High Pressure Side Liquid receiver Expansion valve Compressor Evaporator Liquid Condenser Heat in Heat out Hot Gas Gas COMPRESSOR : 1) Compresses the refrigerant (gaseous state). 2) Raising its Temperature & Pressure. 3) Discharges refrigerant to Condenser.
  • 7. Vapour Compression System Low Pressure Side High Pressure Side Liquid receiver Expansion valve Compressor Evaporator Liquid Condenser Heat in Heat out Hot Gas Gas LIQUEFACTION: 1) Hot refrigerant gas cooled in the condenser. 2) Condensed liquid refrigerant flows into a receiver. 3) Then liquid refrigerant flows to the expansion valve.
  • 8. Vapour Compression System Low Pressure Side High Pressure Side Liquid receiver Expansion valve Compressor Evaporator Liquid Condenser Heat in Heat out Hot Gas Gas EXPANSION: 1) The expansion valve acting as a regulating valve, limits the amount of refrigerant flowing through. 2) Resulting in reduction of pressure of the liquid and expansion takes place.
  • 9. P-H chart ( Pressure – Enthalpy chart ) Sub cooled liquid • Pressure – Absolute pressure Unit : bar , psi • Enthalpy – Total amount of energy per unit weight of substance. Unit : BTU / Lb or kJ / kg • The lines ,saturated liquid & vapour respectively are plots of pressure vs enthalpy for the saturated state of a given refrigerant. • This chart is used to understand the property changes that takes place in each phase of the cycle. Saturated liquid line Saturated vapour line Superheated region Sub-cooled region Liquid – vapour mixture
  • 10. • Enthalpy – Total amount of energy per unit weight of substance. Unit : BTU / Lb or kJ / kg • Entropy – Measure of heat dispersion in a system divided by temperature. Unit : BTU / Lb / deg change or kJ / kg / deg change for a substance. Refrigeration Cycle : Pressure-Enthalpy graph
  • 11. Ideal Refrigeration Cycle : Pressure-Enthalpy chart Superheated vapour Sub cooled liquid Liquid vapour mixture Ideal Refrigeration Cycle : Pressure – Enthalpy chart Enthalpy ( BTU / lbs or KJ / kg ) Pressure(absolute) P1 P2 1 2 34
  • 12. Refrigeration Cycle : Pressure-Enthalpy chart Non ideal Refrigeration Cycle : Pressure – Enthalpy chart , showing superheating & sub cooling Sub cooled liquid Superheated vapour Liquid vapour mixture Enthalpy ( BTU / lbs or KJ / kg ) Pressure(absolute) 1 4 2 Liquid to Vapour Transformation in EVAPORATOR Throttling at expansion valve Vapour to Liquid transformation in CONDENSER Work done in the compressor Liquid vapour mixture superheated Superheated subcooling 3
  • 13. Non ideal Refrigeration Cycle : Pressure – Enthalpy chart , showing superheating & sub cooling Sub cooled liquid Superheated vapour Liquid vapour mixture Enthalpy ( BTU / lbs or KJ / kg ) Pressure(absolute) 1 34 2Liquid to Vapour Transformation in EVAPORATOR Throttling at expansion valve Vapour to Liquid transformation in CONDENSER Work done in the compressor H1 H2 H3 The amount of heat that the refrigerant absorb must equal the cooling load. (1) Refrigerant cooling load ( F ) = cooling load / ( H2 – H1) (2) Work done by compressor = F x ( H3 – H2 ) (3) Heat rejected by condenser = F x ( H3 – H1 ) (4) Heat absorbed by evaporator = F x ( H2 – H1 ) Coefficient of Performance (COP) = heat absorbed by refrigerant / Energy required driving compressor = ( H2 – H1) / ( H3 – H2)
  • 14. Pressure-Enthalpy chart Pressure ( bar ) Enthalpy ( KJ / kg of refrigerant ) Liquid to Vapour Transformation in EVAPORATOR at -13 deg C Vapour to Liquid transformation in CONDENSER at 42 deg C Work done in the compressor Throttling at expansion valve 1 4 1-2 : EVAPORATOR – extraction of heat from room 2-3 : COMPRESSOR – compression work 3-4 : CONDENSER – energy thrown to sea 4-1 : EXPANSION VALVE – throttling at the expansion valve 3 2 16 3.2 150 304 365 For each kg of refrigerant flow , Energy extracted from meat room : 304 - 150 = 154 KJ / kg Work spent on compressor = 365 – 304 = 61 KJ / Kg Coefficient of Performance ( COP ) = Energy extracted from room / Energy spent = 154 / 61 or 2.52
  • 15. • Pressure – Enthalpy chart , of a practical cycle (refer to page 8) • Effects of pressure loss resulting from friction.
  • 16. Superheating & Sub-cooling compressor condenser receiver refrigerant control (expansion valve) evaporator Heat exchanger Saturated liquid Superheated suction vapour Saturated suction vapour Sub cooled liquid Improvement in cycle efficiency with a heat exchanger – as compared to another cycle where vapour is superheated without producing any useful cooling Page 7
  • 17. Refrigeration system capacity • Rate at which system removes heat from. • Rate depends : (1) mass of refrigerant circulated per unit time (2) refrigerating effect per unit mass circulated (undercooling increases the refrigerating effect)
  • 18. Two systems employed: • Direct Expansion System • Indirect expansion system aka Brine System
  • 19. Direct Expansion System : Provisional Refrigeration System Condenser Cooling water in / out Fan/blower expansion valve Solenoid stop valve Thermostat Temperature sensor MEAT ROOM LP pressure switch HP pressure switch Refrigerant compressor Sight glass Drier Evaporator Capillarytube : Refrigerant flow From FISH ROOM From VEGETABLE ROOM To FISH ROOM To VEGETABLE ROOM Oil separator Oil return to compressor sump Bulb T1 T2 receiver Oil pressure switch Purging line LP pressure gauge Oil pressure gauge HP pressure gauge Back pressure regulating valve
  • 20. Indirect Expansion (Brine System) Condenser / Receiver Cooling water in / out expansion valve Solenoid stop valve Thermostat Temperature sensor LP pressure switch HP pressure switch Refrigerant compressor Sight glass Drier Evaporator Capillarytube : Refrigerant flow Oil separator Oil return to compressor sump Bulb T1 T2 pump Brine header tank Secondary refrigerant to various compartment Oil pressure switch
  • 21. Back pressure regulating valve • Normally fitted to higher temperature rooms, ie the vegetable room not for the fish room or meat room. Purpose : • Act as system balancing diverters – a) When all solenoid valves are opened, the valve restrict liquid flowing into the vegetable room & therefore deliver the bulk to the colder rooms. b) Limits the pressure drops across the expansion valve by giving a set minimum pressure in the evaporator coil. Prevents cold air blowing directly onto delicate vegetables.
  • 22. Refrigerant Compressor types: • Reciprocating • Rotary • Centrifugal • Screw
  • 23. Oil Separator Gas from compressor Float Oil to compressor crankcase Oil Gas to condenser Internal baffles Page 12
  • 24. Liquid-line Filter / Drier Desiccant (dehydrating material) Refrigerant in Clean,dry refrigerant Fine filter to remove small particles Course filter to remove large particles Felt pad Drying agent : silica gel or activated alumina Page 13
  • 25. Condenser: • Air cooled type – up to 5 hp • Large capacity – shell & tube type , SW cool • Tubes – aluminium brass (option ext. fins) • Water velocity < 2.5 m/s minimise erosion • Anodes – avoid corrosion non ferrous metals
  • 26. Throttling device: • Metering of refrigerant – rate suitable to maintain designed operating pressures at different load. • Maintain pressure differential between HP & LP side. The pressure of the refrigerant is reduced as it passes through the small orifice of the throttling device. With the reduction in pressure, the corresponding boiling point of the liquid is reduced. Types of throttling devices: • Hand expansion valves • Automatic constant pressure expansion valve • Thermostatic expansion valve • Externally equalized expansion valve • Pressure balancing expansion valve • Expansion valves with centrifugal type distributors • Flow control device for flooded evaporators
  • 27. Expansion valve • automatic expansion valve • thermostatic expansion valve • externally equalised thermostatic expansion va
  • 31. Capacity control methods • Manual start/stop • Speed variation • Cylinder unloading reciprocating compressor • Suction side throttling centrifugal compressor • Inlet guide vane centrifugal compressor • Hot gas bypass • Compressor in parallel • Slide valve Screw compressor - control effective working length of rotor. To maintain constant temperature, a constant pressure must be present in the EVAPORATOR. Ideally, the compressor should remove from the EVAPORATOR exactly the volume of refrigerant that boils off in it. Change in loading : change in quantity of boiling off the refrigerant.