SlideShare una empresa de Scribd logo
1 de 31
Descargar para leer sin conexión
Assessment of Low Impact Design (LID)
Strategies using Integrated and Distributed
Surface Water/Groundwater Models
Presented to:
IAH Conference
October 2, 2013
Dirk Kassenaar, M.Sc. P.Eng.
M.A. Marchildon, M.Sc. P.Eng.
2
Land Development Impacts
► “They paved paradise and put up a parking
lot…” Assessing the impacts of land
development is certainly important!
► SW assessments have focused on peak flows
and, more recently, on how Low Impact
Development (LID) can mitigate storm sewer
“end of pipe” flows.
► Recent work indicates that a more holistic
approach is needed, including assessment of
the whole flow regime (not just peak flows)
and impact to GW levels and baseflow
discharge to wetlands
3
Low Impact Development (LID) Strategies
Local LID Features:
- A local LID feature captures
and attenuates storm water
- e.g. bioswales, permeable
paving, rain barrels, green
roofs, soak-away pits, etc.
A bioswale can attenuate pavement
runoff by enhancing ET and GW
infiltration
4
Assessment of Low Impact Development
► Low Impact Development strategies offer significant benefits
► Not all LID strategies will work in all locations. Need to consider:
 Soil and surficial geologic conditions (infiltration capacity)
 Depth to water table (possible rejected infiltration)
 Other factors such as terrain, slope accumulation, and pervious/impervious
configuration
► SW-only models are focussed on end of pipe sewer flows and
stormwater ponds:
 Cannot predict if hydrogeologic conditions are suitable for a specific LID design
 Cannot predict if ecologic and hydrogeologic benefits will actually be achieved.
► GW-only models cannot predict the complex change in 3D recharge
► Only an integrated GW/SW model approach can assess all aspects of a
LID implementation
 Which LID is optimal and where? Will the ecological benefits be achieved?
5
Integrated Water Systems Modelling
► Integrated GW/SW modelling involves:
 Groundwater: Flow through the subsurface
 Hydrology: Vegetation, land use and soil
zone
 Hydraulics: Flow in streams, wetlands and
lakes
► “Fully-distributed” modelling approach
 Study area is subdivided into millions of
cells
 Soil zone hydrology and groundwater
processes simulated in each unique cell
 Streamflow simulated in a linear channel
network that accepts cascading overland
runoff and pickup (or loss) from the aquifer
systems
6
USGS-GSFLOW
6
Integrated Ground-Water and Surface-Water Flow Model Based on the Integration of the
Precipitation-Runoff Modeling System (PRMS) and the Modular Ground-Water Flow Model
(MODFLOW)
7
GSFLOW Hydrology: Sub-Cell Processes
► Each upper layer model cell has both pervious and impervious areas and processes.
Impervious areas &
Depression storage
Pervious
area
Tree canopy
(interception)
Micro-topographic
depressions
Parking Lot
Rooftop
8
Conceptualization of LIDs in GSFLOW
► A Manabe (1969) Reservoir was added to each cell to represent the local LID feature
► The LID Reservoir can receive water from the impervious area and, depending on the E, Q
and D parameters, attenuate and infiltrate that water Impervious areas &
Depression storage
Pervious
area
Tree canopy
(interception)
Micro-topographic
depressions
Parking Lot
Rooftop
LID Reservoir Parameters:
E =Evaporative loss
Q=Overflow
D =Drainage
9
► Bioswales
 E>0, Q>0, D=K
► Green Roofs
 E>0, Q>0, D=0
► Retention Ponds
 E>0, Q=0, D>0
 (Smax=∞)
E =Evaporative loss
Q=Overflow
D =Drainage
► Detention Ponds
 E>0, Q>0, D>0
► Infiltration Galleries
 E=0, Q>0, D=K
► Rain Harvesters
 E=0, Q>0, D=D(t)
GSFLOW Manabe Reservoir
- One reservoir available per model cell
- Parameters adjusted to represent a
variety of LID features
(Figures from CVC & TRCA, 2010)
10
Additional LID Conceptualization:
Permeable Pavement
Simulated by decreasing the (effective) percent
imperviousness
Roof Downspout Disconnection
Simulated by routing impervious runoff to
(same-cell) pervious area
(CVC & TRCA, 2010)
(CVC & TRCA, 2010)
11
Centralized LID Features
11
Centralized LID Features are
larger scale features that receive
water from upslope impervious
sources or 3rd-pipe roof runoff
12
Modification of Cascade Network for
Centralized LIDS
► A cascade network is used to
route overland flow and
interflow
► Segments of the network can be
changed (red arrow) to direct a
portion of locally captured water
to a Centralized LID
12
(Markstrom et.al., 2008)
13
Seaton MESP LID Assessment Objectives
► Proposed new development for 70,000 residents north of Pickering,
Ontario
► Simulation Objectives:
 Evaluate overall cumulative effects of various LID configurations
► Which LID strategy (or combination) should be used, and where?
 Will the ecological function of the wetlands and ponds be preserved?
► Will buffers around the NHS lands be sufficient?
 Can the impacts on the underlying aquifers be mitigated through LIDS?
► Issues:
 Commercial-industrial land use planned for high recharge Iroquois Beach sands
 Need for quantitative comparison of alternatives
14
Seaton Lands - Hydrogeologic Conditions
► Complex hydrogeology: 3 Aquifers day-lighting along Duffins Creek
► Extensive wetland connectivity and riparian zones
A A’
A
A’
15
Seaton Existing Landuse
Agricultural
Natural Heritage
Urban
15
16
Seaton Proposed Landuse
16
Agricultural
Natural Heritage
Residential
Parks
Commercial
Institutional
17
Implemented LIDs
► Employment areas: Rooftop capture and 90% of the overflow being
redirected to bioswales
► Residential, recreational and school areas
 Roof-to-lawn routing of impervious runoff (amount dependent on roof coverage as a
proportion of modelled cell);
► Unlined (leaky) storm water management ponds
► Infiltration gallery for commercial developments on the Iroqouois
Beach
► Road side ditches along rural cross sections as opposed to serviced
roadways.
18
Existing Conditions: Generated Runoff
19
Post Development: Generated Runoff
20
Post Development with LID: Generated Runoff
21
Existing Conditions: Cascading Runoff
Click for Animation
22
Post Development: Cascading Runoff
Click for Animation
23
Existing Conditions: Actual ET
24
Post Development: Actual ET
25
Post Development with LID: Actual ET
Bioswales
26
Existing Conditions: GW Recharge
Iroquois Beach Sands
27
Post Development: GW Recharge
Iroquois Beach Sands
28
Post Development with LID: GW Recharge
Iroquois Beach Sands
29
Predicted GW Impacts – No LIDS
► Simulations indicate unmitigated development would cause up to 4 m
of aquifer drawdown and a corresponding decrease in baseflow
discharge to streams
30
Predicted GW Impacts – With LIDS
► Simulations indicate LIDS would sustain groundwater recharge and
mitigate effects on aquifer levels and stream baseflow
31
Seaton LIDS Analysis: Conclusions
► Integrated modelling identified the unique and site specific recharge
functions in the Seaton Lands MESP area
► Detailed cell-based simulations were able to represent site specific LID
implement issues and benefits
► Modelling provided a framework for comparison of LID scenarios, and
facilitated discussions with the Municipality and TRCA

Más contenido relacionado

La actualidad más candente

Analysis of Groundwater/Surface Water Interaction at the Site Scale Babcock R...
Analysis of Groundwater/Surface Water Interaction at the Site Scale Babcock R...Analysis of Groundwater/Surface Water Interaction at the Site Scale Babcock R...
Analysis of Groundwater/Surface Water Interaction at the Site Scale Babcock R...Dirk Kassenaar M.Sc. P.Eng.
 
Integrated Modelling with GSFLOW in a Complex Watershed on the Niagara Escarp...
Integrated Modelling with GSFLOW in a Complex Watershed on the Niagara Escarp...Integrated Modelling with GSFLOW in a Complex Watershed on the Niagara Escarp...
Integrated Modelling with GSFLOW in a Complex Watershed on the Niagara Escarp...Dirk Kassenaar M.Sc. P.Eng.
 
Data Management and Calibration Strategies for Integrated Modelling
Data Management and Calibration Strategies for Integrated ModellingData Management and Calibration Strategies for Integrated Modelling
Data Management and Calibration Strategies for Integrated ModellingDirk Kassenaar M.Sc. P.Eng.
 
Applications of Integrated Models to Watershed and Sub-Watershed Scale Analys...
Applications of Integrated Models to Watershed and Sub-Watershed Scale Analys...Applications of Integrated Models to Watershed and Sub-Watershed Scale Analys...
Applications of Integrated Models to Watershed and Sub-Watershed Scale Analys...Dirk Kassenaar M.Sc. P.Eng.
 
Integrated Surface Water and Groundwater Interaction Modelling using GSFLOW
Integrated Surface Water and Groundwater Interaction Modelling using GSFLOWIntegrated Surface Water and Groundwater Interaction Modelling using GSFLOW
Integrated Surface Water and Groundwater Interaction Modelling using GSFLOWDirk Kassenaar M.Sc. P.Eng.
 
Thermal Impact Assessment of Below-Water-Table Aggregate Extraction
Thermal Impact Assessment of Below-Water-Table Aggregate ExtractionThermal Impact Assessment of Below-Water-Table Aggregate Extraction
Thermal Impact Assessment of Below-Water-Table Aggregate ExtractionDirk Kassenaar M.Sc. P.Eng.
 
Simulating hydrologic response to climate change and drought with an integrat...
Simulating hydrologic response to climate change and drought with an integrat...Simulating hydrologic response to climate change and drought with an integrat...
Simulating hydrologic response to climate change and drought with an integrat...Dirk Kassenaar M.Sc. P.Eng.
 
Assessing Sensitivity to Drought and Climate Change with an Integrated Surfac...
Assessing Sensitivity to Drought and Climate Change with an Integrated Surfac...Assessing Sensitivity to Drought and Climate Change with an Integrated Surfac...
Assessing Sensitivity to Drought and Climate Change with an Integrated Surfac...Dirk Kassenaar M.Sc. P.Eng.
 
Assessing Cumulative Effects with Integrated Modelling
Assessing Cumulative Effects with Integrated ModellingAssessing Cumulative Effects with Integrated Modelling
Assessing Cumulative Effects with Integrated ModellingDirk Kassenaar M.Sc. P.Eng.
 
Integrated surface water/groundwater modelling to simulate drought and climat...
Integrated surface water/groundwater modelling to simulate drought and climat...Integrated surface water/groundwater modelling to simulate drought and climat...
Integrated surface water/groundwater modelling to simulate drought and climat...Dirk Kassenaar M.Sc. P.Eng.
 
Issues and Strategies for Integrated Model Calibration
Issues and Strategies for Integrated Model CalibrationIssues and Strategies for Integrated Model Calibration
Issues and Strategies for Integrated Model CalibrationDirk Kassenaar M.Sc. P.Eng.
 
Incorporating a Dynamic Irrigation Demand Module into an Integrated Surface ...
Incorporating a Dynamic Irrigation Demand Module into an Integrated Surface ...Incorporating a Dynamic Irrigation Demand Module into an Integrated Surface ...
Incorporating a Dynamic Irrigation Demand Module into an Integrated Surface ...Dirk Kassenaar M.Sc. P.Eng.
 
Issues and Strategies for Integrated Model Calibration
Issues and Strategies for Integrated Model CalibrationIssues and Strategies for Integrated Model Calibration
Issues and Strategies for Integrated Model CalibrationDirk Kassenaar M.Sc. P.Eng.
 
Dusting Off the Source Water Protection Models: Adaptation and Application of...
Dusting Off the Source Water Protection Models: Adaptation and Application of...Dusting Off the Source Water Protection Models: Adaptation and Application of...
Dusting Off the Source Water Protection Models: Adaptation and Application of...Dirk Kassenaar M.Sc. P.Eng.
 
Estimation of Groundwater Recharge Using WetSpass and MODFLOW
Estimation of Groundwater Recharge  Using WetSpass and MODFLOWEstimation of Groundwater Recharge  Using WetSpass and MODFLOW
Estimation of Groundwater Recharge Using WetSpass and MODFLOWPutika Ashfar Khoiri
 
Introduction to Groundwater Modelling
Introduction to Groundwater ModellingIntroduction to Groundwater Modelling
Introduction to Groundwater ModellingC. P. Kumar
 

La actualidad más candente (20)

Analysis of Groundwater/Surface Water Interaction at the Site Scale Babcock R...
Analysis of Groundwater/Surface Water Interaction at the Site Scale Babcock R...Analysis of Groundwater/Surface Water Interaction at the Site Scale Babcock R...
Analysis of Groundwater/Surface Water Interaction at the Site Scale Babcock R...
 
Integrated Modelling with GSFLOW in a Complex Watershed on the Niagara Escarp...
Integrated Modelling with GSFLOW in a Complex Watershed on the Niagara Escarp...Integrated Modelling with GSFLOW in a Complex Watershed on the Niagara Escarp...
Integrated Modelling with GSFLOW in a Complex Watershed on the Niagara Escarp...
 
Data Management and Calibration Strategies for Integrated Modelling
Data Management and Calibration Strategies for Integrated ModellingData Management and Calibration Strategies for Integrated Modelling
Data Management and Calibration Strategies for Integrated Modelling
 
Applications of Integrated Models to Watershed and Sub-Watershed Scale Analys...
Applications of Integrated Models to Watershed and Sub-Watershed Scale Analys...Applications of Integrated Models to Watershed and Sub-Watershed Scale Analys...
Applications of Integrated Models to Watershed and Sub-Watershed Scale Analys...
 
Integrated Surface Water and Groundwater Interaction Modelling using GSFLOW
Integrated Surface Water and Groundwater Interaction Modelling using GSFLOWIntegrated Surface Water and Groundwater Interaction Modelling using GSFLOW
Integrated Surface Water and Groundwater Interaction Modelling using GSFLOW
 
Thermal Impact Assessment of Below-Water-Table Aggregate Extraction
Thermal Impact Assessment of Below-Water-Table Aggregate ExtractionThermal Impact Assessment of Below-Water-Table Aggregate Extraction
Thermal Impact Assessment of Below-Water-Table Aggregate Extraction
 
Simulating hydrologic response to climate change and drought with an integrat...
Simulating hydrologic response to climate change and drought with an integrat...Simulating hydrologic response to climate change and drought with an integrat...
Simulating hydrologic response to climate change and drought with an integrat...
 
Assessing Sensitivity to Drought and Climate Change with an Integrated Surfac...
Assessing Sensitivity to Drought and Climate Change with an Integrated Surfac...Assessing Sensitivity to Drought and Climate Change with an Integrated Surfac...
Assessing Sensitivity to Drought and Climate Change with an Integrated Surfac...
 
Assessing Cumulative Effects with Integrated Modelling
Assessing Cumulative Effects with Integrated ModellingAssessing Cumulative Effects with Integrated Modelling
Assessing Cumulative Effects with Integrated Modelling
 
Re-thinking recharge
Re-thinking recharge Re-thinking recharge
Re-thinking recharge
 
Integrated surface water/groundwater modelling to simulate drought and climat...
Integrated surface water/groundwater modelling to simulate drought and climat...Integrated surface water/groundwater modelling to simulate drought and climat...
Integrated surface water/groundwater modelling to simulate drought and climat...
 
Issues and Strategies for Integrated Model Calibration
Issues and Strategies for Integrated Model CalibrationIssues and Strategies for Integrated Model Calibration
Issues and Strategies for Integrated Model Calibration
 
Incorporating a Dynamic Irrigation Demand Module into an Integrated Surface ...
Incorporating a Dynamic Irrigation Demand Module into an Integrated Surface ...Incorporating a Dynamic Irrigation Demand Module into an Integrated Surface ...
Incorporating a Dynamic Irrigation Demand Module into an Integrated Surface ...
 
Integrated Modelling: Insights and Blind Spots
Integrated Modelling: Insights and Blind SpotsIntegrated Modelling: Insights and Blind Spots
Integrated Modelling: Insights and Blind Spots
 
Issues and Strategies for Integrated Model Calibration
Issues and Strategies for Integrated Model CalibrationIssues and Strategies for Integrated Model Calibration
Issues and Strategies for Integrated Model Calibration
 
Dusting Off the Source Water Protection Models: Adaptation and Application of...
Dusting Off the Source Water Protection Models: Adaptation and Application of...Dusting Off the Source Water Protection Models: Adaptation and Application of...
Dusting Off the Source Water Protection Models: Adaptation and Application of...
 
Dirk Kassenaar EarthFX Watertech 2016
Dirk Kassenaar EarthFX Watertech 2016 Dirk Kassenaar EarthFX Watertech 2016
Dirk Kassenaar EarthFX Watertech 2016
 
Estimation of Groundwater Recharge Using WetSpass and MODFLOW
Estimation of Groundwater Recharge  Using WetSpass and MODFLOWEstimation of Groundwater Recharge  Using WetSpass and MODFLOW
Estimation of Groundwater Recharge Using WetSpass and MODFLOW
 
Groundwater Modeling and GIS
Groundwater Modeling and GISGroundwater Modeling and GIS
Groundwater Modeling and GIS
 
Introduction to Groundwater Modelling
Introduction to Groundwater ModellingIntroduction to Groundwater Modelling
Introduction to Groundwater Modelling
 

Destacado

Assessing Cumulative Effects of SAGD Operations in the Mackay Watershed
Assessing Cumulative Effects of SAGD Operations in the Mackay WatershedAssessing Cumulative Effects of SAGD Operations in the Mackay Watershed
Assessing Cumulative Effects of SAGD Operations in the Mackay WatershedDirk Kassenaar M.Sc. P.Eng.
 
Long term socio ecological research sites for CRP6 – designing the methodology
Long term socio ecological research sites for CRP6 – designing the methodologyLong term socio ecological research sites for CRP6 – designing the methodology
Long term socio ecological research sites for CRP6 – designing the methodologyForest Trees Sentinel Landscapes
 
Web excerpts-md-navcrs-v5-aug14
Web excerpts-md-navcrs-v5-aug14Web excerpts-md-navcrs-v5-aug14
Web excerpts-md-navcrs-v5-aug14mdslidedshare
 
Financial Analysis as an Instrument In Predicting The Company Performance
Financial Analysis as an Instrument In Predicting The Company PerformanceFinancial Analysis as an Instrument In Predicting The Company Performance
Financial Analysis as an Instrument In Predicting The Company PerformanceLuqman Praditio
 
CWRA 2016 Assessing Cumulative Effects of SAGD Operations in the Mackay Water...
CWRA 2016 Assessing Cumulative Effects of SAGD Operations in the Mackay Water...CWRA 2016 Assessing Cumulative Effects of SAGD Operations in the Mackay Water...
CWRA 2016 Assessing Cumulative Effects of SAGD Operations in the Mackay Water...Dirk Kassenaar M.Sc. P.Eng.
 
Stream 2: Tackling Climate Change Challenges and Opportunities
Stream 2: Tackling Climate Change Challenges and OpportunitiesStream 2: Tackling Climate Change Challenges and Opportunities
Stream 2: Tackling Climate Change Challenges and OpportunitiesForest Trees Sentinel Landscapes
 
Climate Smart Territories in Central America: Nicacentral and Trifinio (MAPNo...
Climate Smart Territories in Central America: Nicacentral and Trifinio (MAPNo...Climate Smart Territories in Central America: Nicacentral and Trifinio (MAPNo...
Climate Smart Territories in Central America: Nicacentral and Trifinio (MAPNo...Forest Trees Sentinel Landscapes
 
CV Tony Smith - Lecturer Chef Students
CV Tony Smith - Lecturer Chef StudentsCV Tony Smith - Lecturer Chef Students
CV Tony Smith - Lecturer Chef Studentstony smith
 
Meta consolidado de educacion artistica efrain ichpas paquiyauri
Meta consolidado de educacion artistica  efrain ichpas paquiyauriMeta consolidado de educacion artistica  efrain ichpas paquiyauri
Meta consolidado de educacion artistica efrain ichpas paquiyauriEfrain Ichpas Paquiyauri
 
To Win the Peace by Richard Hawkins
To Win the Peace by Richard HawkinsTo Win the Peace by Richard Hawkins
To Win the Peace by Richard HawkinsRichard Hawkins
 
Apa Peran NGO Untuk Mengurangi Kemiskinan?
Apa Peran NGO Untuk Mengurangi Kemiskinan?Apa Peran NGO Untuk Mengurangi Kemiskinan?
Apa Peran NGO Untuk Mengurangi Kemiskinan?Luqman Praditio
 
Investment Opportunities in FinTech - Techsauce Summit Bangkok
Investment Opportunities in FinTech - Techsauce Summit BangkokInvestment Opportunities in FinTech - Techsauce Summit Bangkok
Investment Opportunities in FinTech - Techsauce Summit Bangkoktryb
 
Characterizing Change of High Frequency Return Periods in Urbanizing Southern...
Characterizing Change of High Frequency Return Periods in Urbanizing Southern...Characterizing Change of High Frequency Return Periods in Urbanizing Southern...
Characterizing Change of High Frequency Return Periods in Urbanizing Southern...Dirk Kassenaar M.Sc. P.Eng.
 
Контролируемый сегмент BTC на базе публичной сети BTC (ver.2.1)
Контролируемый сегмент BTC на базе публичной сети BTC (ver.2.1)Контролируемый сегмент BTC на базе публичной сети BTC (ver.2.1)
Контролируемый сегмент BTC на базе публичной сети BTC (ver.2.1)Alexander Chegodaev
 

Destacado (20)

Assessing Cumulative Effects of SAGD Operations in the Mackay Watershed
Assessing Cumulative Effects of SAGD Operations in the Mackay WatershedAssessing Cumulative Effects of SAGD Operations in the Mackay Watershed
Assessing Cumulative Effects of SAGD Operations in the Mackay Watershed
 
Long term socio ecological research sites for CRP6 – designing the methodology
Long term socio ecological research sites for CRP6 – designing the methodologyLong term socio ecological research sites for CRP6 – designing the methodology
Long term socio ecological research sites for CRP6 – designing the methodology
 
Does ASEM matter?
Does ASEM matter?Does ASEM matter?
Does ASEM matter?
 
Web excerpts-md-navcrs-v5-aug14
Web excerpts-md-navcrs-v5-aug14Web excerpts-md-navcrs-v5-aug14
Web excerpts-md-navcrs-v5-aug14
 
Linking Household to other data
Linking Household to other dataLinking Household to other data
Linking Household to other data
 
Financial Analysis as an Instrument In Predicting The Company Performance
Financial Analysis as an Instrument In Predicting The Company PerformanceFinancial Analysis as an Instrument In Predicting The Company Performance
Financial Analysis as an Instrument In Predicting The Company Performance
 
CWRA 2016 Assessing Cumulative Effects of SAGD Operations in the Mackay Water...
CWRA 2016 Assessing Cumulative Effects of SAGD Operations in the Mackay Water...CWRA 2016 Assessing Cumulative Effects of SAGD Operations in the Mackay Water...
CWRA 2016 Assessing Cumulative Effects of SAGD Operations in the Mackay Water...
 
Stream 2: Tackling Climate Change Challenges and Opportunities
Stream 2: Tackling Climate Change Challenges and OpportunitiesStream 2: Tackling Climate Change Challenges and Opportunities
Stream 2: Tackling Climate Change Challenges and Opportunities
 
Climate Smart Territories in Central America: Nicacentral and Trifinio (MAPNo...
Climate Smart Territories in Central America: Nicacentral and Trifinio (MAPNo...Climate Smart Territories in Central America: Nicacentral and Trifinio (MAPNo...
Climate Smart Territories in Central America: Nicacentral and Trifinio (MAPNo...
 
Identifying climate stressors – A matter of scale
Identifying climate stressors – A matter of scaleIdentifying climate stressors – A matter of scale
Identifying climate stressors – A matter of scale
 
CV Tony Smith - Lecturer Chef Students
CV Tony Smith - Lecturer Chef StudentsCV Tony Smith - Lecturer Chef Students
CV Tony Smith - Lecturer Chef Students
 
Sentinel Landscapes
Sentinel LandscapesSentinel Landscapes
Sentinel Landscapes
 
Meta consolidado de educacion artistica efrain ichpas paquiyauri
Meta consolidado de educacion artistica  efrain ichpas paquiyauriMeta consolidado de educacion artistica  efrain ichpas paquiyauri
Meta consolidado de educacion artistica efrain ichpas paquiyauri
 
To Win the Peace by Richard Hawkins
To Win the Peace by Richard HawkinsTo Win the Peace by Richard Hawkins
To Win the Peace by Richard Hawkins
 
Apa Peran NGO Untuk Mengurangi Kemiskinan?
Apa Peran NGO Untuk Mengurangi Kemiskinan?Apa Peran NGO Untuk Mengurangi Kemiskinan?
Apa Peran NGO Untuk Mengurangi Kemiskinan?
 
Investment Opportunities in FinTech - Techsauce Summit Bangkok
Investment Opportunities in FinTech - Techsauce Summit BangkokInvestment Opportunities in FinTech - Techsauce Summit Bangkok
Investment Opportunities in FinTech - Techsauce Summit Bangkok
 
Using IFRI data: Two examples
Using IFRI data: Two examplesUsing IFRI data: Two examples
Using IFRI data: Two examples
 
Dynamic growth
Dynamic growthDynamic growth
Dynamic growth
 
Characterizing Change of High Frequency Return Periods in Urbanizing Southern...
Characterizing Change of High Frequency Return Periods in Urbanizing Southern...Characterizing Change of High Frequency Return Periods in Urbanizing Southern...
Characterizing Change of High Frequency Return Periods in Urbanizing Southern...
 
Контролируемый сегмент BTC на базе публичной сети BTC (ver.2.1)
Контролируемый сегмент BTC на базе публичной сети BTC (ver.2.1)Контролируемый сегмент BTC на базе публичной сети BTC (ver.2.1)
Контролируемый сегмент BTC на базе публичной сети BTC (ver.2.1)
 

Similar a Assessment of Low Impact Design (LID)

Water resource model modflow
Water resource model modflowWater resource model modflow
Water resource model modflowManoj Patley
 
Data Goldmines
Data GoldminesData Goldmines
Data GoldminesDon Talend
 
Virginia Constructed Wetlands Design Spec
Virginia Constructed Wetlands Design SpecVirginia Constructed Wetlands Design Spec
Virginia Constructed Wetlands Design SpecFu Michael Justin
 
Storm water collection (itp)
Storm water collection (itp)Storm water collection (itp)
Storm water collection (itp)AjayPatel389
 
Addressing Hydrology at the Watershed Scale: A Novel Approach to Stormwater M...
Addressing Hydrology at the Watershed Scale: A Novel Approach to Stormwater M...Addressing Hydrology at the Watershed Scale: A Novel Approach to Stormwater M...
Addressing Hydrology at the Watershed Scale: A Novel Approach to Stormwater M...TWCA
 
Modeling the Effects of Land Use Change on Flooding
Modeling the Effects of Land Use Change on FloodingModeling the Effects of Land Use Change on Flooding
Modeling the Effects of Land Use Change on FloodingAdam Nayak
 
WaterServices&projectsExperienceADJllr
WaterServices&projectsExperienceADJllrWaterServices&projectsExperienceADJllr
WaterServices&projectsExperienceADJllrAlejandro DUSSAILLANT
 
2010 tn green infrastructure
2010 tn green infrastructure2010 tn green infrastructure
2010 tn green infrastructurecurt_jawdy
 
River flood modelling with mike 11 case of nzoia river (budalangi) in kenya
River flood modelling with mike 11 case of nzoia river (budalangi) in kenyaRiver flood modelling with mike 11 case of nzoia river (budalangi) in kenya
River flood modelling with mike 11 case of nzoia river (budalangi) in kenyaAlexander Decker
 
River flood modelling with mike 11 case of nzoia river (budalangi) in kenya
River flood modelling with mike 11 case of nzoia river (budalangi) in kenyaRiver flood modelling with mike 11 case of nzoia river (budalangi) in kenya
River flood modelling with mike 11 case of nzoia river (budalangi) in kenyaAlexander Decker
 
Critical assesment of the Sustainable Urban Drainage component of the Church ...
Critical assesment of the Sustainable Urban Drainage component of the Church ...Critical assesment of the Sustainable Urban Drainage component of the Church ...
Critical assesment of the Sustainable Urban Drainage component of the Church ...Achim von Malotki
 

Similar a Assessment of Low Impact Design (LID) (20)

Water resource model modflow
Water resource model modflowWater resource model modflow
Water resource model modflow
 
Applications of remote sensing and modelling in flood risk analysis and irrig...
Applications of remote sensing and modelling in flood risk analysis and irrig...Applications of remote sensing and modelling in flood risk analysis and irrig...
Applications of remote sensing and modelling in flood risk analysis and irrig...
 
Data Goldmines
Data GoldminesData Goldmines
Data Goldmines
 
Srorm water management
Srorm water managementSrorm water management
Srorm water management
 
7th class
7th class7th class
7th class
 
Low impact development_coupled_with_floodplain_mitigation
Low impact development_coupled_with_floodplain_mitigationLow impact development_coupled_with_floodplain_mitigation
Low impact development_coupled_with_floodplain_mitigation
 
Virginia Constructed Wetlands Design Spec
Virginia Constructed Wetlands Design SpecVirginia Constructed Wetlands Design Spec
Virginia Constructed Wetlands Design Spec
 
Storm water collection (itp)
Storm water collection (itp)Storm water collection (itp)
Storm water collection (itp)
 
Ph d presentation npc final
Ph d presentation npc finalPh d presentation npc final
Ph d presentation npc final
 
Addressing Hydrology at the Watershed Scale: A Novel Approach to Stormwater M...
Addressing Hydrology at the Watershed Scale: A Novel Approach to Stormwater M...Addressing Hydrology at the Watershed Scale: A Novel Approach to Stormwater M...
Addressing Hydrology at the Watershed Scale: A Novel Approach to Stormwater M...
 
Modeling the Effects of Land Use Change on Flooding
Modeling the Effects of Land Use Change on FloodingModeling the Effects of Land Use Change on Flooding
Modeling the Effects of Land Use Change on Flooding
 
Design manual chapter7_revjan_2013
Design manual chapter7_revjan_2013Design manual chapter7_revjan_2013
Design manual chapter7_revjan_2013
 
WaterServices&projectsExperienceADJllr
WaterServices&projectsExperienceADJllrWaterServices&projectsExperienceADJllr
WaterServices&projectsExperienceADJllr
 
Seminar aparna
Seminar aparnaSeminar aparna
Seminar aparna
 
Capstone
CapstoneCapstone
Capstone
 
2010 tn green infrastructure
2010 tn green infrastructure2010 tn green infrastructure
2010 tn green infrastructure
 
River flood modelling with mike 11 case of nzoia river (budalangi) in kenya
River flood modelling with mike 11 case of nzoia river (budalangi) in kenyaRiver flood modelling with mike 11 case of nzoia river (budalangi) in kenya
River flood modelling with mike 11 case of nzoia river (budalangi) in kenya
 
River flood modelling with mike 11 case of nzoia river (budalangi) in kenya
River flood modelling with mike 11 case of nzoia river (budalangi) in kenyaRiver flood modelling with mike 11 case of nzoia river (budalangi) in kenya
River flood modelling with mike 11 case of nzoia river (budalangi) in kenya
 
Critical assesment of the Sustainable Urban Drainage component of the Church ...
Critical assesment of the Sustainable Urban Drainage component of the Church ...Critical assesment of the Sustainable Urban Drainage component of the Church ...
Critical assesment of the Sustainable Urban Drainage component of the Church ...
 
GROUNDWATER MODELING SYSTEM
GROUNDWATER MODELING SYSTEMGROUNDWATER MODELING SYSTEM
GROUNDWATER MODELING SYSTEM
 

Último

Proposed Amendments to Chapter 15, Article X: Wetland Conservation Areas
Proposed Amendments to Chapter 15, Article X: Wetland Conservation AreasProposed Amendments to Chapter 15, Article X: Wetland Conservation Areas
Proposed Amendments to Chapter 15, Article X: Wetland Conservation Areas💥Victoria K. Colangelo
 
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995garthraymundo123
 
Call Girls Moshi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Moshi Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Moshi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Moshi Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...SUHANI PANDEY
 
Book Sex Workers Available Pune Call Girls Kondhwa 6297143586 Call Hot India...
Book Sex Workers Available Pune Call Girls Kondhwa  6297143586 Call Hot India...Book Sex Workers Available Pune Call Girls Kondhwa  6297143586 Call Hot India...
Book Sex Workers Available Pune Call Girls Kondhwa 6297143586 Call Hot India...Call Girls in Nagpur High Profile
 
Verified Trusted Kalyani Nagar Call Girls 8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...
Verified Trusted Kalyani Nagar Call Girls  8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...Verified Trusted Kalyani Nagar Call Girls  8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...
Verified Trusted Kalyani Nagar Call Girls 8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...tanu pandey
 
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...SUHANI PANDEY
 
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...Pooja Nehwal
 
Booking open Available Pune Call Girls Budhwar Peth 6297143586 Call Hot Indi...
Booking open Available Pune Call Girls Budhwar Peth  6297143586 Call Hot Indi...Booking open Available Pune Call Girls Budhwar Peth  6297143586 Call Hot Indi...
Booking open Available Pune Call Girls Budhwar Peth 6297143586 Call Hot Indi...Call Girls in Nagpur High Profile
 
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Hertwich_EnvironmentalImpacts_BuildingsGRO.pptx
Hertwich_EnvironmentalImpacts_BuildingsGRO.pptxHertwich_EnvironmentalImpacts_BuildingsGRO.pptx
Hertwich_EnvironmentalImpacts_BuildingsGRO.pptxEdgar Hertwich
 
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...SUHANI PANDEY
 
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Bookingtanu pandey
 
VIP Model Call Girls Uruli Kanchan ( Pune ) Call ON 8005736733 Starting From ...
VIP Model Call Girls Uruli Kanchan ( Pune ) Call ON 8005736733 Starting From ...VIP Model Call Girls Uruli Kanchan ( Pune ) Call ON 8005736733 Starting From ...
VIP Model Call Girls Uruli Kanchan ( Pune ) Call ON 8005736733 Starting From ...SUHANI PANDEY
 
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Call Now ☎️🔝 9332606886 🔝 Call Girls ❤ Service In Muzaffarpur Female Escorts ...
Call Now ☎️🔝 9332606886 🔝 Call Girls ❤ Service In Muzaffarpur Female Escorts ...Call Now ☎️🔝 9332606886 🔝 Call Girls ❤ Service In Muzaffarpur Female Escorts ...
Call Now ☎️🔝 9332606886 🔝 Call Girls ❤ Service In Muzaffarpur Female Escorts ...Anamikakaur10
 

Último (20)

Proposed Amendments to Chapter 15, Article X: Wetland Conservation Areas
Proposed Amendments to Chapter 15, Article X: Wetland Conservation AreasProposed Amendments to Chapter 15, Article X: Wetland Conservation Areas
Proposed Amendments to Chapter 15, Article X: Wetland Conservation Areas
 
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
 
RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995
 
Call Girls Moshi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Moshi Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Moshi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Moshi Call Me 7737669865 Budget Friendly No Advance Booking
 
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
 
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
 
Book Sex Workers Available Pune Call Girls Kondhwa 6297143586 Call Hot India...
Book Sex Workers Available Pune Call Girls Kondhwa  6297143586 Call Hot India...Book Sex Workers Available Pune Call Girls Kondhwa  6297143586 Call Hot India...
Book Sex Workers Available Pune Call Girls Kondhwa 6297143586 Call Hot India...
 
Verified Trusted Kalyani Nagar Call Girls 8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...
Verified Trusted Kalyani Nagar Call Girls  8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...Verified Trusted Kalyani Nagar Call Girls  8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...
Verified Trusted Kalyani Nagar Call Girls 8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...
 
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
 
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...
 
Booking open Available Pune Call Girls Budhwar Peth 6297143586 Call Hot Indi...
Booking open Available Pune Call Girls Budhwar Peth  6297143586 Call Hot Indi...Booking open Available Pune Call Girls Budhwar Peth  6297143586 Call Hot Indi...
Booking open Available Pune Call Girls Budhwar Peth 6297143586 Call Hot Indi...
 
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
 
Hertwich_EnvironmentalImpacts_BuildingsGRO.pptx
Hertwich_EnvironmentalImpacts_BuildingsGRO.pptxHertwich_EnvironmentalImpacts_BuildingsGRO.pptx
Hertwich_EnvironmentalImpacts_BuildingsGRO.pptx
 
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
 
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
 
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
 
VIP Model Call Girls Uruli Kanchan ( Pune ) Call ON 8005736733 Starting From ...
VIP Model Call Girls Uruli Kanchan ( Pune ) Call ON 8005736733 Starting From ...VIP Model Call Girls Uruli Kanchan ( Pune ) Call ON 8005736733 Starting From ...
VIP Model Call Girls Uruli Kanchan ( Pune ) Call ON 8005736733 Starting From ...
 
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
 
(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7
(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7
(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7
 
Call Now ☎️🔝 9332606886 🔝 Call Girls ❤ Service In Muzaffarpur Female Escorts ...
Call Now ☎️🔝 9332606886 🔝 Call Girls ❤ Service In Muzaffarpur Female Escorts ...Call Now ☎️🔝 9332606886 🔝 Call Girls ❤ Service In Muzaffarpur Female Escorts ...
Call Now ☎️🔝 9332606886 🔝 Call Girls ❤ Service In Muzaffarpur Female Escorts ...
 

Assessment of Low Impact Design (LID)

  • 1. Assessment of Low Impact Design (LID) Strategies using Integrated and Distributed Surface Water/Groundwater Models Presented to: IAH Conference October 2, 2013 Dirk Kassenaar, M.Sc. P.Eng. M.A. Marchildon, M.Sc. P.Eng.
  • 2. 2 Land Development Impacts ► “They paved paradise and put up a parking lot…” Assessing the impacts of land development is certainly important! ► SW assessments have focused on peak flows and, more recently, on how Low Impact Development (LID) can mitigate storm sewer “end of pipe” flows. ► Recent work indicates that a more holistic approach is needed, including assessment of the whole flow regime (not just peak flows) and impact to GW levels and baseflow discharge to wetlands
  • 3. 3 Low Impact Development (LID) Strategies Local LID Features: - A local LID feature captures and attenuates storm water - e.g. bioswales, permeable paving, rain barrels, green roofs, soak-away pits, etc. A bioswale can attenuate pavement runoff by enhancing ET and GW infiltration
  • 4. 4 Assessment of Low Impact Development ► Low Impact Development strategies offer significant benefits ► Not all LID strategies will work in all locations. Need to consider:  Soil and surficial geologic conditions (infiltration capacity)  Depth to water table (possible rejected infiltration)  Other factors such as terrain, slope accumulation, and pervious/impervious configuration ► SW-only models are focussed on end of pipe sewer flows and stormwater ponds:  Cannot predict if hydrogeologic conditions are suitable for a specific LID design  Cannot predict if ecologic and hydrogeologic benefits will actually be achieved. ► GW-only models cannot predict the complex change in 3D recharge ► Only an integrated GW/SW model approach can assess all aspects of a LID implementation  Which LID is optimal and where? Will the ecological benefits be achieved?
  • 5. 5 Integrated Water Systems Modelling ► Integrated GW/SW modelling involves:  Groundwater: Flow through the subsurface  Hydrology: Vegetation, land use and soil zone  Hydraulics: Flow in streams, wetlands and lakes ► “Fully-distributed” modelling approach  Study area is subdivided into millions of cells  Soil zone hydrology and groundwater processes simulated in each unique cell  Streamflow simulated in a linear channel network that accepts cascading overland runoff and pickup (or loss) from the aquifer systems
  • 6. 6 USGS-GSFLOW 6 Integrated Ground-Water and Surface-Water Flow Model Based on the Integration of the Precipitation-Runoff Modeling System (PRMS) and the Modular Ground-Water Flow Model (MODFLOW)
  • 7. 7 GSFLOW Hydrology: Sub-Cell Processes ► Each upper layer model cell has both pervious and impervious areas and processes. Impervious areas & Depression storage Pervious area Tree canopy (interception) Micro-topographic depressions Parking Lot Rooftop
  • 8. 8 Conceptualization of LIDs in GSFLOW ► A Manabe (1969) Reservoir was added to each cell to represent the local LID feature ► The LID Reservoir can receive water from the impervious area and, depending on the E, Q and D parameters, attenuate and infiltrate that water Impervious areas & Depression storage Pervious area Tree canopy (interception) Micro-topographic depressions Parking Lot Rooftop LID Reservoir Parameters: E =Evaporative loss Q=Overflow D =Drainage
  • 9. 9 ► Bioswales  E>0, Q>0, D=K ► Green Roofs  E>0, Q>0, D=0 ► Retention Ponds  E>0, Q=0, D>0  (Smax=∞) E =Evaporative loss Q=Overflow D =Drainage ► Detention Ponds  E>0, Q>0, D>0 ► Infiltration Galleries  E=0, Q>0, D=K ► Rain Harvesters  E=0, Q>0, D=D(t) GSFLOW Manabe Reservoir - One reservoir available per model cell - Parameters adjusted to represent a variety of LID features (Figures from CVC & TRCA, 2010)
  • 10. 10 Additional LID Conceptualization: Permeable Pavement Simulated by decreasing the (effective) percent imperviousness Roof Downspout Disconnection Simulated by routing impervious runoff to (same-cell) pervious area (CVC & TRCA, 2010) (CVC & TRCA, 2010)
  • 11. 11 Centralized LID Features 11 Centralized LID Features are larger scale features that receive water from upslope impervious sources or 3rd-pipe roof runoff
  • 12. 12 Modification of Cascade Network for Centralized LIDS ► A cascade network is used to route overland flow and interflow ► Segments of the network can be changed (red arrow) to direct a portion of locally captured water to a Centralized LID 12 (Markstrom et.al., 2008)
  • 13. 13 Seaton MESP LID Assessment Objectives ► Proposed new development for 70,000 residents north of Pickering, Ontario ► Simulation Objectives:  Evaluate overall cumulative effects of various LID configurations ► Which LID strategy (or combination) should be used, and where?  Will the ecological function of the wetlands and ponds be preserved? ► Will buffers around the NHS lands be sufficient?  Can the impacts on the underlying aquifers be mitigated through LIDS? ► Issues:  Commercial-industrial land use planned for high recharge Iroquois Beach sands  Need for quantitative comparison of alternatives
  • 14. 14 Seaton Lands - Hydrogeologic Conditions ► Complex hydrogeology: 3 Aquifers day-lighting along Duffins Creek ► Extensive wetland connectivity and riparian zones A A’ A A’
  • 16. 16 Seaton Proposed Landuse 16 Agricultural Natural Heritage Residential Parks Commercial Institutional
  • 17. 17 Implemented LIDs ► Employment areas: Rooftop capture and 90% of the overflow being redirected to bioswales ► Residential, recreational and school areas  Roof-to-lawn routing of impervious runoff (amount dependent on roof coverage as a proportion of modelled cell); ► Unlined (leaky) storm water management ponds ► Infiltration gallery for commercial developments on the Iroqouois Beach ► Road side ditches along rural cross sections as opposed to serviced roadways.
  • 20. 20 Post Development with LID: Generated Runoff
  • 21. 21 Existing Conditions: Cascading Runoff Click for Animation
  • 22. 22 Post Development: Cascading Runoff Click for Animation
  • 25. 25 Post Development with LID: Actual ET Bioswales
  • 26. 26 Existing Conditions: GW Recharge Iroquois Beach Sands
  • 27. 27 Post Development: GW Recharge Iroquois Beach Sands
  • 28. 28 Post Development with LID: GW Recharge Iroquois Beach Sands
  • 29. 29 Predicted GW Impacts – No LIDS ► Simulations indicate unmitigated development would cause up to 4 m of aquifer drawdown and a corresponding decrease in baseflow discharge to streams
  • 30. 30 Predicted GW Impacts – With LIDS ► Simulations indicate LIDS would sustain groundwater recharge and mitigate effects on aquifer levels and stream baseflow
  • 31. 31 Seaton LIDS Analysis: Conclusions ► Integrated modelling identified the unique and site specific recharge functions in the Seaton Lands MESP area ► Detailed cell-based simulations were able to represent site specific LID implement issues and benefits ► Modelling provided a framework for comparison of LID scenarios, and facilitated discussions with the Municipality and TRCA