A Quantitative Study of the Contribution of Earned Value Management to Project Success on External Projects Under Contract Robert A. Marshall Ph.D. Thesis Defense August 20, 2007
Candidate’s appreciation of the committee Philippe Ruiz, Ph.D., Committee Chairman and Professor of Statistics Christophe Bredillet, Ph.D.,  Dean’s Representative and Program Director  Frank Anbari, Ph.D.,  Professor of Project Management George Washington University Wayne Abba, MPA,  EVM Subject Matter Expert
Candidate’s appreciation of the committee  cont. Russell Archibald, Ph.D. PMI/APM/IPMA Fellow Darren Dalcher, Ph.D.  Professor of Project Management Middlesex University  Lynn Crawford, DBA Professor of Project Management Univ. of Technology Sydney
Three part outline of the presentation PART A   Background, framework, results and contribution PART B   Technical aspects of research   and data PART C   Summary and directions for future research
PART A Background, framework, results and contribution
Research in the domain of project procurement management
The domain is in need of more research generally “ The area of contracts is one aspect of project management that is in definite need of new ideas and tools.” (Abu-Hijleh and Ibbs, 1989) Only 2.4% of project management conference papers presented in the US and abroad from 1996-1998 were classified as procurement (Zobel & Wearne, 2000) Only 4% of project management research articles printed in English between 1960-1999 were classified as procurement (Kloppenborg & Opfer, 2002)
What is Earned Value Management?  ,[object Object],[object Object],[object Object]
EVM is actively promoted by major project management organizations Project Management Institute (PMI) Association of Project Management (APM) Association for the Advancement of Cost Engineering (AACE) Project Management Association of Japan (PMAJ)
Accumulation of evidence indicates a low level of EVM use  Less than 1% of projects (Fleming and Koppelman, 1996)  “ If such a favorable view (merits of EVM) is so strongly stated, why then is EVM methodology still not used widely as suggested by existing literature? (Kim, 2000) High potential; low usage  (Besner and Hobbs, 2006)
The reason for the low level of EVM use is vague and problematic  –  favorable   research results on  the one hand ,[object Object],[object Object],[object Object]
The reason for the low level of EVM use is vague  and problematic–   unfavorable   research   results on the other hand ,[object Object],[object Object]
The reason for the low level of EVM use is vague and problematic –  unfavorable   research arguments ,[object Object],[object Object],[object Object]
EVM’s applicability to contracts also vague and problematic –  bias towards cost-plus contracts   ,[object Object],[object Object],[object Object],[object Object]
The guiding research questions coming out of the review of literature are threefold ,[object Object],[object Object],[object Object]
Theoretical Framework
Variable No. 1: Principles of EVM (ANSI/EIA-748) a.     Plan all work scope for the project to completion; b.     Decompose the scope into finite pieces that can be assigned to a responsible person or organization to control;  c.     Integrate program work scope, schedule, and cost objective into a performance measurement baseline plan against which accomplishments may be measured. Control changes to the baseline;  d.     Use actual costs incurred and recorded in accomplishing the work performed;
Variable No. 1: Principles of EVM (ANSI/EIA-748)  cont. e.     Objectively assess accomplishments at the work performance level; f.      Analyze significant variances from the plan, forecast impacts, and prepare an estimate at completion based on performance to date and work to be performed;  g.      Use EVMS information in the company's management processes.  
Variable No. 2:  Work Breakdown Structure  (WBS) with respect to  Contract Formation  Items a.      Scope development (wbs1) b.     Risk assessment (wbs2) c.     Should cost-estimates (wbs3) d.     Schedule planning (wbs4) e.     Payment planning (wbs5) f.      Evaluating bids and negotiating with bidders (wbs6) g.     Ensuring fairness and equity to contract (wbs7)
Variable No. 2: “S” Curves with respect to a single Contract Administration item   a. Monitoring work (scurve)  
Variable No. 2: EVM Performance metrics with respect to multiple Contract Administration items   a.  Controlling schedule (metric1) b.     Controlling scope (metric2) c.     Controlling cost (metric3) d.     Evaluating and processing change orders (metric4) e.     Evaluating and processing payment requests (metric5)
Variable No. 2: EVM Performance metrics with respect to multiple Contract Administration items   cont. f.      Evaluation and analyzing delays (metric6) g.     Evaluating and analyzing claims (metric7) h.     Acceptance of completed work (metric8) i.      Contract close-out (release of claims) (metric9) j.      Post-project audits (metric10)  
Variable No. 3:  Project Success (Shenhar et al., 1997)     a.    Meeting Schedule and Budget Goals - how well the project satisfied the resource constraints of schedule and budget.  b.    Benefit to Customer – how well the project satisfied the functional requirements and technical specifications of the organization that benefit from the project’s realization.
Variable No. 3:  Project Success (Shenhar et al., 1997)  cont.   c.     Commercial Success.  How well the project satisfies the desired business results (includes return on investment for performing organization; or enhancing the profits of the benefiting organization). d.     Preparing for the Future - The contribution the project made to the performing organization in developing new business opportunities; technologies or increasing core competencies.   
Theoretical Framework
Research hypotheses based on low EVM usage and belief that a bias may exist – H1 and H2 ,[object Object],[object Object]
Research hypotheses based on low EVM usage and belief that a bias may exist – H3, H4 and H5 H3:  There will be no significant difference between Fixed-price and Cost-plus contracts on the contributions of  EVM’s Work breakdown Structure  during  Contract Formation H4: There will be no significant difference between Fixed-price and Cost-plus contracts on the contribution of  EVM’s "S” Curve  during  Contract Administration H5:  There will be no significant difference between Fixed-price and Cost-plus contracts on the use of  EVM’s Performance Metrics  during  Contract Administration
Findings: H1 Results offered support for H1.   Linear correlation-regression showed a moderately strong relationship between the independent variable  Principles of EVM  and  dependent  variable  Project Success  ( r  = .474;  β   = .474,  t  = 6.443,  n   =145).  The results were significant setting  p  at  p  < .05 ( a  = .000).  The independent variable explains 22.47% of the variation in the dependent variable (R² = .2247).  As predicted,  Principles of EVM  are significant positive predictors of  Project Success
X-Y Scatter Plot (n=145)
Findings: H2 Results did not offer support for H2.   Contrary to the prediction, a difference exists between fixed-price and cost-plus contracted projects with respect to the contribution of  Principles of EVM  to  Project Success , measured separately.  The results favor fixed-price contracted projects.  Linear correlation-regression showed a moderately strong positive relationship between the independent variable  Principles of EVM  and the dependent variable  Project Success  for the cost-plus group ( r  = .405;  β   = .405,  t  = 4.432,  n =102); and a moderately strong and relatively higher positive relationship for the fixed-price group ( r  = .585;  β  = .585,  t  = 4.622,  n =43).  The independent variable explains 16.40% of the variation in the dependent variable in cost-plus contracted projects; and 34.22% in fixed-price contracted projects.  The results are statistically significant setting p at  p  < .05 ( a  = .000), separately
Findings: H3 Results offered support for H3, with exceptions.   As predicted, there are no significant differences between fixed-price and cost-plus contracted projects on the contributions of EVM’s Work Breakdown Structure to  Contract Formation  items with the exception of wbs4 (Schedule Planning) and wbs5 (Payment Planning) (Wilks’ λ = .936, χ² = 9.389, df2,  p  = .009)(eigenvalue = .068; canonical correlation = .253).  Five items were removed leaving a single canonical root with two discriminant coefficients (wbs4 and wbs5).  No significant differences between fixed-price and cost-plus contracts were observed with respect to the contribution of  EVM’s WBS  to  Contract Formation  items   for wbs1, 2, 3, 6, and 7
Two canonical coefficients distinguish fixed-price from cost-plus contracted projects with respect to the use of the WBS The contribution of wbs5 (Payment Planning) was  relatively greater in FP as compared to CP contracted projects The contribution of wbs4 (Schedule planning) was  relatively greater in CP as  compared to FP contracted projects
Findings: H4 Results offered support for H4.   As predicted, there is no significant difference between fixed-price and cost-plus contracted projects on the contribution of  EVM’s &quot;S” Curve  to  Contract Administration  items   (single item included in H5 analysis)
Findings: H5 Results offered support for H5, with exceptions.   The results show no significant difference between fixed-price and cost-plus contracted projects on the contributions of  EVM’s Metrics  to  Contract Administration  (Wilks’ λ = .943, χ² = 8.434, df1,  p  = .004) (eigenvalue = .061; canonical correlation = .240), with the exception of metric5 ( Evaluating and Processing Payment Requests ).  A total of ten items were removed during the analysis leaving a single canonical root with one discriminant coefficient (metric5).  No significant differences between fixed-price and cost-plus contracts were observed with respect to the contribution of  EVM’s Metrics  to  Contract Administration  items for scurve, metric1, 2, 3, 4, 6, 7, 8, 9, and 10
A single canonical coefficient distinguishes fixed-price from cost-plus contracted projects with respect to the use of the S-curve and EVM performance metrics The contribution of metric5 ( Evaluating and processing payment requests ) was relatively greater in FP as compared to CP contracted projects
Multiple implications stem from this research EVM directly and measurable contributes to project success EVM is dynamic (not a checklist) EVM alone does not explain project success Both CP and FP contract types benefit from EVM EVM optimized in FP contracts
Multiple implications stem from this research  cont. EVM planning is as important as EVM control Emphasize WBS schedule planning in CP projects Emphasize WBS payment planning in FP projects Emphasize metrics in processing payment requests in FP projects
This research increases the body of knowledge regarding project procurement management Five publications to date have stemmed from this research which have reached a global audience
Related publishing's Marshall, Robert A. (2005). “The Case for Earned Value Management with Fixed Price Contracts.” C ontract Management Magazine.  Marshall, Robert A. (2006). “The contribution of earned value management to project success on contracted efforts: A quantitative statistics approach within the population of experienced practitioners.”  Proceedings of the International Research Conference on Organizing by Projects (IRNOP7). Marshall, Robert A. (Editor, 2nd Ed.). (2007).  Professional Practice Guide to Earned Value.  Association for the Advancement of Cost Engineering International. AACE:  Morgantown, WV.
Related publishing's  cont. Marshall, Robert A. (2007). “The Principles of Earned Value Management as Predictor Variables of Project Success.”  Transactions  o f the 51st Annual International Meeting of the Association for the Advancement of Cost Engineering (AACE).  Morgantown, WV. Marshall, Robert A. (2007). “The contribution of earned value management to project success on contracted efforts: A quantitative statistics approach within the population of experienced practitioners.”  Journal of Contract Management.  (September Issue)
This research offers nine specific contributions The unique (and repeatable) testing of the ANSI-748 principles of EVM as predictor variables of project success The unique inference that fixed-price contracted projects benefit as much as, if not more, than cost-plus contracts when applying EVM Unique quantitative approach with respect to the contribution of the principles of EVM to project success which solidify beliefs through methodological triangulation
This research offers nine specific contributions  cont. The unique inference that the contribution of the mechanics of EVM (WBS, S-curve and metrics) do not significantly differ between fixed-price contracted projects and cost-plus contracted projects (with three exceptions noted below) The unique inference that the contribution of the WBS to  payment planning  is greater in fixed-price contracted projects as compared to cost-plus contracts The unique inference that the contribution of the WBS in  schedule planning  is greater in cost-plus contracted projects as compared to fixed-price contracts
This research offers nine specific contributions  cont. The unique inference that the contribution of the EVM metrics to  evaluating and processing payment requests  is relatively greater in fixed-price contracted projects as compared to cost-plus contracted projects The mechanics of EVM contribute as much to project planning (WBS) as they do to control (S-curve and metrics)
The results are timely and relevant  EVM shown to have high potential; low usage (Besner and Hobbs, 2006) Schedule management techniques are more important to high-uncertainty projects (Shenhar, et, 2002) “ Schedule risk is often under appreciated for its contribution to driving contract performance and cost overruns” (U.S. DoD EVM Implementation Guide, 2005) Budget and scope management techniques more important with projects with low uncertainty (Shenhar, et al, 2002)
PART B Technical aspects of research
  Technical aspects of research and data Pre-survey tasks Research approach and methodology determination  Survey instrument development Data collection strategy determination and effort Post-survey tasks Survey instrument testing Sample testing for social desirability of group responses Data testing for reliability and assumptions Data treatments Statistical analysis
Research approach selected was quantitative Appropriate for testing hypotheses  Lends itself to relatively short duration studies Uses known measurement and analytic techniques Needed representative sample available Compliments existing research and strengthens  knowledge through methodological triangulation
Three primary statistical methods were used Pearson’s product-moment correlation -  r  Bivariate linear regression –  β   Canonical discriminant analysis -  Wilks’ λ
Survey instrument developed for ease of use and analysis Thirty-eight (38) questions (plus MC-10 battery) Likert-type semantic differential scaling  Interval level scale for continuous data Available on-line (July 6, 2005 - March 10, 2006)  Approx. 7-10 minutes to take
Data collection strategy included attributes of random and purposive sampling Deliberate sampling frame included four subgroups with requisite experience DAU EVM Community  PMI CPM  APM EVM SIG AACE EVM SIG Approximate sampling frame size of 2500  Participants solicited via email without bias on two separate occasions
Survey data attributes   148 of 256 respondents completed survey -  57.8% 145 of potentially 2500 samples used - 5.8%  Three outlier data points (residual values > 3 σ removed) Less than one percent missing values ( μ  -  imputation) Residuals displayed normal homoscedasticity and normal linear relationship to expected value
Survey data predominantly public projects, defense and information technology  Industry 3 2.1 2.1 2 1.4 3.4 19 13.1 16.6 67 46.2 62.8 16 11.0 73.8 10 6.9 80.7 15 10.3 91.0 7 4.8 95.9 6 4.1 100.0 145 100.0 Description Heavy construction Light construction (residential and commercial) Government/public works Military/defense Information technology Professional services (banking, consulting, management, etc.) Aerospace Software development Other Total Frequency Percent Cum. Percent
Independent samples t-test of MC-10 social desirability data indicating no significant different in scores about CR and FP groups Independent Samples Test 2.597 .109 .520 143 .604 .20565 .39546 -.57606 .98736 .487 68.9 .628 .20565 .42217 -.63658 1.048 Assumptions Equal variances assumed Equal variances not assumed Dependent variable Contract type F Sig. Levene's test for equality   of variances t df Sig. (2-tailed) M Difference SE Difference Lower Upper 95% CI of the Difference t-test for equality of means
X-Y Scatter Plot (n=148)
X-Y Scatter Plot (n=145)
Sample data showing normal linearity
Sample data showing normal homoscedasticity
Tests and treatments to assure highest reliability  ,[object Object],[object Object],[object Object],[object Object]
Distribution of Principles of EVM composites
Distribution of Project Success composites
Limitations of research approach and results ,[object Object],[object Object],[object Object],[object Object]
PART C   Summary and direction for future research
Summary of what led to the research goal
Summary of contribution
Directions for future research Qualitative or quantitative study as they relate to EVM or are otherwise affected by the core project management processes of initiating or closing  The depth to which scope should be defined.  The question yet to be answered regarding EVM is whether an optimal level of WBS exists. Second, how the utility curve for varying degrees of WBS decomposition might look
Directions for future research  cont. Greater stratification of contract types as categorical variables with respect to the principles of EVM and project success Exploration of variables and dimensions not covered by this study  Predictive ability of EVM principles for the specific achievement of project financial objectives

Más contenido relacionado

La actualidad más candente

Value engineering practical
Value engineering practicalValue engineering practical
Value engineering practical
Abada Saad
 
Zieger.alfred
Zieger.alfredZieger.alfred
Zieger.alfred
NASAPMC
 
3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs
harwoodr
 
Resume - Nermeen Atef sam
Resume - Nermeen Atef samResume - Nermeen Atef sam
Resume - Nermeen Atef sam
Nermeen gerges
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
InSync Conference
 

La actualidad más candente (19)

construction project managment_civileng
construction project managment_civilengconstruction project managment_civileng
construction project managment_civileng
 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
 
Value engineering practical
Value engineering practicalValue engineering practical
Value engineering practical
 
Zieger.alfred
Zieger.alfredZieger.alfred
Zieger.alfred
 
Integrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceIntegrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performance
 
Construction KPIs & Dashboards
Construction KPIs & DashboardsConstruction KPIs & Dashboards
Construction KPIs & Dashboards
 
Eva[1]
Eva[1]Eva[1]
Eva[1]
 
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationEarned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
 
Ray stratton aace presentation
Ray stratton aace presentationRay stratton aace presentation
Ray stratton aace presentation
 
3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs
 
Resume - Nermeen Atef sam
Resume - Nermeen Atef samResume - Nermeen Atef sam
Resume - Nermeen Atef sam
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
BioPharma Projects: Essentials in Project Controls
BioPharma Projects: Essentials in Project ControlsBioPharma Projects: Essentials in Project Controls
BioPharma Projects: Essentials in Project Controls
 
Project Control System
Project Control SystemProject Control System
Project Control System
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
H1303055462
H1303055462H1303055462
H1303055462
 
Cost plan
Cost planCost plan
Cost plan
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
 

Similar a Marshall Esc Lille Defense R2

Urban Local Bodies Case Study
Urban Local Bodies Case StudyUrban Local Bodies Case Study
Urban Local Bodies Case Study
Sandra Ahn
 
Whole life performance lecture south bank university
Whole life performance lecture   south bank universityWhole life performance lecture   south bank university
Whole life performance lecture south bank university
Kim Newman
 

Similar a Marshall Esc Lille Defense R2 (20)

Urban Local Bodies Case Study
Urban Local Bodies Case StudyUrban Local Bodies Case Study
Urban Local Bodies Case Study
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.
 
Impact of Rework on Cost and Schedule
Impact of Rework on Cost and ScheduleImpact of Rework on Cost and Schedule
Impact of Rework on Cost and Schedule
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
Strategic Cost Management for Construction Project Success : A Systematic Study
Strategic Cost Management for Construction Project Success : A Systematic StudyStrategic Cost Management for Construction Project Success : A Systematic Study
Strategic Cost Management for Construction Project Success : A Systematic Study
 
STRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDY
STRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDYSTRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDY
STRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDY
 
STRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDY
STRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDYSTRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDY
STRATEGIC COST MANAGEMENT FOR CONSTRUCTION PROJECT SUCCESS: A SYSTEMATIC STUDY
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
 
Edg resume 06.2016
Edg resume 06.2016Edg resume 06.2016
Edg resume 06.2016
 
Edg resume 06.2016
Edg resume 06.2016Edg resume 06.2016
Edg resume 06.2016
 
EDG Resume 06.2016
EDG Resume 06.2016EDG Resume 06.2016
EDG Resume 06.2016
 
Application of value engineering in construction
Application of value engineering in constructionApplication of value engineering in construction
Application of value engineering in construction
 
IRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and ProgramsIRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and Programs
 
Front-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas IndustryFront-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas Industry
 
Pmwg.110603
Pmwg.110603Pmwg.110603
Pmwg.110603
 
Whole life performance lecture south bank university
Whole life performance lecture   south bank universityWhole life performance lecture   south bank university
Whole life performance lecture south bank university
 
Conference paper-11-9-2017
Conference paper-11-9-2017Conference paper-11-9-2017
Conference paper-11-9-2017
 

Marshall Esc Lille Defense R2

  • 1. A Quantitative Study of the Contribution of Earned Value Management to Project Success on External Projects Under Contract Robert A. Marshall Ph.D. Thesis Defense August 20, 2007
  • 2. Candidate’s appreciation of the committee Philippe Ruiz, Ph.D., Committee Chairman and Professor of Statistics Christophe Bredillet, Ph.D., Dean’s Representative and Program Director Frank Anbari, Ph.D., Professor of Project Management George Washington University Wayne Abba, MPA, EVM Subject Matter Expert
  • 3. Candidate’s appreciation of the committee cont. Russell Archibald, Ph.D. PMI/APM/IPMA Fellow Darren Dalcher, Ph.D. Professor of Project Management Middlesex University Lynn Crawford, DBA Professor of Project Management Univ. of Technology Sydney
  • 4. Three part outline of the presentation PART A Background, framework, results and contribution PART B Technical aspects of research and data PART C Summary and directions for future research
  • 5. PART A Background, framework, results and contribution
  • 6. Research in the domain of project procurement management
  • 7. The domain is in need of more research generally “ The area of contracts is one aspect of project management that is in definite need of new ideas and tools.” (Abu-Hijleh and Ibbs, 1989) Only 2.4% of project management conference papers presented in the US and abroad from 1996-1998 were classified as procurement (Zobel & Wearne, 2000) Only 4% of project management research articles printed in English between 1960-1999 were classified as procurement (Kloppenborg & Opfer, 2002)
  • 8.
  • 9. EVM is actively promoted by major project management organizations Project Management Institute (PMI) Association of Project Management (APM) Association for the Advancement of Cost Engineering (AACE) Project Management Association of Japan (PMAJ)
  • 10. Accumulation of evidence indicates a low level of EVM use Less than 1% of projects (Fleming and Koppelman, 1996) “ If such a favorable view (merits of EVM) is so strongly stated, why then is EVM methodology still not used widely as suggested by existing literature? (Kim, 2000) High potential; low usage (Besner and Hobbs, 2006)
  • 11.
  • 12.
  • 13.
  • 14.
  • 15.
  • 17. Variable No. 1: Principles of EVM (ANSI/EIA-748) a.     Plan all work scope for the project to completion; b.     Decompose the scope into finite pieces that can be assigned to a responsible person or organization to control; c.     Integrate program work scope, schedule, and cost objective into a performance measurement baseline plan against which accomplishments may be measured. Control changes to the baseline; d.     Use actual costs incurred and recorded in accomplishing the work performed;
  • 18. Variable No. 1: Principles of EVM (ANSI/EIA-748) cont. e.     Objectively assess accomplishments at the work performance level; f.      Analyze significant variances from the plan, forecast impacts, and prepare an estimate at completion based on performance to date and work to be performed; g.      Use EVMS information in the company's management processes.  
  • 19. Variable No. 2: Work Breakdown Structure (WBS) with respect to Contract Formation Items a.      Scope development (wbs1) b.    Risk assessment (wbs2) c.     Should cost-estimates (wbs3) d.     Schedule planning (wbs4) e.     Payment planning (wbs5) f.      Evaluating bids and negotiating with bidders (wbs6) g.     Ensuring fairness and equity to contract (wbs7)
  • 20. Variable No. 2: “S” Curves with respect to a single Contract Administration item a. Monitoring work (scurve)  
  • 21. Variable No. 2: EVM Performance metrics with respect to multiple Contract Administration items a. Controlling schedule (metric1) b.     Controlling scope (metric2) c.     Controlling cost (metric3) d.     Evaluating and processing change orders (metric4) e.     Evaluating and processing payment requests (metric5)
  • 22. Variable No. 2: EVM Performance metrics with respect to multiple Contract Administration items cont. f.      Evaluation and analyzing delays (metric6) g.     Evaluating and analyzing claims (metric7) h.     Acceptance of completed work (metric8) i.      Contract close-out (release of claims) (metric9) j.      Post-project audits (metric10)  
  • 23. Variable No. 3: Project Success (Shenhar et al., 1997)   a.    Meeting Schedule and Budget Goals - how well the project satisfied the resource constraints of schedule and budget. b.    Benefit to Customer – how well the project satisfied the functional requirements and technical specifications of the organization that benefit from the project’s realization.
  • 24. Variable No. 3: Project Success (Shenhar et al., 1997) cont. c.     Commercial Success. How well the project satisfies the desired business results (includes return on investment for performing organization; or enhancing the profits of the benefiting organization). d.     Preparing for the Future - The contribution the project made to the performing organization in developing new business opportunities; technologies or increasing core competencies.  
  • 26.
  • 27. Research hypotheses based on low EVM usage and belief that a bias may exist – H3, H4 and H5 H3: There will be no significant difference between Fixed-price and Cost-plus contracts on the contributions of EVM’s Work breakdown Structure during Contract Formation H4: There will be no significant difference between Fixed-price and Cost-plus contracts on the contribution of EVM’s &quot;S” Curve during Contract Administration H5: There will be no significant difference between Fixed-price and Cost-plus contracts on the use of EVM’s Performance Metrics during Contract Administration
  • 28. Findings: H1 Results offered support for H1. Linear correlation-regression showed a moderately strong relationship between the independent variable Principles of EVM and dependent variable Project Success ( r = .474; β = .474, t = 6.443, n =145). The results were significant setting p at p < .05 ( a = .000). The independent variable explains 22.47% of the variation in the dependent variable (R² = .2247). As predicted, Principles of EVM are significant positive predictors of Project Success
  • 29. X-Y Scatter Plot (n=145)
  • 30. Findings: H2 Results did not offer support for H2. Contrary to the prediction, a difference exists between fixed-price and cost-plus contracted projects with respect to the contribution of Principles of EVM to Project Success , measured separately. The results favor fixed-price contracted projects. Linear correlation-regression showed a moderately strong positive relationship between the independent variable Principles of EVM and the dependent variable Project Success for the cost-plus group ( r = .405; β = .405, t = 4.432, n =102); and a moderately strong and relatively higher positive relationship for the fixed-price group ( r = .585; β = .585, t = 4.622, n =43). The independent variable explains 16.40% of the variation in the dependent variable in cost-plus contracted projects; and 34.22% in fixed-price contracted projects. The results are statistically significant setting p at p < .05 ( a = .000), separately
  • 31. Findings: H3 Results offered support for H3, with exceptions. As predicted, there are no significant differences between fixed-price and cost-plus contracted projects on the contributions of EVM’s Work Breakdown Structure to Contract Formation items with the exception of wbs4 (Schedule Planning) and wbs5 (Payment Planning) (Wilks’ λ = .936, χ² = 9.389, df2, p = .009)(eigenvalue = .068; canonical correlation = .253). Five items were removed leaving a single canonical root with two discriminant coefficients (wbs4 and wbs5). No significant differences between fixed-price and cost-plus contracts were observed with respect to the contribution of EVM’s WBS to Contract Formation items for wbs1, 2, 3, 6, and 7
  • 32. Two canonical coefficients distinguish fixed-price from cost-plus contracted projects with respect to the use of the WBS The contribution of wbs5 (Payment Planning) was relatively greater in FP as compared to CP contracted projects The contribution of wbs4 (Schedule planning) was relatively greater in CP as compared to FP contracted projects
  • 33. Findings: H4 Results offered support for H4. As predicted, there is no significant difference between fixed-price and cost-plus contracted projects on the contribution of EVM’s &quot;S” Curve to Contract Administration items (single item included in H5 analysis)
  • 34. Findings: H5 Results offered support for H5, with exceptions. The results show no significant difference between fixed-price and cost-plus contracted projects on the contributions of EVM’s Metrics to Contract Administration (Wilks’ λ = .943, χ² = 8.434, df1, p = .004) (eigenvalue = .061; canonical correlation = .240), with the exception of metric5 ( Evaluating and Processing Payment Requests ). A total of ten items were removed during the analysis leaving a single canonical root with one discriminant coefficient (metric5). No significant differences between fixed-price and cost-plus contracts were observed with respect to the contribution of EVM’s Metrics to Contract Administration items for scurve, metric1, 2, 3, 4, 6, 7, 8, 9, and 10
  • 35. A single canonical coefficient distinguishes fixed-price from cost-plus contracted projects with respect to the use of the S-curve and EVM performance metrics The contribution of metric5 ( Evaluating and processing payment requests ) was relatively greater in FP as compared to CP contracted projects
  • 36. Multiple implications stem from this research EVM directly and measurable contributes to project success EVM is dynamic (not a checklist) EVM alone does not explain project success Both CP and FP contract types benefit from EVM EVM optimized in FP contracts
  • 37. Multiple implications stem from this research cont. EVM planning is as important as EVM control Emphasize WBS schedule planning in CP projects Emphasize WBS payment planning in FP projects Emphasize metrics in processing payment requests in FP projects
  • 38. This research increases the body of knowledge regarding project procurement management Five publications to date have stemmed from this research which have reached a global audience
  • 39. Related publishing's Marshall, Robert A. (2005). “The Case for Earned Value Management with Fixed Price Contracts.” C ontract Management Magazine. Marshall, Robert A. (2006). “The contribution of earned value management to project success on contracted efforts: A quantitative statistics approach within the population of experienced practitioners.” Proceedings of the International Research Conference on Organizing by Projects (IRNOP7). Marshall, Robert A. (Editor, 2nd Ed.). (2007). Professional Practice Guide to Earned Value. Association for the Advancement of Cost Engineering International. AACE: Morgantown, WV.
  • 40. Related publishing's cont. Marshall, Robert A. (2007). “The Principles of Earned Value Management as Predictor Variables of Project Success.” Transactions o f the 51st Annual International Meeting of the Association for the Advancement of Cost Engineering (AACE). Morgantown, WV. Marshall, Robert A. (2007). “The contribution of earned value management to project success on contracted efforts: A quantitative statistics approach within the population of experienced practitioners.” Journal of Contract Management. (September Issue)
  • 41. This research offers nine specific contributions The unique (and repeatable) testing of the ANSI-748 principles of EVM as predictor variables of project success The unique inference that fixed-price contracted projects benefit as much as, if not more, than cost-plus contracts when applying EVM Unique quantitative approach with respect to the contribution of the principles of EVM to project success which solidify beliefs through methodological triangulation
  • 42. This research offers nine specific contributions cont. The unique inference that the contribution of the mechanics of EVM (WBS, S-curve and metrics) do not significantly differ between fixed-price contracted projects and cost-plus contracted projects (with three exceptions noted below) The unique inference that the contribution of the WBS to payment planning is greater in fixed-price contracted projects as compared to cost-plus contracts The unique inference that the contribution of the WBS in schedule planning is greater in cost-plus contracted projects as compared to fixed-price contracts
  • 43. This research offers nine specific contributions cont. The unique inference that the contribution of the EVM metrics to evaluating and processing payment requests is relatively greater in fixed-price contracted projects as compared to cost-plus contracted projects The mechanics of EVM contribute as much to project planning (WBS) as they do to control (S-curve and metrics)
  • 44. The results are timely and relevant EVM shown to have high potential; low usage (Besner and Hobbs, 2006) Schedule management techniques are more important to high-uncertainty projects (Shenhar, et, 2002) “ Schedule risk is often under appreciated for its contribution to driving contract performance and cost overruns” (U.S. DoD EVM Implementation Guide, 2005) Budget and scope management techniques more important with projects with low uncertainty (Shenhar, et al, 2002)
  • 45. PART B Technical aspects of research
  • 46. Technical aspects of research and data Pre-survey tasks Research approach and methodology determination Survey instrument development Data collection strategy determination and effort Post-survey tasks Survey instrument testing Sample testing for social desirability of group responses Data testing for reliability and assumptions Data treatments Statistical analysis
  • 47. Research approach selected was quantitative Appropriate for testing hypotheses Lends itself to relatively short duration studies Uses known measurement and analytic techniques Needed representative sample available Compliments existing research and strengthens knowledge through methodological triangulation
  • 48. Three primary statistical methods were used Pearson’s product-moment correlation - r Bivariate linear regression – β Canonical discriminant analysis - Wilks’ λ
  • 49. Survey instrument developed for ease of use and analysis Thirty-eight (38) questions (plus MC-10 battery) Likert-type semantic differential scaling Interval level scale for continuous data Available on-line (July 6, 2005 - March 10, 2006) Approx. 7-10 minutes to take
  • 50. Data collection strategy included attributes of random and purposive sampling Deliberate sampling frame included four subgroups with requisite experience DAU EVM Community PMI CPM APM EVM SIG AACE EVM SIG Approximate sampling frame size of 2500 Participants solicited via email without bias on two separate occasions
  • 51. Survey data attributes 148 of 256 respondents completed survey - 57.8% 145 of potentially 2500 samples used - 5.8% Three outlier data points (residual values > 3 σ removed) Less than one percent missing values ( μ - imputation) Residuals displayed normal homoscedasticity and normal linear relationship to expected value
  • 52. Survey data predominantly public projects, defense and information technology Industry 3 2.1 2.1 2 1.4 3.4 19 13.1 16.6 67 46.2 62.8 16 11.0 73.8 10 6.9 80.7 15 10.3 91.0 7 4.8 95.9 6 4.1 100.0 145 100.0 Description Heavy construction Light construction (residential and commercial) Government/public works Military/defense Information technology Professional services (banking, consulting, management, etc.) Aerospace Software development Other Total Frequency Percent Cum. Percent
  • 53. Independent samples t-test of MC-10 social desirability data indicating no significant different in scores about CR and FP groups Independent Samples Test 2.597 .109 .520 143 .604 .20565 .39546 -.57606 .98736 .487 68.9 .628 .20565 .42217 -.63658 1.048 Assumptions Equal variances assumed Equal variances not assumed Dependent variable Contract type F Sig. Levene's test for equality of variances t df Sig. (2-tailed) M Difference SE Difference Lower Upper 95% CI of the Difference t-test for equality of means
  • 54. X-Y Scatter Plot (n=148)
  • 55. X-Y Scatter Plot (n=145)
  • 56. Sample data showing normal linearity
  • 57. Sample data showing normal homoscedasticity
  • 58.
  • 59. Distribution of Principles of EVM composites
  • 60. Distribution of Project Success composites
  • 61.
  • 62. PART C Summary and direction for future research
  • 63. Summary of what led to the research goal
  • 65. Directions for future research Qualitative or quantitative study as they relate to EVM or are otherwise affected by the core project management processes of initiating or closing The depth to which scope should be defined. The question yet to be answered regarding EVM is whether an optimal level of WBS exists. Second, how the utility curve for varying degrees of WBS decomposition might look
  • 66. Directions for future research cont. Greater stratification of contract types as categorical variables with respect to the principles of EVM and project success Exploration of variables and dimensions not covered by this study Predictive ability of EVM principles for the specific achievement of project financial objectives