SlideShare una empresa de Scribd logo
1 de 12
Descargar para leer sin conexión
RISK SURVEY | 1
CAPITAL PROJECT RISK SURVEY
2015
2 | gardinertheobald
RISK SURVEY | 3
Introduction					 			 4
Executive Summary				 			 5
	 Scope Changes by Owner			 		 5
	 Design Errors and Omissions		 			 6
	 Unforeseen Site Conditions		 			 6
	 Quality of Design Team			 		 6
	 Quality of Construction Manager/General Contractor	 6
	 Long Lead Procurement			 		 6
Advice						 			 6
Breakdown of Projects			 			 7
Breakdown by Sector			 			 8
	 Scope Changes by Owner	 		 		 8
	 Design Errors and Omissions		 			 9
	 Unforeseen Site Conditions		 			 9
	 Long Lead Procurement	 		 		 10
	 Payment Delays				 		 10
Contact Information			 			 11
CONTENTS
4 | gardinertheobald
Gardiner  Theobald is an independent global
consultancy offering a range of services to the
construction and property industry including
project and cost management. Founded in 1835
in London, we have more than 1000 staff working
across the world with expertise in many sectors.
Our blue chip client portfolio includes occupiers,
developers, contractors, financial institutions and
local and central governments across the world.
Gardiner  Theobald Inc has been delivering projects of all
types throughout North America for the last 22 years. We
have offices located in New York City, Los Angeles and Miami.
With 122 full time staff in the United States offices, we have a
deep rooted history which provides a level of professionalism
and a culture of client service.
INTRODUCTION
RISK SURVEY | 5
EXECUTIVE SUMMARY
In early 2015, we conducted a company wide survey with our professional staff to capture a snapshot of the risks our projects face.
The survey asked each staff member to identify which risks had occurred on their recent projects that had caused a significant
impact to the project’s cost and/or schedule.
EXECUTIVE SUMMARY
Risks to projects come in all forms. Some risks can be transferred to the contractor at the time of award. Other risks are
transferable by buying insurance, such as injury or fire insurance. However, even with risk transfer, large parts of the project are
still at risk. When looking at the risks that have occurred on projects that Gardiner  Theobald Inc. has been involved with, a
clear pattern emerges as to where the risks come from.
Scope Changes by Owner
The survey shows a staggering 70% of the projects listed Scope Changes by the Owner as a risk that caused significant impact
to the project. When the project’s owner initiates scope changes after the project’s budget and schedule has been baselined, it
invariably would cause an impact to the project. The impact is exasperated after the construction contract has been awarded,
since any changes that occur during construction will not have been bought by the contractor. Unless the project owner has
sufficient management contingencies (for time and cost) in place for this risk, this will have a negative impact to the project.
Scope changes by owner
Design errors and omissions
Unforeseen conditions (geotechnical, environmental, underground...)
Quality of design team
Inspection risks (building department, fire department inspections)
Design team’s review time for RFIs, submittals, etc.
Delays in payment to contractors/consultants
Right of way/real estate agreements
Quality of construction manager/general contractor
Severe weather
Permitting risks (DOB, DOT, etc)
Funding (approval/obtaining)
Third party impacts
Long lead items/delivery
Delays caused by utilities
Market conditions
Quality of contractors/Sub - contractors
Government regulations and approvals
Constructual risks
Labor issues and strikes
Other
RISKS THAT OCCUR ON PROJECTS
0.0% 10.0% 40.0%20.0% 50.0% 70.0%30.0% 60.0% 80.0%
6 | gardinertheobald
EXECUTIVE SUMMARY
Design Errors and Omissions
According to the survey, design errors and omissions is the
second most likely risk to occur on a project. This risk captures
errors to the design, which results in change orders by the
contractors. As a risk that occurs on 55% of projects, this is a
significant risk that can be reduced if the design documents are
better defined through additional QA/QC (Quality Assurance/
Quality Control). Design consultants are required to provide
professional liability insurance to cover for their mistakes,
although in practice, it is not a comprehensive deterrent to this
risk. Recent technological improvements available, such as
BIM (Building Information Modelling), offers project designs
to have a higher level of confidence in the reduction of errors.
While the upfront costs for using BIM might be a concern
to the project owner, the risks of design errors found during
construction could be even more costly.
Unforeseen Site Conditions
Approximately 40% of projects had unforeseen site conditions
as a realized risk. This risk includes site conditions that differ
from what was budgeted and planned for, including hazmat,
soil conditions and elements hidden in walls and ceilings.
While not all unforeseen conditions can be identified before
construction begins, projects should conduct the required
number of surveys. In addition, the project should carry
sufficient levels of contingencies, particularly since it is easy to
be optimistic at project inception when no risks have occurred
yet.
Quality of Design Team
Related to design errors and omissions, the quality of the
design team was identified as a risk that occurred on 38%
of the projects. This risk includes design errors, quality of
design, response time from design team to correct mistakes,
etc. Potential causes of this risk include accepting low bids
from design consultants, which results in inadequate staffing
required to support the project. Better oversight of the design
team, adherence to contract terms and stronger contracts are
possible mitigation actions.
Quality of Construction Manager/General Contractor
Poor quality of the construction management team (including
Construction Management and General Contractors) occurred
on 35% of the responders’ projects. Often due to performance
falling below expectations. Projects should be careful of the
selection of its CM/GC contractors, including due diligence and
contract terms. The type of contract used should be in line with
the risks associated with the project to offer the adequate level
of risk transference. Staffing levels and adherence to contract
terms need to be strictly monitored.
Long Lead Procurement
Long lead items that arrive later than planned occurred on
28% of the projects. Specialized materials and architectural
designs that are not readily available can result in optimistic
schedules being at risk. The selection of materials with proper
due diligence can reduce this risk. Proper tracking of materials
against the baseline schedule with alternatives as backup can
also avoid lengthy delays.
	
ADVICE
Risks are inherently unknown. However, based on the survey
responses, it’s clear that projects should be mindful of the most
likely risks that could occur and take the proper measures to
mitigate them. Mitigation should include the following actions:
•	 Understand the level of risk specific to the project. Not all
risks are transferable and adequate levels of cost and time
contingencies should be determined.
•	 Contract terms should be understood clearly. Projects
need to be mindful of what risks have and have not
been transferred to the design team and construction
management team/contractors. Monitoring and enforcing
of contract terms must be maintained throughout the project
life cycle.
•	 Optimism bias often occurs at project inception. Proper
due diligence of the risks is required to avoid issues that are
inherent in all construction projects.
RISK SURVEY | 7
BREAKDOWN OF PROJECTS
We are currently managing projects with a combined total value in excess of $8 Billion, ranging from
landscaping and master planning, luxury hospitality to high-end residential, and from commercial
developments to civic buildings and museums. Projects in this survey include a varied mix of sector
types. The largest category is office fit-out with 43% of responses. Other large sector categories
include government projects at 13%, residential projects at 10% and hotel projects at 11%.
Office fit-out projects included in this survey are typically for large corporate clients, ranging from
10,000 sf to 550,000 sf. Government projects vary from large office buildings to entire building
campuses. The residential projects are mostly large multi-tenant buildings such as condominiums.
Hotel projects are typically high-end multi-story buildings in major cities.
Other sectors in the survey include building infrastructure, retail, mixed-use, restaurant, art, education
and media studios.
BREAKDOWN OF PROJECTS
Others
24.35%
Residential
9.6%
Hotel
11.0%
Government
12.5%
Office
42.6%
8 | gardinertheobald
BREAKDOWN BY SECTOR
BREAKDOWN BY SECTOR
The following section analyzes the top risks by sector type. The sectors compared include office fit-out,
government, hotels and residential projects.
SCOPE CHANGES BY OWNER
The chart shows that, regardless of the sector, all projects have a high risk of scope changes by owner
sometime during the project.
Government projects are especially susceptible to this risk due to multiple stakeholders and end users,
making consensus on the final design of the project more difficult. There are also political risks within
government projects that could change scope requirements, particularly with large projects that span
five to ten years.
Office fit-out projects also encounter changing requirement needs as the project progresses due to
changes with business needs, head counts and office politics.
Hotel projects included in this survey are typically unique one-off designs, such as boutique and luxury
hotels. Standardized chain hotels would not have such a high risk as the design scope would follow
standard design requirements.
0.0% 10.0% 40.0%20.0% 50.0% 70.0%30.0% 60.0% 80.0%
OFFICE
GOVERNMENT
HOTEL
RESIDENTIAL
SURVEY AVERAGE
Scope changes by owner
RISK SURVEY | 9
BREAKDOWN BY SECTOR
Design errors and omissions are significant risks on all projects, especially within the government and
hotel sectors.
Government projects in this survey are large complex projects. They often include all components
of construction, such as building core and shell, fit-out, complicated MEP and IT infrastructure. As
such, there is a higher likelihood risks would occur if there is insufficient QA/QC on the design before
construction begins.
Residential projects in this survey include many conversion projects. These typically encounter issues
with unforeseen site conditions, such as hazmat, utilities and structural deficiencies.
DESIGN ERRORS AND OMISSIONS
0.0% 10.0% 40.0%20.0% 50.0% 70.0%30.0% 60.0% 80.0%
OFFICE
GOVERNMENT
HOTEL
RESIDENTIAL
SURVEY AVERAGE
UNFORESEEN SITE CONDITIONS
0.0% 10.0% 40.0%20.0% 50.0% 70.0%30.0% 60.0% 80.0%
OFFICE
GOVERNMENT
HOTEL
RESIDENTIAL
SURVEY AVERAGE
Unforeseen site conditions
Design errors and omissions
10 | gardinertheobald
BREAKDOWN BY SECTOR
Payment delays
Long lead procurement
Long lead procurement is a significant risk on office fit-out and residential projects. These two
types of sectors often include specialized finishes, which take a long time to design, approve and
procure. These projects also have a shorter project duration, compared to government projects, so the
procurement time is more sensitive to the overall schedule.
Government projects often result in schedule impacts caused by delays to payment. Payment
procedures with government agencies are complicated and take longer than commercial projects,
resulting in extended periods to review and approve payment, as well as change orders. This results
in pressure on the contractors and consultants to perform as it impacts their cash flow. The project
itself could suffer if the contractors reduce their resources when they are unable to be paid in a timely
manner.
LONG LEAD PROCUREMENT
0.0% 10.0% 40.0%20.0% 50.0% 70.0%30.0% 60.0% 80.0%
OFFICE
GOVERNMENT
HOTEL
RESIDENTIAL
SURVEY AVERAGE
PAYMENT DELAYS
0.0% 10.0% 40.0%20.0% 50.0% 70.0%30.0% 60.0% 80.0%
OFFICE
GOVERNMENT
HOTEL
RESIDENTIAL
SURVEY AVERAGE
RISK SURVEY | 11
CONTACT INFORMATION
FOR FURTHER INFORMATION, PLEASE CONTACT:
Eric Ho, PMI-RMP
Senior Risk Manager
T: (212) 661-6624
E: e.ho@gardinerusa.com
535 Fifth Avenue, 3rd Floor
New York, NY 10017
www.gardiner.com
	
@gt_llp
RISK SURVEY
August 2015
www.gardiner.com

Más contenido relacionado

La actualidad más candente

Word Version for Resume Mark Dimmitt 2.5.15
Word Version for Resume Mark Dimmitt 2.5.15Word Version for Resume Mark Dimmitt 2.5.15
Word Version for Resume Mark Dimmitt 2.5.15
Mark Dimmitt
 
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceClaim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Francis Ho
 
Capital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_GasCapital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_Gas
Mircea Tomescu
 

La actualidad más candente (20)

Project management risks for rail projects
Project management risks for rail projectsProject management risks for rail projects
Project management risks for rail projects
 
A Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksA Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction Risks
 
Word Version for Resume Mark Dimmitt 2.5.15
Word Version for Resume Mark Dimmitt 2.5.15Word Version for Resume Mark Dimmitt 2.5.15
Word Version for Resume Mark Dimmitt 2.5.15
 
Group 1 presentation intro to cpm
Group 1 presentation intro to cpmGroup 1 presentation intro to cpm
Group 1 presentation intro to cpm
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
 
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
 
ACH 121 Lecture 02 (Arch. Basic Services )
ACH 121 Lecture 02 (Arch. Basic Services )ACH 121 Lecture 02 (Arch. Basic Services )
ACH 121 Lecture 02 (Arch. Basic Services )
 
Epc Vs Epcm
Epc Vs EpcmEpc Vs Epcm
Epc Vs Epcm
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 
ACH 216 Lecture 01 (Intro To CM)
ACH 216 Lecture 01 (Intro To CM)ACH 216 Lecture 01 (Intro To CM)
ACH 216 Lecture 01 (Intro To CM)
 
IJET-V2I6P23
IJET-V2I6P23IJET-V2I6P23
IJET-V2I6P23
 
Bridging Gt Apr09
Bridging Gt Apr09Bridging Gt Apr09
Bridging Gt Apr09
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceClaim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
 
Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)
 
Capital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_GasCapital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_Gas
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
Project mngmnt risks3.2
Project mngmnt risks3.2Project mngmnt risks3.2
Project mngmnt risks3.2
 
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”
 
Risk Management of PPP
Risk Management of PPPRisk Management of PPP
Risk Management of PPP
 

Similar a Capital Project Risk Survey

Mining Project Management Systems: Driving Predictable Project Outcomes
Mining Project Management Systems: Driving Predictable Project OutcomesMining Project Management Systems: Driving Predictable Project Outcomes
Mining Project Management Systems: Driving Predictable Project Outcomes
Jamie Morien
 
PROJ 420 Course Project
PROJ 420 Course ProjectPROJ 420 Course Project
PROJ 420 Course Project
gsb100
 
Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter Summery
Derek Cooksey
 

Similar a Capital Project Risk Survey (20)

Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...
 
[Report] Who's protecting your blindside? Construction Management: Protectin...
[Report] Who's protecting your blindside?  Construction Management: Protectin...[Report] Who's protecting your blindside?  Construction Management: Protectin...
[Report] Who's protecting your blindside? Construction Management: Protectin...
 
CPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxCPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docx
 
Standard forms lgtf
Standard forms lgtfStandard forms lgtf
Standard forms lgtf
 
Mining Project Management Systems: Driving Predictable Project Outcomes
Mining Project Management Systems: Driving Predictable Project OutcomesMining Project Management Systems: Driving Predictable Project Outcomes
Mining Project Management Systems: Driving Predictable Project Outcomes
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
 
PASBA 2010 presentation
PASBA 2010 presentationPASBA 2010 presentation
PASBA 2010 presentation
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
Risk-Management_Professional Practice 3_Architecture.pdf
Risk-Management_Professional Practice 3_Architecture.pdfRisk-Management_Professional Practice 3_Architecture.pdf
Risk-Management_Professional Practice 3_Architecture.pdf
 
Project finance
Project financeProject finance
Project finance
 
Quantity surveyors
Quantity surveyorsQuantity surveyors
Quantity surveyors
 
Maximizing Project Value with Construction Management Platforms..pdf
Maximizing Project Value with Construction Management Platforms..pdfMaximizing Project Value with Construction Management Platforms..pdf
Maximizing Project Value with Construction Management Platforms..pdf
 
PROJ 420 Course Project
PROJ 420 Course ProjectPROJ 420 Course Project
PROJ 420 Course Project
 
Construction Compliance Consultants
Construction Compliance ConsultantsConstruction Compliance Consultants
Construction Compliance Consultants
 
Project Management- Managerial Appraisal
Project Management- Managerial AppraisalProject Management- Managerial Appraisal
Project Management- Managerial Appraisal
 
What Are the Roles of a Construction Quantity Surveyor on Site
What Are the Roles of a Construction Quantity Surveyor on SiteWhat Are the Roles of a Construction Quantity Surveyor on Site
What Are the Roles of a Construction Quantity Surveyor on Site
 
Today's Contracting - Contracts Risks and Disputes
Today's Contracting - Contracts Risks and Disputes Today's Contracting - Contracts Risks and Disputes
Today's Contracting - Contracts Risks and Disputes
 
Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter Summery
 
Research paper on TQM
Research paper on TQM Research paper on TQM
Research paper on TQM
 
A.Sanchez_The rising cost and risks of large scale capital projects
A.Sanchez_The rising cost and risks of large scale capital projectsA.Sanchez_The rising cost and risks of large scale capital projects
A.Sanchez_The rising cost and risks of large scale capital projects
 

Capital Project Risk Survey

  • 1. RISK SURVEY | 1 CAPITAL PROJECT RISK SURVEY 2015
  • 3. RISK SURVEY | 3 Introduction 4 Executive Summary 5 Scope Changes by Owner 5 Design Errors and Omissions 6 Unforeseen Site Conditions 6 Quality of Design Team 6 Quality of Construction Manager/General Contractor 6 Long Lead Procurement 6 Advice 6 Breakdown of Projects 7 Breakdown by Sector 8 Scope Changes by Owner 8 Design Errors and Omissions 9 Unforeseen Site Conditions 9 Long Lead Procurement 10 Payment Delays 10 Contact Information 11 CONTENTS
  • 4. 4 | gardinertheobald Gardiner Theobald is an independent global consultancy offering a range of services to the construction and property industry including project and cost management. Founded in 1835 in London, we have more than 1000 staff working across the world with expertise in many sectors. Our blue chip client portfolio includes occupiers, developers, contractors, financial institutions and local and central governments across the world. Gardiner Theobald Inc has been delivering projects of all types throughout North America for the last 22 years. We have offices located in New York City, Los Angeles and Miami. With 122 full time staff in the United States offices, we have a deep rooted history which provides a level of professionalism and a culture of client service. INTRODUCTION
  • 5. RISK SURVEY | 5 EXECUTIVE SUMMARY In early 2015, we conducted a company wide survey with our professional staff to capture a snapshot of the risks our projects face. The survey asked each staff member to identify which risks had occurred on their recent projects that had caused a significant impact to the project’s cost and/or schedule. EXECUTIVE SUMMARY Risks to projects come in all forms. Some risks can be transferred to the contractor at the time of award. Other risks are transferable by buying insurance, such as injury or fire insurance. However, even with risk transfer, large parts of the project are still at risk. When looking at the risks that have occurred on projects that Gardiner Theobald Inc. has been involved with, a clear pattern emerges as to where the risks come from. Scope Changes by Owner The survey shows a staggering 70% of the projects listed Scope Changes by the Owner as a risk that caused significant impact to the project. When the project’s owner initiates scope changes after the project’s budget and schedule has been baselined, it invariably would cause an impact to the project. The impact is exasperated after the construction contract has been awarded, since any changes that occur during construction will not have been bought by the contractor. Unless the project owner has sufficient management contingencies (for time and cost) in place for this risk, this will have a negative impact to the project. Scope changes by owner Design errors and omissions Unforeseen conditions (geotechnical, environmental, underground...) Quality of design team Inspection risks (building department, fire department inspections) Design team’s review time for RFIs, submittals, etc. Delays in payment to contractors/consultants Right of way/real estate agreements Quality of construction manager/general contractor Severe weather Permitting risks (DOB, DOT, etc) Funding (approval/obtaining) Third party impacts Long lead items/delivery Delays caused by utilities Market conditions Quality of contractors/Sub - contractors Government regulations and approvals Constructual risks Labor issues and strikes Other RISKS THAT OCCUR ON PROJECTS 0.0% 10.0% 40.0%20.0% 50.0% 70.0%30.0% 60.0% 80.0%
  • 6. 6 | gardinertheobald EXECUTIVE SUMMARY Design Errors and Omissions According to the survey, design errors and omissions is the second most likely risk to occur on a project. This risk captures errors to the design, which results in change orders by the contractors. As a risk that occurs on 55% of projects, this is a significant risk that can be reduced if the design documents are better defined through additional QA/QC (Quality Assurance/ Quality Control). Design consultants are required to provide professional liability insurance to cover for their mistakes, although in practice, it is not a comprehensive deterrent to this risk. Recent technological improvements available, such as BIM (Building Information Modelling), offers project designs to have a higher level of confidence in the reduction of errors. While the upfront costs for using BIM might be a concern to the project owner, the risks of design errors found during construction could be even more costly. Unforeseen Site Conditions Approximately 40% of projects had unforeseen site conditions as a realized risk. This risk includes site conditions that differ from what was budgeted and planned for, including hazmat, soil conditions and elements hidden in walls and ceilings. While not all unforeseen conditions can be identified before construction begins, projects should conduct the required number of surveys. In addition, the project should carry sufficient levels of contingencies, particularly since it is easy to be optimistic at project inception when no risks have occurred yet. Quality of Design Team Related to design errors and omissions, the quality of the design team was identified as a risk that occurred on 38% of the projects. This risk includes design errors, quality of design, response time from design team to correct mistakes, etc. Potential causes of this risk include accepting low bids from design consultants, which results in inadequate staffing required to support the project. Better oversight of the design team, adherence to contract terms and stronger contracts are possible mitigation actions. Quality of Construction Manager/General Contractor Poor quality of the construction management team (including Construction Management and General Contractors) occurred on 35% of the responders’ projects. Often due to performance falling below expectations. Projects should be careful of the selection of its CM/GC contractors, including due diligence and contract terms. The type of contract used should be in line with the risks associated with the project to offer the adequate level of risk transference. Staffing levels and adherence to contract terms need to be strictly monitored. Long Lead Procurement Long lead items that arrive later than planned occurred on 28% of the projects. Specialized materials and architectural designs that are not readily available can result in optimistic schedules being at risk. The selection of materials with proper due diligence can reduce this risk. Proper tracking of materials against the baseline schedule with alternatives as backup can also avoid lengthy delays. ADVICE Risks are inherently unknown. However, based on the survey responses, it’s clear that projects should be mindful of the most likely risks that could occur and take the proper measures to mitigate them. Mitigation should include the following actions: • Understand the level of risk specific to the project. Not all risks are transferable and adequate levels of cost and time contingencies should be determined. • Contract terms should be understood clearly. Projects need to be mindful of what risks have and have not been transferred to the design team and construction management team/contractors. Monitoring and enforcing of contract terms must be maintained throughout the project life cycle. • Optimism bias often occurs at project inception. Proper due diligence of the risks is required to avoid issues that are inherent in all construction projects.
  • 7. RISK SURVEY | 7 BREAKDOWN OF PROJECTS We are currently managing projects with a combined total value in excess of $8 Billion, ranging from landscaping and master planning, luxury hospitality to high-end residential, and from commercial developments to civic buildings and museums. Projects in this survey include a varied mix of sector types. The largest category is office fit-out with 43% of responses. Other large sector categories include government projects at 13%, residential projects at 10% and hotel projects at 11%. Office fit-out projects included in this survey are typically for large corporate clients, ranging from 10,000 sf to 550,000 sf. Government projects vary from large office buildings to entire building campuses. The residential projects are mostly large multi-tenant buildings such as condominiums. Hotel projects are typically high-end multi-story buildings in major cities. Other sectors in the survey include building infrastructure, retail, mixed-use, restaurant, art, education and media studios. BREAKDOWN OF PROJECTS Others 24.35% Residential 9.6% Hotel 11.0% Government 12.5% Office 42.6%
  • 8. 8 | gardinertheobald BREAKDOWN BY SECTOR BREAKDOWN BY SECTOR The following section analyzes the top risks by sector type. The sectors compared include office fit-out, government, hotels and residential projects. SCOPE CHANGES BY OWNER The chart shows that, regardless of the sector, all projects have a high risk of scope changes by owner sometime during the project. Government projects are especially susceptible to this risk due to multiple stakeholders and end users, making consensus on the final design of the project more difficult. There are also political risks within government projects that could change scope requirements, particularly with large projects that span five to ten years. Office fit-out projects also encounter changing requirement needs as the project progresses due to changes with business needs, head counts and office politics. Hotel projects included in this survey are typically unique one-off designs, such as boutique and luxury hotels. Standardized chain hotels would not have such a high risk as the design scope would follow standard design requirements. 0.0% 10.0% 40.0%20.0% 50.0% 70.0%30.0% 60.0% 80.0% OFFICE GOVERNMENT HOTEL RESIDENTIAL SURVEY AVERAGE Scope changes by owner
  • 9. RISK SURVEY | 9 BREAKDOWN BY SECTOR Design errors and omissions are significant risks on all projects, especially within the government and hotel sectors. Government projects in this survey are large complex projects. They often include all components of construction, such as building core and shell, fit-out, complicated MEP and IT infrastructure. As such, there is a higher likelihood risks would occur if there is insufficient QA/QC on the design before construction begins. Residential projects in this survey include many conversion projects. These typically encounter issues with unforeseen site conditions, such as hazmat, utilities and structural deficiencies. DESIGN ERRORS AND OMISSIONS 0.0% 10.0% 40.0%20.0% 50.0% 70.0%30.0% 60.0% 80.0% OFFICE GOVERNMENT HOTEL RESIDENTIAL SURVEY AVERAGE UNFORESEEN SITE CONDITIONS 0.0% 10.0% 40.0%20.0% 50.0% 70.0%30.0% 60.0% 80.0% OFFICE GOVERNMENT HOTEL RESIDENTIAL SURVEY AVERAGE Unforeseen site conditions Design errors and omissions
  • 10. 10 | gardinertheobald BREAKDOWN BY SECTOR Payment delays Long lead procurement Long lead procurement is a significant risk on office fit-out and residential projects. These two types of sectors often include specialized finishes, which take a long time to design, approve and procure. These projects also have a shorter project duration, compared to government projects, so the procurement time is more sensitive to the overall schedule. Government projects often result in schedule impacts caused by delays to payment. Payment procedures with government agencies are complicated and take longer than commercial projects, resulting in extended periods to review and approve payment, as well as change orders. This results in pressure on the contractors and consultants to perform as it impacts their cash flow. The project itself could suffer if the contractors reduce their resources when they are unable to be paid in a timely manner. LONG LEAD PROCUREMENT 0.0% 10.0% 40.0%20.0% 50.0% 70.0%30.0% 60.0% 80.0% OFFICE GOVERNMENT HOTEL RESIDENTIAL SURVEY AVERAGE PAYMENT DELAYS 0.0% 10.0% 40.0%20.0% 50.0% 70.0%30.0% 60.0% 80.0% OFFICE GOVERNMENT HOTEL RESIDENTIAL SURVEY AVERAGE
  • 11. RISK SURVEY | 11 CONTACT INFORMATION FOR FURTHER INFORMATION, PLEASE CONTACT: Eric Ho, PMI-RMP Senior Risk Manager T: (212) 661-6624 E: e.ho@gardinerusa.com 535 Fifth Avenue, 3rd Floor New York, NY 10017 www.gardiner.com @gt_llp