CRITICAL PATH METHOD
(CEE 320 – VDC SEMINAR)
Jesse Santiago & Desirae Magallon4 February 2009
Overview
Background & History
CPM Defined
The CPM approach
Definitions
Class Exercise
Background & History
Developed in the 1950s by the US Navy
Originally, the critical path method considered only logical
dependencies between terminal elements
Since then, it has been expanded to allow for the inclusion of
resources related to each activity, through processes called
activity-based resource assignments and resource leveling.
Critical Path Method for the construction industry
Non-computer approach
John Fondahl
John Fondahl
Stanford CE Professor Emeritus – 35 years
Passed away last September 13th, 2008
US Marine Corps Sergeant in Iwo Jima
His father was USMC LtCol
Co-founder of the CEM program
1961 Paper for the US Navy – "Non-Computer
Approach to the Critical Path Method for the
Construction Industry"
What is CPM?
The Critical Path Method or Critical Path Analysis, is a
mathematically based algorithm for scheduling a set of project
activities
It is an important tool for effective project management
Commonly used with all forms of projects, including
construction, software development, research projects, product
development, engineering, and plant maintenance, among
others
Any project with interdependent activities can apply this
method of scheduling
What is CPM?
The essential technique for using CPM is to construct
a model of the project that includes the following:
A list of all activities required to complete the project
(also known as Work Breakdown Structure)
The time (duration) that each activity will take to
completion
The dependencies between the activities.
What is CPM?
CPM calculates
The longest path of planned activities to the end of the project
The earliest and latest that each activity can start and finish without
making the project longer
Determines “critical” activities (on the longest path)
Prioritize activities for the effective management and to
shorten the planned critical path of a project by:
Pruning critical path activities
“Fast tracking" (performing more activities in parallel)
“Crashing the critical path" (shortening the durations of critical path
activities by adding resources)
The CPM Approach
Phase I
Break project into operations necessary for completion
Determine sequential relationship of operations
Every operation must have event to mark commencement –
i.e. completion of preceding operation
Can operations overlap?
The CPM Approach
Phase II
Create time estimates for each operation
Determine earliest possible start date, earliest possible
finish date , latest start & finish
Determine “free float” and “total float”
Revised after completion of Phase III
The CPM Approach
Phase III
Establish time-cost relationship
Establish scheduling variations
Determine most favorable balance between time-cost
Normal Start – normal time, least cost
All-Crash Start – least time, higher cost
The CPM Approach
Definitions
Float (slack) - amount of time that a task can be delayed without causing a
delay to:
subsequent tasks (free float)
project completion date (total float)
Critical path is the sequence of activities which add up to the longest overall
duration. It is the shortest time possible to complete the project. Any delay of
an activity on the critical path directly impacts the planned project completion
date (there is no float on the critical path). A project can have several, parallel,
near critical paths. An additional parallel path through the network with the
total durations shorter than the critical path is called a sub-critical or non-critical
path.
Critical activity – activity with zero float
Resource leveling – iterative process of assigning crews to activities in order to
calculate their duration
Definitions
Activity ID
Early Start
(ES)
Late Finish
(LF)
Late Start
(LS)
Early Finish
(EF)
Duration
Activity Identity box
Class Exercise
C
E
G
H
F
DB
A
Activity ID Duration Dependency
A 7
B 3
C 6 A
D 3 B
E 3 D,F
F 2 B
G 3 C
H 2 E,G
STAR
T
Class Exercise
A
0 7
0 7
7
C
7 13
7 13
6
G
13 16
13 16
3
H
16 18
16 18
2
B
7 10
0 3
3
D
10 13
3 6
3
E
13 16
6 9
3
F
11 13
3 5
2
Class Exercise
Gantt Chart
Summary
Critical Path Analysis is an effective and powerful method of
assessing:
Tasks which must be carried out
Where parallel activity can be carried out
The shortest time in which a project can be completed
Resources needed to achieve a project
The sequence of activities, scheduling, and timings involved
Task priorities
References
Fondahl, John W., “Non-Computer Approach to the Critical Path Method for
the Construction Industry”, Report #9, Stanford University, 1961
Fondahl, John W. “The History of Modern Project Management –
Precedence Diagramming Methods: Origins and Early Development”.
Project Management Journal. Volume XVIII. No. 2. June 1987.
Hendrickson, Chris & Au, Tung, Project Management for Construction,
Prentice Hall, 1989
Weber, Sandra C., Scheduling Construction Projects: Principles and Practices,
Prentice Hall, 2005
Questions???

Más contenido relacionado

La actualidad más candente

Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)Nikka Lopez
 
Critical path method
Critical path methodCritical path method
Critical path methodDhruv Shah
 
CPM - Critical Path Method
CPM - Critical Path MethodCPM - Critical Path Method
CPM - Critical Path MethodParth Desani
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesSAJID ALI RUK
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Abhishek Pachisia
 
Project presentation
Project presentationProject presentation
Project presentationali ucar
 
Assignment iii cpm
Assignment iii cpmAssignment iii cpm
Assignment iii cpmahsanrabbani
 
Programe evaluation review technique
Programe evaluation review techniquePrograme evaluation review technique
Programe evaluation review techniqueshynusamuel
 
Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...IJERA Editor
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chartdanishrafiq
 
Mba ii pmom_unit-4.3 scheduling-gantt chart a
Mba ii pmom_unit-4.3 scheduling-gantt chart aMba ii pmom_unit-4.3 scheduling-gantt chart a
Mba ii pmom_unit-4.3 scheduling-gantt chart aRai University
 
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...IOSR Journals
 
4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysisDr.R. SELVAM
 

La actualidad más candente (20)

Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
2 planning
2 planning2 planning
2 planning
 
Critical path method
Critical path methodCritical path method
Critical path method
 
CPM - Critical Path Method
CPM - Critical Path MethodCPM - Critical Path Method
CPM - Critical Path Method
 
Critical Path Method presentation.
Critical Path Method presentation.Critical Path Method presentation.
Critical Path Method presentation.
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
Pert Diagram & Gantt chart
Pert Diagram & Gantt chartPert Diagram & Gantt chart
Pert Diagram & Gantt chart
 
Project presentation
Project presentationProject presentation
Project presentation
 
Assignment iii cpm
Assignment iii cpmAssignment iii cpm
Assignment iii cpm
 
Programe evaluation review technique
Programe evaluation review techniquePrograme evaluation review technique
Programe evaluation review technique
 
Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...
 
Ch08 pm2ndhalf
Ch08 pm2ndhalfCh08 pm2ndhalf
Ch08 pm2ndhalf
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chart
 
Mba ii pmom_unit-4.3 scheduling-gantt chart a
Mba ii pmom_unit-4.3 scheduling-gantt chart aMba ii pmom_unit-4.3 scheduling-gantt chart a
Mba ii pmom_unit-4.3 scheduling-gantt chart a
 
Gantt pert
Gantt pertGantt pert
Gantt pert
 
Bar chart
Bar chartBar chart
Bar chart
 
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
 
4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysis
 

Similar a Cpm

Project managemen PERT VS CPM
Project managemen  PERT VS CPMProject managemen  PERT VS CPM
Project managemen PERT VS CPMPadamNepal1
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPMstudent
 
Critical path presentation for timely project completion
Critical path presentation for timely project completionCritical path presentation for timely project completion
Critical path presentation for timely project completionAniruddha Kulkarni
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementAmit Kumbar
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGJignesh Kariya
 
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...Aravind NC
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615EqraBaig
 
Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing AlgorithmIOSR Journals
 
Network analysis cpm module3
Network analysis cpm module3Network analysis cpm module3
Network analysis cpm module3ahsanrabbani
 
Project management
Project managementProject management
Project managementChou Bảo
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesYousef Abugosh, PMP, MA
 

Similar a Cpm (20)

Project managemen PERT VS CPM
Project managemen  PERT VS CPMProject managemen  PERT VS CPM
Project managemen PERT VS CPM
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Project management
Project managementProject management
Project management
 
Ijmet 09 11_006
Ijmet 09 11_006Ijmet 09 11_006
Ijmet 09 11_006
 
Critical path presentation for timely project completion
Critical path presentation for timely project completionCritical path presentation for timely project completion
Critical path presentation for timely project completion
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULING
 
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615
 
Network Anaysis_ critical path methods
Network Anaysis_ critical path methodsNetwork Anaysis_ critical path methods
Network Anaysis_ critical path methods
 
PERT/CPM
PERT/CPMPERT/CPM
PERT/CPM
 
Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing Algorithm
 
Network analysis cpm module3
Network analysis cpm module3Network analysis cpm module3
Network analysis cpm module3
 
Project management
Project managementProject management
Project management
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
Pert cpm
Pert cpm Pert cpm
Pert cpm
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 

Más de Béla Ulicsák

Visual workflow management
Visual workflow managementVisual workflow management
Visual workflow managementBéla Ulicsák
 
Visual workflow management
Visual workflow managementVisual workflow management
Visual workflow managementBéla Ulicsák
 
Itil v3-hungarian-glossary-magyar4332
Itil v3-hungarian-glossary-magyar4332Itil v3-hungarian-glossary-magyar4332
Itil v3-hungarian-glossary-magyar4332Béla Ulicsák
 
Understandin gprince2
Understandin gprince2 Understandin gprince2
Understandin gprince2 Béla Ulicsák
 

Más de Béla Ulicsák (6)

Kuglof receptek
Kuglof receptekKuglof receptek
Kuglof receptek
 
Visual workflow management
Visual workflow managementVisual workflow management
Visual workflow management
 
Visual workflow management
Visual workflow managementVisual workflow management
Visual workflow management
 
Project wbs
Project wbsProject wbs
Project wbs
 
Itil v3-hungarian-glossary-magyar4332
Itil v3-hungarian-glossary-magyar4332Itil v3-hungarian-glossary-magyar4332
Itil v3-hungarian-glossary-magyar4332
 
Understandin gprince2
Understandin gprince2 Understandin gprince2
Understandin gprince2
 

Último

Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptxRoofing Contractor
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecZurliaSoop
 
BeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdfBeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdfDerekIwanaka1
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 MonthsIndeedSEO
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...meghakumariji156
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwaitdaisycvs
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165meghakumariji156
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizharallensay1
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon investment
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...ssuserf63bd7
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperityhemanthkumar470700
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Timegargpaaro
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfwill854175
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPanhandleOilandGas
 

Último (20)

!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
 
BeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdfBeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdf
 
Buy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail AccountsBuy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail Accounts
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 

Cpm

  • 1. CRITICAL PATH METHOD (CEE 320 – VDC SEMINAR) Jesse Santiago & Desirae Magallon4 February 2009
  • 2. Overview Background & History CPM Defined The CPM approach Definitions Class Exercise
  • 3. Background & History Developed in the 1950s by the US Navy Originally, the critical path method considered only logical dependencies between terminal elements Since then, it has been expanded to allow for the inclusion of resources related to each activity, through processes called activity-based resource assignments and resource leveling. Critical Path Method for the construction industry Non-computer approach John Fondahl
  • 4. John Fondahl Stanford CE Professor Emeritus – 35 years Passed away last September 13th, 2008 US Marine Corps Sergeant in Iwo Jima His father was USMC LtCol Co-founder of the CEM program 1961 Paper for the US Navy – "Non-Computer Approach to the Critical Path Method for the Construction Industry"
  • 5. What is CPM? The Critical Path Method or Critical Path Analysis, is a mathematically based algorithm for scheduling a set of project activities It is an important tool for effective project management Commonly used with all forms of projects, including construction, software development, research projects, product development, engineering, and plant maintenance, among others Any project with interdependent activities can apply this method of scheduling
  • 6. What is CPM? The essential technique for using CPM is to construct a model of the project that includes the following: A list of all activities required to complete the project (also known as Work Breakdown Structure) The time (duration) that each activity will take to completion The dependencies between the activities.
  • 7. What is CPM? CPM calculates The longest path of planned activities to the end of the project The earliest and latest that each activity can start and finish without making the project longer Determines “critical” activities (on the longest path) Prioritize activities for the effective management and to shorten the planned critical path of a project by: Pruning critical path activities “Fast tracking" (performing more activities in parallel) “Crashing the critical path" (shortening the durations of critical path activities by adding resources)
  • 8. The CPM Approach Phase I Break project into operations necessary for completion Determine sequential relationship of operations Every operation must have event to mark commencement – i.e. completion of preceding operation Can operations overlap?
  • 9. The CPM Approach Phase II Create time estimates for each operation Determine earliest possible start date, earliest possible finish date , latest start & finish Determine “free float” and “total float” Revised after completion of Phase III
  • 10. The CPM Approach Phase III Establish time-cost relationship Establish scheduling variations Determine most favorable balance between time-cost Normal Start – normal time, least cost All-Crash Start – least time, higher cost
  • 12. Definitions Float (slack) - amount of time that a task can be delayed without causing a delay to: subsequent tasks (free float) project completion date (total float) Critical path is the sequence of activities which add up to the longest overall duration. It is the shortest time possible to complete the project. Any delay of an activity on the critical path directly impacts the planned project completion date (there is no float on the critical path). A project can have several, parallel, near critical paths. An additional parallel path through the network with the total durations shorter than the critical path is called a sub-critical or non-critical path. Critical activity – activity with zero float Resource leveling – iterative process of assigning crews to activities in order to calculate their duration
  • 13. Definitions Activity ID Early Start (ES) Late Finish (LF) Late Start (LS) Early Finish (EF) Duration Activity Identity box
  • 14. Class Exercise C E G H F DB A Activity ID Duration Dependency A 7 B 3 C 6 A D 3 B E 3 D,F F 2 B G 3 C H 2 E,G STAR T
  • 15. Class Exercise A 0 7 0 7 7 C 7 13 7 13 6 G 13 16 13 16 3 H 16 18 16 18 2 B 7 10 0 3 3 D 10 13 3 6 3 E 13 16 6 9 3 F 11 13 3 5 2
  • 17. Summary Critical Path Analysis is an effective and powerful method of assessing: Tasks which must be carried out Where parallel activity can be carried out The shortest time in which a project can be completed Resources needed to achieve a project The sequence of activities, scheduling, and timings involved Task priorities
  • 18. References Fondahl, John W., “Non-Computer Approach to the Critical Path Method for the Construction Industry”, Report #9, Stanford University, 1961 Fondahl, John W. “The History of Modern Project Management – Precedence Diagramming Methods: Origins and Early Development”. Project Management Journal. Volume XVIII. No. 2. June 1987. Hendrickson, Chris & Au, Tung, Project Management for Construction, Prentice Hall, 1989 Weber, Sandra C., Scheduling Construction Projects: Principles and Practices, Prentice Hall, 2005