A PROJECT REPORT
ON
24 DAY INDUSTRIAL TRAINING
SUBMITTED IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE
AWARD OF
DIPLOMA IN
CIVIL ENGINEERING
(2018 – 2021 )
SUBMITTED TO
SUBMITTED BY
Yogesh Meena
START DATE:- 14-12-2020 END DATE:- 08-01-2021
GUIDED BY
Er. Shyam Sir
D R . N I D H I P O O N I A
INDEX
SECTION CONTENT
Acknowledgement
Project details
Section-1 Introduction
Safety induction
Site location
Section-2 Construction steps of building
Site clearance
Excavation
Slump Test
Compressive Strength Test
Formwork
Concreting
Beams & columns construction
Slab construction
Section-3 Materials & Equipment’s
Materials used at site
Equipment’s used
Section-4 Miscellaneous images
GOVERNMENT RAMCHANDRA KHAITAN
POLYTECHNIC COLLEGE, JAIPUR
ACKNOWLEDGMENT
This project is done as a major project titled, a part of course CIVIL
ENGINEERING DILOMA.
We are really thankful to the HOD RAKESH ASWAL, CIVIL ENGINEERING,
Govt. Ram Chandra Khaitan Polytechnic, Jaipur, for their invaluable
guidance and assistance, without which the accomplishment of the task
would have never been possible.
We also thank K2K REAL ESTATE PVT. LTD. JAIPUR, for giving us this
opportunity to explore the real world and complete our project work
within limited time fram e.
YOGESH MEENA
CIVILENGINEERING
III YEAR
PROJECT DETAIL
Multi Story Clubhouse : Located at Prem Sagar, Jagatpura, Jaipur launched by
ASHADEEP andContractfor the constructionof this building awarded to K2K REAL
ESTATE PVT. LTD
Scope: Design and contructionof building including car parking, serviceroad.
1) No of floor – G+7 2) Estimated Cost – 12.4 crores
3) ConstructionPeriod- 2.5 Years 4) ConcreteUsed– M25
(5 Months Extended Due to Lockdown)
5) Total Area – 14800 sq ft 6) Start Date – 19 Feb 2019
SAFETY INDUCTION
Safety is very important partof any work. An induction video wasshowed
which highlighted the need and importance of safety at construction site. Most
accidentscan be preventedby taking simple measuresor adopting proper
working procedures. Itis very important todiscuss issues on safetyand health
that should be paid attention to on construction sites for easy referenceby the
workers. If wework carefully and take appropriatesafetymeasures,there will
definitely be fewer work injury cases,and our siteswill become a safe and
secure place to work in. It is important to educate everyonein the site
regarding safety for following purposes.
■ Workers safety
■ Construction progress
■ Standard procedure
■ Legalcases
■ Working efficiency
Precautions at site for safety-
■ Wear protectiveequipment.
■ Wear FaceMask. 
■ Do not drink or take drugs while working.
■ Pay attentionto personalhygiene
■ Do not play in the workplace.
■ Reportto your supervisor immediately if you noticeany unsafe condition.
.
SITE LOCATION
PREM SAGAR NEAR D-MART JAGATPURA, JAIPUR 302017
Advantagesof this site
■Land.
■Store.
■Parking space.
■Swimming pool.
■Cricket Ground.
■Badminton Court.
■ServiceRoad.
SITE LOCATION
• Site location from Govt. RC Khaitan Polythecnic College
• Arial view of site
SECTION-2
CONSTRUCTION STEPS INVOLVED IN BUILDING CONSTRUCTIONS
• Site clearance.
• .
Excavation.
• Concreting.
• Beam and Columns.
SITE CLEARANCE
A no of conditions determinethe kind of building that may beerectedon a
plot of ground. These conditions determinewhere on the plot it may be
located. There arealso convenantsthat are legally binding regulations. These
may be setting height of building, prohibitutility of buildings or ban rooftop
network towersetc.
EXCAVATION
Excavation work on the site wasbeing done by the JCB Machinesand
excavatedsoil wastransferred using dumpers.
Followingmeasures shouldbe preventedwhile excavationwork.
1-There should be proper timbering whileexcavationfor basement
area.
2-Dewatering should bedone before construction work.
3-During rainy seasonexcavationwork should be avoided.
Pic source:- Nearby SIte
Slump Test Of Concrete
Concrete Slump Test is a measurement of concrete's workability, or fluidity.
It's an indirect measurement of concrete consistency or stiffness. A slump
test is a method used to determine the consistency of concrete. The
consistency, or stiffness, indicates how much water has been used in the
mix. The stiffness of the concrete mix should be matched to the
requirements for the finished product quality
Compressive Strength Test Of Concrete
Compressive strength of concrete is the Strength of hardened
concrete measured by the compression test. The compression strength of
concrete is a measure of the concrete's ability to resist loads which tend to
compress it. It is measured by crushing cylindrical concrete specimens in
compression testing machine.
Anuj
Compressive strength = Total force on cube / Area of cube
FORMWORK
Yogesh And Dashrath
Formwork (Shuttering) is temporary support as a mould for fresh
concrete, in which concrete is poured and cast in the desired shape and
gain initial strength, hardened and matured.
CONCRETING
Aftershuttering and scaffolding concreting should bedone.
Duringconcretingfollowingequipment’sareused-
■Concretemixer.
■Mountedconcretepump.
■Concretevibrators (e.g. Needle vibrator, plate/ surfacevibrator etc.)
*Only Needle vibrator is being used at our site
Duringconcretingworkfollowinginstructionsshouldbe followed-
■There should be proper compaction of poured concrete.
■There should be spacers/cover blocksto provide cover to reinforcement.
■There should be proper curing of concreteconstruction.
BEAMS AND COLUMNS
In framed structure fixedtypebeamsareconstructed. In such typeof
beamsproper reinforcement should bedone for positive as well as
negative bending moments.
In such typeof structures shortcolumns are constructed withminimum eccentricity. In
square or rectangular shaped columns min. 4 no’sof 12 mm diameterbarsmust be
used and spacing should notbe morethan as per code IS Code 456:2000.
SLAB CASTING
Reinforcement
8 mm dialateralties 25mmdia longitudionalbars
1. COLUMN SIZE:- 600x900mm
2. ROD :-Reinforcement used in column10 ROD.
3. ROD DIAMETER:- (8)32mm, (18)25mm
4. RING USED IN COLUMN:- BOTTOM TO ROOF TOTAL-
24RING.
5. RING DIAMETER:- 8mm
6. RING AROUND ANGLE-90,135DEGREE
Fact- Rebar is the short form of Reinforcement Bar
Curing
Curing of concrete is defined as providing adequate moisture,
temperature, and time to allow the concrete to achieve the desired
properties for its intended use
*hessian cloth is used for supporting curing at our site
Hessian cloth
SECTION-3
MATERIALS
MATERIALS USED FOR CONSTRUCTION AT SITE
At the construction site following materials werebeing used
Cement
The function of cementis to combine with water and to form cementpaste.
This paste first sets i.e. it becomesfirms and thenhardens dueto chemical
reaction, calledhydration, betweenthecementand water. Onsetting &
hardening, thecementbinds the aggregate together into a stone like hard
mass & thus provides strength, durability & water-tightentothe concrete.
Quality of cementis based on grade of cement.The grades of cement are as-
■33 Grades
■43 Grades
■53 Grades
■At the site Portlandcementof 53 grades(ULTRATECHCEMENT) wasused.
■The initial setting time of cement = 30 minutes (1/2 hr.)
■The final setting time of cement= 10hrs.
The material that develops a good bond with concrete in order to increase
its strength is called reinforcement. Steel bars are highly strong in tension,
shear,bending moment, torsion and compression.
■Functionof reinforcement-
Reinforcement working asa tension member because concreteis strong in
compression and week in tension so reinforcementresiststhe tensile
stresses in the concretemembers. Atthe site contractor using thehigh
strengthsteel barsand T.M.T. (Thermo Mechanically Treated) barsof
diameter8 mm,10 mm, 16 mm,& 32 mm as per requirementof design.
At constructionsite8 mm, 10 mm, 16 mm,& 32 mm(T.M.T.) reinforcement
barswerebeing used.
The barswere of grade Fe415 for 8mm and Fe500 for other diameter
bars. The barswereof brand TATA TISCON.
■The main reasonof usingsteel barsinRCC is that, the coefficients of
thermal expansionof steel bars and concreteisof approximately equal
value.
EQUIPMENTS USED
Concretepump
Rotarymixerfor transporting
R.M.C.
Crane
Boompump(usedin construction of retaining wallwhere transportation of
R.M.C.was very difficult because of excavation work
Ready MixConcreteplant
IMAGES OF EQUIPMENTS USED-
SECTION-4
Miscllaeneous images of construction site
We studying about the site construction
Reinforcementforstaircase atsite
Dashrath,Yogesh,Devansh
Reinforcementinbeam&column
Scaffolding Gugu
Spacers/Cover Block
Coupler
24 DAY INDUSTRIAL TRAINING- CIVIL DIPLOMA

Más contenido relacionado

La actualidad más candente

Construction plan 29.08. 14
Construction plan 29.08. 14Construction plan 29.08. 14
Construction plan 29.08. 14
Winter Sonata
 
Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surface
Minh Bui Si
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
Abhishek Singh
 

La actualidad más candente (20)

construction study project sjce ctm
construction study project sjce ctmconstruction study project sjce ctm
construction study project sjce ctm
 
Industrial training presentation
Industrial training presentationIndustrial training presentation
Industrial training presentation
 
Design & Construction Errors- Building Maintenance and Repairs
Design & Construction Errors- Building Maintenance and Repairs Design & Construction Errors- Building Maintenance and Repairs
Design & Construction Errors- Building Maintenance and Repairs
 
QA/QC Civil Engineer
QA/QC Civil EngineerQA/QC Civil Engineer
QA/QC Civil Engineer
 
Construction of residential building
Construction of residential buildingConstruction of residential building
Construction of residential building
 
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONPROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
 
INTERNSHIP REPORT FOR CONCSTRUCTION MANAGEMENT AND ORGANISING WORKS OF A BUIL...
INTERNSHIP REPORT FOR CONCSTRUCTION MANAGEMENT AND ORGANISING WORKS OF A BUIL...INTERNSHIP REPORT FOR CONCSTRUCTION MANAGEMENT AND ORGANISING WORKS OF A BUIL...
INTERNSHIP REPORT FOR CONCSTRUCTION MANAGEMENT AND ORGANISING WORKS OF A BUIL...
 
Method of Statement - Road furniture works
Method of Statement - Road furniture worksMethod of Statement - Road furniture works
Method of Statement - Road furniture works
 
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking Construction
 
Construction plan 29.08. 14
Construction plan 29.08. 14Construction plan 29.08. 14
Construction plan 29.08. 14
 
Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surface
 
Deterioration of Concrete
Deterioration of ConcreteDeterioration of Concrete
Deterioration of Concrete
 
Airport Construction
Airport ConstructionAirport Construction
Airport Construction
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
 
Summer training report on cement Road Construction
 Summer training report on cement Road Construction Summer training report on cement Road Construction
Summer training report on cement Road Construction
 
Central Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training reportCentral Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training report
 
Summer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteSummer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction Site
 
Column & beam
Column & beamColumn & beam
Column & beam
 
Civil Engineer Resume
 Civil Engineer Resume Civil Engineer Resume
Civil Engineer Resume
 

Similar a 24 DAY INDUSTRIAL TRAINING- CIVIL DIPLOMA

Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
Minh Bui Si
 

Similar a 24 DAY INDUSTRIAL TRAINING- CIVIL DIPLOMA (20)

Abhishek presentation.pptx
Abhishek presentation.pptxAbhishek presentation.pptx
Abhishek presentation.pptx
 
IRJET- Strengthening of New Building
IRJET- Strengthening of New BuildingIRJET- Strengthening of New Building
IRJET- Strengthening of New Building
 
Building Industrial Training report for CIVIL ENGINEERING
Building Industrial Training report for CIVIL ENGINEERINGBuilding Industrial Training report for CIVIL ENGINEERING
Building Industrial Training report for CIVIL ENGINEERING
 
B.Tech Final Year Internship @ Delhi Metro Rail Corporation
B.Tech Final Year Internship @ Delhi Metro Rail CorporationB.Tech Final Year Internship @ Delhi Metro Rail Corporation
B.Tech Final Year Internship @ Delhi Metro Rail Corporation
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
 
Rishabh kumar
Rishabh kumarRishabh kumar
Rishabh kumar
 
internship report report
internship report reportinternship report report
internship report report
 
IRJET- Effect of Different Curing on Strength of Concrete
IRJET-  	  Effect of Different Curing on Strength of ConcreteIRJET-  	  Effect of Different Curing on Strength of Concrete
IRJET- Effect of Different Curing on Strength of Concrete
 
Construction of post tension slab
Construction of post tension slabConstruction of post tension slab
Construction of post tension slab
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentation
 
Concrete pdf
Concrete pdfConcrete pdf
Concrete pdf
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Site report
Site reportSite report
Site report
 
Buildng construction report
Buildng construction reportBuildng construction report
Buildng construction report
 
A012550107
A012550107A012550107
A012550107
 
4
44
4
 
om industrial training report.pptx
om industrial training report.pptxom industrial training report.pptx
om industrial training report.pptx
 
capstoe PPT FINAL GLAX G.S.pptx
capstoe PPT FINAL GLAX G.S.pptxcapstoe PPT FINAL GLAX G.S.pptx
capstoe PPT FINAL GLAX G.S.pptx
 
IRJET- Experimental Investigation for Strength of Concrete by using Rice Husk
IRJET- Experimental Investigation for Strength of Concrete by using Rice HuskIRJET- Experimental Investigation for Strength of Concrete by using Rice Husk
IRJET- Experimental Investigation for Strength of Concrete by using Rice Husk
 

Más de Department of Management Studies, Malaviya National Institute of Technology Jaipur

Investment Avenues in India
Investment Avenues in IndiaInvestment Avenues in India

Más de Department of Management Studies, Malaviya National Institute of Technology Jaipur (15)

Consumer Protection and Consumers Rights
Consumer Protection and Consumers RightsConsumer Protection and Consumers Rights
Consumer Protection and Consumers Rights
 
Sample Resume Freshers - Business Analytics/Business Consultant
Sample Resume Freshers - Business Analytics/Business ConsultantSample Resume Freshers - Business Analytics/Business Consultant
Sample Resume Freshers - Business Analytics/Business Consultant
 
We Care For You- Sample Pitch Deck
We Care For You- Sample Pitch DeckWe Care For You- Sample Pitch Deck
We Care For You- Sample Pitch Deck
 
Social Media Marketing- Conceptual Study
Social Media Marketing- Conceptual StudySocial Media Marketing- Conceptual Study
Social Media Marketing- Conceptual Study
 
An Analysis on Union Budget
An Analysis on Union BudgetAn Analysis on Union Budget
An Analysis on Union Budget
 
Business Analytics For Managers Brochure
Business Analytics For Managers BrochureBusiness Analytics For Managers Brochure
Business Analytics For Managers Brochure
 
Derivatives - Payoff
Derivatives - Payoff Derivatives - Payoff
Derivatives - Payoff
 
Investment Avenues in India
Investment Avenues in IndiaInvestment Avenues in India
Investment Avenues in India
 
Case- Uber vs. Didi
Case- Uber vs. DidiCase- Uber vs. Didi
Case- Uber vs. Didi
 
Bad Boy Billionaries
Bad Boy BillionariesBad Boy Billionaries
Bad Boy Billionaries
 
Report: Tips to Make Your Resume and Interview Performance Stand Out
Report: Tips to Make Your Resume and Interview Performance Stand OutReport: Tips to Make Your Resume and Interview Performance Stand Out
Report: Tips to Make Your Resume and Interview Performance Stand Out
 
Case Study- Times have Changed
Case Study- Times have ChangedCase Study- Times have Changed
Case Study- Times have Changed
 
Dabbawala's Management Practices
Dabbawala's Management PracticesDabbawala's Management Practices
Dabbawala's Management Practices
 
Introduction to Management Accounting
Introduction to Management AccountingIntroduction to Management Accounting
Introduction to Management Accounting
 
The Power Of Your Subconscious Mind
The Power Of Your Subconscious MindThe Power Of Your Subconscious Mind
The Power Of Your Subconscious Mind
 

Último

Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
dharasingh5698
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
amitlee9823
 

Último (20)

Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 

24 DAY INDUSTRIAL TRAINING- CIVIL DIPLOMA

  • 1. A PROJECT REPORT ON 24 DAY INDUSTRIAL TRAINING SUBMITTED IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE AWARD OF DIPLOMA IN CIVIL ENGINEERING (2018 – 2021 ) SUBMITTED TO SUBMITTED BY Yogesh Meena START DATE:- 14-12-2020 END DATE:- 08-01-2021 GUIDED BY Er. Shyam Sir D R . N I D H I P O O N I A
  • 2. INDEX SECTION CONTENT Acknowledgement Project details Section-1 Introduction Safety induction Site location Section-2 Construction steps of building Site clearance Excavation Slump Test Compressive Strength Test Formwork Concreting Beams & columns construction Slab construction Section-3 Materials & Equipment’s Materials used at site Equipment’s used Section-4 Miscellaneous images
  • 3. GOVERNMENT RAMCHANDRA KHAITAN POLYTECHNIC COLLEGE, JAIPUR ACKNOWLEDGMENT This project is done as a major project titled, a part of course CIVIL ENGINEERING DILOMA. We are really thankful to the HOD RAKESH ASWAL, CIVIL ENGINEERING, Govt. Ram Chandra Khaitan Polytechnic, Jaipur, for their invaluable guidance and assistance, without which the accomplishment of the task would have never been possible. We also thank K2K REAL ESTATE PVT. LTD. JAIPUR, for giving us this opportunity to explore the real world and complete our project work within limited time fram e. YOGESH MEENA CIVILENGINEERING III YEAR
  • 4. PROJECT DETAIL Multi Story Clubhouse : Located at Prem Sagar, Jagatpura, Jaipur launched by ASHADEEP andContractfor the constructionof this building awarded to K2K REAL ESTATE PVT. LTD Scope: Design and contructionof building including car parking, serviceroad. 1) No of floor – G+7 2) Estimated Cost – 12.4 crores 3) ConstructionPeriod- 2.5 Years 4) ConcreteUsed– M25 (5 Months Extended Due to Lockdown) 5) Total Area – 14800 sq ft 6) Start Date – 19 Feb 2019
  • 5. SAFETY INDUCTION Safety is very important partof any work. An induction video wasshowed which highlighted the need and importance of safety at construction site. Most accidentscan be preventedby taking simple measuresor adopting proper working procedures. Itis very important todiscuss issues on safetyand health that should be paid attention to on construction sites for easy referenceby the workers. If wework carefully and take appropriatesafetymeasures,there will definitely be fewer work injury cases,and our siteswill become a safe and secure place to work in. It is important to educate everyonein the site regarding safety for following purposes. ■ Workers safety ■ Construction progress ■ Standard procedure ■ Legalcases ■ Working efficiency Precautions at site for safety- ■ Wear protectiveequipment. ■ Wear FaceMask.  ■ Do not drink or take drugs while working. ■ Pay attentionto personalhygiene ■ Do not play in the workplace. ■ Reportto your supervisor immediately if you noticeany unsafe condition. .
  • 6. SITE LOCATION PREM SAGAR NEAR D-MART JAGATPURA, JAIPUR 302017 Advantagesof this site ■Land. ■Store. ■Parking space. ■Swimming pool. ■Cricket Ground. ■Badminton Court. ■ServiceRoad.
  • 7. SITE LOCATION • Site location from Govt. RC Khaitan Polythecnic College • Arial view of site
  • 8. SECTION-2 CONSTRUCTION STEPS INVOLVED IN BUILDING CONSTRUCTIONS • Site clearance. • . Excavation. • Concreting. • Beam and Columns. SITE CLEARANCE A no of conditions determinethe kind of building that may beerectedon a plot of ground. These conditions determinewhere on the plot it may be located. There arealso convenantsthat are legally binding regulations. These may be setting height of building, prohibitutility of buildings or ban rooftop network towersetc. EXCAVATION Excavation work on the site wasbeing done by the JCB Machinesand excavatedsoil wastransferred using dumpers. Followingmeasures shouldbe preventedwhile excavationwork. 1-There should be proper timbering whileexcavationfor basement area. 2-Dewatering should bedone before construction work. 3-During rainy seasonexcavationwork should be avoided. Pic source:- Nearby SIte
  • 9. Slump Test Of Concrete Concrete Slump Test is a measurement of concrete's workability, or fluidity. It's an indirect measurement of concrete consistency or stiffness. A slump test is a method used to determine the consistency of concrete. The consistency, or stiffness, indicates how much water has been used in the mix. The stiffness of the concrete mix should be matched to the requirements for the finished product quality
  • 10. Compressive Strength Test Of Concrete Compressive strength of concrete is the Strength of hardened concrete measured by the compression test. The compression strength of concrete is a measure of the concrete's ability to resist loads which tend to compress it. It is measured by crushing cylindrical concrete specimens in compression testing machine. Anuj Compressive strength = Total force on cube / Area of cube
  • 11. FORMWORK Yogesh And Dashrath Formwork (Shuttering) is temporary support as a mould for fresh concrete, in which concrete is poured and cast in the desired shape and gain initial strength, hardened and matured.
  • 12. CONCRETING Aftershuttering and scaffolding concreting should bedone. Duringconcretingfollowingequipment’sareused- ■Concretemixer. ■Mountedconcretepump. ■Concretevibrators (e.g. Needle vibrator, plate/ surfacevibrator etc.) *Only Needle vibrator is being used at our site Duringconcretingworkfollowinginstructionsshouldbe followed- ■There should be proper compaction of poured concrete. ■There should be spacers/cover blocksto provide cover to reinforcement. ■There should be proper curing of concreteconstruction.
  • 13. BEAMS AND COLUMNS In framed structure fixedtypebeamsareconstructed. In such typeof beamsproper reinforcement should bedone for positive as well as negative bending moments. In such typeof structures shortcolumns are constructed withminimum eccentricity. In square or rectangular shaped columns min. 4 no’sof 12 mm diameterbarsmust be used and spacing should notbe morethan as per code IS Code 456:2000. SLAB CASTING
  • 14. Reinforcement 8 mm dialateralties 25mmdia longitudionalbars 1. COLUMN SIZE:- 600x900mm 2. ROD :-Reinforcement used in column10 ROD. 3. ROD DIAMETER:- (8)32mm, (18)25mm 4. RING USED IN COLUMN:- BOTTOM TO ROOF TOTAL- 24RING. 5. RING DIAMETER:- 8mm 6. RING AROUND ANGLE-90,135DEGREE Fact- Rebar is the short form of Reinforcement Bar
  • 15. Curing Curing of concrete is defined as providing adequate moisture, temperature, and time to allow the concrete to achieve the desired properties for its intended use *hessian cloth is used for supporting curing at our site Hessian cloth
  • 16. SECTION-3 MATERIALS MATERIALS USED FOR CONSTRUCTION AT SITE At the construction site following materials werebeing used Cement The function of cementis to combine with water and to form cementpaste. This paste first sets i.e. it becomesfirms and thenhardens dueto chemical reaction, calledhydration, betweenthecementand water. Onsetting & hardening, thecementbinds the aggregate together into a stone like hard mass & thus provides strength, durability & water-tightentothe concrete. Quality of cementis based on grade of cement.The grades of cement are as- ■33 Grades ■43 Grades ■53 Grades ■At the site Portlandcementof 53 grades(ULTRATECHCEMENT) wasused. ■The initial setting time of cement = 30 minutes (1/2 hr.) ■The final setting time of cement= 10hrs.
  • 17. The material that develops a good bond with concrete in order to increase its strength is called reinforcement. Steel bars are highly strong in tension, shear,bending moment, torsion and compression. ■Functionof reinforcement- Reinforcement working asa tension member because concreteis strong in compression and week in tension so reinforcementresiststhe tensile stresses in the concretemembers. Atthe site contractor using thehigh strengthsteel barsand T.M.T. (Thermo Mechanically Treated) barsof diameter8 mm,10 mm, 16 mm,& 32 mm as per requirementof design. At constructionsite8 mm, 10 mm, 16 mm,& 32 mm(T.M.T.) reinforcement barswerebeing used. The barswere of grade Fe415 for 8mm and Fe500 for other diameter bars. The barswereof brand TATA TISCON. ■The main reasonof usingsteel barsinRCC is that, the coefficients of thermal expansionof steel bars and concreteisof approximately equal value.
  • 18. EQUIPMENTS USED Concretepump Rotarymixerfor transporting R.M.C. Crane Boompump(usedin construction of retaining wallwhere transportation of R.M.C.was very difficult because of excavation work Ready MixConcreteplant IMAGES OF EQUIPMENTS USED-
  • 19. SECTION-4 Miscllaeneous images of construction site We studying about the site construction Reinforcementforstaircase atsite Dashrath,Yogesh,Devansh