Introducton to High-Rise
Building Structures in China
Zhang yanxia
zhangyanxia@bucea.edu.cn
Beijing University of Civil Engineering and Architecture
July 19th,2011
Introduction to high-rise building structures in China
Outlines
Main structural types in high-rise building structures
 Intruduction to steel-concrete hybrid structures
 Example1:Beijing Fortune Plaza 2 Office Tower
Example2: China World Trade Centre 3
1.Main structural types in high-rise
building structures
(according to different material)

Concrete Structures
Steel Structures
Steel-Concrete Hybrid
Structures
3
Concrete Structure

1 CITIC Plaza ,Guangzhou ,1996 ,390m
2 Jinmao International Plaza, Shanghai, 2006, 333m
3 Chongqing World Trade Center , Chongqing, 2005, 283m

4
Steel Structure

1 Beijing TV Centre, Beijing,2007 ,294m
2 Minsheng Bank Building, Wuhan, 2008, 331m
3 CCTV Tower, Beijing, 2011, 239m

5
Phoenix International Media Center
Phoenix International Media Center is a
multipurpose
and
comprehensive
architecture with functions of television
programming, offices and business. As
usual, media building has large space such
as broadcasting hall, as well as typical
office floors vertically. It is hard for this two
parts to achieve a harmonious effect.
However, in this program, Designers resort
to the pattern of Mobius, that is, combines
high office floor with media broadcasting
hall. While satisfying the need of the place
for programming as well as other
supporting establishments, it becomes a
complete space and volume. Unique
building shape combines with the natural
scene in Chaoyang Park.

6
Phoenix International Media Center

7
2. Introduction of hybrid structure
Hybrid structure system composed
by steel frame ,steel reinforcement
concrete( SRC) frame or concrete
filled tube( CFT) frame and RC
core tube is a new optional
structure system, which is widely
used in the design of high-rise
buildings, especially the super
high-rise buildings, in China
nowadays.

8
Hybrid Structure

1 Greenland Financial Center, Nanjing, 2010, 450m
2 Shanghai World Financial Center, Shanghai, 2008, 492m
3 China World Trade Center III, Beijing, 2010, 330m

9
The main advantages of hybrid structures:
Compared with concrete structures
•Decrease the structural weight
•Reduce the components section
•Speed up the progress of construction
•Improve the performance of the structures
10
The main advantages of hybrid structures:
Compared with steel structure
Improve the fire proof performance of the
structure
Decrease the overall cost
Increase the lateral stiffness of the structure
Improve the comfortable performance under
wind load

11
2. Introduction of hybrid structure
At present, many high-rise buildings which is about 150m to
200m height or even above 300m height are hybrid structure,
but most of those buildings are located in the area of seismic
intensity fortification 7( design basic acceleration is 0.10g or
0.15g).
According to Chinese building code JGJ3-2002, the maximum
application height for hybrid structures is 150m for the area of
seismic intensity fortification 8( design basic acceleration is
0.20g).
The Beijing Fortune Plaza 2 office tower is 265m tall and will
become the second tallest building after the CWTC 3A mega
tower in Beijing,, which is in the area of seismic intensity
fortification 8, and the tallest CFT frame-RC core wall hybrid
structure in Beijing.

12
typical buildings of hybrid structure
Xuelian Building
Xuelian building is a high-rise
structure, and is built in high
seismic intensity region. It has 36
floors above the ground, and is
146.30m totally high. It s irregular
plan and non-orthogonal frame
result in weak lateral stiffness. To
solve these structural difficulties,
the following measures are
adopted.
The
structure
is
designed as a mixed structure
which is composed of concretefilled rectangular steel tube frames
and reinforced concrete tubes.
Two strengthening stories are
designed with outriggers and belt
members.

13
typical buildings of hybrid structure

Xuelian Building in construction
14
typical buildings of hybrid structure

Connections in Xuelian Building
15
typical buildings of hybrid structure
CNPC Office Building
CNPC Office Building include 4 tower and several podium
buildings. Tower is 90m high, has 22 stories above the
ground( Tower D is 18 stories),and has 4 stories basement. The
podium building is 38.2m high,and has 10 stories above the
ground.The standard story height is 3.9m.

16
Construction Progress
04.12.8
05.1.1
05.2.1
05.3.1
05.4.2
05.5.2
05.6.2
05.7.2
05.8.5
05.9.2
05.10.2
05.11.8
05.12.8
17
Construction Progress

18
Construction Progress

19
Construction Progress

20
typical buildings of hybrid structure
Jinmao Tower
The building is located on a
24000m² plot of land near the Lujiazui
metro station. The 88 floors (93 if the
spire floors are counted) are divided into
16 segments, each of which is 1/8
shorter than the 16-storey base. The
tower is built around an octagonshaped concrete shear
wall core
surrounded by 8 exterior composite
super columns and 8 exterior steel
columns. Three sets of 8 two-story
high outrigger
trusses connect
the
columns to the core at six of the floors to
provide additional support.
21
typical buildings of hybrid structure
Shanghai World Finacial Center
The building is a supertall skyscraper in
Pudong, Shanghai. In order to decrease
the weight of the building, the majority of
that decrease had to be found in a
reduction of the thickness of the
concrete shear walls of the services
core. This reduction could be achieved
only by decreasing the wind and
earthquake induced lateral forces
resisted by those walls. That decrease
could be found only by increasing the
stiffness of the lateral force resisting
system of the perimeter wall.
22
typical buildings of hybrid structure
Shanghai World Finacial Center
To resist the forces from typhoon
(hurricane) winds and earthquakes,
three parallel and interacting structural
systems were incorporated:
1) The mega-structure, consisting of the
major structural columns, the major
diagonals, and the belt trusses.
2) The concrete walls of the services
core.
3) The interaction between the concrete
walls of the services core and the megacolumns, as created by the outrigger
trusses.

23
Example1 Beijing Fortune Plaza 2 Office Tower
3.1 Introduction :
Location : the Center Business District (CBD) Beijing;
Height: 256.35m ;
Floor : 59 floors and 4 floors underground ;
Architectural Area : 150,000m2
Structure System : CFT frame-RC shear wall core
24
3 Beijing Fortune Plaza 2 Office Tower
3.2 DESIGN STANDARDS
The design of the proposed development will comply the following
current code of practices in China:
(1) Unified standard for reliability design of building structures GB50068-2001
(2) General definitions & symbols Architectural Design GB/T50083-97
(3) General definitions & symbols Structural Design GBJ132-90
(4) Specifications for Loading in Building Structure GB50009-2001
(5) Code of Seismic Design of Buildings GB50011-2001
(6) Code for Design of Concrete Structures GB50010-2002
(7) Code for Design of Steel Structures GB50017-2003
(8) Technical Specification for Steel Structure of Tall Buildings JGJ99-98

25
2 Beijing Fortune Plaza 2 Office Tower
(9) Technical Specification for Box and Raft Foundation JGJ6-99
for Tall Buildings
(10) Specification for Pile Foundation of Buildings JGJ94-94
(11) Beijing Standard – Specifications for Foundation Design DBJ01-501-92
(12) Technical Specification for Tall Reinforced Concrete Buildings JGJ3-2002
(13) Technical Specification for Steel Reinforced Concrete JGJ138-2001
Composite Structures
In case where elements are not covered by Chinese Standard, reference to the
following standard would be made.
(1) Prestandard and Commentary for the Seismic Rehabilitation FEMA356
of Building
(2) Seismic Evaluation and Retrofit of Concrete Buildings ATC40

26
2 Beijing Fortune Plaza 2 Office Tower
2.3 MATERIAL DATA
2.3.1 Concrete
Grade of concrete for structural components must not less than C30,
according to GB50010-2002.
Design parameters are as follows:
Concrete Grade Standard Value

fck (N/mm²)

C30
C35
C40
C45
C50
C60

20.1
23.4
26.8
29.6
32.4
38.5

Design Value,
fc (N/mm²)
14.3
16.7
19.1
21.1
23.1
27.5

Young’s Modulus
Ec (N/mm²)
3.00×104
3.15×104
3.25×104
3.35×104
3.45×104
3.6×104

27
3 Beijing Fortune Plaza 2 Office Tower
3.3.2 Reinforcement
All reinforcement complies with Chinese Standard GB50010-2002.
Type

dia
(mm)

Standard Value
fyk (N/mm2)

DesignValue
fy , fy’
(N/mm2)

Young’s Modulus
Es (N/mm2)

HPB235
HRB335

8~20
6~50

235
335

210/210
300/300

2.1×105
2.0×105

HRB400

6~50

400

360/360

2.0×105

28
2 Beijing Fortune Plaza 2 Office Tower
2.3.3 Structural Steel
All structural steel would be either British Standard Grade 43/Grade 50
or Chinese Standard Q235/Q345.

29
2 Beijing Fortune Plaza 2 Office Tower

30
3 Beijing Fortune Plaza 2 Office Tower
3.4 LOADS
3.4.1 Floor Loads
The following live and superimposed loads based on the Chinese Code
GB50009-2001 are used.
Standard loads of the Fortune Plaza 2 office tower (kN/m²)
Location / Type of Loading
Roof

Live load
1.5 or actual load

E&M

Finishes

1.5

4.8

–
1.0

Typical Office Floor

3.0

0.5

1.7*

Typical Hotel Floor

2.0

0.3

1.2

Staircase

3.0

–

1.2

Mechanical room
Refuge Floor
* ceiling = 0.5, finishes = 1.2

Not less than 7.5 or actual load
5.0

Partitions

–

According to
framing plan
–

1.2

–

1.2

–

31
3 Beijing Fortune Plaza 2 Office Tower
3.4.2 wind loads
The wind loads based on the Chinese Code GB50009-2001. Based on
100 years return period, Design wind Load is 0.50kN/m².
Wind loads and acceleration for the engineering are still being
expected from wind tunnel tests conducted by BMT company. The
result of test is similar with the calculation of Chinese Code GB500092001.

Wind tunnel test

3.4.3 Snow loads
Based on 100 years return period, Design Snow Load is 0.45kN/m².

32
3 Beijing Fortune Plaza 2 Office Tower
3.4.4 Earthquake Loads
The data below is based on Chinese Code GB50011-2001 and the
recommendations from the “Seismic Hazard Assessment Report ”
provided in June, 2008. The Site Category and Seismic Intensity
fortification are based on Chinese Code GB50011-2001.
•Seismic intensity fortification: Degree 8
Design basic acceleration = 0.20g
•Site Category: Category II, Group 1, Tg = 0.37s
•Period reduce modulus:0.9;
•Structural damping ratio:0.04(frequent earthquake),0.04(design
earthquake),0.05(rare earthquake);

33
3 Beijing Fortune Plaza 2 Office Tower

34
3 Beijing Fortune Plaza 2 Office Tower
3.5 Comparison with Code Limits
Requirement in Chinese
Building Codes
Structure System
Story

Tower
Basement

CFT Frame - RC Core
Tube
59
4

Tower

256.35m(part 7.3m above
the roof)

Basement

Height
(m)

Note

JGJ3-2002 Table
11.1.2 : the maximal
application height for
Unsatisfied
hybrid structures is 150m
for the area of seismic
intensity 8

18.5

Dimension of Standard
Floor Plan (Length×Width,
m)
Structure Height to Width
Ratio

64.33×41.85

256.35/41.85 =6.13

JGJ 3-2002
Table11.1.3:the value
should less than 6

Unsatisfied
35
3 Beijing Fortune Plaza 2 Office Tower

Torsion
Irregularity

Horizontal
Irregularity

Geometric
Irregularity

Diaphragm
Discontinuity
Irregularity

Y-Direction: all less than
1.2; X-Direction: part
beyond 1.2 , but less
than 1.3,others less than
1.2

JGJ 3-2002§4.3.5:for the Class B
structure, the torsion displacement
Mainly
ratio should less than 1.2, must less
Satisfied
than 1.4, when accidental torsion
effect is considered.

—

JGJ3-2002§4.3.6:reduced
floor
width should less than 50% of the
total
width.GB50011-2001§3.4.2: Satisfied
reduced floor width should less than
30% of the total width in one side.

—

GB50011-2001§3.4:floor
effective
width less than 50% of the total
width, the open area of floor should Satisfied
less than 30% of the total area, and
no out-of-plan offset exist.

36
3 Beijing Fortune Plaza 2 Office Tower
Stiffness mutation exist at the
stories adjoin to the
Stiffness Soft
strengthen story , but still
Story Irregularity
satisfy with the code
requirement.
Vertical
Discontinuity in
Irregularity
Vertical Lateral

Weak Story
Irregularity

GB50011-2001§3.4.2:
story
lateral stiffness should not less
than 70% of the stiffness of the
Satisfied
upper story, and 80% of the
average stiffness of the upper 3
stories.

GB50011-2001§3.4.2:
vertical
Discontinuity in vertical lateral
force should not be transferred by Satisfied
not exist
horizontal members.
JGJ3-2002§4.4.3:for the Class B
Bearing Capacity mutation structure, the story shear bearing
exist for the strengthen stories capacity should not less than
exist.
75% of the capacity of the upper
story.

Story Shear to Weight Ratio Minimum Value : 0.024

JGJ3-2002§3.3.13:to structure
whose fundamental period
beyond 5s,the minimum value is
0.024

Satisfied

37
3 Beijing Fortune Plaza 2 Office Tower
3.6 Floor Diaphragm
•Profiled steel sheeting-concrete
composite slabs
•Steel beam connected with RC slab by shear
resisting stud
•C40 concrete is used
•Thickness:
a.130mm for office stories(requirement of
comfortable) 200mm for mechanical
stories/strengthen stories(the result of elastic
calculation)
b.200mm for the 1st bottom floor(requirement of
embed)
c.200mm for the roof, 130mm for the concrete
floor in the core tube.
38
3 Beijing Fortune Plaza 2 Office Tower
3.7 Lateral Resisting System—Core Tube

39
3 Beijing Fortune Plaza 2 Office Tower
3.7 Lateral Resisting System—Core Tube
•Dimension:
42.3m×15.9m(Footing-44th Story),34.8m×15.1m(45th Story-Roof)
•Thickness:
Decrease smoothly from 1200mm to 600mm with story increasing
•The core tube resists most of the gravity and lateral force, and shows a great
torsion resisting capacity.

40
3 Beijing Fortune Plaza 2 Office Tower
3.7 Lateral Resisting System—Core Tube
According to the Chinese Building
Codes, the seismic resisting level
of the core tube is special 1st ,so
the bottom ,1st Story to 16th Story,
should be strengthen.
Composite steel plate shear
wall(CSPSW) is used to increase
the ultimate bearing capacity and
the ductility of the core tube.

41
3Beijing Fortune Plaza 2 Office Tower
3.7 Lateral Resisting System—Core Tube

The core tube should satisfy with the
requirement of keeping elastic under
precautionary seismic intensity.
Ratio of axial compression stress to strength
should be controlled strictly

42
3 Beijing Fortune Plaza 2 Office Tower
3.7 Lateral Resisting System—Core Tube
The section of hidden beam and hidden column around CSPSW
should be increased, so that the hidden beam and column can
constrain the steel plate effectively to make full use of the steel plate.
Hidden column should be settled at the corner of the core tube, and
connected with the hidden beam.

43
3 Beijing Fortune Plaza 2 Office Tower
3.7 Lateral Resisting System—Core Tube
Advantage of CSPSW
a.Reduce the weight of core wall and seismic response
b.Reduce the needs of the pipes under the core wall and the settlement of subsoil
c.Reduce the ratio of axial compression stress to strength of the bottom wall
d.Increase the capacity of the core wall
e.Increase the performance of the structure under the rare earthquake, delay the
appearance of the plastic hinge and increase the stability of the hole structure.

44
3 Beijing Fortune Plaza 2 Office Tower
3.7 Lateral Resisting System—Core Tube

Disadvantage of CSPSW
a.Increase the cost
b.Hard to construct
c.Increase the requirement of professional and equipment

45
3 Beijing Fortune Plaza 2 Office Tower
3.8 Outriggers
Single storey steel outriggers are introduced at Level
26A , Level41A and top level within the double storey height
belt truss to mobilize the lateral resistance of the perimeter frame
through push-pull action of perimeter columns straddling the
connection between the outrigger and belt truss. The use of an
outrigger increases the core’s rotational resistance by placing a
restoring moment into the core and hence reduces the lateral
deflection.
The outriggers connect to belt trusses on respective levels so that
the columns on both sides of each outrigger could be mobilized
for the push-pull action. Since the mobilized columns are not at
corner, the shear-lag effect is diminished to a large degrees.
46
3 Beijing Fortune Plaza 2 Office Tower

L11A belt trusses

L26
A,L41A outrigger

47
2 Beijing Fortune Plaza 2 Office Tower

48
3 Beijing Fortune Plaza 2 Office Tower
3.9 Perimeter Frame
Dimension: 64m×41.5m,Perimeter
columns are spaced at 6m
All the perimeter columns are used
as part of the building lateral
resisting system.
Perimeter beams are steel beam,
and the beam to column
connection are rigid.

49
According to Chinese Building Codes,
the base shear resisted by perimeter
frame must not less than the maximum
value of 20% of the total force and 1.5
times the maximum of story shear
force. In fact, the criteria reflect the
objective needs of arranging the
perimeter frame reasonable. Only the
perimeter frame has a proper stiffness
can the design satisfy with the criteria.

50
3 Beijing Fortune Plaza 2 Office Tower
Introduction of concrete filled tube(CFT) column
In addition to high strength 、 light quantity 、
good shape 、 fast tiredness and fast strike, the
concrete-filled steel tubular structures have a lot
of advantages, such as simple node form 、
flexible construct layout 、 big section inertial
rules 、 good stability 、 convenient
construction and easy fireproofing measure and
so on

51
3Beijing Fortune Plaza 2 Office Tower

Compare of SRC and CFT

Both of SRC and CFT members are so called composite members, and
are widely used in super high-rise buildings as column of perimeter
column. The composite members have better capacity and ductility, so
smaller section can be selected by using the composite members.
Compared with SRC members, CFT members need not be limited the
ratio of axial compression stress to strength, and better capacity to
resist bending. Hence, the CFT column has the advantage in super
high-rise building design.

52
3 Beijing Fortune Plaza 2 Office Tower
3.10 elastic analysis
Analyse result and FEA method model

SATWE

ETABS

53
2 Beijing Fortune Plaza 2 Office Tower
Period and mode of vibration
Mode of vibration

SATWE

ETABS

1

5.496

5.530

2

4.798

4.833

3

3.299

3.603

4

1.547

1.589

5

1.347

1.364

6

1.049

1.137
54
Mode 1 (X direction moving)

Mode 2 ( Y direction moving )

Mode 3 ( Torsion )

55
2 Beijing Fortune Plaza 2 Office Tower
Base shear and overturning moment
SATWE calculation result
Earthquake
Earthquake
load - direction load - direction
X
y

Wind load –
direction x

Wind load –
direction y

Base shear(KN)

54068

55336

30690

20182

Overturning
moment ( M
N.m )

7906

8948

4732

3114

ETABS calculation result
Earthquake
Earthquake
Wind load –
load - direction load - direction
direction x
X
y

Wind load –
direction y

Base shear(KN)

52295

53641

31282

20889

Overturning
moment ( M
N.m )

8105

9064

4947

3150

56
3 Beijing Fortune Plaza 2 Office Tower

The story shear force under horizontal load (SATWE)
57
3 Beijing Fortune Plaza 2 Office Tower
The ratio of Story shear to gravity under horizontal earthquake load
(SATWE&ETABS)

58
3 Beijing Fortune Plaza 2 Office Tower

The calculated result shows that the ratio of story shear to gravity
using two software are similar, and satisfies with Chinese code
demand that the minimum ratio of story shear and gravity should
be bigger than 2.4% basically.

59
3 Beijing Fortune Plaza 2 Office Tower

Interstory drift under horizontal earthquake load and wind load
SATWE
Max ratio of
interstory drift
Max horizontal
Drift of top
story ( mm )
ETABS
Max ratio of
interstory drift
Max horizontal
Drift of top
story ( mm )

Earthquake load
- direction X

Earthquake load
- direction y

Wind load –
direction x

Wind load –
direction y

1/556

1/726

1/1025

1/2177

345

263

196

89

Earthquake load
- direction X

Earthquake load
- direction y

Wind load –
direction x

Wind load –
direction y

1/560

1/737

1/852

1/1587

337

264

201

99

60
Interstory drift under horizontal earthquake load and wind load
(SATWE)
61
3 Beijing Fortune Plaza 2 Office Tower
3.11 Elastic/Elasto-plastic time-history analysis
3.11.1 compare of time-history method, equivalent base shear method
and response spectrum method
Main distinction between time-history method and response spectrum
method is:
Design response spectrum in response spectrum method responses
intension of ground motion and behavior of average frequency
spectrum ,but time-history method responses roundly intension of
ground motion,behavior of spectrum and duration time;

62
3 Beijing Fortune Plaza 2 Office Tower
Response spectrum method based on elasticity assume, but time-history
method directly considers construction members and structure elasticoplasticity behavior, can find out exactly frail link of structure, so that
control structure elastico-plasticity response under the Rare Earthquake,
prevent building collapse;
Response spectrum method only analyses maximum earthquake response,
but time-history method can provide time-history curve, so find out order
of plasticity hinge in construction members, estimates structure destroy
theory.

63
3 Beijing Fortune Plaza 2 Office Tower

3.11.2 Choose and scale ground motion record

Intension of ground motion;
Spectral characteristics;
Duration time

64
Spectral characteristics of picked ground motions;
65
Intension of ground
motion;
Duration time

66
3 Beijing Fortune Plaza 2 Office Tower

3.11.3 Result of time-history analysis

67
3 Beijing Fortune Plaza 2 Office Tower

68
3 Beijing Fortune Plaza 2 Office Tower
3.11.4 Study of outriggers in top
70
60

St or y

50
40

no t op out r i gger
4 pai r 900* 550* 40* 40
3 pai r 900* 550* 40* 40
2 pai r 900* 550* 40* 80

30
20
10
0
0

0. 0005

0. 001

0. 0015

St or y D i f t
r

0. 002

69
3 Beijing Fortune Plaza 2 Office Tower
3.11.5 Elastico-plasticity analysis and design recommendation under
the Rare Earthquake

70
71
4.Example 2 China World Trade Centre Phase 3
4.1 Outline of the Project
China World Trade Centre Phase 3 is
located in the Central Business District
(CBD) Beijing. The site is surround by
the East 3 Ring Road on the east,
China Grand Hotel in the south and
Kerry Centre on the north.
China World Trade Centre Phase 3A includes:
(1) A 330m tall mega tower
(2) A ball room
(3) A retail block
The whole phase 3 will be linked together by means of a basement. Basement
level 1 will be used for retails.
4.2 、 The Mega Tower
The Mega Tower is 330m tall at
its highest level, which is a
helipad. The elevation of main
roof is 316.60m. There are
totally 73 stories above ground,
in which 1/F to 4/F are for
atrium and multipurpose,5/F to
56/F are office levels, and
above 56/F are for hotel. There
are 3 underground levels, B3 is
for parking and MEP, while B2
and B1 re reserved for MEP and
commercial space.
4.3 STRUCTURAL SYSTEM – MEGA TOWER
4.3.1 、 Description

The Mega Tower forms part of the China World Centre Phase 3 development
and consist of the
following :
• Total structural height is 316.6m.
• These are 73 levels above ground comprising of office, hotel and restaurant
usage and 4 levels of
basement.
• A 20m tall façade roof feature above mechanical floor levels encloses a
rooftop helipad.
• Above L73 there are steel structures to support the helipad at 330m high,
surrounded by facade
structure
4.3.2 、 Lateral Stability System
The lateral stability of the Mega
Tower employs a tube-in-tube
structure provided by a perimeter
composite moment frame, a braced
composite central core frame, and
outriggers as a means of linkage
between them.
4.3.3 、 Perimeter Moment Frame

The layout of the perimeter frame basically
follows the floor plan of the building, being a
chamfered square shape in plan. The overall
dimension of the tube varies from around 55.3m
at ground level, to 44m at L73.
The centre to centre distance of columns of the
perimeter frame is 5.6m for hotel levels, but
reducing to 4.2m for all other levels (excluding
belt trusses and bottom levels), maximising the
tube action of the perimeter frame.
4.2 、 Outriggers
Single storey steel outriggers (see Fig. 7.3) are
introduced between Level 28-29 and level 56-57
within the double storey height belt truss to mobilize
the lateral resistance of the perimeter frame through
push-pull action of perimeter columns straddling the
connection between the outrigger and belt truss. The
use of an outrigger increases the core’s rotational
resistance by placing a restoring moment into the
core and hence reduces the lateral deflection.
The outriggers connect to belt trusses on respective
levels so that the columns on both sides of each
outrigger could be mobilised for the push-pull
action. Since the mobilized columns are not at
corner, the shear-lag effect is diminished to a large
degrees.
4.3 Central Core

The overall dimension is about 26.8m x 20.7m from pile
cap to L33, 23.8m x 20.7 from L33 to L57 and 20m x
20m above L57.
The core frames, which are shown in Fig. 7.4 as elevation
1-10, is braced frame composedof steel reinforced
concrete (SRC) columns, steel beams and steel braces.
The SRC columns are L-shaped or rectangular with 2 to 7
steel sections cast in. Steel beams and braces will be
connected to steel sections in SRC columns directly.
өндөр барилгын бүтээц төлөвлөлт үзэж байгаа оюутнуудад хэрэгтэй байж магадгүй
өндөр барилгын бүтээц төлөвлөлт үзэж байгаа оюутнуудад хэрэгтэй байж магадгүй
өндөр барилгын бүтээц төлөвлөлт үзэж байгаа оюутнуудад хэрэгтэй байж магадгүй

Más contenido relacionado

La actualidad más candente

Jinmao tower (11) siti yaumilia salsa
Jinmao tower (11) siti yaumilia salsaJinmao tower (11) siti yaumilia salsa
Jinmao tower (11) siti yaumilia salsa
salsa moyara
 
An over view of the high rise buildings
An over view of the high rise buildingsAn over view of the high rise buildings
An over view of the high rise buildings
hlksd
 
J.S. Daniel paper for high rise building construction cycle
J.S. Daniel paper for high rise building construction cycleJ.S. Daniel paper for high rise building construction cycle
J.S. Daniel paper for high rise building construction cycle
J.S. Daniel
 

La actualidad más candente (20)

presentation ON TALL BUILDING
 presentation ON TALL BUILDING presentation ON TALL BUILDING
presentation ON TALL BUILDING
 
report on high riseee
report on high riseeereport on high riseee
report on high riseee
 
High rise building
High rise buildingHigh rise building
High rise building
 
Jinmao tower (11) siti yaumilia salsa
Jinmao tower (11) siti yaumilia salsaJinmao tower (11) siti yaumilia salsa
Jinmao tower (11) siti yaumilia salsa
 
An over view of the high rise buildings
An over view of the high rise buildingsAn over view of the high rise buildings
An over view of the high rise buildings
 
L6 Vert Struc Pt 4
L6 Vert Struc Pt 4L6 Vert Struc Pt 4
L6 Vert Struc Pt 4
 
SHANGHAI TOWER - Shanghai, China
SHANGHAI TOWER - Shanghai, ChinaSHANGHAI TOWER - Shanghai, China
SHANGHAI TOWER - Shanghai, China
 
High rise construction
High rise constructionHigh rise construction
High rise construction
 
High rise structure & core
High rise  structure & coreHigh rise  structure & core
High rise structure & core
 
kkr 2
kkr 2kkr 2
kkr 2
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
 
High rise building study & report
High rise building study & reportHigh rise building study & report
High rise building study & report
 
High rise
High rise High rise
High rise
 
A building with a difference 'Taipei 101'
A building with a difference 'Taipei 101'A building with a difference 'Taipei 101'
A building with a difference 'Taipei 101'
 
High rise buildings
High rise buildingsHigh rise buildings
High rise buildings
 
One world trade centre
One world trade centreOne world trade centre
One world trade centre
 
J.S. Daniel paper for high rise building construction cycle
J.S. Daniel paper for high rise building construction cycleJ.S. Daniel paper for high rise building construction cycle
J.S. Daniel paper for high rise building construction cycle
 
Shard tower
Shard towerShard tower
Shard tower
 
High rise
High riseHigh rise
High rise
 
H igh rise-01-introduction
H igh rise-01-introductionH igh rise-01-introduction
H igh rise-01-introduction
 

Destacado

Study of Eccentrically Braced Outrigger Frame under Seismic Exitation
Study of Eccentrically Braced Outrigger Frame under Seismic ExitationStudy of Eccentrically Braced Outrigger Frame under Seismic Exitation
Study of Eccentrically Braced Outrigger Frame under Seismic Exitation
IJTET Journal
 
Comparison of symmetric and asymmetric steel diagrid structures by non linear...
Comparison of symmetric and asymmetric steel diagrid structures by non linear...Comparison of symmetric and asymmetric steel diagrid structures by non linear...
Comparison of symmetric and asymmetric steel diagrid structures by non linear...
eSAT Journals
 
Virtual Outriggers in Tall Buildings
Virtual Outriggers in Tall BuildingsVirtual Outriggers in Tall Buildings
Virtual Outriggers in Tall Buildings
Andrew J Horton
 

Destacado (20)

RESPONSE OF LATERAL SYSTEM IN HIGH RISE BUILDING UNDER SEISMIC LOADS
RESPONSE OF LATERAL SYSTEM IN HIGH RISE BUILDING UNDER SEISMIC LOADSRESPONSE OF LATERAL SYSTEM IN HIGH RISE BUILDING UNDER SEISMIC LOADS
RESPONSE OF LATERAL SYSTEM IN HIGH RISE BUILDING UNDER SEISMIC LOADS
 
Project report
Project reportProject report
Project report
 
Modern Architecture
Modern ArchitectureModern Architecture
Modern Architecture
 
A study on behaviour of outrigger system on high rise steel structure by vary...
A study on behaviour of outrigger system on high rise steel structure by vary...A study on behaviour of outrigger system on high rise steel structure by vary...
A study on behaviour of outrigger system on high rise steel structure by vary...
 
I012225463
I012225463I012225463
I012225463
 
Study of Eccentrically Braced Outrigger Frame under Seismic Exitation
Study of Eccentrically Braced Outrigger Frame under Seismic ExitationStudy of Eccentrically Braced Outrigger Frame under Seismic Exitation
Study of Eccentrically Braced Outrigger Frame under Seismic Exitation
 
G012263441
G012263441G012263441
G012263441
 
Analysis of outrigger system for tall vertical irregularites structures subje...
Analysis of outrigger system for tall vertical irregularites structures subje...Analysis of outrigger system for tall vertical irregularites structures subje...
Analysis of outrigger system for tall vertical irregularites structures subje...
 
Comparison of symmetric and asymmetric steel diagrid structures by non linear...
Comparison of symmetric and asymmetric steel diagrid structures by non linear...Comparison of symmetric and asymmetric steel diagrid structures by non linear...
Comparison of symmetric and asymmetric steel diagrid structures by non linear...
 
Virtual Outriggers in Tall Buildings
Virtual Outriggers in Tall BuildingsVirtual Outriggers in Tall Buildings
Virtual Outriggers in Tall Buildings
 
Shanghai World Financial Center
Shanghai World Financial CenterShanghai World Financial Center
Shanghai World Financial Center
 
Shanghai tower Elevator and escalators
Shanghai  tower Elevator and escalators Shanghai  tower Elevator and escalators
Shanghai tower Elevator and escalators
 
Wolfgang Schueller, high-rise systems
Wolfgang Schueller, high-rise systemsWolfgang Schueller, high-rise systems
Wolfgang Schueller, high-rise systems
 
Highrise lecture
Highrise lectureHighrise lecture
Highrise lecture
 
Shanghai tower
Shanghai towerShanghai tower
Shanghai tower
 
Rescue1.asd
Rescue1.asdRescue1.asd
Rescue1.asd
 
Pdf Pai
Pdf PaiPdf Pai
Pdf Pai
 
The popularity of the english language
The popularity of the english languageThe popularity of the english language
The popularity of the english language
 
PMD PMP DIPLOMA
PMD PMP DIPLOMAPMD PMP DIPLOMA
PMD PMP DIPLOMA
 
The Fear of Running out of Money
The Fear of Running out of MoneyThe Fear of Running out of Money
The Fear of Running out of Money
 

Similar a өндөр барилгын бүтээц төлөвлөлт үзэж байгаа оюутнуудад хэрэгтэй байж магадгүй

CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
ashleyyeap
 
2010 structural designconcrete_sherif
2010 structural designconcrete_sherif2010 structural designconcrete_sherif
2010 structural designconcrete_sherif
hlksd
 
CT Assignment Written Report
CT Assignment Written ReportCT Assignment Written Report
CT Assignment Written Report
Yap Xin
 
Ct3 steel space frame roof
Ct3 steel space frame roofCt3 steel space frame roof
Ct3 steel space frame roof
MELVIN tan
 

Similar a өндөр барилгын бүтээц төлөвлөлт үзэж байгаа оюутнуудад хэрэгтэй байж магадгүй (20)

CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
2010 structural designconcrete_sherif
2010 structural designconcrete_sherif2010 structural designconcrete_sherif
2010 structural designconcrete_sherif
 
2010 structural designconcrete_sherif
2010 structural designconcrete_sherif2010 structural designconcrete_sherif
2010 structural designconcrete_sherif
 
Comparative Seismic Analysis of G+20 RC Framed Structure Building for Maximum...
Comparative Seismic Analysis of G+20 RC Framed Structure Building for Maximum...Comparative Seismic Analysis of G+20 RC Framed Structure Building for Maximum...
Comparative Seismic Analysis of G+20 RC Framed Structure Building for Maximum...
 
CT Assignment Written Report
CT Assignment Written ReportCT Assignment Written Report
CT Assignment Written Report
 
Ct3 steel space frame roof
Ct3 steel space frame roofCt3 steel space frame roof
Ct3 steel space frame roof
 
A long span structure in Romania Full paper balint karoly
A long span structure in Romania Full paper balint karolyA long span structure in Romania Full paper balint karoly
A long span structure in Romania Full paper balint karoly
 
Example of engineering specification for an engineering laboratory complex
Example of engineering specification for an engineering laboratory complexExample of engineering specification for an engineering laboratory complex
Example of engineering specification for an engineering laboratory complex
 
The capital nomination 31-08-2013
The capital nomination   31-08-2013The capital nomination   31-08-2013
The capital nomination 31-08-2013
 
IRJET- Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
IRJET-  	  Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...IRJET-  	  Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
IRJET- Dynamic Wind Analysis of RC Bundled Tube in Tube Structure using E...
 
A Review Study of Recent Developments in Concrete-Filled Steel Tubes
A Review Study of Recent Developments in Concrete-Filled Steel TubesA Review Study of Recent Developments in Concrete-Filled Steel Tubes
A Review Study of Recent Developments in Concrete-Filled Steel Tubes
 
2015 10 06_sem_pref_kimura_precast_seminar_in_santiago_final
2015 10 06_sem_pref_kimura_precast_seminar_in_santiago_final2015 10 06_sem_pref_kimura_precast_seminar_in_santiago_final
2015 10 06_sem_pref_kimura_precast_seminar_in_santiago_final
 
2015 10 06_sem_pref_kimura_precast_seminar_in_santiago_final
2015 10 06_sem_pref_kimura_precast_seminar_in_santiago_final2015 10 06_sem_pref_kimura_precast_seminar_in_santiago_final
2015 10 06_sem_pref_kimura_precast_seminar_in_santiago_final
 
Internship report
Internship reportInternship report
Internship report
 
Cctv headquarters, beijing
Cctv headquarters, beijingCctv headquarters, beijing
Cctv headquarters, beijing
 
Comparative Study of Wind Analysis of High Rise Building with Diagrid and Out...
Comparative Study of Wind Analysis of High Rise Building with Diagrid and Out...Comparative Study of Wind Analysis of High Rise Building with Diagrid and Out...
Comparative Study of Wind Analysis of High Rise Building with Diagrid and Out...
 
IBS design proposal of apartment
IBS design proposal of apartmentIBS design proposal of apartment
IBS design proposal of apartment
 
Building Technology I
Building Technology IBuilding Technology I
Building Technology I
 
IRJET- Dynamic Analysis of Tall Tubular Steel Structures of Hexagon Configura...
IRJET- Dynamic Analysis of Tall Tubular Steel Structures of Hexagon Configura...IRJET- Dynamic Analysis of Tall Tubular Steel Structures of Hexagon Configura...
IRJET- Dynamic Analysis of Tall Tubular Steel Structures of Hexagon Configura...
 
IRJET- A Performance Study of (G+20) RCC Structure using Framed Bundled B...
IRJET-  	  A Performance Study of (G+20) RCC Structure using Framed Bundled B...IRJET-  	  A Performance Study of (G+20) RCC Structure using Framed Bundled B...
IRJET- A Performance Study of (G+20) RCC Structure using Framed Bundled B...
 

Más de Ц. Алтангэрэл (6)

modal pushover analysis
modal pushover analysismodal pushover analysis
modal pushover analysis
 
response spectra
response spectraresponse spectra
response spectra
 
Earthquake
EarthquakeEarthquake
Earthquake
 
Finite element method
Finite element methodFinite element method
Finite element method
 
тогтворгүй бүтэцтэй хөрсний механик
тогтворгүй бүтэцтэй хөрсний механиктогтворгүй бүтэцтэй хөрсний механик
тогтворгүй бүтэцтэй хөрсний механик
 
байгууламжийн динамик
байгууламжийн динамикбайгууламжийн динамик
байгууламжийн динамик
 

Último

Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
WSO2
 

Último (20)

Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
A Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source MilvusA Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source Milvus
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot ModelNavi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
 
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu SubbuApidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectors
 

өндөр барилгын бүтээц төлөвлөлт үзэж байгаа оюутнуудад хэрэгтэй байж магадгүй

  • 1. Introducton to High-Rise Building Structures in China Zhang yanxia zhangyanxia@bucea.edu.cn Beijing University of Civil Engineering and Architecture July 19th,2011
  • 2. Introduction to high-rise building structures in China Outlines Main structural types in high-rise building structures  Intruduction to steel-concrete hybrid structures  Example1:Beijing Fortune Plaza 2 Office Tower Example2: China World Trade Centre 3
  • 3. 1.Main structural types in high-rise building structures (according to different material) Concrete Structures Steel Structures Steel-Concrete Hybrid Structures 3
  • 4. Concrete Structure 1 CITIC Plaza ,Guangzhou ,1996 ,390m 2 Jinmao International Plaza, Shanghai, 2006, 333m 3 Chongqing World Trade Center , Chongqing, 2005, 283m 4
  • 5. Steel Structure 1 Beijing TV Centre, Beijing,2007 ,294m 2 Minsheng Bank Building, Wuhan, 2008, 331m 3 CCTV Tower, Beijing, 2011, 239m 5
  • 6. Phoenix International Media Center Phoenix International Media Center is a multipurpose and comprehensive architecture with functions of television programming, offices and business. As usual, media building has large space such as broadcasting hall, as well as typical office floors vertically. It is hard for this two parts to achieve a harmonious effect. However, in this program, Designers resort to the pattern of Mobius, that is, combines high office floor with media broadcasting hall. While satisfying the need of the place for programming as well as other supporting establishments, it becomes a complete space and volume. Unique building shape combines with the natural scene in Chaoyang Park. 6
  • 8. 2. Introduction of hybrid structure Hybrid structure system composed by steel frame ,steel reinforcement concrete( SRC) frame or concrete filled tube( CFT) frame and RC core tube is a new optional structure system, which is widely used in the design of high-rise buildings, especially the super high-rise buildings, in China nowadays. 8
  • 9. Hybrid Structure 1 Greenland Financial Center, Nanjing, 2010, 450m 2 Shanghai World Financial Center, Shanghai, 2008, 492m 3 China World Trade Center III, Beijing, 2010, 330m 9
  • 10. The main advantages of hybrid structures: Compared with concrete structures •Decrease the structural weight •Reduce the components section •Speed up the progress of construction •Improve the performance of the structures 10
  • 11. The main advantages of hybrid structures: Compared with steel structure Improve the fire proof performance of the structure Decrease the overall cost Increase the lateral stiffness of the structure Improve the comfortable performance under wind load 11
  • 12. 2. Introduction of hybrid structure At present, many high-rise buildings which is about 150m to 200m height or even above 300m height are hybrid structure, but most of those buildings are located in the area of seismic intensity fortification 7( design basic acceleration is 0.10g or 0.15g). According to Chinese building code JGJ3-2002, the maximum application height for hybrid structures is 150m for the area of seismic intensity fortification 8( design basic acceleration is 0.20g). The Beijing Fortune Plaza 2 office tower is 265m tall and will become the second tallest building after the CWTC 3A mega tower in Beijing,, which is in the area of seismic intensity fortification 8, and the tallest CFT frame-RC core wall hybrid structure in Beijing. 12
  • 13. typical buildings of hybrid structure Xuelian Building Xuelian building is a high-rise structure, and is built in high seismic intensity region. It has 36 floors above the ground, and is 146.30m totally high. It s irregular plan and non-orthogonal frame result in weak lateral stiffness. To solve these structural difficulties, the following measures are adopted. The structure is designed as a mixed structure which is composed of concretefilled rectangular steel tube frames and reinforced concrete tubes. Two strengthening stories are designed with outriggers and belt members. 13
  • 14. typical buildings of hybrid structure Xuelian Building in construction 14
  • 15. typical buildings of hybrid structure Connections in Xuelian Building 15
  • 16. typical buildings of hybrid structure CNPC Office Building CNPC Office Building include 4 tower and several podium buildings. Tower is 90m high, has 22 stories above the ground( Tower D is 18 stories),and has 4 stories basement. The podium building is 38.2m high,and has 10 stories above the ground.The standard story height is 3.9m. 16
  • 21. typical buildings of hybrid structure Jinmao Tower The building is located on a 24000m² plot of land near the Lujiazui metro station. The 88 floors (93 if the spire floors are counted) are divided into 16 segments, each of which is 1/8 shorter than the 16-storey base. The tower is built around an octagonshaped concrete shear wall core surrounded by 8 exterior composite super columns and 8 exterior steel columns. Three sets of 8 two-story high outrigger trusses connect the columns to the core at six of the floors to provide additional support. 21
  • 22. typical buildings of hybrid structure Shanghai World Finacial Center The building is a supertall skyscraper in Pudong, Shanghai. In order to decrease the weight of the building, the majority of that decrease had to be found in a reduction of the thickness of the concrete shear walls of the services core. This reduction could be achieved only by decreasing the wind and earthquake induced lateral forces resisted by those walls. That decrease could be found only by increasing the stiffness of the lateral force resisting system of the perimeter wall. 22
  • 23. typical buildings of hybrid structure Shanghai World Finacial Center To resist the forces from typhoon (hurricane) winds and earthquakes, three parallel and interacting structural systems were incorporated: 1) The mega-structure, consisting of the major structural columns, the major diagonals, and the belt trusses. 2) The concrete walls of the services core. 3) The interaction between the concrete walls of the services core and the megacolumns, as created by the outrigger trusses. 23
  • 24. Example1 Beijing Fortune Plaza 2 Office Tower 3.1 Introduction : Location : the Center Business District (CBD) Beijing; Height: 256.35m ; Floor : 59 floors and 4 floors underground ; Architectural Area : 150,000m2 Structure System : CFT frame-RC shear wall core 24
  • 25. 3 Beijing Fortune Plaza 2 Office Tower 3.2 DESIGN STANDARDS The design of the proposed development will comply the following current code of practices in China: (1) Unified standard for reliability design of building structures GB50068-2001 (2) General definitions & symbols Architectural Design GB/T50083-97 (3) General definitions & symbols Structural Design GBJ132-90 (4) Specifications for Loading in Building Structure GB50009-2001 (5) Code of Seismic Design of Buildings GB50011-2001 (6) Code for Design of Concrete Structures GB50010-2002 (7) Code for Design of Steel Structures GB50017-2003 (8) Technical Specification for Steel Structure of Tall Buildings JGJ99-98 25
  • 26. 2 Beijing Fortune Plaza 2 Office Tower (9) Technical Specification for Box and Raft Foundation JGJ6-99 for Tall Buildings (10) Specification for Pile Foundation of Buildings JGJ94-94 (11) Beijing Standard – Specifications for Foundation Design DBJ01-501-92 (12) Technical Specification for Tall Reinforced Concrete Buildings JGJ3-2002 (13) Technical Specification for Steel Reinforced Concrete JGJ138-2001 Composite Structures In case where elements are not covered by Chinese Standard, reference to the following standard would be made. (1) Prestandard and Commentary for the Seismic Rehabilitation FEMA356 of Building (2) Seismic Evaluation and Retrofit of Concrete Buildings ATC40 26
  • 27. 2 Beijing Fortune Plaza 2 Office Tower 2.3 MATERIAL DATA 2.3.1 Concrete Grade of concrete for structural components must not less than C30, according to GB50010-2002. Design parameters are as follows: Concrete Grade Standard Value fck (N/mm²) C30 C35 C40 C45 C50 C60 20.1 23.4 26.8 29.6 32.4 38.5 Design Value, fc (N/mm²) 14.3 16.7 19.1 21.1 23.1 27.5 Young’s Modulus Ec (N/mm²) 3.00×104 3.15×104 3.25×104 3.35×104 3.45×104 3.6×104 27
  • 28. 3 Beijing Fortune Plaza 2 Office Tower 3.3.2 Reinforcement All reinforcement complies with Chinese Standard GB50010-2002. Type dia (mm) Standard Value fyk (N/mm2) DesignValue fy , fy’ (N/mm2) Young’s Modulus Es (N/mm2) HPB235 HRB335 8~20 6~50 235 335 210/210 300/300 2.1×105 2.0×105 HRB400 6~50 400 360/360 2.0×105 28
  • 29. 2 Beijing Fortune Plaza 2 Office Tower 2.3.3 Structural Steel All structural steel would be either British Standard Grade 43/Grade 50 or Chinese Standard Q235/Q345. 29
  • 30. 2 Beijing Fortune Plaza 2 Office Tower 30
  • 31. 3 Beijing Fortune Plaza 2 Office Tower 3.4 LOADS 3.4.1 Floor Loads The following live and superimposed loads based on the Chinese Code GB50009-2001 are used. Standard loads of the Fortune Plaza 2 office tower (kN/m²) Location / Type of Loading Roof Live load 1.5 or actual load E&M Finishes 1.5 4.8 – 1.0 Typical Office Floor 3.0 0.5 1.7* Typical Hotel Floor 2.0 0.3 1.2 Staircase 3.0 – 1.2 Mechanical room Refuge Floor * ceiling = 0.5, finishes = 1.2 Not less than 7.5 or actual load 5.0 Partitions – According to framing plan – 1.2 – 1.2 – 31
  • 32. 3 Beijing Fortune Plaza 2 Office Tower 3.4.2 wind loads The wind loads based on the Chinese Code GB50009-2001. Based on 100 years return period, Design wind Load is 0.50kN/m². Wind loads and acceleration for the engineering are still being expected from wind tunnel tests conducted by BMT company. The result of test is similar with the calculation of Chinese Code GB500092001. Wind tunnel test 3.4.3 Snow loads Based on 100 years return period, Design Snow Load is 0.45kN/m². 32
  • 33. 3 Beijing Fortune Plaza 2 Office Tower 3.4.4 Earthquake Loads The data below is based on Chinese Code GB50011-2001 and the recommendations from the “Seismic Hazard Assessment Report ” provided in June, 2008. The Site Category and Seismic Intensity fortification are based on Chinese Code GB50011-2001. •Seismic intensity fortification: Degree 8 Design basic acceleration = 0.20g •Site Category: Category II, Group 1, Tg = 0.37s •Period reduce modulus:0.9; •Structural damping ratio:0.04(frequent earthquake),0.04(design earthquake),0.05(rare earthquake); 33
  • 34. 3 Beijing Fortune Plaza 2 Office Tower 34
  • 35. 3 Beijing Fortune Plaza 2 Office Tower 3.5 Comparison with Code Limits Requirement in Chinese Building Codes Structure System Story Tower Basement CFT Frame - RC Core Tube 59 4 Tower 256.35m(part 7.3m above the roof) Basement Height (m) Note JGJ3-2002 Table 11.1.2 : the maximal application height for Unsatisfied hybrid structures is 150m for the area of seismic intensity 8 18.5 Dimension of Standard Floor Plan (Length×Width, m) Structure Height to Width Ratio 64.33×41.85 256.35/41.85 =6.13 JGJ 3-2002 Table11.1.3:the value should less than 6 Unsatisfied 35
  • 36. 3 Beijing Fortune Plaza 2 Office Tower Torsion Irregularity Horizontal Irregularity Geometric Irregularity Diaphragm Discontinuity Irregularity Y-Direction: all less than 1.2; X-Direction: part beyond 1.2 , but less than 1.3,others less than 1.2 JGJ 3-2002§4.3.5:for the Class B structure, the torsion displacement Mainly ratio should less than 1.2, must less Satisfied than 1.4, when accidental torsion effect is considered. — JGJ3-2002§4.3.6:reduced floor width should less than 50% of the total width.GB50011-2001§3.4.2: Satisfied reduced floor width should less than 30% of the total width in one side. — GB50011-2001§3.4:floor effective width less than 50% of the total width, the open area of floor should Satisfied less than 30% of the total area, and no out-of-plan offset exist. 36
  • 37. 3 Beijing Fortune Plaza 2 Office Tower Stiffness mutation exist at the stories adjoin to the Stiffness Soft strengthen story , but still Story Irregularity satisfy with the code requirement. Vertical Discontinuity in Irregularity Vertical Lateral Weak Story Irregularity GB50011-2001§3.4.2: story lateral stiffness should not less than 70% of the stiffness of the Satisfied upper story, and 80% of the average stiffness of the upper 3 stories. GB50011-2001§3.4.2: vertical Discontinuity in vertical lateral force should not be transferred by Satisfied not exist horizontal members. JGJ3-2002§4.4.3:for the Class B Bearing Capacity mutation structure, the story shear bearing exist for the strengthen stories capacity should not less than exist. 75% of the capacity of the upper story. Story Shear to Weight Ratio Minimum Value : 0.024 JGJ3-2002§3.3.13:to structure whose fundamental period beyond 5s,the minimum value is 0.024 Satisfied 37
  • 38. 3 Beijing Fortune Plaza 2 Office Tower 3.6 Floor Diaphragm •Profiled steel sheeting-concrete composite slabs •Steel beam connected with RC slab by shear resisting stud •C40 concrete is used •Thickness: a.130mm for office stories(requirement of comfortable) 200mm for mechanical stories/strengthen stories(the result of elastic calculation) b.200mm for the 1st bottom floor(requirement of embed) c.200mm for the roof, 130mm for the concrete floor in the core tube. 38
  • 39. 3 Beijing Fortune Plaza 2 Office Tower 3.7 Lateral Resisting System—Core Tube 39
  • 40. 3 Beijing Fortune Plaza 2 Office Tower 3.7 Lateral Resisting System—Core Tube •Dimension: 42.3m×15.9m(Footing-44th Story),34.8m×15.1m(45th Story-Roof) •Thickness: Decrease smoothly from 1200mm to 600mm with story increasing •The core tube resists most of the gravity and lateral force, and shows a great torsion resisting capacity. 40
  • 41. 3 Beijing Fortune Plaza 2 Office Tower 3.7 Lateral Resisting System—Core Tube According to the Chinese Building Codes, the seismic resisting level of the core tube is special 1st ,so the bottom ,1st Story to 16th Story, should be strengthen. Composite steel plate shear wall(CSPSW) is used to increase the ultimate bearing capacity and the ductility of the core tube. 41
  • 42. 3Beijing Fortune Plaza 2 Office Tower 3.7 Lateral Resisting System—Core Tube The core tube should satisfy with the requirement of keeping elastic under precautionary seismic intensity. Ratio of axial compression stress to strength should be controlled strictly 42
  • 43. 3 Beijing Fortune Plaza 2 Office Tower 3.7 Lateral Resisting System—Core Tube The section of hidden beam and hidden column around CSPSW should be increased, so that the hidden beam and column can constrain the steel plate effectively to make full use of the steel plate. Hidden column should be settled at the corner of the core tube, and connected with the hidden beam. 43
  • 44. 3 Beijing Fortune Plaza 2 Office Tower 3.7 Lateral Resisting System—Core Tube Advantage of CSPSW a.Reduce the weight of core wall and seismic response b.Reduce the needs of the pipes under the core wall and the settlement of subsoil c.Reduce the ratio of axial compression stress to strength of the bottom wall d.Increase the capacity of the core wall e.Increase the performance of the structure under the rare earthquake, delay the appearance of the plastic hinge and increase the stability of the hole structure. 44
  • 45. 3 Beijing Fortune Plaza 2 Office Tower 3.7 Lateral Resisting System—Core Tube Disadvantage of CSPSW a.Increase the cost b.Hard to construct c.Increase the requirement of professional and equipment 45
  • 46. 3 Beijing Fortune Plaza 2 Office Tower 3.8 Outriggers Single storey steel outriggers are introduced at Level 26A , Level41A and top level within the double storey height belt truss to mobilize the lateral resistance of the perimeter frame through push-pull action of perimeter columns straddling the connection between the outrigger and belt truss. The use of an outrigger increases the core’s rotational resistance by placing a restoring moment into the core and hence reduces the lateral deflection. The outriggers connect to belt trusses on respective levels so that the columns on both sides of each outrigger could be mobilized for the push-pull action. Since the mobilized columns are not at corner, the shear-lag effect is diminished to a large degrees. 46
  • 47. 3 Beijing Fortune Plaza 2 Office Tower L11A belt trusses L26 A,L41A outrigger 47
  • 48. 2 Beijing Fortune Plaza 2 Office Tower 48
  • 49. 3 Beijing Fortune Plaza 2 Office Tower 3.9 Perimeter Frame Dimension: 64m×41.5m,Perimeter columns are spaced at 6m All the perimeter columns are used as part of the building lateral resisting system. Perimeter beams are steel beam, and the beam to column connection are rigid. 49
  • 50. According to Chinese Building Codes, the base shear resisted by perimeter frame must not less than the maximum value of 20% of the total force and 1.5 times the maximum of story shear force. In fact, the criteria reflect the objective needs of arranging the perimeter frame reasonable. Only the perimeter frame has a proper stiffness can the design satisfy with the criteria. 50
  • 51. 3 Beijing Fortune Plaza 2 Office Tower Introduction of concrete filled tube(CFT) column In addition to high strength 、 light quantity 、 good shape 、 fast tiredness and fast strike, the concrete-filled steel tubular structures have a lot of advantages, such as simple node form 、 flexible construct layout 、 big section inertial rules 、 good stability 、 convenient construction and easy fireproofing measure and so on 51
  • 52. 3Beijing Fortune Plaza 2 Office Tower Compare of SRC and CFT Both of SRC and CFT members are so called composite members, and are widely used in super high-rise buildings as column of perimeter column. The composite members have better capacity and ductility, so smaller section can be selected by using the composite members. Compared with SRC members, CFT members need not be limited the ratio of axial compression stress to strength, and better capacity to resist bending. Hence, the CFT column has the advantage in super high-rise building design. 52
  • 53. 3 Beijing Fortune Plaza 2 Office Tower 3.10 elastic analysis Analyse result and FEA method model SATWE ETABS 53
  • 54. 2 Beijing Fortune Plaza 2 Office Tower Period and mode of vibration Mode of vibration SATWE ETABS 1 5.496 5.530 2 4.798 4.833 3 3.299 3.603 4 1.547 1.589 5 1.347 1.364 6 1.049 1.137 54
  • 55. Mode 1 (X direction moving) Mode 2 ( Y direction moving ) Mode 3 ( Torsion ) 55
  • 56. 2 Beijing Fortune Plaza 2 Office Tower Base shear and overturning moment SATWE calculation result Earthquake Earthquake load - direction load - direction X y Wind load – direction x Wind load – direction y Base shear(KN) 54068 55336 30690 20182 Overturning moment ( M N.m ) 7906 8948 4732 3114 ETABS calculation result Earthquake Earthquake Wind load – load - direction load - direction direction x X y Wind load – direction y Base shear(KN) 52295 53641 31282 20889 Overturning moment ( M N.m ) 8105 9064 4947 3150 56
  • 57. 3 Beijing Fortune Plaza 2 Office Tower The story shear force under horizontal load (SATWE) 57
  • 58. 3 Beijing Fortune Plaza 2 Office Tower The ratio of Story shear to gravity under horizontal earthquake load (SATWE&ETABS) 58
  • 59. 3 Beijing Fortune Plaza 2 Office Tower The calculated result shows that the ratio of story shear to gravity using two software are similar, and satisfies with Chinese code demand that the minimum ratio of story shear and gravity should be bigger than 2.4% basically. 59
  • 60. 3 Beijing Fortune Plaza 2 Office Tower Interstory drift under horizontal earthquake load and wind load SATWE Max ratio of interstory drift Max horizontal Drift of top story ( mm ) ETABS Max ratio of interstory drift Max horizontal Drift of top story ( mm ) Earthquake load - direction X Earthquake load - direction y Wind load – direction x Wind load – direction y 1/556 1/726 1/1025 1/2177 345 263 196 89 Earthquake load - direction X Earthquake load - direction y Wind load – direction x Wind load – direction y 1/560 1/737 1/852 1/1587 337 264 201 99 60
  • 61. Interstory drift under horizontal earthquake load and wind load (SATWE) 61
  • 62. 3 Beijing Fortune Plaza 2 Office Tower 3.11 Elastic/Elasto-plastic time-history analysis 3.11.1 compare of time-history method, equivalent base shear method and response spectrum method Main distinction between time-history method and response spectrum method is: Design response spectrum in response spectrum method responses intension of ground motion and behavior of average frequency spectrum ,but time-history method responses roundly intension of ground motion,behavior of spectrum and duration time; 62
  • 63. 3 Beijing Fortune Plaza 2 Office Tower Response spectrum method based on elasticity assume, but time-history method directly considers construction members and structure elasticoplasticity behavior, can find out exactly frail link of structure, so that control structure elastico-plasticity response under the Rare Earthquake, prevent building collapse; Response spectrum method only analyses maximum earthquake response, but time-history method can provide time-history curve, so find out order of plasticity hinge in construction members, estimates structure destroy theory. 63
  • 64. 3 Beijing Fortune Plaza 2 Office Tower 3.11.2 Choose and scale ground motion record Intension of ground motion; Spectral characteristics; Duration time 64
  • 65. Spectral characteristics of picked ground motions; 65
  • 67. 3 Beijing Fortune Plaza 2 Office Tower 3.11.3 Result of time-history analysis 67
  • 68. 3 Beijing Fortune Plaza 2 Office Tower 68
  • 69. 3 Beijing Fortune Plaza 2 Office Tower 3.11.4 Study of outriggers in top 70 60 St or y 50 40 no t op out r i gger 4 pai r 900* 550* 40* 40 3 pai r 900* 550* 40* 40 2 pai r 900* 550* 40* 80 30 20 10 0 0 0. 0005 0. 001 0. 0015 St or y D i f t r 0. 002 69
  • 70. 3 Beijing Fortune Plaza 2 Office Tower 3.11.5 Elastico-plasticity analysis and design recommendation under the Rare Earthquake 70
  • 71. 71
  • 72. 4.Example 2 China World Trade Centre Phase 3 4.1 Outline of the Project China World Trade Centre Phase 3 is located in the Central Business District (CBD) Beijing. The site is surround by the East 3 Ring Road on the east, China Grand Hotel in the south and Kerry Centre on the north. China World Trade Centre Phase 3A includes: (1) A 330m tall mega tower (2) A ball room (3) A retail block The whole phase 3 will be linked together by means of a basement. Basement level 1 will be used for retails.
  • 73. 4.2 、 The Mega Tower
  • 74. The Mega Tower is 330m tall at its highest level, which is a helipad. The elevation of main roof is 316.60m. There are totally 73 stories above ground, in which 1/F to 4/F are for atrium and multipurpose,5/F to 56/F are office levels, and above 56/F are for hotel. There are 3 underground levels, B3 is for parking and MEP, while B2 and B1 re reserved for MEP and commercial space.
  • 75. 4.3 STRUCTURAL SYSTEM – MEGA TOWER 4.3.1 、 Description The Mega Tower forms part of the China World Centre Phase 3 development and consist of the following : • Total structural height is 316.6m. • These are 73 levels above ground comprising of office, hotel and restaurant usage and 4 levels of basement. • A 20m tall façade roof feature above mechanical floor levels encloses a rooftop helipad. • Above L73 there are steel structures to support the helipad at 330m high, surrounded by facade structure
  • 76. 4.3.2 、 Lateral Stability System The lateral stability of the Mega Tower employs a tube-in-tube structure provided by a perimeter composite moment frame, a braced composite central core frame, and outriggers as a means of linkage between them.
  • 77. 4.3.3 、 Perimeter Moment Frame The layout of the perimeter frame basically follows the floor plan of the building, being a chamfered square shape in plan. The overall dimension of the tube varies from around 55.3m at ground level, to 44m at L73. The centre to centre distance of columns of the perimeter frame is 5.6m for hotel levels, but reducing to 4.2m for all other levels (excluding belt trusses and bottom levels), maximising the tube action of the perimeter frame.
  • 78. 4.2 、 Outriggers Single storey steel outriggers (see Fig. 7.3) are introduced between Level 28-29 and level 56-57 within the double storey height belt truss to mobilize the lateral resistance of the perimeter frame through push-pull action of perimeter columns straddling the connection between the outrigger and belt truss. The use of an outrigger increases the core’s rotational resistance by placing a restoring moment into the core and hence reduces the lateral deflection. The outriggers connect to belt trusses on respective levels so that the columns on both sides of each outrigger could be mobilised for the push-pull action. Since the mobilized columns are not at corner, the shear-lag effect is diminished to a large degrees.
  • 79. 4.3 Central Core The overall dimension is about 26.8m x 20.7m from pile cap to L33, 23.8m x 20.7 from L33 to L57 and 20m x 20m above L57. The core frames, which are shown in Fig. 7.4 as elevation 1-10, is braced frame composedof steel reinforced concrete (SRC) columns, steel beams and steel braces. The SRC columns are L-shaped or rectangular with 2 to 7 steel sections cast in. Steel beams and braces will be connected to steel sections in SRC columns directly.