What is Network Analysis?
Network analysis is the general name given to
certain specific techniques which can be used
for planning, management and control of
project.
Applications:
• Construction of a Residential complex,
• Commercial complex,
• Petro-chemical complex
• Ship building, Aircraft Manufacturing
• Satellite mission development
• Installation of a pipe line project etc...
3. Objectives of Network Analysis
l) Minimization of Total Project Cost
2) Minimization of Total Project Duration
3) Trade-off between Time and Cost of Project
4) Minimization of Idle Resources
5) Minimize Production Delay, Interruptions and Conflicts
Techniques for Network analysis:
The two common techniques which are used in network analysis.
Critical Path Analysis and PERT are powerful tools that help you to
schedule and manage complex projects. They were developed in the
1950s to control large defence projects, and have been used routinely
since then.
1. Critical Path Method (CPM)
2. Program Evaluation and Review Technique (PERT)
Program Evaluation and Review
Technique(PERT):
A probabilistic model which is based in the Beta
Distribution is called PERT (Program Evaluation
and Review Technique). The probability of
occurrence is the basis of its estimates which is
derived in this technique.
Features of PERT:
For any activity three time estimates namely optimistic, normal and pessimistic
times are estimated with consideration of the presence of uncertainties.
• For each activity expected time is calculated with the use of three time
estimates.
• Critical path and slack time are computed. The sequence of activities which has
maximum expected time for the completion of the project determines the
critical path.
• The person who is incharge of the operation provides the three time estimates.
The judgement and experience of the person are the basis of the values of three
time estimates.
• It is assumed that these time estimates follow a beta distribution.
Steps involved in PERT
• Step l: Identify the various activities which are involved in the
project and drawn up in sequential manner that show which
activity follows what.
• Step 2: Estimate the activity time and note on the network.
• Step 3: Determine the critical activities of the project.
• Step 4: Calculate the variability of the project duration and
probability of the project completion in a given time period.
Probability Consideration in PERT :
The analysts of PERT technique have found that the beta-distribution
curve provides the satisfactory results for most of the activities. This
distribution curve is different from the normal curve and has a shape.
Expected Time: tei = (a+4m+b)6.
Where, tei= Expected time of the ith activity,
a = Optimistic time
m = Most likely, or modal time,
b = Pessimistic time.
• In a project network all earliest and latest times are
calculated with the use of expected activity time.
• The Standard deviation, σi of the completion time of
an activity is calculated as follows:
From this, the variance σi2= [(b-a)6]2
• Variance is a measure of the dispersion. If the
variance is large then the uncertainty will be greater
because it depends on the range (b — a).
10. Problem On PERT
An R & D project has a list of tasks to be performed whose time estimates are given in
the Table, as follows.
Time estimates R & D project
1 .Draw the project network.
2. Find the critical path.
3. Find the probability that the project is completed in 19 days. If the
probability is less than 20%, find the probability of completing it in
24days.
Solution:
1. Time expected for each activity is calculated using the formula:
Similarly, the expected time is calculated for all the activities.
tei = (a+4m+b)6 = (4+24+8)6 = 6 days
The variance of activity time is calculated using the formula:
Similarly, variances of all the activities are calculated.
The variance σi2= [(b-a)6]2 = [(8-4)6]2 = 0.444
Calculation of tei , σi2
2. Construct a network diagram:
3. From the network diagram Figure, the critical path is identified as
1-4, 4-6, 6-7, with a project duration of 22 days.
4. The probability of completing the project within 19 days is given
by, P (Z< Z0)
5. To find Z0 ,
6. We know, P (Z <Z Network Model 0) = 0.5 – z (1.3416) (from
normal tables, z (1.3416) = 0.4099) = 0.5 – 0.409 = 0.0901 =
9.01%.Thus, the probability of completing the R&D project in 19
days is 9.01%.
7. Since the probability of completing the project in 19 days is less
than 20% As in question, we find the probability of completing it in
24 days.
Advantages of PERT
• The expected time which is required for completing each activity is
determined.
• It helps in completion of project within an expected time period.
• It reduces the risk factor because it helps the management in
handling the uncertainties which are involved in the project.
• Detailed planning of activities is possible with the help of PERT
technique.
• It helps in taking correcting action for completing the project on
time.
Disadvantages of PERT
• In the absence of past data, it is very difficult to provide
realistic/correct time estimates for new activities.
• In this technique there is not any provision about the requirement
of resources at various activities.
• In PERT technique frequent updates and revision of calculations
are required for the effective control of project which is very costly.
Quantitative analysis for business decision- Program Evaluation and Review Technique (PERT)

Más contenido relacionado

La actualidad más candente

La actualidad más candente (19)

CPM-Updating
CPM-UpdatingCPM-Updating
CPM-Updating
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Project Management
Project Management Project Management
Project Management
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
Network analysis
Network analysisNetwork analysis
Network analysis
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
 
Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing Algorithm
 
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
 
Pert+cpm
Pert+cpmPert+cpm
Pert+cpm
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii reference
 
PERT
PERTPERT
PERT
 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pert
 
PROJECT MANAGEMENT - CPM & PERT
PROJECT MANAGEMENT - CPM & PERTPROJECT MANAGEMENT - CPM & PERT
PROJECT MANAGEMENT - CPM & PERT
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
 
Critical path method
Critical path methodCritical path method
Critical path method
 
CPM NETWORK
CPM NETWORKCPM NETWORK
CPM NETWORK
 

Similar a Quantitative analysis for business decision- Program Evaluation and Review Technique (PERT)

Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02kongara
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLSiddanna Balapgol
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering EconomicsDeepak Paithankar
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking TechniquesAaliButt1
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managersNaganna Chetty
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxMdSabujHossen2
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxMdSabujHossen2
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 pptahsanrabbani
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.pptssusere57332
 
3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdf3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdfPabitraMitra3
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 

Similar a Quantitative analysis for business decision- Program Evaluation and Review Technique (PERT) (20)

Project management
Project managementProject management
Project management
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking Techniques
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
 
Pmp time chapter 6
Pmp time chapter 6Pmp time chapter 6
Pmp time chapter 6
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.ppt
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdf3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdf
 
Pert cpm
Pert cpm Pert cpm
Pert cpm
 
Presentation7
Presentation7Presentation7
Presentation7
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 

Más de Chandra Shekar Immani

MBA Finance- A Study on Funds Flow Analysis With reference to GAIL(India) Lim...
MBA Finance- A Study on Funds Flow Analysis With reference to GAIL(India) Lim...MBA Finance- A Study on Funds Flow Analysis With reference to GAIL(India) Lim...
MBA Finance- A Study on Funds Flow Analysis With reference to GAIL(India) Lim...Chandra Shekar Immani
 
Case Study Analysis-Credit Cards- MBA-PPT
Case Study Analysis-Credit Cards- MBA-PPTCase Study Analysis-Credit Cards- MBA-PPT
Case Study Analysis-Credit Cards- MBA-PPTChandra Shekar Immani
 
Tax management (TM)- Deductions under section 80 of Income Tax act-MBA
Tax management (TM)- Deductions under section 80 of Income Tax act-MBATax management (TM)- Deductions under section 80 of Income Tax act-MBA
Tax management (TM)- Deductions under section 80 of Income Tax act-MBAChandra Shekar Immani
 
Logistics & Supply Chain Management(LSCM)- Sourcing Decisions& Transportation...
Logistics & Supply Chain Management(LSCM)- Sourcing Decisions& Transportation...Logistics & Supply Chain Management(LSCM)- Sourcing Decisions& Transportation...
Logistics & Supply Chain Management(LSCM)- Sourcing Decisions& Transportation...Chandra Shekar Immani
 
Financial Markets & Services (FMS)- Types of Factoring- MBA
Financial Markets & Services (FMS)- Types of Factoring- MBAFinancial Markets & Services (FMS)- Types of Factoring- MBA
Financial Markets & Services (FMS)- Types of Factoring- MBAChandra Shekar Immani
 
Entrepreneurship Development(ED)- Financial Institutions Supporting Entrepren...
Entrepreneurship Development(ED)- Financial Institutions Supporting Entrepren...Entrepreneurship Development(ED)- Financial Institutions Supporting Entrepren...
Entrepreneurship Development(ED)- Financial Institutions Supporting Entrepren...Chandra Shekar Immani
 
Security Analysis and Portfolio Management (SAPM)- Portfolio Evaluation under...
Security Analysis and Portfolio Management (SAPM)- Portfolio Evaluation under...Security Analysis and Portfolio Management (SAPM)- Portfolio Evaluation under...
Security Analysis and Portfolio Management (SAPM)- Portfolio Evaluation under...Chandra Shekar Immani
 
Banking and Insurance Management (BIM)- Functions of Insurers- MBA
Banking and Insurance Management (BIM)- Functions of Insurers- MBABanking and Insurance Management (BIM)- Functions of Insurers- MBA
Banking and Insurance Management (BIM)- Functions of Insurers- MBAChandra Shekar Immani
 
Business Ethics & Corporate Governance(BECG)- Corporate Governance in Develop...
Business Ethics & Corporate Governance(BECG)- Corporate Governance in Develop...Business Ethics & Corporate Governance(BECG)- Corporate Governance in Develop...
Business Ethics & Corporate Governance(BECG)- Corporate Governance in Develop...Chandra Shekar Immani
 
Legal Aspects of Business (LAB)- Discharge of Negotiable Instrument- MBA
Legal Aspects of Business (LAB)- Discharge of Negotiable Instrument- MBALegal Aspects of Business (LAB)- Discharge of Negotiable Instrument- MBA
Legal Aspects of Business (LAB)- Discharge of Negotiable Instrument- MBAChandra Shekar Immani
 
Strategic Management- Strategic Audit- MBA
Strategic Management- Strategic Audit- MBAStrategic Management- Strategic Audit- MBA
Strategic Management- Strategic Audit- MBAChandra Shekar Immani
 
Industry and Competitor Analysis-SM-MBA
Industry and Competitor Analysis-SM-MBAIndustry and Competitor Analysis-SM-MBA
Industry and Competitor Analysis-SM-MBAChandra Shekar Immani
 
Factors That Shape a Company's Strategies-SM-MBA
Factors That Shape a Company's Strategies-SM-MBAFactors That Shape a Company's Strategies-SM-MBA
Factors That Shape a Company's Strategies-SM-MBAChandra Shekar Immani
 
Developing a Strategic Vision, Mission,Objectives and Policies - SM - MBA
Developing a Strategic Vision, Mission,Objectives and Policies - SM - MBADeveloping a Strategic Vision, Mission,Objectives and Policies - SM - MBA
Developing a Strategic Vision, Mission,Objectives and Policies - SM - MBAChandra Shekar Immani
 
Strategic Management Process - PPT- MBA
Strategic Management Process - PPT- MBAStrategic Management Process - PPT- MBA
Strategic Management Process - PPT- MBAChandra Shekar Immani
 
Presentation on Strategic Management (SM)- MBA
Presentation on Strategic Management (SM)- MBAPresentation on Strategic Management (SM)- MBA
Presentation on Strategic Management (SM)- MBAChandra Shekar Immani
 
A Presentation on the Rural Electrification Corporation Limited (RECL)- Mini ...
A Presentation on the Rural Electrification Corporation Limited (RECL)- Mini ...A Presentation on the Rural Electrification Corporation Limited (RECL)- Mini ...
A Presentation on the Rural Electrification Corporation Limited (RECL)- Mini ...Chandra Shekar Immani
 
Case Analysis Presentation- Royal Electronics- MBA
Case Analysis Presentation- Royal  Electronics- MBACase Analysis Presentation- Royal  Electronics- MBA
Case Analysis Presentation- Royal Electronics- MBAChandra Shekar Immani
 

Más de Chandra Shekar Immani (20)

MBA Finance- A Study on Funds Flow Analysis With reference to GAIL(India) Lim...
MBA Finance- A Study on Funds Flow Analysis With reference to GAIL(India) Lim...MBA Finance- A Study on Funds Flow Analysis With reference to GAIL(India) Lim...
MBA Finance- A Study on Funds Flow Analysis With reference to GAIL(India) Lim...
 
Case Study Analysis-Credit Cards- MBA-PPT
Case Study Analysis-Credit Cards- MBA-PPTCase Study Analysis-Credit Cards- MBA-PPT
Case Study Analysis-Credit Cards- MBA-PPT
 
Tax management (TM)- Deductions under section 80 of Income Tax act-MBA
Tax management (TM)- Deductions under section 80 of Income Tax act-MBATax management (TM)- Deductions under section 80 of Income Tax act-MBA
Tax management (TM)- Deductions under section 80 of Income Tax act-MBA
 
Logistics & Supply Chain Management(LSCM)- Sourcing Decisions& Transportation...
Logistics & Supply Chain Management(LSCM)- Sourcing Decisions& Transportation...Logistics & Supply Chain Management(LSCM)- Sourcing Decisions& Transportation...
Logistics & Supply Chain Management(LSCM)- Sourcing Decisions& Transportation...
 
Financial Markets & Services (FMS)- Types of Factoring- MBA
Financial Markets & Services (FMS)- Types of Factoring- MBAFinancial Markets & Services (FMS)- Types of Factoring- MBA
Financial Markets & Services (FMS)- Types of Factoring- MBA
 
Entrepreneurship Development(ED)- Financial Institutions Supporting Entrepren...
Entrepreneurship Development(ED)- Financial Institutions Supporting Entrepren...Entrepreneurship Development(ED)- Financial Institutions Supporting Entrepren...
Entrepreneurship Development(ED)- Financial Institutions Supporting Entrepren...
 
Security Analysis and Portfolio Management (SAPM)- Portfolio Evaluation under...
Security Analysis and Portfolio Management (SAPM)- Portfolio Evaluation under...Security Analysis and Portfolio Management (SAPM)- Portfolio Evaluation under...
Security Analysis and Portfolio Management (SAPM)- Portfolio Evaluation under...
 
Banking and Insurance Management (BIM)- Functions of Insurers- MBA
Banking and Insurance Management (BIM)- Functions of Insurers- MBABanking and Insurance Management (BIM)- Functions of Insurers- MBA
Banking and Insurance Management (BIM)- Functions of Insurers- MBA
 
Business Ethics & Corporate Governance(BECG)- Corporate Governance in Develop...
Business Ethics & Corporate Governance(BECG)- Corporate Governance in Develop...Business Ethics & Corporate Governance(BECG)- Corporate Governance in Develop...
Business Ethics & Corporate Governance(BECG)- Corporate Governance in Develop...
 
Legal Aspects of Business (LAB)- Discharge of Negotiable Instrument- MBA
Legal Aspects of Business (LAB)- Discharge of Negotiable Instrument- MBALegal Aspects of Business (LAB)- Discharge of Negotiable Instrument- MBA
Legal Aspects of Business (LAB)- Discharge of Negotiable Instrument- MBA
 
Strategic Management- Strategic Audit- MBA
Strategic Management- Strategic Audit- MBAStrategic Management- Strategic Audit- MBA
Strategic Management- Strategic Audit- MBA
 
Environmental Scanning-SM-MBA
Environmental Scanning-SM-MBAEnvironmental Scanning-SM-MBA
Environmental Scanning-SM-MBA
 
Industry and Competitor Analysis-SM-MBA
Industry and Competitor Analysis-SM-MBAIndustry and Competitor Analysis-SM-MBA
Industry and Competitor Analysis-SM-MBA
 
Crafting a Strategy-SM-MBA
Crafting a Strategy-SM-MBACrafting a Strategy-SM-MBA
Crafting a Strategy-SM-MBA
 
Factors That Shape a Company's Strategies-SM-MBA
Factors That Shape a Company's Strategies-SM-MBAFactors That Shape a Company's Strategies-SM-MBA
Factors That Shape a Company's Strategies-SM-MBA
 
Developing a Strategic Vision, Mission,Objectives and Policies - SM - MBA
Developing a Strategic Vision, Mission,Objectives and Policies - SM - MBADeveloping a Strategic Vision, Mission,Objectives and Policies - SM - MBA
Developing a Strategic Vision, Mission,Objectives and Policies - SM - MBA
 
Strategic Management Process - PPT- MBA
Strategic Management Process - PPT- MBAStrategic Management Process - PPT- MBA
Strategic Management Process - PPT- MBA
 
Presentation on Strategic Management (SM)- MBA
Presentation on Strategic Management (SM)- MBAPresentation on Strategic Management (SM)- MBA
Presentation on Strategic Management (SM)- MBA
 
A Presentation on the Rural Electrification Corporation Limited (RECL)- Mini ...
A Presentation on the Rural Electrification Corporation Limited (RECL)- Mini ...A Presentation on the Rural Electrification Corporation Limited (RECL)- Mini ...
A Presentation on the Rural Electrification Corporation Limited (RECL)- Mini ...
 
Case Analysis Presentation- Royal Electronics- MBA
Case Analysis Presentation- Royal  Electronics- MBACase Analysis Presentation- Royal  Electronics- MBA
Case Analysis Presentation- Royal Electronics- MBA
 

Último

BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptx
BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptxBPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptx
BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptxMohammedJunaid861692
 
Edukaciniai dropshipping via API with DroFx
Edukaciniai dropshipping via API with DroFxEdukaciniai dropshipping via API with DroFx
Edukaciniai dropshipping via API with DroFxolyaivanovalion
 
ALSO dropshipping via API with DroFx.pptx
ALSO dropshipping via API with DroFx.pptxALSO dropshipping via API with DroFx.pptx
ALSO dropshipping via API with DroFx.pptxolyaivanovalion
 
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAl Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAroojKhan71
 
Mature dropshipping via API with DroFx.pptx
Mature dropshipping via API with DroFx.pptxMature dropshipping via API with DroFx.pptx
Mature dropshipping via API with DroFx.pptxolyaivanovalion
 
Best VIP Call Girls Noida Sector 39 Call Me: 8448380779
Best VIP Call Girls Noida Sector 39 Call Me: 8448380779Best VIP Call Girls Noida Sector 39 Call Me: 8448380779
Best VIP Call Girls Noida Sector 39 Call Me: 8448380779Delhi Call girls
 
Zuja dropshipping via API with DroFx.pptx
Zuja dropshipping via API with DroFx.pptxZuja dropshipping via API with DroFx.pptx
Zuja dropshipping via API with DroFx.pptxolyaivanovalion
 
CebaBaby dropshipping via API with DroFX.pptx
CebaBaby dropshipping via API with DroFX.pptxCebaBaby dropshipping via API with DroFX.pptx
CebaBaby dropshipping via API with DroFX.pptxolyaivanovalion
 
Invezz.com - Grow your wealth with trading signals
Invezz.com - Grow your wealth with trading signalsInvezz.com - Grow your wealth with trading signals
Invezz.com - Grow your wealth with trading signalsInvezz1
 
Log Analysis using OSSEC sasoasasasas.pptx
Log Analysis using OSSEC sasoasasasas.pptxLog Analysis using OSSEC sasoasasasas.pptx
Log Analysis using OSSEC sasoasasasas.pptxJohnnyPlasten
 
VidaXL dropshipping via API with DroFx.pptx
VidaXL dropshipping via API with DroFx.pptxVidaXL dropshipping via API with DroFx.pptx
VidaXL dropshipping via API with DroFx.pptxolyaivanovalion
 
Schema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfSchema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfLars Albertsson
 
Call me @ 9892124323 Cheap Rate Call Girls in Vashi with Real Photo 100% Secure
Call me @ 9892124323  Cheap Rate Call Girls in Vashi with Real Photo 100% SecureCall me @ 9892124323  Cheap Rate Call Girls in Vashi with Real Photo 100% Secure
Call me @ 9892124323 Cheap Rate Call Girls in Vashi with Real Photo 100% SecurePooja Nehwal
 
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Call Girls 🫤 Dwarka ➡️ 9711199171 ➡️ Delhi 🫦 Two shot with one girl
Call Girls 🫤 Dwarka ➡️ 9711199171 ➡️ Delhi 🫦 Two shot with one girlCall Girls 🫤 Dwarka ➡️ 9711199171 ➡️ Delhi 🫦 Two shot with one girl
Call Girls 🫤 Dwarka ➡️ 9711199171 ➡️ Delhi 🫦 Two shot with one girlkumarajju5765
 
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Callshivangimorya083
 
BigBuy dropshipping via API with DroFx.pptx
BigBuy dropshipping via API with DroFx.pptxBigBuy dropshipping via API with DroFx.pptx
BigBuy dropshipping via API with DroFx.pptxolyaivanovalion
 
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Callshivangimorya083
 
Smarteg dropshipping via API with DroFx.pptx
Smarteg dropshipping via API with DroFx.pptxSmarteg dropshipping via API with DroFx.pptx
Smarteg dropshipping via API with DroFx.pptxolyaivanovalion
 

Último (20)

BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptx
BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptxBPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptx
BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptx
 
Edukaciniai dropshipping via API with DroFx
Edukaciniai dropshipping via API with DroFxEdukaciniai dropshipping via API with DroFx
Edukaciniai dropshipping via API with DroFx
 
ALSO dropshipping via API with DroFx.pptx
ALSO dropshipping via API with DroFx.pptxALSO dropshipping via API with DroFx.pptx
ALSO dropshipping via API with DroFx.pptx
 
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAl Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
 
Mature dropshipping via API with DroFx.pptx
Mature dropshipping via API with DroFx.pptxMature dropshipping via API with DroFx.pptx
Mature dropshipping via API with DroFx.pptx
 
Best VIP Call Girls Noida Sector 39 Call Me: 8448380779
Best VIP Call Girls Noida Sector 39 Call Me: 8448380779Best VIP Call Girls Noida Sector 39 Call Me: 8448380779
Best VIP Call Girls Noida Sector 39 Call Me: 8448380779
 
Zuja dropshipping via API with DroFx.pptx
Zuja dropshipping via API with DroFx.pptxZuja dropshipping via API with DroFx.pptx
Zuja dropshipping via API with DroFx.pptx
 
CebaBaby dropshipping via API with DroFX.pptx
CebaBaby dropshipping via API with DroFX.pptxCebaBaby dropshipping via API with DroFX.pptx
CebaBaby dropshipping via API with DroFX.pptx
 
Invezz.com - Grow your wealth with trading signals
Invezz.com - Grow your wealth with trading signalsInvezz.com - Grow your wealth with trading signals
Invezz.com - Grow your wealth with trading signals
 
Log Analysis using OSSEC sasoasasasas.pptx
Log Analysis using OSSEC sasoasasasas.pptxLog Analysis using OSSEC sasoasasasas.pptx
Log Analysis using OSSEC sasoasasasas.pptx
 
VidaXL dropshipping via API with DroFx.pptx
VidaXL dropshipping via API with DroFx.pptxVidaXL dropshipping via API with DroFx.pptx
VidaXL dropshipping via API with DroFx.pptx
 
Schema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfSchema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdf
 
Call me @ 9892124323 Cheap Rate Call Girls in Vashi with Real Photo 100% Secure
Call me @ 9892124323  Cheap Rate Call Girls in Vashi with Real Photo 100% SecureCall me @ 9892124323  Cheap Rate Call Girls in Vashi with Real Photo 100% Secure
Call me @ 9892124323 Cheap Rate Call Girls in Vashi with Real Photo 100% Secure
 
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
 
Call Girls 🫤 Dwarka ➡️ 9711199171 ➡️ Delhi 🫦 Two shot with one girl
Call Girls 🫤 Dwarka ➡️ 9711199171 ➡️ Delhi 🫦 Two shot with one girlCall Girls 🫤 Dwarka ➡️ 9711199171 ➡️ Delhi 🫦 Two shot with one girl
Call Girls 🫤 Dwarka ➡️ 9711199171 ➡️ Delhi 🫦 Two shot with one girl
 
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
 
BigBuy dropshipping via API with DroFx.pptx
BigBuy dropshipping via API with DroFx.pptxBigBuy dropshipping via API with DroFx.pptx
BigBuy dropshipping via API with DroFx.pptx
 
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in Kishangarh
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in  KishangarhDelhi 99530 vip 56974 Genuine Escort Service Call Girls in  Kishangarh
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in Kishangarh
 
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
 
Smarteg dropshipping via API with DroFx.pptx
Smarteg dropshipping via API with DroFx.pptxSmarteg dropshipping via API with DroFx.pptx
Smarteg dropshipping via API with DroFx.pptx
 

Quantitative analysis for business decision- Program Evaluation and Review Technique (PERT)

  • 1. QUANTITATIVE ANALYSIS FOR BUSINESS DECISION First semester --- 2nd Mid PPT IMMANI CHANDRA SHEKAR REGD. NO. :19K61E0020 SUBJECT CODE :18MS01T5
  • 3. What is Network Analysis? Network analysis is the general name given to certain specific techniques which can be used for planning, management and control of project.
  • 4. Applications: • Construction of a Residential complex, • Commercial complex, • Petro-chemical complex • Ship building, Aircraft Manufacturing • Satellite mission development • Installation of a pipe line project etc...
  • 5. 3. Objectives of Network Analysis l) Minimization of Total Project Cost 2) Minimization of Total Project Duration 3) Trade-off between Time and Cost of Project 4) Minimization of Idle Resources 5) Minimize Production Delay, Interruptions and Conflicts
  • 6. Techniques for Network analysis: The two common techniques which are used in network analysis. Critical Path Analysis and PERT are powerful tools that help you to schedule and manage complex projects. They were developed in the 1950s to control large defence projects, and have been used routinely since then. 1. Critical Path Method (CPM) 2. Program Evaluation and Review Technique (PERT)
  • 7. Program Evaluation and Review Technique(PERT): A probabilistic model which is based in the Beta Distribution is called PERT (Program Evaluation and Review Technique). The probability of occurrence is the basis of its estimates which is derived in this technique.
  • 8. Features of PERT: For any activity three time estimates namely optimistic, normal and pessimistic times are estimated with consideration of the presence of uncertainties. • For each activity expected time is calculated with the use of three time estimates. • Critical path and slack time are computed. The sequence of activities which has maximum expected time for the completion of the project determines the critical path. • The person who is incharge of the operation provides the three time estimates. The judgement and experience of the person are the basis of the values of three time estimates. • It is assumed that these time estimates follow a beta distribution.
  • 9. Steps involved in PERT • Step l: Identify the various activities which are involved in the project and drawn up in sequential manner that show which activity follows what. • Step 2: Estimate the activity time and note on the network. • Step 3: Determine the critical activities of the project. • Step 4: Calculate the variability of the project duration and probability of the project completion in a given time period.
  • 10. Probability Consideration in PERT : The analysts of PERT technique have found that the beta-distribution curve provides the satisfactory results for most of the activities. This distribution curve is different from the normal curve and has a shape. Expected Time: tei = (a+4m+b)6. Where, tei= Expected time of the ith activity, a = Optimistic time m = Most likely, or modal time, b = Pessimistic time.
  • 11. • In a project network all earliest and latest times are calculated with the use of expected activity time. • The Standard deviation, σi of the completion time of an activity is calculated as follows: From this, the variance σi2= [(b-a)6]2 • Variance is a measure of the dispersion. If the variance is large then the uncertainty will be greater because it depends on the range (b — a).
  • 12. 10. Problem On PERT An R & D project has a list of tasks to be performed whose time estimates are given in the Table, as follows. Time estimates R & D project
  • 13. 1 .Draw the project network. 2. Find the critical path. 3. Find the probability that the project is completed in 19 days. If the probability is less than 20%, find the probability of completing it in 24days. Solution: 1. Time expected for each activity is calculated using the formula: Similarly, the expected time is calculated for all the activities. tei = (a+4m+b)6 = (4+24+8)6 = 6 days The variance of activity time is calculated using the formula: Similarly, variances of all the activities are calculated. The variance σi2= [(b-a)6]2 = [(8-4)6]2 = 0.444
  • 15. 2. Construct a network diagram:
  • 16. 3. From the network diagram Figure, the critical path is identified as 1-4, 4-6, 6-7, with a project duration of 22 days. 4. The probability of completing the project within 19 days is given by, P (Z< Z0) 5. To find Z0 , 6. We know, P (Z <Z Network Model 0) = 0.5 – z (1.3416) (from normal tables, z (1.3416) = 0.4099) = 0.5 – 0.409 = 0.0901 = 9.01%.Thus, the probability of completing the R&D project in 19 days is 9.01%. 7. Since the probability of completing the project in 19 days is less than 20% As in question, we find the probability of completing it in 24 days.
  • 17.
  • 18. Advantages of PERT • The expected time which is required for completing each activity is determined. • It helps in completion of project within an expected time period. • It reduces the risk factor because it helps the management in handling the uncertainties which are involved in the project. • Detailed planning of activities is possible with the help of PERT technique. • It helps in taking correcting action for completing the project on time.
  • 19. Disadvantages of PERT • In the absence of past data, it is very difficult to provide realistic/correct time estimates for new activities. • In this technique there is not any provision about the requirement of resources at various activities. • In PERT technique frequent updates and revision of calculations are required for the effective control of project which is very costly.