Solution to Final Exam (2014-2015)
Salahaddin University Date 01/06/2015
College of Engineering Time: 3 Hours
Dams & Water Resources Eng. Dept. Subject: Engineering Statistics
Class: 2rd
Year Lecturer: M. Chener S. Qadr
Q1: (28%)
The following series is the minimum monthly flow in m3 .
S-1
over the period 1947 to 2007 of a certain
river.
21 36 4 16 21 21 23 11 46 10
25 12 9 16 10 6 11 12 17 3
11 26 2 6 12 22 13 11 26 20
26 12 8 15 7 10 8 13 19 22
57 37 29 36 38 31 58 63 72 83
86 88 88 83 14 7 9 95 73 69
A) Construct frequency distribution table for the data, including relative and cumulative frequency,
class boundaries and class midpoint.
For the First CLASS: the LOWER CLASS LIMIT = 0
(10%)
B) Calculate Mean, Median, Mode, and Standard deviation for the data (10%)
C) Present the data in form of Ogive, and Pie Chart. (8%)
N.B: More than one solution is acceptable for Q-1- Part A
Solution to Q-1:
Q-1-A
Number of data = 60
Lowest value = 2
Highest Value =95
60, 2, 95
1 3.322log(N)
1 3.322log(60) 6.907 7
95 3
13.28 15
7
,7
N number of data Lowest value Highest value
Number of Classes
Number of Classes use classes
Highest value lowest value
Class width use
N
Use classes with class wi
   
 
  
 
  
 15, lim 0 ( )dth of Lower class it of the First Class GIVEN
The lower Class Limit of Successive Class = Lower Class limit of Proceeding Class + Class Width
The lower Class Limit of 2nd
Class = 0 + 15 =15
The lower Class Limit of 3rd
Class = 15+15=30 and So on.
Lower Class Boundary of Class = (lower Class limt of the same class + Upper Class limit of the
proceeding Class) /2
Lower Class boundary of 2nd
Class = (15+14)/2 = 14.5
Page 2 of 12
Lowe
r
Class
Limit
Upper
Class
Limit
Freq. Relative
Freq.
Classes Cum.
Frequency
Lower Class
Boundary
Upper Class
Boundary
Class
Midpoi
nt
Fx Fx2
1 0 14 25 41.7 Less than 15 25 -0.5 14.5 7 175 1225
2 15 29 17 28.3 Less than 30 42 14.5 29.5 22 374 8228
3 30 44 5 8.3 Less than 45 47 29.5 44.5 37 185 6845
4 45 59 3 5 Less than 60 50 44.5 59.5 52 156 8112
5 60 74 4 6.7 Less than 75 54 59.5 74.5 67 268 17956
6 75 89 5 8.3 Less than 90 59 74.5 89.5 82 410 33620
7 90 104 1 1.7 Less than 105 60 89.5 104.5 97 97 9409
Sum (N) =60 1665 85395
Q-1-B
a) Mean
60 ( ) 1665
( ) 1665
27.75
•
•
60
f
Mean x
f x
f x
x
f
  
   



b) Median
Lower Class
Limit
Upper Class
Limit
Freq. Relative
Freq.
Cum.
Frequency
Lower Class
Boundary
Upper Class
Boundary
Class
Midpoint
1 0 14 25 41.7 25 -0.5 14.5 7 MODAL CLASS
2 15 29 17 28.3 42 14.5 29.5 22 Median CLASS
The second is the Median Class, since Cumulative frequency of 2nd class = 42 > N/2
60 30 14.5
2
15 60
14.5 25 18.91
2 17 2
N
N l
h n
X l c X
f
  
   
          
   
c) Mode
1 2
1 2
0.5 14.5
25 0 25, 25 17 8
L L
d d
  
     
 
1
1 2 1
1 2
( )
25
( 0.5) 14.5 ( 0.5 10.86
25 8
d
Mode L L L
d d
Mode
  

     

d) Standard Deviation
2
( ) 1664 ( ) 5• 539• 8f x f x  
2 2 2
[ ( )] [ ( )] 60 85395 1665
25.77
( 1) 60 (60 1)
n f x f x
S
n n
      
  
  
Solution to Engineering Statistics Exam 2014-2015 Dam and Water Resources Department
Page 3 of 12
Q-1-C
360 360
Component Part Frequencyof theclass
Angle
Whole part Total Frequency
   
Class 1 2 3 4 5 6 7
Frequency 25 17 5 3 4 5 1
Angle 150 102 30 18 24 6 30
0
10
20
30
40
50
60
70
0 20 40 60 80 100 120
CumulativeFrequency
Class Midpoint
OGIVE CHART
1st Class, 150, 42%
2nd Class, 102, 28%
3rd Class, 30, 8%
4th Class, 18, 5%
5th Class, 24, 7%
6th Class, 30, 8%
7th Class, 6, 2%
PIE chart
Class 1st Class 2nd Class 3rd Class 4th Class 5th Class 6th Class 7th Class
Page 4 of 12
Q2: (8%): The following data represent score fo 20 student in a certain test out of 30
{2, 7, 5, 8, 13, 14, 18, 13, 12, 17, 15, 12, 19, 11, 14, 14, 18, 22, 23, 29}
A) Find the percentile rank of a score of 19 (2%)
B) Make a box-and-whisker plot of the data. Find the interquartile range (3%)
C) Find the value corresponding to the 30th
and 91th
(3%)
Solution Q-2:
Sort the data from lowest to highest
{2, 7, 5, 8, 11, 12, 12, 13, 13, 14, 14, 14, 15, 17, 18, 18, 19, 22, 23, 29}
a) Percentile rank of a score of 19
0.5
100
16 0.5
19 100 82.5%
20
Number of valueslessthan X
Percentile of Value X
Total number of values
Percentile of Score

 

  
b) Make a box-and-whisker plot of the data. Find the interquartile range
 1
11 12
Q , 11.5
2
median Low MD

  
 2
14 14
Q , 14
2
median Low High

  
 3
18 18
Q , 18
2
median MD High

  
Now you can draw box and whisker plot from the data
c) Find the value corresponding to the 30th and 91th
{2, 7, 5, 8, 11, 12, 12, 13, 13, 14, 14, 14, 15, 17, 18, 18, 19, 22, 23, 29}
6th value, 7th value
30
30
20 6
100 100
1 6 12 7 12
   
     . ,
k
L n L
L L L L L
∴ L=12
A score of 12 correspond to 30th percentile. In another meaning A Student with a score of
12, did better than 30 percent of the students,
91
91
20 18 2 19
100 100
      .
k
L n L next whole number
L19 = 23
A score of 23 correspond to 91th percentile. In another meaning A Student with a score of 23, did
better than 91 percent of the students.
Solution to Engineering Statistics Exam 2014-2015 Dam and Water Resources Department
Page 5 of 12
Q3: (8%)
A developer of a new subdivision offers prospective home buyers a choice of Tudor, rustic, colonial, and
traditional exterior styling in ranch, two-story, and split-level floor plans.
A) Prepare Tree Diagram (4%)
B) In how many different ways can a buyer order one of these homes? (4%)
Solution to Q-3
A) Tree Diagram
B) In how many different ways can a buyer order one of these homes?
, , , 41 Tudor rustic colonial and traditin Exterior st onal exteryling ior 
2 , , 3ranch two story and spn lFloor P it levellan   
1 2 4 3 12
in12wayscan a buyer order one of thesehomes
n n   

Page 6 of 12
Q4: (6%)
If a two dice is tossed in a balanced dice.
A) What is the probability of getting a total of 7 or 11 when pair of fair dice is tossed? (3%)
B) Fair dice are rolled. What is the probability of getting a sum less than 7 or a sum equal to 10? (3%)
SOLUTION Q-4
Q-4-A
Let A = Probability of getting a sum of 7
For getting a sum of 7,
(1,6) (2,5) (3,4) (4,3) (5,2) and (6,1) are favourable outcomes
2
Samplespace=Totalnumberof possibleoutcomes 6 36
Probability of getting a sum of 7
6

36
N
n
PA
N
  
  
For getting a sum of 11,
Let B = Probability of getting a sum of 11
(5,6) and (6,5) are favourable outcomes
Probability of getting a sum of 11
2
36
n
PB
N
  
Probability of getting a sum of 7 or 11 =
6 2 8
36 36 36
PAOR B PA PB PA PB      
Q-4-B
For getting a sum of less than 7,
Let C = Probability of getting a sum of less than 7
Sums less than 7= 2, 3, 4, 5, 6
∴ Favourable outcomes are:
Outcomes that give a sum of 2: 1-1
Outcomes that give a sum of 3: 1-2, 2-1
Outcomes that give a sum of 4: 1-3, 2-2, 3-1
Outcomes that give a sum of 5: 1-4, 2-3, 3-2, 4-1
Outcomes that give a sum of 6: 1-5, 2-4, 3-3, 4-2, 5-1
Total number of outcomes in our EVENT: 15
15
3
7
6
Probability of getting a su
n
PBm of less tha
N
n   
For getting a sum equal to 10,
Let D = Probability of getting a sum of 10
(4,6) (5,5) (6,4) are favourable outcomes
1
6
0
3
3
Probability of getting
n
PBa sum of
N
   
Probability of getting a sum of less than 7 or a sum equal to 10
18 3 21
36 36 36
PC or D PC PD PC PD      
Solution to Engineering Statistics Exam 2014-2015 Dam and Water Resources Department
Page 7 of 12
Q5: (7%)
Find the probability of a couple having at least 2 boy among 5 children. Assume that boys and girls are
equally likely and that the gender of a child is independent of any other child.
Solution to Q5:
Sample Space:
Sample space for No boy: (G, G, G, G, G)
Sample space for One boy:
(B, G, G, G, G) (G, B, G, G, G) (G, G, B, G, G) (G, G, G, B, G) (G, G, G, G, B)
Let A=havingat least twoboys
1
(at least one)
1
(at least twoboys)
having lessthan twoboys
P P
none
P PA P
none
P P P
none Noboy One boy
 
  
  
5
( )( )
1
P
2
Sample Spacefor one child ( , ) 2
Sample Spacefor 5 child 2 32
girlboy
P
Boy Girl
 
 
 
1
( )
1
(at least twoboys)
having lessthan twoboy
P P
at least one none
P PA P
none
P s P P
none Noboy One boy
 
  
  
Girl and Girl andGirl and Girl and Girl
1 5
,
32 32
1 5 6
32 32 32
P
Noboy
P P
Noboy one boy
P none P P
Noboy one boy

 
    
1
( )
6 26
1
( ) 32 32
P P
at least one none
P PA
at least twoboys
 
   
Page 8 of 12
Q6: (8%)
A town has two fire engines operating independently. The probability that a specific engine is available
when needed is 0.96
A) What is the probability that neither is available when needed? (4%)
B) What is the probability that a fire engine is available when needed?
SOLUTION Q6: (8%)
(4%)
Or Probability that a fire engine is available when need needed = One or both fire engine available
= Probability of at least one
atleat one fireengineisavailble
let
P PA
1
0.016 ( )
PA Pnone
Pnone both fire enginesarenot available from part A
 
 
1
0.0016 ( )
1 1 0.0016 0.9984
PA Pnone
Pnone both fire engines arenot available from part A
PA Pnone
 
 

    
Solution to Engineering Statistics Exam 2014-2015 Dam and Water Resources Department
Page 9 of 12
Q7: (15%)
In 1970, 11% of Americans completed four years of college; 43% of them were women. In 1990, 22% of
Americans completed four years of college; 53% of them were women.
A) What is the probability that a woman finished four years of college in 1990? (3%)
B) What is the probability that a man had not finished college in 1990? (4%)
C) Given that a person was man, what is the probability that a person completed four years of
college in 1990?
(4%)
D) Given that a person completed four years of college in 1970, what is the probability that
the person was a woman?
(4%)
Illustrative Figure
1970
11% Completed four years of college
89% DID NOT completed four years of
college
57% Man
43% Woman
43% Man
57% Woman
1990
22% Completed four years of college
78% DID NOT completed four years of college
53% Woman
P(𝐴̅∩C)=0.78×0.53
47% Man
P A and B =0.22×0.53
53% Man
47% Woman
Page 10 of 12
Solution Q-7
Q-7-A
What is the probability that a woman finished four years of college in 1990?
let
F= American finished four years of college in 1990
W= American woman finished four years of college in 1990
M= American man finished four years of college in 1990
( ) 0.22 0.53 0.1166 11.66%P F W    
Q-7-B
What is the probability that a man had not finished college in 1990?
F

= American HAD NOT finished four years of college in 1990
∴22% of American finished 4 year college, then 78% had not finished college
( ) 0.78 0.53 0.4134 41.34%P F M

    
Q-7-C
Given that a person was man, what is the probability that a person completed four years of college
in 1990?
( / ) 0.47P F M 
Q-7-D
Given that a person completed four years of college in 1970, what is the probability that the person
was a woman?
( / ) 0.43P W F 
Solution to Engineering Statistics Exam 2014-2015 Dam and Water Resources Department
Page 11 of 12
Q8: (20%)
The demand for a particular type of pump at an isolated mine is random and independent of previous
occurrences, but the average demand in a week (7 days) is for 2.8pumps. Further supplies are ordered
each Tuesday morning and arrive on the weekly plane on Friday morning. Last Tuesday morning only
one pump was in stock, so the stores man ordered six more to come in Friday morning.
A) Find the probability that one pump will still be in stock on Friday morning when new
stock arrives.
(6%)
B) Find the probability that stock will be exhausted and there will be unsatisfied demand for
at least one pump by Friday morning.
(6%)
C) Find the probability that one pump will still be in stock this Friday morning and at least
five will be in stock next Tuesday morning.
(8%)
Solution to Q-8
First we have to recognize that the Poisson distribution will apply.
2.8
0.4 /
7
day  
Q-8-A
(3 ) 0.4 3 1.2day   
X = Demand of pump per day.
If one pump will still be in stock in Friday,
It means that the demand on Pump in three days was zero ∴ X=0
1.2 0
( 0)
1.2
(No demand in 3days) 0.3012
! 0!
x
x
e e
P P
x

 
   
(No demand in 3days) ( ) 0.3012P P one pump will be in stock at Fridaymorning 
Q-8-B
If stock will be exhausted and there will be unsatisfied demand for at least one pump by Friday
morning
∴ X= ( one pump in stock + unsatisfied demand for at least one)
∴ X= Demand at least two
( 3days) ( 2) 1Demand of at least two pump x noneP P P  
(Demand for zero or onepumpinthree days)noneP P
( 0) ( 1)
1.2 0 1.2 1
1.2 1.2
0.3012 0.3614 0.6626
0! 1!
none x x
none
P P P
e e
P
 
 
 
    
Page 12 of 12
( 2)
( 2)
(Demandof at least two pump 3days)
(Demandof at least two pump 3days)
1
1 0.6626 0.3374
x none
x
P P P
P P


  
   
( 2)
(unsatisfied demand for a
(Demandof at least twopump 3day
t least one pump by Friday mo
s)
rning)
0.3374
0.3374
xP P
P
 
 
Q-8-C
Find the probability that one pump will still be in stock this Friday morning and at least five will be
in stock next Tuesday morning.
at least five will be in stock next Tuesday morning.
Pr(one pump in stock this Friday and at least five
let A=Onepump beinstock this
will be in stock next Tue
fridaymornin
sday)=P(A
g
B=
andB)
It is a dependant multiplication rule,
P(A ) P(A B) PA PB/ Aand B    
from Part A,
0 0.3012PA Px  
From Friday Morning to Tuesday morning, there is 4 days: Saturday, Sunday Monday, Tuesday =4
0.4 4 1.6
(4 )day
   
After the new stock arrives, we will have 1+ 6 = 7 pump in stock Friday morning.
If we have at least five in stock Tuesday morning, then the demand in four days most be ≤ 2 pump.
( 3days) ( 2) ( 0) ( 0) ( 2)Demand of at mosttwo pump x x x xP P P P P      
( 4days) ( 2) ( 0) ( 0) ( 2)
1.6 0 1.6 1 1.6 2
( 2)
1.2 1.2 1.2
0.7834
0! 1! 2!
Demand of at mosttwo pump x x x x
x
P P P P P
e e e
P
   
  

   
   
( 4days) ( 2)
(at leastfivewill be in stock nextTuesdaygiven that thereisone stockin friday)
0.7834
/ 0.7834
Demand of at most two pump xP P
P PB A
 
  
P(A ) P(A B) PA PB/ A
P(A B) 0.3012 0.7834 0.236
and B    
   

Más contenido relacionado

Similar a Solution to final exam engineering statistics 2014 2015

1PPTs-Handout One-An Overview of Descriptive Statistics-Chapter 1_2.pptx
1PPTs-Handout One-An Overview of Descriptive Statistics-Chapter 1_2.pptx1PPTs-Handout One-An Overview of Descriptive Statistics-Chapter 1_2.pptx
1PPTs-Handout One-An Overview of Descriptive Statistics-Chapter 1_2.pptxAbdulHananSheikh1
 
Cumulative Frequency Revision
Cumulative Frequency RevisionCumulative Frequency Revision
Cumulative Frequency RevisionPuna Ripiye
 
Mathematical Statistics with Applications in R 2nd Edition Ramachandran Solut...
Mathematical Statistics with Applications in R 2nd Edition Ramachandran Solut...Mathematical Statistics with Applications in R 2nd Edition Ramachandran Solut...
Mathematical Statistics with Applications in R 2nd Edition Ramachandran Solut...Alvaradoree
 
Cumulative frequency revision card
Cumulative frequency revision cardCumulative frequency revision card
Cumulative frequency revision cardPuna Ripiye
 
30 Statistics.pptx It Is ppt about nimcet
30 Statistics.pptx It Is ppt about nimcet30 Statistics.pptx It Is ppt about nimcet
30 Statistics.pptx It Is ppt about nimcetMaheshWadekar6
 
Ce gate-2022-forenoon-solution
Ce gate-2022-forenoon-solutionCe gate-2022-forenoon-solution
Ce gate-2022-forenoon-solutionsyed adnan andrabi
 
0113 examia
0113 examia0113 examia
0113 examiapschlein
 
CXC MATHEMATICS MULTIPLE CHOICE
CXC MATHEMATICS MULTIPLE CHOICECXC MATHEMATICS MULTIPLE CHOICE
CXC MATHEMATICS MULTIPLE CHOICEMadanaDookieram
 
Chi Squared
Chi SquaredChi Squared
Chi SquaredGeoBlogs
 
C2 st lecture 13 revision for test b handout
C2 st lecture 13   revision for test b handoutC2 st lecture 13   revision for test b handout
C2 st lecture 13 revision for test b handoutfatima d
 
1of 20Use the formula for the sum of the first n terms of a geom.docx
1of 20Use the formula for the sum of the first n terms of a geom.docx1of 20Use the formula for the sum of the first n terms of a geom.docx
1of 20Use the formula for the sum of the first n terms of a geom.docxhyacinthshackley2629
 
QuizTop of FormQuestion 1 (24 points)Question 1True or Fa.docx
QuizTop of FormQuestion 1 (24 points)Question 1True or Fa.docxQuizTop of FormQuestion 1 (24 points)Question 1True or Fa.docx
QuizTop of FormQuestion 1 (24 points)Question 1True or Fa.docxsleeperharwell
 
[Question Paper] Quantitative Technology (Revised Course) [September / 2013]
[Question Paper] Quantitative Technology (Revised Course) [September / 2013][Question Paper] Quantitative Technology (Revised Course) [September / 2013]
[Question Paper] Quantitative Technology (Revised Course) [September / 2013]Mumbai B.Sc.IT Study
 
analytical representation of data
 analytical representation of data analytical representation of data
analytical representation of dataUnsa Shakir
 
QuizQuestion 1 (24 points)Question 1True or Fal.docx
QuizQuestion 1 (24 points)Question 1True or Fal.docxQuizQuestion 1 (24 points)Question 1True or Fal.docx
QuizQuestion 1 (24 points)Question 1True or Fal.docxsleeperharwell
 

Similar a Solution to final exam engineering statistics 2014 2015 (20)

1PPTs-Handout One-An Overview of Descriptive Statistics-Chapter 1_2.pptx
1PPTs-Handout One-An Overview of Descriptive Statistics-Chapter 1_2.pptx1PPTs-Handout One-An Overview of Descriptive Statistics-Chapter 1_2.pptx
1PPTs-Handout One-An Overview of Descriptive Statistics-Chapter 1_2.pptx
 
Cumulative Frequency Revision
Cumulative Frequency RevisionCumulative Frequency Revision
Cumulative Frequency Revision
 
Mathematical Statistics with Applications in R 2nd Edition Ramachandran Solut...
Mathematical Statistics with Applications in R 2nd Edition Ramachandran Solut...Mathematical Statistics with Applications in R 2nd Edition Ramachandran Solut...
Mathematical Statistics with Applications in R 2nd Edition Ramachandran Solut...
 
Prac excises 3[1].5
Prac excises 3[1].5Prac excises 3[1].5
Prac excises 3[1].5
 
Cumulative frequency revision card
Cumulative frequency revision cardCumulative frequency revision card
Cumulative frequency revision card
 
30 Statistics.pptx It Is ppt about nimcet
30 Statistics.pptx It Is ppt about nimcet30 Statistics.pptx It Is ppt about nimcet
30 Statistics.pptx It Is ppt about nimcet
 
Ce gate-2022-forenoon-solution
Ce gate-2022-forenoon-solutionCe gate-2022-forenoon-solution
Ce gate-2022-forenoon-solution
 
Cat sample-1
Cat sample-1Cat sample-1
Cat sample-1
 
0113 examia
0113 examia0113 examia
0113 examia
 
CXC MATHEMATICS MULTIPLE CHOICE
CXC MATHEMATICS MULTIPLE CHOICECXC MATHEMATICS MULTIPLE CHOICE
CXC MATHEMATICS MULTIPLE CHOICE
 
Chi Squared
Chi SquaredChi Squared
Chi Squared
 
Practice test1 solution
Practice test1 solutionPractice test1 solution
Practice test1 solution
 
C2 st lecture 13 revision for test b handout
C2 st lecture 13   revision for test b handoutC2 st lecture 13   revision for test b handout
C2 st lecture 13 revision for test b handout
 
1of 20Use the formula for the sum of the first n terms of a geom.docx
1of 20Use the formula for the sum of the first n terms of a geom.docx1of 20Use the formula for the sum of the first n terms of a geom.docx
1of 20Use the formula for the sum of the first n terms of a geom.docx
 
QuizTop of FormQuestion 1 (24 points)Question 1True or Fa.docx
QuizTop of FormQuestion 1 (24 points)Question 1True or Fa.docxQuizTop of FormQuestion 1 (24 points)Question 1True or Fa.docx
QuizTop of FormQuestion 1 (24 points)Question 1True or Fa.docx
 
[Question Paper] Quantitative Technology (Revised Course) [September / 2013]
[Question Paper] Quantitative Technology (Revised Course) [September / 2013][Question Paper] Quantitative Technology (Revised Course) [September / 2013]
[Question Paper] Quantitative Technology (Revised Course) [September / 2013]
 
analytical representation of data
 analytical representation of data analytical representation of data
analytical representation of data
 
4. parameter and statistic
4. parameter and statistic4. parameter and statistic
4. parameter and statistic
 
QuizQuestion 1 (24 points)Question 1True or Fal.docx
QuizQuestion 1 (24 points)Question 1True or Fal.docxQuizQuestion 1 (24 points)Question 1True or Fal.docx
QuizQuestion 1 (24 points)Question 1True or Fal.docx
 
Chapter12
Chapter12Chapter12
Chapter12
 

Último

TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 

Último (20)

POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 

Solution to final exam engineering statistics 2014 2015

  • 1. Solution to Engineering Statistics Exam 2014-2015 Dam and Water Resources Department Page 1 of 12 Solution to Final Exam (2014-2015) Salahaddin University Date 01/06/2015 College of Engineering Time: 3 Hours Dams & Water Resources Eng. Dept. Subject: Engineering Statistics Class: 2rd Year Lecturer: M. Chener S. Qadr Q1: (28%) The following series is the minimum monthly flow in m3 . S-1 over the period 1947 to 2007 of a certain river. 21 36 4 16 21 21 23 11 46 10 25 12 9 16 10 6 11 12 17 3 11 26 2 6 12 22 13 11 26 20 26 12 8 15 7 10 8 13 19 22 57 37 29 36 38 31 58 63 72 83 86 88 88 83 14 7 9 95 73 69 A) Construct frequency distribution table for the data, including relative and cumulative frequency, class boundaries and class midpoint. For the First CLASS: the LOWER CLASS LIMIT = 0 (10%) B) Calculate Mean, Median, Mode, and Standard deviation for the data (10%) C) Present the data in form of Ogive, and Pie Chart. (8%) N.B: More than one solution is acceptable for Q-1- Part A Solution to Q-1: Q-1-A Number of data = 60 Lowest value = 2 Highest Value =95 60, 2, 95 1 3.322log(N) 1 3.322log(60) 6.907 7 95 3 13.28 15 7 ,7 N number of data Lowest value Highest value Number of Classes Number of Classes use classes Highest value lowest value Class width use N Use classes with class wi                15, lim 0 ( )dth of Lower class it of the First Class GIVEN The lower Class Limit of Successive Class = Lower Class limit of Proceeding Class + Class Width The lower Class Limit of 2nd Class = 0 + 15 =15 The lower Class Limit of 3rd Class = 15+15=30 and So on. Lower Class Boundary of Class = (lower Class limt of the same class + Upper Class limit of the proceeding Class) /2 Lower Class boundary of 2nd Class = (15+14)/2 = 14.5
  • 2. Page 2 of 12 Lowe r Class Limit Upper Class Limit Freq. Relative Freq. Classes Cum. Frequency Lower Class Boundary Upper Class Boundary Class Midpoi nt Fx Fx2 1 0 14 25 41.7 Less than 15 25 -0.5 14.5 7 175 1225 2 15 29 17 28.3 Less than 30 42 14.5 29.5 22 374 8228 3 30 44 5 8.3 Less than 45 47 29.5 44.5 37 185 6845 4 45 59 3 5 Less than 60 50 44.5 59.5 52 156 8112 5 60 74 4 6.7 Less than 75 54 59.5 74.5 67 268 17956 6 75 89 5 8.3 Less than 90 59 74.5 89.5 82 410 33620 7 90 104 1 1.7 Less than 105 60 89.5 104.5 97 97 9409 Sum (N) =60 1665 85395 Q-1-B a) Mean 60 ( ) 1665 ( ) 1665 27.75 • • 60 f Mean x f x f x x f           b) Median Lower Class Limit Upper Class Limit Freq. Relative Freq. Cum. Frequency Lower Class Boundary Upper Class Boundary Class Midpoint 1 0 14 25 41.7 25 -0.5 14.5 7 MODAL CLASS 2 15 29 17 28.3 42 14.5 29.5 22 Median CLASS The second is the Median Class, since Cumulative frequency of 2nd class = 42 > N/2 60 30 14.5 2 15 60 14.5 25 18.91 2 17 2 N N l h n X l c X f                       c) Mode 1 2 1 2 0.5 14.5 25 0 25, 25 17 8 L L d d            1 1 2 1 1 2 ( ) 25 ( 0.5) 14.5 ( 0.5 10.86 25 8 d Mode L L L d d Mode            d) Standard Deviation 2 ( ) 1664 ( ) 5• 539• 8f x f x   2 2 2 [ ( )] [ ( )] 60 85395 1665 25.77 ( 1) 60 (60 1) n f x f x S n n             
  • 3. Solution to Engineering Statistics Exam 2014-2015 Dam and Water Resources Department Page 3 of 12 Q-1-C 360 360 Component Part Frequencyof theclass Angle Whole part Total Frequency     Class 1 2 3 4 5 6 7 Frequency 25 17 5 3 4 5 1 Angle 150 102 30 18 24 6 30 0 10 20 30 40 50 60 70 0 20 40 60 80 100 120 CumulativeFrequency Class Midpoint OGIVE CHART 1st Class, 150, 42% 2nd Class, 102, 28% 3rd Class, 30, 8% 4th Class, 18, 5% 5th Class, 24, 7% 6th Class, 30, 8% 7th Class, 6, 2% PIE chart Class 1st Class 2nd Class 3rd Class 4th Class 5th Class 6th Class 7th Class
  • 4. Page 4 of 12 Q2: (8%): The following data represent score fo 20 student in a certain test out of 30 {2, 7, 5, 8, 13, 14, 18, 13, 12, 17, 15, 12, 19, 11, 14, 14, 18, 22, 23, 29} A) Find the percentile rank of a score of 19 (2%) B) Make a box-and-whisker plot of the data. Find the interquartile range (3%) C) Find the value corresponding to the 30th and 91th (3%) Solution Q-2: Sort the data from lowest to highest {2, 7, 5, 8, 11, 12, 12, 13, 13, 14, 14, 14, 15, 17, 18, 18, 19, 22, 23, 29} a) Percentile rank of a score of 19 0.5 100 16 0.5 19 100 82.5% 20 Number of valueslessthan X Percentile of Value X Total number of values Percentile of Score        b) Make a box-and-whisker plot of the data. Find the interquartile range  1 11 12 Q , 11.5 2 median Low MD      2 14 14 Q , 14 2 median Low High      3 18 18 Q , 18 2 median MD High     Now you can draw box and whisker plot from the data c) Find the value corresponding to the 30th and 91th {2, 7, 5, 8, 11, 12, 12, 13, 13, 14, 14, 14, 15, 17, 18, 18, 19, 22, 23, 29} 6th value, 7th value 30 30 20 6 100 100 1 6 12 7 12          . , k L n L L L L L L ∴ L=12 A score of 12 correspond to 30th percentile. In another meaning A Student with a score of 12, did better than 30 percent of the students, 91 91 20 18 2 19 100 100       . k L n L next whole number L19 = 23 A score of 23 correspond to 91th percentile. In another meaning A Student with a score of 23, did better than 91 percent of the students.
  • 5. Solution to Engineering Statistics Exam 2014-2015 Dam and Water Resources Department Page 5 of 12 Q3: (8%) A developer of a new subdivision offers prospective home buyers a choice of Tudor, rustic, colonial, and traditional exterior styling in ranch, two-story, and split-level floor plans. A) Prepare Tree Diagram (4%) B) In how many different ways can a buyer order one of these homes? (4%) Solution to Q-3 A) Tree Diagram B) In how many different ways can a buyer order one of these homes? , , , 41 Tudor rustic colonial and traditin Exterior st onal exteryling ior  2 , , 3ranch two story and spn lFloor P it levellan    1 2 4 3 12 in12wayscan a buyer order one of thesehomes n n    
  • 6. Page 6 of 12 Q4: (6%) If a two dice is tossed in a balanced dice. A) What is the probability of getting a total of 7 or 11 when pair of fair dice is tossed? (3%) B) Fair dice are rolled. What is the probability of getting a sum less than 7 or a sum equal to 10? (3%) SOLUTION Q-4 Q-4-A Let A = Probability of getting a sum of 7 For getting a sum of 7, (1,6) (2,5) (3,4) (4,3) (5,2) and (6,1) are favourable outcomes 2 Samplespace=Totalnumberof possibleoutcomes 6 36 Probability of getting a sum of 7 6 36 N n PA N       For getting a sum of 11, Let B = Probability of getting a sum of 11 (5,6) and (6,5) are favourable outcomes Probability of getting a sum of 11 2 36 n PB N    Probability of getting a sum of 7 or 11 = 6 2 8 36 36 36 PAOR B PA PB PA PB       Q-4-B For getting a sum of less than 7, Let C = Probability of getting a sum of less than 7 Sums less than 7= 2, 3, 4, 5, 6 ∴ Favourable outcomes are: Outcomes that give a sum of 2: 1-1 Outcomes that give a sum of 3: 1-2, 2-1 Outcomes that give a sum of 4: 1-3, 2-2, 3-1 Outcomes that give a sum of 5: 1-4, 2-3, 3-2, 4-1 Outcomes that give a sum of 6: 1-5, 2-4, 3-3, 4-2, 5-1 Total number of outcomes in our EVENT: 15 15 3 7 6 Probability of getting a su n PBm of less tha N n    For getting a sum equal to 10, Let D = Probability of getting a sum of 10 (4,6) (5,5) (6,4) are favourable outcomes 1 6 0 3 3 Probability of getting n PBa sum of N     Probability of getting a sum of less than 7 or a sum equal to 10 18 3 21 36 36 36 PC or D PC PD PC PD      
  • 7. Solution to Engineering Statistics Exam 2014-2015 Dam and Water Resources Department Page 7 of 12 Q5: (7%) Find the probability of a couple having at least 2 boy among 5 children. Assume that boys and girls are equally likely and that the gender of a child is independent of any other child. Solution to Q5: Sample Space: Sample space for No boy: (G, G, G, G, G) Sample space for One boy: (B, G, G, G, G) (G, B, G, G, G) (G, G, B, G, G) (G, G, G, B, G) (G, G, G, G, B) Let A=havingat least twoboys 1 (at least one) 1 (at least twoboys) having lessthan twoboys P P none P PA P none P P P none Noboy One boy         5 ( )( ) 1 P 2 Sample Spacefor one child ( , ) 2 Sample Spacefor 5 child 2 32 girlboy P Boy Girl       1 ( ) 1 (at least twoboys) having lessthan twoboy P P at least one none P PA P none P s P P none Noboy One boy         Girl and Girl andGirl and Girl and Girl 1 5 , 32 32 1 5 6 32 32 32 P Noboy P P Noboy one boy P none P P Noboy one boy         1 ( ) 6 26 1 ( ) 32 32 P P at least one none P PA at least twoboys      
  • 8. Page 8 of 12 Q6: (8%) A town has two fire engines operating independently. The probability that a specific engine is available when needed is 0.96 A) What is the probability that neither is available when needed? (4%) B) What is the probability that a fire engine is available when needed? SOLUTION Q6: (8%) (4%) Or Probability that a fire engine is available when need needed = One or both fire engine available = Probability of at least one atleat one fireengineisavailble let P PA 1 0.016 ( ) PA Pnone Pnone both fire enginesarenot available from part A     1 0.0016 ( ) 1 1 0.0016 0.9984 PA Pnone Pnone both fire engines arenot available from part A PA Pnone          
  • 9. Solution to Engineering Statistics Exam 2014-2015 Dam and Water Resources Department Page 9 of 12 Q7: (15%) In 1970, 11% of Americans completed four years of college; 43% of them were women. In 1990, 22% of Americans completed four years of college; 53% of them were women. A) What is the probability that a woman finished four years of college in 1990? (3%) B) What is the probability that a man had not finished college in 1990? (4%) C) Given that a person was man, what is the probability that a person completed four years of college in 1990? (4%) D) Given that a person completed four years of college in 1970, what is the probability that the person was a woman? (4%) Illustrative Figure 1970 11% Completed four years of college 89% DID NOT completed four years of college 57% Man 43% Woman 43% Man 57% Woman 1990 22% Completed four years of college 78% DID NOT completed four years of college 53% Woman P(𝐴̅∩C)=0.78×0.53 47% Man P A and B =0.22×0.53 53% Man 47% Woman
  • 10. Page 10 of 12 Solution Q-7 Q-7-A What is the probability that a woman finished four years of college in 1990? let F= American finished four years of college in 1990 W= American woman finished four years of college in 1990 M= American man finished four years of college in 1990 ( ) 0.22 0.53 0.1166 11.66%P F W     Q-7-B What is the probability that a man had not finished college in 1990? F  = American HAD NOT finished four years of college in 1990 ∴22% of American finished 4 year college, then 78% had not finished college ( ) 0.78 0.53 0.4134 41.34%P F M       Q-7-C Given that a person was man, what is the probability that a person completed four years of college in 1990? ( / ) 0.47P F M  Q-7-D Given that a person completed four years of college in 1970, what is the probability that the person was a woman? ( / ) 0.43P W F 
  • 11. Solution to Engineering Statistics Exam 2014-2015 Dam and Water Resources Department Page 11 of 12 Q8: (20%) The demand for a particular type of pump at an isolated mine is random and independent of previous occurrences, but the average demand in a week (7 days) is for 2.8pumps. Further supplies are ordered each Tuesday morning and arrive on the weekly plane on Friday morning. Last Tuesday morning only one pump was in stock, so the stores man ordered six more to come in Friday morning. A) Find the probability that one pump will still be in stock on Friday morning when new stock arrives. (6%) B) Find the probability that stock will be exhausted and there will be unsatisfied demand for at least one pump by Friday morning. (6%) C) Find the probability that one pump will still be in stock this Friday morning and at least five will be in stock next Tuesday morning. (8%) Solution to Q-8 First we have to recognize that the Poisson distribution will apply. 2.8 0.4 / 7 day   Q-8-A (3 ) 0.4 3 1.2day    X = Demand of pump per day. If one pump will still be in stock in Friday, It means that the demand on Pump in three days was zero ∴ X=0 1.2 0 ( 0) 1.2 (No demand in 3days) 0.3012 ! 0! x x e e P P x        (No demand in 3days) ( ) 0.3012P P one pump will be in stock at Fridaymorning  Q-8-B If stock will be exhausted and there will be unsatisfied demand for at least one pump by Friday morning ∴ X= ( one pump in stock + unsatisfied demand for at least one) ∴ X= Demand at least two ( 3days) ( 2) 1Demand of at least two pump x noneP P P   (Demand for zero or onepumpinthree days)noneP P ( 0) ( 1) 1.2 0 1.2 1 1.2 1.2 0.3012 0.3614 0.6626 0! 1! none x x none P P P e e P           
  • 12. Page 12 of 12 ( 2) ( 2) (Demandof at least two pump 3days) (Demandof at least two pump 3days) 1 1 0.6626 0.3374 x none x P P P P P          ( 2) (unsatisfied demand for a (Demandof at least twopump 3day t least one pump by Friday mo s) rning) 0.3374 0.3374 xP P P     Q-8-C Find the probability that one pump will still be in stock this Friday morning and at least five will be in stock next Tuesday morning. at least five will be in stock next Tuesday morning. Pr(one pump in stock this Friday and at least five let A=Onepump beinstock this will be in stock next Tue fridaymornin sday)=P(A g B= andB) It is a dependant multiplication rule, P(A ) P(A B) PA PB/ Aand B     from Part A, 0 0.3012PA Px   From Friday Morning to Tuesday morning, there is 4 days: Saturday, Sunday Monday, Tuesday =4 0.4 4 1.6 (4 )day     After the new stock arrives, we will have 1+ 6 = 7 pump in stock Friday morning. If we have at least five in stock Tuesday morning, then the demand in four days most be ≤ 2 pump. ( 3days) ( 2) ( 0) ( 0) ( 2)Demand of at mosttwo pump x x x xP P P P P       ( 4days) ( 2) ( 0) ( 0) ( 2) 1.6 0 1.6 1 1.6 2 ( 2) 1.2 1.2 1.2 0.7834 0! 1! 2! Demand of at mosttwo pump x x x x x P P P P P e e e P                 ( 4days) ( 2) (at leastfivewill be in stock nextTuesdaygiven that thereisone stockin friday) 0.7834 / 0.7834 Demand of at most two pump xP P P PB A      P(A ) P(A B) PA PB/ A P(A B) 0.3012 0.7834 0.236 and B        