Measuring In-progress Project Performance
Measuring performance is a critical factor in optimizing performance. Optimal performance
is sustainably achieving multiple, often conflicting, objectives under changing conditions.
Project performance, on the surface, seems easy to measure; just track time, cost and scope
and it’s done. But when we look more deeply we find that it is not that simple.
First, we find that there is confusion about what we actually want to measure. Is it the success
of a single project, the success of project performance across many projects, or the success of
project management and a project office? If our objective is to measure the success of a
single project, are we looking at the project during its life or at the project after it has been
completed?
Once we determine what we really want to evaluate we can identify the key performance
indicators (KPIs) that will tell us whether we have been or are being successful or not and to
what degree. KPIs give managers the most important performance information to enable
them to assess the performance of a project or process. Generally we look for from two to
five or so indicators. One is not enough for any complex process and project performance is a
complex process. Too many KPIs make it difficult to see the big picture clearly. Too few
make it difficult to diagnose and correct the issues that get in the way of optimal
performance.
Projectand BusinessObjectives
Keep in mind that KPIs are not objectives. They are readings that enable a manager to assess
performance towards the achievement of objectives. On a personal level we use KPIs such as
weight, blood pressure, and cholesterol level to assess general health. The objective is general
health, the measures are indicators that can be used to determine if we are tracking towards
the objective, or not.
Project objectives are to deliver goods and services, within time, cost, quality and other
constraints, satisfying stakeholder expectations. Project deliverables are used to deliver
benefits to satisfy the needs of sponsors and clients.
Note the difference between project and business objectives. Projects deliver goods and
services that are generally used after the project has ended to achieve business objectives
such as reducing costs and risks, increasing revenues, etc. Projects are initiated to achieve
business objectives. Project objectives are a means to that end.
When measuring project success, particularly when the project is on-going, it is necessary to
focus on the project objectives and performance against schedule and budget estimates. In
most cases, we cannot measure a project’s success in achieving business objectives until well
after the project has ended. Further, there are factors that are outside of the control of the
project that influence benefits realization. For example, in product development the
performance of sales and marketing, market conditions, and other factors impact the degree
to which expected benefits are achieved.
ProjectPerformance– ScheduleandBudget
Performance measurement during a project is to know how things are going so that we can
have early warning of problems that might get in the way of achieving project objectives and
so that we can manage expectations. A secondary benefit is information that can be used to
improve the planning and performance of future projects.
Typical KPIs are schedule and budget compliance, number of scope changes, number of
issues and defects, and stakeholder satisfaction.
There is broad agreement that schedule and budget compliance during the course of the
project are essential indicators. Projects must end and completion time is often closely linked
to the business objectives that drove the project’s initiation. Tracking to a budget in dollars
and/or resource time is a key indicator because it gives us a sense of whether we are
performing as we have expected to perform. In most cases, project sponsors and clients are
cost conscious. They want to know how much they will spend on the project and they want to
know it before the project is over.
Assessing the degree to which the project is tracking to its schedule and budget provides an
indication of whether the team is going to meet stakeholder expectations (a critical objective
in any project). It highlights the need to look into the causes of variance. Causes may be poor
estimating, loss of resources, price changes, underperforming resources, too many changes,
errors, omissions and defects, etc. Once the causes are understood a course of action can be
decided, either accepting things as they are or making changes to remediate any problem that
has been identified.
As in earned value management we need to combine schedule and budget perspectives to get
a true sense of overall project health. Do not rely on these measures independent of one
another, a project can be under budget because it is behind schedule, because prices have
gone down, because performers have used clever means to get their work done less
expensively, or for other reasons. A stakeholder who is budget oriented can easily get the
wrong idea of project health by looking at stand alone budget data.
QualityDeliverables
To effectively measure performance it is necessary to plan so that tasks are defined in terms
of specific deliverables with clearly stated requirements. The availability of an accepted
deliverable is the only measure of the successful completion of a task. It is all too easy to
deliver something that doesn’t work or meet requirements.
Agile project approaches use Velocity as a KPI to measure the team’s rate of progress.
Velocity is the number of features (or use cases, components, deliverables, etc.) delivered
versus the number planned. This is clearly measuring against schedule but highlights the need
for linking tasks to concrete, useful deliverables. Whether or not you are using an Agile
approach, it is a best practice to ensure that task completion is defined as the delivery of a
specific and meaningful deliverable.
EffortandCost Tracking
Whether you use velocity or earned value you need to account for effort and the cost of other
resources to monitor budget compliance and to estimate to project completion based on
current performance.
Can you measure project performance without tracking effort and cost? Of course you can. It
is done all the time. However, without a sense of the effort/cost being expended, any
assessment of schedule compliance is overly subjective, it is a guess. Capturing and using
effort and cost data is often difficult, requiring appropriate tools and cultural change, but if
you want to manage your project effectively, do it.
ProjectPerformance– Other Indicators
Other indicators, aside from schedule and budget performance, monitor the number and types
of issues, changes, and/or defects and the degree to which they are quickly addressed.
Issues are questions, disputes or problems that arise during a project and that must be
addressed to satisfy stakeholders and ensure that the project is heading in the right direction.
Issues vary in priority, complexity and the amount of time and effort they require. Issues are
inevitable, plan for them and track the effort required to address them against your estimate.
Scope changes result from requests for change in requirements. Changes require analysis,
decision making and execution. Scope changes, particularly those that occur late in project
life, are disruptive. When planning the project it is best to estimate time, effort and cost to
create a fund for expected changes and then to monitor actuals against this fund.
Defects are discovered when testing is performed to validate deliverables. Defects require
effort to determine their cause and correct or accept them. Again, it is best to estimate defects
and their impact in duration and cost and to track against this estimate.
Each of these is a KPI. High instances of each indicate that there will be project schedule and
budget slippage. Issues, changes and defects should be tracked and aged to give management
a sense of what is happening outside of the schedule and budget.
One of the most important and underutilized project performance indicators is stakeholder
satisfaction. During the course of a project assess the degree to which clients, sponsors and
performers are satisfied with responsiveness to their issues, the sense that progress is being
made, the degree to which they are involved, the health of relationships and their general
feeling regarding the project’s performance.
Performance Reports inProject Management
By Fahad Usmani 14 Comments
I wrote this blog post on Performance Reports a few years back based on the fourth edition of
the PMBOK Guide. Now the fifth edition of the PMBOK Guide has arrived, and there are
many changes in this new version of the guide.
The concept of Performance Reports is also not untouched by these changes. Therefore, to
keep this blog post relevant, I am updating and aligning it with the current version of the
PMBOK Guide.
If you go through the fourth edition of the PMBOK Guide, you will see that in this edition
Report Performance was a process itself, and Performance Reports were an output of this
process.
If you dig further, you will find that the Report Performance process was input to the
following processes:
 Manage ProjectTeam
 Distribute Information
 Monitorand Control ProjectWork
 Monitorand Control Risks
 Administrative Procurement
And now in the fifth edition of the PMBOK Guide, there is no more Report Performance
Process; Performance Reports are now an output of the Monitor & Control Project Work
process, and input to the following processes:
 PerformIntegratedChange Control
 Manage ProjectTeam
 Manage Communication
 Control Risks
 Control Procurement
I hope you now understand the changes in Performance Reports between both editions of the
PMBOK Guide.
Okay, now we come to the topic.
However, before you start reading further, I strongly suggest you go through my other blog
post on Work Performance Data and Work Performance Information, because Performance
Reports are based on these two elements.
Visit: Work Performance Data and Work Performance Information
PerformanceReports
From the previous discussion you have seen that Performance Reports are an output of the
Monitor & Control Project Work process, and input to various managing and controlling
processes.
As the name suggests, Performance Reports have various information pertaining to project
parameters, and updates on the project’s progress.
The fifth edition of the PMBOK Guide defines the Performance Reports as follows:
“The physical or electronic representation of work performance information compiled in
project documents, intended to generate decision or raise issues, actions or awareness.”
In other words, you can say that the Performance Reports organize and summarize the
information collected through work performance data and work performance information,
and represent it to the stakeholders in such a way that they can understand the direction the
project is going.
Performance Reports show the stakeholders the current status of the project and its
performance against the planned baselines.
If the stakeholders see that the project is not progressing as planned, they may decide to take
any corrective action, such as if any extra funds or resources are required, or any time
extension is needed to complete the project, etc.
Performance Reports can be given to stakeholders in a format desired by them and decided in
the communication management plan. They can be a detailed report or just a summary.
The content of the Performance Reports includes, but is not limited to:
 Percentage of the workcompletedduringthe reportingperiod
 Balance of the workto be completed
 Cost incurredduringthe reportingperiod
 Balance of fundsavailable
 Balance of time available
 Major risksthat have occurred,or passedwithoutoccurring
 Major remainingidentifiedrisks
 Resultsof variance analysis:e.g.schedulevariance andcostvariance
 Performance indexes:e.g.schedule performanceindex andcostperformance index
 Forecastedfundrequiredtocompletethe remainingwork(if the projectcostisoverrunor
underrun)
 Forecastedtime requiredtocomplete the remainingwork(if the projectisdelayedorahead
of schedule)
 Summaryof majorapprovedchange requestsduringthe reportingperiodetc.
The format of the Performance Reports may be any combination of these formats:
 BurndownChart
 S-Curve
 Bar Charts
 Histograms
 Tables
 Run Charts.
With this information on hand, stakeholders are very well aware of the project health, and can
make a decision based on these objective data and analysis.
So you see how important the Performance Reports are to project management. This is a very
important communication tool for the project manager to keep all stakeholders on board.
Before I conclude this blog post, let’s summarize all the concepts for the last time.
Summary
Work performance data is a collection of raw information of the project’s status. On the other
hand, work performance information is a comparison of various performances, like cost and
schedule, etc. Work performance data and work performance information are the basis for the
Performance Reports.
The Performance Reports are the reports given to project stakeholders to make them aware of
the current status and the forecasted progress of the project.
The Performance Reports show stakeholders how the project is going, the forecast analysis of
what they should expect if the project is allowed to keep going in the same way, or what
additional funds or resources may be required to complete the project if there is any deviation
from any baselines (e.g. cost and schedule baselines).
What is Monitoring?
Monitoring is the regular observation and recording of activities taking place in a project or
programme. It is a process of routinely gathering information on all aspects of the project.
To monitor is to check on how project activities are progressing. It is observation; ─
systematic and purposeful observation.
Monitoring also involves giving feedback about the progress of the project to the donors,
implementors and beneficiaries of the project.
Reporting enables the gathered information to be used in making decisions for improving
project performance.
Purpose of Monitoring:
Monitoring is very important in project planning and implementation.
It is like watching where you are going while riding a bicycle; you can adjust as you go along
and ensure that you are on the right track.
Monitoring provides information that will be useful in:
 Analysing the situation in the community and its project;
 Determining whether the inputs in the project are well utilized;
 Identifying problems facing the community or project and finding solutions;
 Ensuring all activities are carried out properly by the right people and in time;
 Using lessons from one project experience on to another; and
 Determining whether the way the project was planned is the most appropriate way of
solving the problem at hand.

Más contenido relacionado

La actualidad más candente

PMP - Project Initiation Template for Professionals
PMP - Project Initiation Template for ProfessionalsPMP - Project Initiation Template for Professionals
PMP - Project Initiation Template for ProfessionalsDaniel_Mccrea
 
Project management evaluation kpi
Project management evaluation kpiProject management evaluation kpi
Project management evaluation kpiOlivier Laquinte
 
Project Tracking and Scope Management
Project Tracking and Scope ManagementProject Tracking and Scope Management
Project Tracking and Scope ManagementTalha Siddiqui
 
16 Essential Project KPIs
16 Essential Project KPIs16 Essential Project KPIs
16 Essential Project KPIsScoro
 
New projectplandefinition1
New projectplandefinition1New projectplandefinition1
New projectplandefinition1Jonathan Joyce
 
Project Execution and PM Elements
Project Execution and PM ElementsProject Execution and PM Elements
Project Execution and PM Elementsharoldtaylor1113
 
Milestone Summary Report
Milestone Summary ReportMilestone Summary Report
Milestone Summary ReportAnnette Compton
 
Project Initiation Checklist
Project Initiation ChecklistProject Initiation Checklist
Project Initiation ChecklistAnand Subramaniam
 
How NYU Langone Med Center integrated Primavera Unifier and PeopleSoft to enh...
How NYU Langone Med Center integrated Primavera Unifier and PeopleSoft to enh...How NYU Langone Med Center integrated Primavera Unifier and PeopleSoft to enh...
How NYU Langone Med Center integrated Primavera Unifier and PeopleSoft to enh...p6academy
 
Project Management Toolkit - Presentation
Project Management Toolkit - PresentationProject Management Toolkit - Presentation
Project Management Toolkit - PresentationHassan Rizwan
 
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15Project Control | PROJ CTRL
 
Change management and dispute resolution
Change management and dispute resolutionChange management and dispute resolution
Change management and dispute resolutionAlex Iskandar
 
Project audit and closure
Project audit and closureProject audit and closure
Project audit and closureSanjay Vaij
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Effective Executive Status Reporting Webinar By KW3 Consulting
Effective Executive Status Reporting Webinar By KW3 ConsultingEffective Executive Status Reporting Webinar By KW3 Consulting
Effective Executive Status Reporting Webinar By KW3 ConsultingKirk Williams
 
Project management milestones-webinar
Project management milestones-webinarProject management milestones-webinar
Project management milestones-webinarmodijs
 

La actualidad más candente (19)

PMP - Project Initiation Template for Professionals
PMP - Project Initiation Template for ProfessionalsPMP - Project Initiation Template for Professionals
PMP - Project Initiation Template for Professionals
 
Project management evaluation kpi
Project management evaluation kpiProject management evaluation kpi
Project management evaluation kpi
 
Project Tracking and Scope Management
Project Tracking and Scope ManagementProject Tracking and Scope Management
Project Tracking and Scope Management
 
16 Essential Project KPIs
16 Essential Project KPIs16 Essential Project KPIs
16 Essential Project KPIs
 
New projectplandefinition1
New projectplandefinition1New projectplandefinition1
New projectplandefinition1
 
Project Execution and PM Elements
Project Execution and PM ElementsProject Execution and PM Elements
Project Execution and PM Elements
 
Milestone Summary Report
Milestone Summary ReportMilestone Summary Report
Milestone Summary Report
 
Project Initiation Checklist
Project Initiation ChecklistProject Initiation Checklist
Project Initiation Checklist
 
How NYU Langone Med Center integrated Primavera Unifier and PeopleSoft to enh...
How NYU Langone Med Center integrated Primavera Unifier and PeopleSoft to enh...How NYU Langone Med Center integrated Primavera Unifier and PeopleSoft to enh...
How NYU Langone Med Center integrated Primavera Unifier and PeopleSoft to enh...
 
Project Management Toolkit - Presentation
Project Management Toolkit - PresentationProject Management Toolkit - Presentation
Project Management Toolkit - Presentation
 
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
 
Change management and dispute resolution
Change management and dispute resolutionChange management and dispute resolution
Change management and dispute resolution
 
Prince 2 project managment Document,Project quality plan
Prince 2 project managment Document,Project quality planPrince 2 project managment Document,Project quality plan
Prince 2 project managment Document,Project quality plan
 
Project audit and closure
Project audit and closureProject audit and closure
Project audit and closure
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Project audit
Project auditProject audit
Project audit
 
Project Management KPIs
Project Management KPIsProject Management KPIs
Project Management KPIs
 
Effective Executive Status Reporting Webinar By KW3 Consulting
Effective Executive Status Reporting Webinar By KW3 ConsultingEffective Executive Status Reporting Webinar By KW3 Consulting
Effective Executive Status Reporting Webinar By KW3 Consulting
 
Project management milestones-webinar
Project management milestones-webinarProject management milestones-webinar
Project management milestones-webinar
 

Destacado

Destacado (18)

Proyecto
ProyectoProyecto
Proyecto
 
El desempleo
El desempleoEl desempleo
El desempleo
 
Plantilla para registrar y analizar información
Plantilla para registrar y analizar informaciónPlantilla para registrar y analizar información
Plantilla para registrar y analizar información
 
Practica 2 copia
Practica 2   copiaPractica 2   copia
Practica 2 copia
 
ESTADISTICA
ESTADISTICAESTADISTICA
ESTADISTICA
 
Conociendo mi chile
Conociendo mi chileConociendo mi chile
Conociendo mi chile
 
11 volumetria (2 oopcion)
11 volumetria (2 oopcion)11 volumetria (2 oopcion)
11 volumetria (2 oopcion)
 
Hawaii General Election 2014: Final Results
Hawaii General Election 2014: Final ResultsHawaii General Election 2014: Final Results
Hawaii General Election 2014: Final Results
 
Presentation' making castles out of junk materials'
Presentation' making castles out of junk materials'Presentation' making castles out of junk materials'
Presentation' making castles out of junk materials'
 
Enviar 24 marzo proyecto niños desaparecidos.doc segunda versión
Enviar 24 marzo proyecto niños desaparecidos.doc segunda versiónEnviar 24 marzo proyecto niños desaparecidos.doc segunda versión
Enviar 24 marzo proyecto niños desaparecidos.doc segunda versión
 
Odysseus and the cyclop
Odysseus and the cyclopOdysseus and the cyclop
Odysseus and the cyclop
 
Equipo 4 tema ftp
Equipo 4 tema ftpEquipo 4 tema ftp
Equipo 4 tema ftp
 
Trabajo del emilio
Trabajo del emilioTrabajo del emilio
Trabajo del emilio
 
Simbolos patrios del perú power
Simbolos patrios del perú powerSimbolos patrios del perú power
Simbolos patrios del perú power
 
Planificacion
PlanificacionPlanificacion
Planificacion
 
Ejercicio 7 de word
Ejercicio 7 de wordEjercicio 7 de word
Ejercicio 7 de word
 
Ejercicio3
Ejercicio3Ejercicio3
Ejercicio3
 
Diapositivas
Diapositivas Diapositivas
Diapositivas
 

Similar a Measuring in

Understand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases IntroductionUnderstand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases IntroductionDivya Malik
 
project-management.pdffjfjfwjfwoifjweoifjwefoi
project-management.pdffjfjfwjfwoifjweoifjwefoiproject-management.pdffjfjfwjfwoifjweoifjwefoi
project-management.pdffjfjfwjfwoifjweoifjwefoiEarlFrancisGalino
 
Session Five- DETERMINING PROJECT PROGRESS AND RESULTS .pptx
Session Five- DETERMINING PROJECT PROGRESS AND RESULTS .pptxSession Five- DETERMINING PROJECT PROGRESS AND RESULTS .pptx
Session Five- DETERMINING PROJECT PROGRESS AND RESULTS .pptxyuduf1
 
Maksym Vyshnivetskyi: PMO KPIs ( UA ).
Maksym  Vyshnivetskyi:  PMO KPIs ( UA ).Maksym  Vyshnivetskyi:  PMO KPIs ( UA ).
Maksym Vyshnivetskyi: PMO KPIs ( UA ).Lviv Startup Club
 
Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12Jason Uyder
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project managementselinasimpson1601
 
Tavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-FinalTavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-FinalSEKHAR KOMMURI
 
Navigating Project Success A Deep Dive into Planning, Tracking, and Mastering...
Navigating Project Success A Deep Dive into Planning, Tracking, and Mastering...Navigating Project Success A Deep Dive into Planning, Tracking, and Mastering...
Navigating Project Success A Deep Dive into Planning, Tracking, and Mastering...RealcoderzSeo
 
Unit2 Project phases.pptx
Unit2 Project phases.pptxUnit2 Project phases.pptx
Unit2 Project phases.pptxAtulBhagwat6
 
Project Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleProject Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleKate Pynn
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology OverviewDaniel Brody
 
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docxgilbertkpeters11344
 
Bsc how to fill initiatives templates-14 june10
Bsc how to fill initiatives templates-14 june10Bsc how to fill initiatives templates-14 june10
Bsc how to fill initiatives templates-14 june10Ajoy Jauhar
 
Optimizing Organizational Performance by Managing Project Benefits
Optimizing Organizational Performance by Managing Project BenefitsOptimizing Organizational Performance by Managing Project Benefits
Optimizing Organizational Performance by Managing Project BenefitsUMT
 
Identifying a project in trouble and re-planning
Identifying a project in trouble and re-planningIdentifying a project in trouble and re-planning
Identifying a project in trouble and re-planningmfarbstein
 
Welcome back executive summery of stakeholder
Welcome back executive summery of stakeholderWelcome back executive summery of stakeholder
Welcome back executive summery of stakeholderAbdullah Al Mamun
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure CycleGlen Alleman
 

Similar a Measuring in (20)

Assignment
Assignment Assignment
Assignment
 
Understand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases IntroductionUnderstand the Project Cycle Management & Its Phases Introduction
Understand the Project Cycle Management & Its Phases Introduction
 
project-management.pdffjfjfwjfwoifjweoifjwefoi
project-management.pdffjfjfwjfwoifjweoifjwefoiproject-management.pdffjfjfwjfwoifjweoifjwefoi
project-management.pdffjfjfwjfwoifjweoifjwefoi
 
Session Five- DETERMINING PROJECT PROGRESS AND RESULTS .pptx
Session Five- DETERMINING PROJECT PROGRESS AND RESULTS .pptxSession Five- DETERMINING PROJECT PROGRESS AND RESULTS .pptx
Session Five- DETERMINING PROJECT PROGRESS AND RESULTS .pptx
 
Maksym Vyshnivetskyi: PMO KPIs ( UA ).
Maksym  Vyshnivetskyi:  PMO KPIs ( UA ).Maksym  Vyshnivetskyi:  PMO KPIs ( UA ).
Maksym Vyshnivetskyi: PMO KPIs ( UA ).
 
Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
Tavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-FinalTavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-Final
 
Navigating Project Success A Deep Dive into Planning, Tracking, and Mastering...
Navigating Project Success A Deep Dive into Planning, Tracking, and Mastering...Navigating Project Success A Deep Dive into Planning, Tracking, and Mastering...
Navigating Project Success A Deep Dive into Planning, Tracking, and Mastering...
 
Unit2 Project phases.pptx
Unit2 Project phases.pptxUnit2 Project phases.pptx
Unit2 Project phases.pptx
 
Project Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleProject Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training Example
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview
 
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx
 
Bsc how to fill initiatives templates-14 june10
Bsc how to fill initiatives templates-14 june10Bsc how to fill initiatives templates-14 june10
Bsc how to fill initiatives templates-14 june10
 
Optimizing Organizational Performance by Managing Project Benefits
Optimizing Organizational Performance by Managing Project BenefitsOptimizing Organizational Performance by Managing Project Benefits
Optimizing Organizational Performance by Managing Project Benefits
 
Identifying a project in trouble and re-planning
Identifying a project in trouble and re-planningIdentifying a project in trouble and re-planning
Identifying a project in trouble and re-planning
 
Welcome back executive summery of stakeholder
Welcome back executive summery of stakeholderWelcome back executive summery of stakeholder
Welcome back executive summery of stakeholder
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure Cycle
 
Measurement & metrics
Measurement & metricsMeasurement & metrics
Measurement & metrics
 
Ngo’s project management
Ngo’s project managementNgo’s project management
Ngo’s project management
 

Más de Davinder Singh

Más de Davinder Singh (12)

What is project control
What is project controlWhat is project control
What is project control
 
The project management information system
The project management information systemThe project management information system
The project management information system
 
Soliciting proposal
Soliciting proposalSoliciting proposal
Soliciting proposal
 
Project meetings ddddd
Project meetings dddddProject meetings ddddd
Project meetings ddddd
 
Cost
CostCost
Cost
 
Measuring in
Measuring inMeasuring in
Measuring in
 
Cost
CostCost
Cost
 
What is project control
What is project controlWhat is project control
What is project control
 
The project management information system
The project management information systemThe project management information system
The project management information system
 
Soliciting proposal
Soliciting proposalSoliciting proposal
Soliciting proposal
 
Project meetings ddddd
Project meetings dddddProject meetings ddddd
Project meetings ddddd
 
Davinder Resume
Davinder ResumeDavinder Resume
Davinder Resume
 

Measuring in

  • 1. Measuring In-progress Project Performance Measuring performance is a critical factor in optimizing performance. Optimal performance is sustainably achieving multiple, often conflicting, objectives under changing conditions. Project performance, on the surface, seems easy to measure; just track time, cost and scope and it’s done. But when we look more deeply we find that it is not that simple. First, we find that there is confusion about what we actually want to measure. Is it the success of a single project, the success of project performance across many projects, or the success of project management and a project office? If our objective is to measure the success of a single project, are we looking at the project during its life or at the project after it has been completed? Once we determine what we really want to evaluate we can identify the key performance indicators (KPIs) that will tell us whether we have been or are being successful or not and to what degree. KPIs give managers the most important performance information to enable them to assess the performance of a project or process. Generally we look for from two to five or so indicators. One is not enough for any complex process and project performance is a complex process. Too many KPIs make it difficult to see the big picture clearly. Too few make it difficult to diagnose and correct the issues that get in the way of optimal performance. Projectand BusinessObjectives Keep in mind that KPIs are not objectives. They are readings that enable a manager to assess performance towards the achievement of objectives. On a personal level we use KPIs such as weight, blood pressure, and cholesterol level to assess general health. The objective is general health, the measures are indicators that can be used to determine if we are tracking towards the objective, or not. Project objectives are to deliver goods and services, within time, cost, quality and other constraints, satisfying stakeholder expectations. Project deliverables are used to deliver benefits to satisfy the needs of sponsors and clients. Note the difference between project and business objectives. Projects deliver goods and services that are generally used after the project has ended to achieve business objectives such as reducing costs and risks, increasing revenues, etc. Projects are initiated to achieve business objectives. Project objectives are a means to that end. When measuring project success, particularly when the project is on-going, it is necessary to focus on the project objectives and performance against schedule and budget estimates. In most cases, we cannot measure a project’s success in achieving business objectives until well after the project has ended. Further, there are factors that are outside of the control of the project that influence benefits realization. For example, in product development the performance of sales and marketing, market conditions, and other factors impact the degree to which expected benefits are achieved.
  • 2. ProjectPerformance– ScheduleandBudget Performance measurement during a project is to know how things are going so that we can have early warning of problems that might get in the way of achieving project objectives and so that we can manage expectations. A secondary benefit is information that can be used to improve the planning and performance of future projects. Typical KPIs are schedule and budget compliance, number of scope changes, number of issues and defects, and stakeholder satisfaction. There is broad agreement that schedule and budget compliance during the course of the project are essential indicators. Projects must end and completion time is often closely linked to the business objectives that drove the project’s initiation. Tracking to a budget in dollars and/or resource time is a key indicator because it gives us a sense of whether we are performing as we have expected to perform. In most cases, project sponsors and clients are cost conscious. They want to know how much they will spend on the project and they want to know it before the project is over. Assessing the degree to which the project is tracking to its schedule and budget provides an indication of whether the team is going to meet stakeholder expectations (a critical objective in any project). It highlights the need to look into the causes of variance. Causes may be poor estimating, loss of resources, price changes, underperforming resources, too many changes, errors, omissions and defects, etc. Once the causes are understood a course of action can be decided, either accepting things as they are or making changes to remediate any problem that has been identified. As in earned value management we need to combine schedule and budget perspectives to get a true sense of overall project health. Do not rely on these measures independent of one another, a project can be under budget because it is behind schedule, because prices have gone down, because performers have used clever means to get their work done less expensively, or for other reasons. A stakeholder who is budget oriented can easily get the wrong idea of project health by looking at stand alone budget data. QualityDeliverables To effectively measure performance it is necessary to plan so that tasks are defined in terms of specific deliverables with clearly stated requirements. The availability of an accepted deliverable is the only measure of the successful completion of a task. It is all too easy to deliver something that doesn’t work or meet requirements. Agile project approaches use Velocity as a KPI to measure the team’s rate of progress. Velocity is the number of features (or use cases, components, deliverables, etc.) delivered versus the number planned. This is clearly measuring against schedule but highlights the need for linking tasks to concrete, useful deliverables. Whether or not you are using an Agile approach, it is a best practice to ensure that task completion is defined as the delivery of a specific and meaningful deliverable.
  • 3. EffortandCost Tracking Whether you use velocity or earned value you need to account for effort and the cost of other resources to monitor budget compliance and to estimate to project completion based on current performance. Can you measure project performance without tracking effort and cost? Of course you can. It is done all the time. However, without a sense of the effort/cost being expended, any assessment of schedule compliance is overly subjective, it is a guess. Capturing and using effort and cost data is often difficult, requiring appropriate tools and cultural change, but if you want to manage your project effectively, do it. ProjectPerformance– Other Indicators Other indicators, aside from schedule and budget performance, monitor the number and types of issues, changes, and/or defects and the degree to which they are quickly addressed. Issues are questions, disputes or problems that arise during a project and that must be addressed to satisfy stakeholders and ensure that the project is heading in the right direction. Issues vary in priority, complexity and the amount of time and effort they require. Issues are inevitable, plan for them and track the effort required to address them against your estimate. Scope changes result from requests for change in requirements. Changes require analysis, decision making and execution. Scope changes, particularly those that occur late in project life, are disruptive. When planning the project it is best to estimate time, effort and cost to create a fund for expected changes and then to monitor actuals against this fund. Defects are discovered when testing is performed to validate deliverables. Defects require effort to determine their cause and correct or accept them. Again, it is best to estimate defects and their impact in duration and cost and to track against this estimate. Each of these is a KPI. High instances of each indicate that there will be project schedule and budget slippage. Issues, changes and defects should be tracked and aged to give management a sense of what is happening outside of the schedule and budget. One of the most important and underutilized project performance indicators is stakeholder satisfaction. During the course of a project assess the degree to which clients, sponsors and performers are satisfied with responsiveness to their issues, the sense that progress is being made, the degree to which they are involved, the health of relationships and their general feeling regarding the project’s performance. Performance Reports inProject Management By Fahad Usmani 14 Comments
  • 4. I wrote this blog post on Performance Reports a few years back based on the fourth edition of the PMBOK Guide. Now the fifth edition of the PMBOK Guide has arrived, and there are many changes in this new version of the guide. The concept of Performance Reports is also not untouched by these changes. Therefore, to keep this blog post relevant, I am updating and aligning it with the current version of the PMBOK Guide. If you go through the fourth edition of the PMBOK Guide, you will see that in this edition Report Performance was a process itself, and Performance Reports were an output of this process. If you dig further, you will find that the Report Performance process was input to the following processes:  Manage ProjectTeam  Distribute Information  Monitorand Control ProjectWork  Monitorand Control Risks  Administrative Procurement And now in the fifth edition of the PMBOK Guide, there is no more Report Performance Process; Performance Reports are now an output of the Monitor & Control Project Work process, and input to the following processes:  PerformIntegratedChange Control  Manage ProjectTeam  Manage Communication  Control Risks  Control Procurement I hope you now understand the changes in Performance Reports between both editions of the PMBOK Guide. Okay, now we come to the topic.
  • 5. However, before you start reading further, I strongly suggest you go through my other blog post on Work Performance Data and Work Performance Information, because Performance Reports are based on these two elements. Visit: Work Performance Data and Work Performance Information PerformanceReports From the previous discussion you have seen that Performance Reports are an output of the Monitor & Control Project Work process, and input to various managing and controlling processes. As the name suggests, Performance Reports have various information pertaining to project parameters, and updates on the project’s progress. The fifth edition of the PMBOK Guide defines the Performance Reports as follows: “The physical or electronic representation of work performance information compiled in project documents, intended to generate decision or raise issues, actions or awareness.” In other words, you can say that the Performance Reports organize and summarize the information collected through work performance data and work performance information, and represent it to the stakeholders in such a way that they can understand the direction the project is going. Performance Reports show the stakeholders the current status of the project and its performance against the planned baselines. If the stakeholders see that the project is not progressing as planned, they may decide to take any corrective action, such as if any extra funds or resources are required, or any time extension is needed to complete the project, etc. Performance Reports can be given to stakeholders in a format desired by them and decided in the communication management plan. They can be a detailed report or just a summary. The content of the Performance Reports includes, but is not limited to:  Percentage of the workcompletedduringthe reportingperiod  Balance of the workto be completed  Cost incurredduringthe reportingperiod  Balance of fundsavailable  Balance of time available  Major risksthat have occurred,or passedwithoutoccurring  Major remainingidentifiedrisks  Resultsof variance analysis:e.g.schedulevariance andcostvariance  Performance indexes:e.g.schedule performanceindex andcostperformance index  Forecastedfundrequiredtocompletethe remainingwork(if the projectcostisoverrunor underrun)  Forecastedtime requiredtocomplete the remainingwork(if the projectisdelayedorahead of schedule)
  • 6.  Summaryof majorapprovedchange requestsduringthe reportingperiodetc. The format of the Performance Reports may be any combination of these formats:  BurndownChart  S-Curve  Bar Charts  Histograms  Tables  Run Charts. With this information on hand, stakeholders are very well aware of the project health, and can make a decision based on these objective data and analysis. So you see how important the Performance Reports are to project management. This is a very important communication tool for the project manager to keep all stakeholders on board. Before I conclude this blog post, let’s summarize all the concepts for the last time. Summary Work performance data is a collection of raw information of the project’s status. On the other hand, work performance information is a comparison of various performances, like cost and schedule, etc. Work performance data and work performance information are the basis for the Performance Reports. The Performance Reports are the reports given to project stakeholders to make them aware of the current status and the forecasted progress of the project. The Performance Reports show stakeholders how the project is going, the forecast analysis of what they should expect if the project is allowed to keep going in the same way, or what additional funds or resources may be required to complete the project if there is any deviation from any baselines (e.g. cost and schedule baselines). What is Monitoring? Monitoring is the regular observation and recording of activities taking place in a project or programme. It is a process of routinely gathering information on all aspects of the project. To monitor is to check on how project activities are progressing. It is observation; ─ systematic and purposeful observation. Monitoring also involves giving feedback about the progress of the project to the donors, implementors and beneficiaries of the project. Reporting enables the gathered information to be used in making decisions for improving project performance. Purpose of Monitoring:
  • 7. Monitoring is very important in project planning and implementation. It is like watching where you are going while riding a bicycle; you can adjust as you go along and ensure that you are on the right track. Monitoring provides information that will be useful in:  Analysing the situation in the community and its project;  Determining whether the inputs in the project are well utilized;  Identifying problems facing the community or project and finding solutions;  Ensuring all activities are carried out properly by the right people and in time;  Using lessons from one project experience on to another; and  Determining whether the way the project was planned is the most appropriate way of solving the problem at hand.