SlideShare una empresa de Scribd logo
1 de 16
Distribution Network Reconfiguration for
Loss Reduction and Voltage Profile
Improvement using B-PSO
Presented
by
Gaddafi S. Shehu
Abdullahi B. Kunya, ABU Zaria-Nigeria
Adamu Y. Ilyasu, KUST Kano-Nigeria
Sunusi G. Mohammed, BUK Kano-Nigeria
1
• Introduction
• Problems formulation
• Test systems description
• Results and discussions
• Conclusion
2
• DN carry electrical power right from transmission system to consumers.
• DN contributes at least 40% of the total power loss occurring in the entire system.
• Most DNs are built meshed and operated radially.
Fig. 1 IEEE 16 bus test system section
3
S7 and S8 are tie switches
• DN is vulnerable to outages due to its radial nature, as fault on a single line can result in
blackout to many customers.
• However, network modification is a non-linear, multi-objective, highly constrained
problem.
• The complexity of the problem arises due to distribution network topology has to be
radial.
• Power flow constraints are nonlinear in nature.
• Previous studies of DN reconfiguration focus on planning, and cost of construction
minimization.
4
• Advantage of handling both discrete and continuous parameters.
• Initializing search space with swarm particles, xi randomly.
• The search space in this problem is the set of all the sectionalizing and tie
switches.
• At each iteration, the position of ith particle is updated by its previous position in
the velocity vector, vi according (1)
• The velocity vector is updated according to the following equation (2)
5
• The problem involves determining the optimal DNR, taking into account different
technical constraints.
• The objective is to minimize power loss and voltage deviation as formulated in
objective function.
first
and
6
For second OF
7
• The following constrains are consider
8
3. Radial network structure are maintained, no loop are
allow in the network
• Three IEEE standard test distribution networks are tested
Fig. 2 IEEE 16 bus test system
• The network has total loads of 28.125 MW and 13.53 MVAr on 12.65 kV
substation voltage
9
• The second test system used in the study is 33-bus distribution feeder with a total active
and reactive load demand of 3.72 MW and 2.30 MVAr respectively.
• It has 37 branches, 32 sectionalizing switches and 5 tie switches
Fig. 3 IEEE 33 bus test system
10
• A 69 buses, 73 branches and 5 tie switches, is used. The network has a total load demand of
3.80MW and 2.70MVAr.
Fig. 4 IEEE 69 bus test system
11
16-bus test system
• After reconfiguration
Fig. 6 16-bus test system voltage profile
Fig. 5 Optimized Configuration of 16 bus test system
16 Bus Test System Results
12.3364%
8.8903%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
0.965
0.97
0.975
0.98
0.985
0.99
0.995
1
Bus Number
Voltage(pu)
Before Reconfiguration
After Reconfiguration
12
33-bus test system
• After reconfiguration
Parameters Before
Reconfiguration
After
Reconfiguration
Tie switches 33, 34, 35, 36, 37 7, 11, 14, 28, 32
Power loss 208.4592 kW 141.6346 kW
Voltage dev. 1.6610 pu 1.0991 pu
Min. Voltage 0.9108 pu 0.9413 pu
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33
0.91
0.92
0.93
0.94
0.95
0.96
0.97
0.98
0.99
1
Voltage(p.u)
Bus Number
Before Reconfiguration
After Reconfiguration
Fig. 8 33-bus test system voltage profile.
Fig. 7 Optimized Configuration of 33 bus test system
33 Bus Test System Results
32.0564%
33.8290%
13
69-bus test system
• After reconfiguration
Paramete
rs
Before
Reconfiguration
After
Reconfiguration
Tie
switches
69, 70, 71, 72, 73 14, 58, 61, 69, 70
Power
loss
224.9804 kW 98.5952 kW
Voltage
dev.
0.2140 pu 0.1876 pu
Min.
Voltage
0.9092 pu 0.9495 pu
69 BUS TEST SYSTEM RESULTS
Fig. 9 Optimized Configuration of 69 bus test system
Power loss reduced by 56.1761 %
Voltage deviation improved 64.6758%.
14
69-bus test system
• Fig. 10, 69-bus test system voltage profile
1 6 11 16 21 26 31 36 41 46 51 56 61 66 69
0.9
0.91
0.92
0.93
0.94
0.95
0.96
0.97
0.98
0.99
1
Voltage(p.u)
Bus Number
Before Reconfiguration
After Reconfiguration
observed at bus 41- 46 due to
introduction of loads at bus 15
– 27 and bus 62 – 65 by
opening s14 and closing s71.
15
• The objective of the proposed technique is to minimize the active power loss and voltage
deviation.
• The decision variables are the open/close status of the sectionalizing and tie switches.
• IEEE multi-feeder 16-bus and single feeder 33-bus and 69-bus test distribution networks
are used for testing the proposed technique.
• With the optimized reconfiguration, the radial nature is maintained, no mesh network is
formed.
• While reconfiguring the networks, opening or closing some loads are transferring from
one feeder to another, hence overloading it.
• Distributed generation is needed at those overloaded feeders to support its load carrying
capacity.
• It is envisioned as future work to incorporate distributed generation to support the loaded
feeders.
• Same technique will be used to determine their optimal siting and sizing.
16

Más contenido relacionado

La actualidad más candente

Integration of Renewable Energy In Grid
Integration of Renewable Energy In GridIntegration of Renewable Energy In Grid
Integration of Renewable Energy In Grid
Tejaswi Shukla
 
Grid Integration of Renewables: Challenges and Solutions
Grid Integration of Renewables: Challenges and SolutionsGrid Integration of Renewables: Challenges and Solutions
Grid Integration of Renewables: Challenges and Solutions
Power System Operation
 

La actualidad más candente (20)

Generation shift factor and line outage factor
Generation shift factor and line outage factorGeneration shift factor and line outage factor
Generation shift factor and line outage factor
 
LOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMS
LOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMSLOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMS
LOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMS
 
TRANSIENT ANGLE STABILITY
TRANSIENT ANGLE STABILITYTRANSIENT ANGLE STABILITY
TRANSIENT ANGLE STABILITY
 
Power System Planning
Power System PlanningPower System Planning
Power System Planning
 
Voltage and Frequency Control of the Grid
Voltage and Frequency Control of the GridVoltage and Frequency Control of the Grid
Voltage and Frequency Control of the Grid
 
Power system voltage stability
Power system voltage stabilityPower system voltage stability
Power system voltage stability
 
Electrical Grid Substation
Electrical Grid SubstationElectrical Grid Substation
Electrical Grid Substation
 
MTDC SYSTEMS
MTDC SYSTEMSMTDC SYSTEMS
MTDC SYSTEMS
 
POWER QUALITY IMPROVEMENT AND FAULT RIDE THROUGH OF GRID CONNECTED WIND ENE...
POWER QUALITY IMPROVEMENT AND FAULT RIDE THROUGH OF   GRID CONNECTED WIND ENE...POWER QUALITY IMPROVEMENT AND FAULT RIDE THROUGH OF   GRID CONNECTED WIND ENE...
POWER QUALITY IMPROVEMENT AND FAULT RIDE THROUGH OF GRID CONNECTED WIND ENE...
 
Grid Connected PV Systems
Grid Connected PV SystemsGrid Connected PV Systems
Grid Connected PV Systems
 
Deregulation of electricity-background
Deregulation of electricity-backgroundDeregulation of electricity-background
Deregulation of electricity-background
 
Integration of Renewable Energy In Grid
Integration of Renewable Energy In GridIntegration of Renewable Energy In Grid
Integration of Renewable Energy In Grid
 
Comparision of svc and statcom
Comparision of svc and statcomComparision of svc and statcom
Comparision of svc and statcom
 
Introduction to power system analysis
Introduction to power system analysisIntroduction to power system analysis
Introduction to power system analysis
 
Load Frequency Control of Two Area System
Load Frequency Control of Two Area SystemLoad Frequency Control of Two Area System
Load Frequency Control of Two Area System
 
Power quality ppt
Power quality pptPower quality ppt
Power quality ppt
 
Grid Integration of Renewables: Challenges and Solutions
Grid Integration of Renewables: Challenges and SolutionsGrid Integration of Renewables: Challenges and Solutions
Grid Integration of Renewables: Challenges and Solutions
 
Ehv line design
Ehv line designEhv line design
Ehv line design
 
power flow and optimal power flow
power flow and optimal power flowpower flow and optimal power flow
power flow and optimal power flow
 
Power transformers rating
Power transformers ratingPower transformers rating
Power transformers rating
 

Destacado

Run time dynamic partial reconfiguration using microblaze soft core processor...
Run time dynamic partial reconfiguration using microblaze soft core processor...Run time dynamic partial reconfiguration using microblaze soft core processor...
Run time dynamic partial reconfiguration using microblaze soft core processor...
eSAT Journals
 

Destacado (11)

P1111143901
P1111143901P1111143901
P1111143901
 
slide FYP 2
slide FYP 2slide FYP 2
slide FYP 2
 
Run time dynamic partial reconfiguration using microblaze soft core processor...
Run time dynamic partial reconfiguration using microblaze soft core processor...Run time dynamic partial reconfiguration using microblaze soft core processor...
Run time dynamic partial reconfiguration using microblaze soft core processor...
 
Network configuration
Network configurationNetwork configuration
Network configuration
 
Wind power forecasting accuracy and uncertainty in Finland
Wind power forecasting accuracy and uncertainty in FinlandWind power forecasting accuracy and uncertainty in Finland
Wind power forecasting accuracy and uncertainty in Finland
 
VOLTAGE SAG AND SWELL ALLEVIATION IN DISTRIBUTION NETWORK USING CUSTOM POWER...
 VOLTAGE SAG AND SWELL ALLEVIATION IN DISTRIBUTION NETWORK USING CUSTOM POWER... VOLTAGE SAG AND SWELL ALLEVIATION IN DISTRIBUTION NETWORK USING CUSTOM POWER...
VOLTAGE SAG AND SWELL ALLEVIATION IN DISTRIBUTION NETWORK USING CUSTOM POWER...
 
OPTIMAL PLACEMENT OF DISTRIBUTED GENERATION
OPTIMAL PLACEMENT OF DISTRIBUTED GENERATION OPTIMAL PLACEMENT OF DISTRIBUTED GENERATION
OPTIMAL PLACEMENT OF DISTRIBUTED GENERATION
 
role of distributed generation
role of distributed generation role of distributed generation
role of distributed generation
 
P1151351311
P1151351311P1151351311
P1151351311
 
Capacitor Placement and Reconfiguration of Distribution System with hybrid Fu...
Capacitor Placement and Reconfiguration of Distribution System with hybrid Fu...Capacitor Placement and Reconfiguration of Distribution System with hybrid Fu...
Capacitor Placement and Reconfiguration of Distribution System with hybrid Fu...
 
Network ppt
Network pptNetwork ppt
Network ppt
 

Similar a Distribution network reconfiguration for loss reduction and voltage

4 paper conference
4 paper conference4 paper conference
4 paper conference
dungsp4
 
Rehabilitation of nablus electrical network by adding a new connection point
Rehabilitation of nablus electrical network by adding a new connection pointRehabilitation of nablus electrical network by adding a new connection point
Rehabilitation of nablus electrical network by adding a new connection point
slmnsvn
 
ppt on the Super conducting power cable in dc electric railway systems
ppt on the Super conducting power cable in dc electric railway systemsppt on the Super conducting power cable in dc electric railway systems
ppt on the Super conducting power cable in dc electric railway systems
Yuvraj Singh
 
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdfDesign_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Engnr Kami Zeb
 

Similar a Distribution network reconfiguration for loss reduction and voltage (20)

Extra high voltage long ac transmission lines
Extra high voltage long ac transmission linesExtra high voltage long ac transmission lines
Extra high voltage long ac transmission lines
 
4 paper conference
4 paper conference4 paper conference
4 paper conference
 
Simultaneous network reconfiguration and capacitor allocations using a novel ...
Simultaneous network reconfiguration and capacitor allocations using a novel ...Simultaneous network reconfiguration and capacitor allocations using a novel ...
Simultaneous network reconfiguration and capacitor allocations using a novel ...
 
Rehabilitation of nablus electrical network by adding a new connection point
Rehabilitation of nablus electrical network by adding a new connection pointRehabilitation of nablus electrical network by adding a new connection point
Rehabilitation of nablus electrical network by adding a new connection point
 
BEF43303 - 201620171 W1 Power System Analysis and Protection.pdf
BEF43303 - 201620171 W1 Power System Analysis and Protection.pdfBEF43303 - 201620171 W1 Power System Analysis and Protection.pdf
BEF43303 - 201620171 W1 Power System Analysis and Protection.pdf
 
Super conducting power cable in dc electric railway systems
Super conducting power cable in dc electric railway systemsSuper conducting power cable in dc electric railway systems
Super conducting power cable in dc electric railway systems
 
Ssfcl
SsfclSsfcl
Ssfcl
 
Seminar
SeminarSeminar
Seminar
 
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
 
A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...
A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...
A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...
 
Design of Highly Reliable and Efficient Next Generation Power Converters(Tran...
Design of Highly Reliable and Efficient Next Generation Power Converters(Tran...Design of Highly Reliable and Efficient Next Generation Power Converters(Tran...
Design of Highly Reliable and Efficient Next Generation Power Converters(Tran...
 
Stabilized Supply in Voltage 14.4 V and 300 A Current for Automotive Applicat...
Stabilized Supply in Voltage 14.4 V and 300 A Current for Automotive Applicat...Stabilized Supply in Voltage 14.4 V and 300 A Current for Automotive Applicat...
Stabilized Supply in Voltage 14.4 V and 300 A Current for Automotive Applicat...
 
ppt on the Super conducting power cable in dc electric railway systems
ppt on the Super conducting power cable in dc electric railway systemsppt on the Super conducting power cable in dc electric railway systems
ppt on the Super conducting power cable in dc electric railway systems
 
High Proficiency Grid ConnectedPhotovoltaic Power Generation System
High Proficiency Grid ConnectedPhotovoltaic Power Generation SystemHigh Proficiency Grid ConnectedPhotovoltaic Power Generation System
High Proficiency Grid ConnectedPhotovoltaic Power Generation System
 
Optimal Capacitor Placement for Improving Electrical Performance in distribut...
Optimal Capacitor Placement for Improving Electrical Performance in distribut...Optimal Capacitor Placement for Improving Electrical Performance in distribut...
Optimal Capacitor Placement for Improving Electrical Performance in distribut...
 
POWER SYSTEM ANALYSIS_254ppt.pdf
POWER SYSTEM ANALYSIS_254ppt.pdfPOWER SYSTEM ANALYSIS_254ppt.pdf
POWER SYSTEM ANALYSIS_254ppt.pdf
 
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdfDesign_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
Design_and_Investigation_of_FRT_Schemes_for_Three-Phase_Grid-Tied_PV_System.pdf
 
PECO Co-op Presentation-Final
PECO Co-op Presentation-FinalPECO Co-op Presentation-Final
PECO Co-op Presentation-Final
 
Fundamentals of electrical distribution
Fundamentals of electrical distributionFundamentals of electrical distribution
Fundamentals of electrical distribution
 
174072012 ee2404-lm
174072012 ee2404-lm174072012 ee2404-lm
174072012 ee2404-lm
 

Último

Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
chumtiyababu
 

Último (20)

Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 

Distribution network reconfiguration for loss reduction and voltage

  • 1. Distribution Network Reconfiguration for Loss Reduction and Voltage Profile Improvement using B-PSO Presented by Gaddafi S. Shehu Abdullahi B. Kunya, ABU Zaria-Nigeria Adamu Y. Ilyasu, KUST Kano-Nigeria Sunusi G. Mohammed, BUK Kano-Nigeria 1
  • 2. • Introduction • Problems formulation • Test systems description • Results and discussions • Conclusion 2
  • 3. • DN carry electrical power right from transmission system to consumers. • DN contributes at least 40% of the total power loss occurring in the entire system. • Most DNs are built meshed and operated radially. Fig. 1 IEEE 16 bus test system section 3 S7 and S8 are tie switches
  • 4. • DN is vulnerable to outages due to its radial nature, as fault on a single line can result in blackout to many customers. • However, network modification is a non-linear, multi-objective, highly constrained problem. • The complexity of the problem arises due to distribution network topology has to be radial. • Power flow constraints are nonlinear in nature. • Previous studies of DN reconfiguration focus on planning, and cost of construction minimization. 4
  • 5. • Advantage of handling both discrete and continuous parameters. • Initializing search space with swarm particles, xi randomly. • The search space in this problem is the set of all the sectionalizing and tie switches. • At each iteration, the position of ith particle is updated by its previous position in the velocity vector, vi according (1) • The velocity vector is updated according to the following equation (2) 5
  • 6. • The problem involves determining the optimal DNR, taking into account different technical constraints. • The objective is to minimize power loss and voltage deviation as formulated in objective function. first and 6
  • 8. • The following constrains are consider 8 3. Radial network structure are maintained, no loop are allow in the network
  • 9. • Three IEEE standard test distribution networks are tested Fig. 2 IEEE 16 bus test system • The network has total loads of 28.125 MW and 13.53 MVAr on 12.65 kV substation voltage 9
  • 10. • The second test system used in the study is 33-bus distribution feeder with a total active and reactive load demand of 3.72 MW and 2.30 MVAr respectively. • It has 37 branches, 32 sectionalizing switches and 5 tie switches Fig. 3 IEEE 33 bus test system 10
  • 11. • A 69 buses, 73 branches and 5 tie switches, is used. The network has a total load demand of 3.80MW and 2.70MVAr. Fig. 4 IEEE 69 bus test system 11
  • 12. 16-bus test system • After reconfiguration Fig. 6 16-bus test system voltage profile Fig. 5 Optimized Configuration of 16 bus test system 16 Bus Test System Results 12.3364% 8.8903% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 0.965 0.97 0.975 0.98 0.985 0.99 0.995 1 Bus Number Voltage(pu) Before Reconfiguration After Reconfiguration 12
  • 13. 33-bus test system • After reconfiguration Parameters Before Reconfiguration After Reconfiguration Tie switches 33, 34, 35, 36, 37 7, 11, 14, 28, 32 Power loss 208.4592 kW 141.6346 kW Voltage dev. 1.6610 pu 1.0991 pu Min. Voltage 0.9108 pu 0.9413 pu 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 0.91 0.92 0.93 0.94 0.95 0.96 0.97 0.98 0.99 1 Voltage(p.u) Bus Number Before Reconfiguration After Reconfiguration Fig. 8 33-bus test system voltage profile. Fig. 7 Optimized Configuration of 33 bus test system 33 Bus Test System Results 32.0564% 33.8290% 13
  • 14. 69-bus test system • After reconfiguration Paramete rs Before Reconfiguration After Reconfiguration Tie switches 69, 70, 71, 72, 73 14, 58, 61, 69, 70 Power loss 224.9804 kW 98.5952 kW Voltage dev. 0.2140 pu 0.1876 pu Min. Voltage 0.9092 pu 0.9495 pu 69 BUS TEST SYSTEM RESULTS Fig. 9 Optimized Configuration of 69 bus test system Power loss reduced by 56.1761 % Voltage deviation improved 64.6758%. 14
  • 15. 69-bus test system • Fig. 10, 69-bus test system voltage profile 1 6 11 16 21 26 31 36 41 46 51 56 61 66 69 0.9 0.91 0.92 0.93 0.94 0.95 0.96 0.97 0.98 0.99 1 Voltage(p.u) Bus Number Before Reconfiguration After Reconfiguration observed at bus 41- 46 due to introduction of loads at bus 15 – 27 and bus 62 – 65 by opening s14 and closing s71. 15
  • 16. • The objective of the proposed technique is to minimize the active power loss and voltage deviation. • The decision variables are the open/close status of the sectionalizing and tie switches. • IEEE multi-feeder 16-bus and single feeder 33-bus and 69-bus test distribution networks are used for testing the proposed technique. • With the optimized reconfiguration, the radial nature is maintained, no mesh network is formed. • While reconfiguring the networks, opening or closing some loads are transferring from one feeder to another, hence overloading it. • Distributed generation is needed at those overloaded feeders to support its load carrying capacity. • It is envisioned as future work to incorporate distributed generation to support the loaded feeders. • Same technique will be used to determine their optimal siting and sizing. 16