SlideShare una empresa de Scribd logo
1 de 33
Descargar para leer sin conexión
A Gentle Introduction to Earned Value
               Management Systems

 “Good metrics let us see if we are doing the
     right things and doing them well."




                                            Niwot Ridge Consulting
                                            4347 Pebble Beach
                                            Niwot, Colorao
                                            www.niwotridge.com
What do Project Managers What to Know?


       Is the project on schedule?
       Is the project on budget?
       Simple project analysis tools can answer these
       questions using time and cost tracking

       Earned value asks and answers more important
       questions:
         How much of the budget “should have been” spent at this
         point in the project?
         How much “value” has the work on the project “earned” so
         far?

2/33
What is Earned Value Analysis?


       It is a way to measure the amount of work actually
       performed on a project.
       It is a way to forecast a project’s cost and completion
       date using historical and statistical projections.
       It is a way to tell how well a project is “performing”
       compared to its original plan.
       Given this information it is a way to forecast how well
       the project will perform in the future.




3/33
Some Introductory Definitions

       Budgeted Cost of Work Scheduled – “The Plan”
       This is the total budgeted cost. It answers the question “how much
       do we plan to spend?” A second question that is answered is
       “How much work should be been completed by this date?”
       Budgeted Cost of Work Performed – “Earned Value”
       This is the cost originally budgeted to accomplish the work that
       has been completed. It answers the question “how much work has
       been actually completed?”
       Actual Cost of Work Performed – “The Investment”
       The actual cost to accomplish all the work that was performed by
       a specific date. It answers the question “how much did we actually
       spend to deliver the Earned Value?”



4/33
Basic Concepts of Earned Value
                                            Management

       Three dimensions of Earned Value
          The Plan – Budgeted Cost of Work Scheduled (BCWS)
          The Performance – Budgeted Cost of Work Performed (BCWP)
          The costs of Performance – Actual Cost of Work Performed (ACWP)
       BCWS
          Authorized work – scheduled tasks
          Time frame for the work
          Sum of planned values – baseline plan
       BCWP – “How much of the planned work was accomplished?”
       ACWP – the money spent to convert BCWS into BCWP.
       Cost Variance = BCWP – ACWP (negative CV is “bad”)
       Schedule Variance = BCWP – BCWS (negative SV is “bad”)


5/33
Some More Useful Terms

       CPI – Cost Performance Index
          CPI = BCWP / ACWP
       SPI – Schedule Performance Index
          SPI = BCWP / BCWS
       BAC – Budget at Completion
       EAC – Estimate at Completion
       IEAC – Independent Estimate at Completion
          IEAC = BAC / CPI
       ISAC – Independent Schedule at Completion
          ISAC = Schedule / SPI
       VAC – Variance at Completion
          VAC = BAC – EAC



6/33
A Simple but Edible Example


It’s the holidays, it’s cookie baking time!




                                              Niwot Ridge Consulting
                                              4347 Pebble Beach
                                              Niwot, Colorao
                                              www.niwotridge.com
EVMS of our Holiday Cookie Baking Process


       Our “Plan”
         40 cookies per batch
         5 batches per hour (200 cookies per hour)
         Schedule: 5 hours to make 1,000 cookies
         Budgeted cost per cookie – $0.05
         Total Budget = $50.00
       Analysis after one (1) hour of baking we’ve made …
         150 edible cookies – some were burnt, some hit the floor, the
         kids ate some, and fed some to the dog.
         Actual cost of ingredients after one hour (ACWP) = $9.00



8/33
After One Hour of Making Cookies


       Simple EVMS
         BCWS = $10.00
         BCWP = 150 cookies X $0.05/Cookie = $7.50
         ACWP = $9.00
       Cost and Schedule Variance
         SV = BCWP – BCWS = –$2.50 (we’re behind schedule)
         CV = BCWP – ACWP = $7.50 – $9.00 = –$1.50 (we’re over
         budget)
         SPI = BCWP / BCWS = 0.75 (we’re running at 75% of planned
         schedule)
         CPI = BCWP / ACWP = 0.833 (we’re running about 17% over
         budget)
9/33
Forecasting the Cookie Schedule and Budget


        IEAC = BAC / CPI = $50.00 / 0.833 = $60.00
        VAC = BAC – IEAC = $50.00 – $60.00 = –$10.00 ($10
        over)
        ISAC = 5 hours / SPI = 5 / 0.75 = 6.67 hours

        It’ll take 6 2/3 hours and $60.00 to make 1,000 edible
        cookies if the productivity of this cookie project doesn’t
        improve.




10/33
Can we Catch Up?


        TCPI = “To Complete” Performance Index
          TCPIEAC = (BAC – BCWPCUM) / (EAC – ACWPCUM)
          EAC = the amount we estimate we will spend in the end
        The numerator (Budget at Completion – BCWP) is how
        much work is left
        The dominator (EAC – ACWP) is how much we have
        left to spend

        If EAC = IEAC, then TCPI = CPI
          “If we don’t change our performance, IEAC is the correct
          estimate of the final cost.”
11/33
Our “Catch Up” Plan


        We want to finish this little baking exercise with a
        $50.00 budget.
           TCPI = (Budget – BCWP) / (EAC – ACWP)
           TCPI = (50.00 – 7.50) / (50.00 – 9.00) = 42.50 / 41.00 = 1.036


        We must perform at 103.6% of the originally planned
        performance in order to maintain the budget goal




12/33
A Simple EVMS Chart

        $50.00




        $40.00
                                         BCWS                       SV
                                                                    in $   CV
        $30.00



        $20.00   SV in hours

                                ACWP
        $10.00

                                BCWP

                       Hour 1   Hour 2   Hour 3   Hour 4   Hour 5




13/33
Putting This Simple Concept into
                             Practice

   EVMS can be deployed in many ways. A
straight forward way is to “micro–schedule” the
                 work activities.




                                             Niwot Ridge Consulting
                                             4347 Pebble Beach
                                             Niwot, Colorao
                                             www.niwotridge.com
Micro–Schedule


        Micro–scheduling does NOT mean micro–managing.
        It means planning at a sufficient level of detail to
        identify useful tasks that can be measured in days (3
        to 5) or at most a week.
        Micro–schedule consists of:
          Objective completion criteria – so we know when we are
          done.
          “Budgets” and “Values” – usually representing person days
          and some “measurable” value to the customer in terms of
          dollars.
          Planned Completion Dates – so we know when to expect
          these tasks to be done.
15/33
Some Fundamental Concepts of EVMS


        Never relate what was planned to be spent (BCWS) to
        the actual amount spent (ACWP).
          This tells us nothing of value
          It can even warp our thinking into attempting to under–spend
          our allowed amount to report favorable numbers.
        Cost Performance (CV) must focus on what has been
        accomplished (BCWP) versus what was invested to
        accomplish that work (ACWP)




16/33
A Framework for Deploying EVMS




Let’s do it the “standard” way with a twist of
       “agility” and “common sense.”†
  † Common    sense has the very curious property of being more correct retrospectively
  than prospectively, it seems to me that one of the principal criteria to be applied to
  successful projects is that its results are almost always obvious retrospectively;
  unfortunately, they seldom are successful prospectively. Common sense provides a
  kind of ultimate validation after the work after the project has completed its work; it
  seldom anticipates what the work is going to discover. Russel Lincoln Ackoff, The Art
  of Problem Solving, 1978
                                                                                            Niwot Ridge Consulting
                                                                                            4347 Pebble Beach
                                                                                            Niwot, Colorao
                                                                                            www.niwotridge.com
ANSI/EIA–748A–2002 and Success Criteria
                      of Earned Value Management

        The EIA 748A–2002 specification calls out 35
        performance criteria required for compliance.
        These criteria are too complex for our “agile”
        environment.
        There are 10 key criteria that can be deployed here.




18/33
10 Criteria for Successful EVMS

        Define authorized work elements
        Identify project organizational structure
        Provide integrated planning, scheduling, budgeting, work
        authorization, and cost accumulation processes
        Schedule the authorized work in a sequential manner that
        identifies the the significant task dependencies
        Identify physical products and organizations
        Establish and maintain time–phased budget baseline
        Record direct costs consistently in a formal manner
        Periodically generate project metrics
        Develop revised cost estimates–at–completion based on
        performance to date.
        Incorporate authorized changes in a timely manner.

19/33
Define Authorized Work Elements


        Create a Work Breakdown Structure (WBS) for all
        activities at the micro–schedule level
        The scope of the entire project must be defined in
        order to measure performance.
           This is a problem for agile methods, since scope evolves as
           the project evolves
           Schedule major iterations on 2 to 3 week boundaries
           Generate “macro” estimates of future work and “micro”
           estimates of the current iteration's work
        Defined project objectives, deliverables, and key
        milestones are based primarily on experience.

20/33
Identify Project Organizational Structure


        Identify the structure of the functional organizations
        performing the work
        Define all organizational elements responsible for
        delivering value
        Identify who is doing what and what value they are
        delivering
        Assign all tasks to specific named resources
        Identify the major milestones and those responsible for
        meeting the commitments represented by these
        milestone

21/33
Provide Integrated Planning, Scheduling, Budgeting, Work
                 Authorization, and Cost Accumulation Processes


           Provide integration of the firms:
              Planning,
              Scheduling,
              Budgeting,
              Work Authorization
              Cost accumulation
           Project management process should be integrated
           with the WBS and the functional organization.




22/33
Schedule the Authorized Work in a Sequential Manner
         That Identifies the the Significant Task Dependencies


        Describe the work sequence
        Identify significant dependencies required to meet the
        requirements
        Identify which tasks are impending the process of
        other tasks
        Create a “master schedule” for larger projects to
        connect the subordinate projects




23/33
Identify Physical Products and Organizations


        All project must be able to identify and measure
        physical performance
        Define metrics which convert to “planned values” into
        “earned values”
        Project must specify:
          Physical Products,
          Deliverables,
          Outputs,
          Metrics,
          Milestones
          Technical performance indicators

24/33
Establish & Maintain Time–Phased Budget Baseline


           Establish initial budgets on internal management
           estimates and external negotiated targets
           Budget for long–term efforts must be held at higher
           levels of the organization
           Time–phase budget is required to measure
           performance
              Staff
              ODCs




25/33
Record Direct Cost Consistency in a Formal System


        “Applied Direct Costs” is the preferred method of
        accounting for the accrual of “value”
        Isolate Level of Effort costs in a separate WBS
        element




26/33
Periodically Generate Project Metrics


        The amount of planned versus budgets earned for the
        work accomplished
        The amount of budget earned versus the actual direct
        costs for the same work
          This is the “cost variance”
        This differentiates EVMS from other “actual versus
        budget” cost analysis
          Weekly measures are now the “norm”
          Comparisons need to be detailed enough to provide
          intervention opportunities


27/33
Develop Revised Cost Estimates–at–Completion
                 (EAC) Based on Performance to Date

         Compare this information with the performance
         measure baseline to identify variances at completion




28/33
Incorporate Authorized Changes in a Timely
                                              Manner

        All changes must be addressed as they effect budget
        and schedule
        Base changes on the estimated amount and
        assignment to functional organizations needs to be
        recorded as well
        All approved changes must be incorporated into the
        project baseline




29/33
Ten Benefits of EVMS

        1. It is a single management control system to provide reliable and
            consistent data on project performance.
        2. It integrates work, schedule, and cost using a work breakdown structure.
        3. The associated database of completed projects is useful for comparative
            analysis.
        4. The cumulative cost performance index (CPI) provides an early warning
            signal.
        5. The schedule performance index provides an early warning signal.
        6. The CPI is a predictor for the final cost of the project.
        7. It uses an index–based method to forecast the final cost of the project.
        8. The “to-complete” performance index allows evaluation of the forecasted
            final cost.
        9. The periodic (e.g., weekly or monthly) CPI is a benchmark.
        10. The management by exception principle can reduce information
            overload.

30/33
What’s Next


Now that we have some tools that can be used
 to “manage” our efforts, what can we do with
them in order for them – and us – to “earn our
                    value?”




                                            Niwot Ridge Consulting
                                            4347 Pebble Beach
                                            Niwot, Colorao
                                            www.niwotridge.com
Deployment Plan


        Identify critical projects in both applications and infrastructure
        Baseline these projects
        Track the actual costs using time recording, Work Authorization
        and a project management system
        Report CV, SV, BCWP (Value) for the projects on weekly basis.
        Use this information to “manage” our efforts in a predictive
        manner.
        In the past we were “driving in the rearview mirror”
           It can be done, but it’s real sporty
        Let’s drive by looking out the front wind shield instead.
           The scenery is better, and we end up with less road kill.



32/33
Some More Details We’ll Need Along the Way

        Planning, budgeting, and   Analysis and management
        scheduling                    Cost variance
           Scheduling                 Schedule variance
           Cost account baseline
                                      Variance analysis
           Budgets
                                      Reporting
           Management reserve
           Undistributed budget       Estimates at completion
           Overhead budget            Indirect cost analysis
           Project target cost        Management action
        Accounting                 Revisions and Data
           Direct costs            Maintenance
           Indirect costs             Authorized changes
           Material costs             Unauthorized changes
           Summarization              Budget reconciliation

33/33

Más contenido relacionado

La actualidad más candente

DAP AN CHI TIET DE THI KE TOAN - GIAO DICH VIEN VIETINBANK
DAP AN CHI TIET DE THI KE TOAN - GIAO DICH VIEN VIETINBANKDAP AN CHI TIET DE THI KE TOAN - GIAO DICH VIEN VIETINBANK
DAP AN CHI TIET DE THI KE TOAN - GIAO DICH VIEN VIETINBANKdinhnguyenvn
 
Bài giải bài tập kiểm toán bctc
Bài giải bài tập kiểm toán bctcBài giải bài tập kiểm toán bctc
Bài giải bài tập kiểm toán bctclovesick0908
 
Zappos Financials
Zappos FinancialsZappos Financials
Zappos FinancialsJohn Mecke
 
Làm game với Unity Engine
Làm game với Unity EngineLàm game với Unity Engine
Làm game với Unity EngineColeman Ferry
 
Báo cáo tốt nghiệp kế toán tiền lương
Báo cáo tốt nghiệp kế toán tiền lươngBáo cáo tốt nghiệp kế toán tiền lương
Báo cáo tốt nghiệp kế toán tiền lươngHọc kế toán thực tế
 
Demonstração de resultados - Portuguese Architect
Demonstração de resultados - Portuguese ArchitectDemonstração de resultados - Portuguese Architect
Demonstração de resultados - Portuguese Architectmiguelpmelo
 
Bim Presentation
Bim PresentationBim Presentation
Bim Presentationrsalbin
 
Slide luận văn kiểm toán atax
Slide luận văn kiểm toán ataxSlide luận văn kiểm toán atax
Slide luận văn kiểm toán ataxNguyễn Công Huy
 
Strategic management vietcombank-ppt
Strategic management vietcombank-pptStrategic management vietcombank-ppt
Strategic management vietcombank-pptcarot_lk
 
Các dạng bài tập và lời giải kế toán thuế
Các dạng bài tập và lời giải kế toán thuếCác dạng bài tập và lời giải kế toán thuế
Các dạng bài tập và lời giải kế toán thuếHọc kế toán thực tế
 
Tóm tắt bước 1 và 3 của quá trình kiểm toán
Tóm tắt bước 1 và 3 của  quá trình kiểm toánTóm tắt bước 1 và 3 của  quá trình kiểm toán
Tóm tắt bước 1 và 3 của quá trình kiểm toánPhahamy Phahamy
 
BuildingSmart COBie presentation March 2014
BuildingSmart COBie presentation March 2014BuildingSmart COBie presentation March 2014
BuildingSmart COBie presentation March 2014Graham H Stewart
 
Doko.vn 153787-huong-dan-giai-bai-tap-quan-tri-tai-chin
Doko.vn 153787-huong-dan-giai-bai-tap-quan-tri-tai-chinDoko.vn 153787-huong-dan-giai-bai-tap-quan-tri-tai-chin
Doko.vn 153787-huong-dan-giai-bai-tap-quan-tri-tai-chinHằng Đào
 
Thuyet trình FDI môn quản trị doanh nghiệp
Thuyet trình FDI môn quản trị doanh nghiệpThuyet trình FDI môn quản trị doanh nghiệp
Thuyet trình FDI môn quản trị doanh nghiệpNông Dân Khoảng
 

La actualidad más candente (20)

DAP AN CHI TIET DE THI KE TOAN - GIAO DICH VIEN VIETINBANK
DAP AN CHI TIET DE THI KE TOAN - GIAO DICH VIEN VIETINBANKDAP AN CHI TIET DE THI KE TOAN - GIAO DICH VIEN VIETINBANK
DAP AN CHI TIET DE THI KE TOAN - GIAO DICH VIEN VIETINBANK
 
ktqt Chuong 9
ktqt Chuong 9ktqt Chuong 9
ktqt Chuong 9
 
Resposta questao 3
Resposta questao 3Resposta questao 3
Resposta questao 3
 
Bài giải bài tập kiểm toán bctc
Bài giải bài tập kiểm toán bctcBài giải bài tập kiểm toán bctc
Bài giải bài tập kiểm toán bctc
 
Đề tài: Kiểm toán tài sản cố định tại công ty kiểm toán quốc tế (IFC)
Đề tài: Kiểm toán tài sản cố định tại công ty kiểm toán quốc tế (IFC)Đề tài: Kiểm toán tài sản cố định tại công ty kiểm toán quốc tế (IFC)
Đề tài: Kiểm toán tài sản cố định tại công ty kiểm toán quốc tế (IFC)
 
Zappos Financials
Zappos FinancialsZappos Financials
Zappos Financials
 
Làm game với Unity Engine
Làm game với Unity EngineLàm game với Unity Engine
Làm game với Unity Engine
 
Báo cáo tốt nghiệp kế toán tiền lương
Báo cáo tốt nghiệp kế toán tiền lươngBáo cáo tốt nghiệp kế toán tiền lương
Báo cáo tốt nghiệp kế toán tiền lương
 
Demonstração de resultados - Portuguese Architect
Demonstração de resultados - Portuguese ArchitectDemonstração de resultados - Portuguese Architect
Demonstração de resultados - Portuguese Architect
 
Bim Presentation
Bim PresentationBim Presentation
Bim Presentation
 
Slide luận văn kiểm toán atax
Slide luận văn kiểm toán ataxSlide luận văn kiểm toán atax
Slide luận văn kiểm toán atax
 
Strategic management vietcombank-ppt
Strategic management vietcombank-pptStrategic management vietcombank-ppt
Strategic management vietcombank-ppt
 
Nguyên lý kế toán
Nguyên lý kế toánNguyên lý kế toán
Nguyên lý kế toán
 
Các dạng bài tập và lời giải kế toán thuế
Các dạng bài tập và lời giải kế toán thuếCác dạng bài tập và lời giải kế toán thuế
Các dạng bài tập và lời giải kế toán thuế
 
Tóm tắt bước 1 và 3 của quá trình kiểm toán
Tóm tắt bước 1 và 3 của  quá trình kiểm toánTóm tắt bước 1 và 3 của  quá trình kiểm toán
Tóm tắt bước 1 và 3 của quá trình kiểm toán
 
BuildingSmart COBie presentation March 2014
BuildingSmart COBie presentation March 2014BuildingSmart COBie presentation March 2014
BuildingSmart COBie presentation March 2014
 
Doko.vn 153787-huong-dan-giai-bai-tap-quan-tri-tai-chin
Doko.vn 153787-huong-dan-giai-bai-tap-quan-tri-tai-chinDoko.vn 153787-huong-dan-giai-bai-tap-quan-tri-tai-chin
Doko.vn 153787-huong-dan-giai-bai-tap-quan-tri-tai-chin
 
Đề tài: Công tác kế toán chi phi sản xuất tại công ty Mỹ Hảo, HAY
Đề tài: Công tác kế toán chi phi sản xuất tại công ty Mỹ Hảo, HAYĐề tài: Công tác kế toán chi phi sản xuất tại công ty Mỹ Hảo, HAY
Đề tài: Công tác kế toán chi phi sản xuất tại công ty Mỹ Hảo, HAY
 
BSC
BSCBSC
BSC
 
Thuyet trình FDI môn quản trị doanh nghiệp
Thuyet trình FDI môn quản trị doanh nghiệpThuyet trình FDI môn quản trị doanh nghiệp
Thuyet trình FDI môn quản trị doanh nghiệp
 

Destacado

Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management EssentialsGlen Alleman
 
Django10 cheat-sheet-grayscale
Django10 cheat-sheet-grayscaleDjango10 cheat-sheet-grayscale
Django10 cheat-sheet-grayscaleAmir Reza Zareian
 
Executive Overview of Managing Agile Programs with Earned Value
Executive Overview of Managing Agile Programs with Earned ValueExecutive Overview of Managing Agile Programs with Earned Value
Executive Overview of Managing Agile Programs with Earned ValueGlen Alleman
 
Jerald kerby
Jerald kerbyJerald kerby
Jerald kerbyNASAPMC
 
Learning Earned Value Management using Lego Bricks
Learning Earned Value Management using Lego BricksLearning Earned Value Management using Lego Bricks
Learning Earned Value Management using Lego BricksYoussef Mourra
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Vivek Prakash
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementTiago Franco
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...Tipsographic . com
 
Earned value management
Earned value managementEarned value management
Earned value managementAshif AR
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPJustAcademy
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)Glen Alleman
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
Project Controls Expo 09/10 Nov London 2011 - "Integrating Risk and Earned Va...
Project Controls Expo 09/10 Nov London 2011 - "Integrating Risk and Earned Va...Project Controls Expo 09/10 Nov London 2011 - "Integrating Risk and Earned Va...
Project Controls Expo 09/10 Nov London 2011 - "Integrating Risk and Earned Va...Project Controls Expo
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionPlanisware
 

Destacado (20)

Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management Essentials
 
Django10 cheat-sheet-grayscale
Django10 cheat-sheet-grayscaleDjango10 cheat-sheet-grayscale
Django10 cheat-sheet-grayscale
 
Executive Overview of Managing Agile Programs with Earned Value
Executive Overview of Managing Agile Programs with Earned ValueExecutive Overview of Managing Agile Programs with Earned Value
Executive Overview of Managing Agile Programs with Earned Value
 
Jerald kerby
Jerald kerbyJerald kerby
Jerald kerby
 
Learning Earned Value Management using Lego Bricks
Learning Earned Value Management using Lego BricksLearning Earned Value Management using Lego Bricks
Learning Earned Value Management using Lego Bricks
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
 
EVA/EVM
EVA/EVMEVA/EVM
EVA/EVM
 
Earned Value fundamentals
Earned Value fundamentalsEarned Value fundamentals
Earned Value fundamentals
 
Earned Value Management - Foundation
Earned Value Management - FoundationEarned Value Management - Foundation
Earned Value Management - Foundation
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMP
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Project Controls Expo 09/10 Nov London 2011 - "Integrating Risk and Earned Va...
Project Controls Expo 09/10 Nov London 2011 - "Integrating Risk and Earned Va...Project Controls Expo 09/10 Nov London 2011 - "Integrating Risk and Earned Va...
Project Controls Expo 09/10 Nov London 2011 - "Integrating Risk and Earned Va...
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 

Similar a A Gentle Introduction to Earned Value Management Systems

A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)Glen Alleman
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMansoor Shoaib
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy piecesGlen Alleman
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...Fahad Ali
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasAnand Bobade
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentationProPM Academy
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the NumbersPMI-Montréal
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptAsBali1
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementProPM Academy
 
EARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptEARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptBetshaTizazu1
 

Similar a A Gentle Introduction to Earned Value Management Systems (20)

A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy pieces
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
 
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.pptModule 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
EARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptEARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.ppt
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Earned Value
Earned ValueEarned Value
Earned Value
 
Earned value understanding
Earned value understandingEarned value understanding
Earned value understanding
 
Earned value
Earned valueEarned value
Earned value
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 

Más de Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 

Más de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 

Último

EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUK Journal
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessPixlogix Infotech
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 

Último (20)

EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your Business
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 

A Gentle Introduction to Earned Value Management Systems

  • 1. A Gentle Introduction to Earned Value Management Systems “Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com
  • 2. What do Project Managers What to Know? Is the project on schedule? Is the project on budget? Simple project analysis tools can answer these questions using time and cost tracking Earned value asks and answers more important questions: How much of the budget “should have been” spent at this point in the project? How much “value” has the work on the project “earned” so far? 2/33
  • 3. What is Earned Value Analysis? It is a way to measure the amount of work actually performed on a project. It is a way to forecast a project’s cost and completion date using historical and statistical projections. It is a way to tell how well a project is “performing” compared to its original plan. Given this information it is a way to forecast how well the project will perform in the future. 3/33
  • 4. Some Introductory Definitions Budgeted Cost of Work Scheduled – “The Plan” This is the total budgeted cost. It answers the question “how much do we plan to spend?” A second question that is answered is “How much work should be been completed by this date?” Budgeted Cost of Work Performed – “Earned Value” This is the cost originally budgeted to accomplish the work that has been completed. It answers the question “how much work has been actually completed?” Actual Cost of Work Performed – “The Investment” The actual cost to accomplish all the work that was performed by a specific date. It answers the question “how much did we actually spend to deliver the Earned Value?” 4/33
  • 5. Basic Concepts of Earned Value Management Three dimensions of Earned Value The Plan – Budgeted Cost of Work Scheduled (BCWS) The Performance – Budgeted Cost of Work Performed (BCWP) The costs of Performance – Actual Cost of Work Performed (ACWP) BCWS Authorized work – scheduled tasks Time frame for the work Sum of planned values – baseline plan BCWP – “How much of the planned work was accomplished?” ACWP – the money spent to convert BCWS into BCWP. Cost Variance = BCWP – ACWP (negative CV is “bad”) Schedule Variance = BCWP – BCWS (negative SV is “bad”) 5/33
  • 6. Some More Useful Terms CPI – Cost Performance Index CPI = BCWP / ACWP SPI – Schedule Performance Index SPI = BCWP / BCWS BAC – Budget at Completion EAC – Estimate at Completion IEAC – Independent Estimate at Completion IEAC = BAC / CPI ISAC – Independent Schedule at Completion ISAC = Schedule / SPI VAC – Variance at Completion VAC = BAC – EAC 6/33
  • 7. A Simple but Edible Example It’s the holidays, it’s cookie baking time! Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com
  • 8. EVMS of our Holiday Cookie Baking Process Our “Plan” 40 cookies per batch 5 batches per hour (200 cookies per hour) Schedule: 5 hours to make 1,000 cookies Budgeted cost per cookie – $0.05 Total Budget = $50.00 Analysis after one (1) hour of baking we’ve made … 150 edible cookies – some were burnt, some hit the floor, the kids ate some, and fed some to the dog. Actual cost of ingredients after one hour (ACWP) = $9.00 8/33
  • 9. After One Hour of Making Cookies Simple EVMS BCWS = $10.00 BCWP = 150 cookies X $0.05/Cookie = $7.50 ACWP = $9.00 Cost and Schedule Variance SV = BCWP – BCWS = –$2.50 (we’re behind schedule) CV = BCWP – ACWP = $7.50 – $9.00 = –$1.50 (we’re over budget) SPI = BCWP / BCWS = 0.75 (we’re running at 75% of planned schedule) CPI = BCWP / ACWP = 0.833 (we’re running about 17% over budget) 9/33
  • 10. Forecasting the Cookie Schedule and Budget IEAC = BAC / CPI = $50.00 / 0.833 = $60.00 VAC = BAC – IEAC = $50.00 – $60.00 = –$10.00 ($10 over) ISAC = 5 hours / SPI = 5 / 0.75 = 6.67 hours It’ll take 6 2/3 hours and $60.00 to make 1,000 edible cookies if the productivity of this cookie project doesn’t improve. 10/33
  • 11. Can we Catch Up? TCPI = “To Complete” Performance Index TCPIEAC = (BAC – BCWPCUM) / (EAC – ACWPCUM) EAC = the amount we estimate we will spend in the end The numerator (Budget at Completion – BCWP) is how much work is left The dominator (EAC – ACWP) is how much we have left to spend If EAC = IEAC, then TCPI = CPI “If we don’t change our performance, IEAC is the correct estimate of the final cost.” 11/33
  • 12. Our “Catch Up” Plan We want to finish this little baking exercise with a $50.00 budget. TCPI = (Budget – BCWP) / (EAC – ACWP) TCPI = (50.00 – 7.50) / (50.00 – 9.00) = 42.50 / 41.00 = 1.036 We must perform at 103.6% of the originally planned performance in order to maintain the budget goal 12/33
  • 13. A Simple EVMS Chart $50.00 $40.00 BCWS SV in $ CV $30.00 $20.00 SV in hours ACWP $10.00 BCWP Hour 1 Hour 2 Hour 3 Hour 4 Hour 5 13/33
  • 14. Putting This Simple Concept into Practice EVMS can be deployed in many ways. A straight forward way is to “micro–schedule” the work activities. Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com
  • 15. Micro–Schedule Micro–scheduling does NOT mean micro–managing. It means planning at a sufficient level of detail to identify useful tasks that can be measured in days (3 to 5) or at most a week. Micro–schedule consists of: Objective completion criteria – so we know when we are done. “Budgets” and “Values” – usually representing person days and some “measurable” value to the customer in terms of dollars. Planned Completion Dates – so we know when to expect these tasks to be done. 15/33
  • 16. Some Fundamental Concepts of EVMS Never relate what was planned to be spent (BCWS) to the actual amount spent (ACWP). This tells us nothing of value It can even warp our thinking into attempting to under–spend our allowed amount to report favorable numbers. Cost Performance (CV) must focus on what has been accomplished (BCWP) versus what was invested to accomplish that work (ACWP) 16/33
  • 17. A Framework for Deploying EVMS Let’s do it the “standard” way with a twist of “agility” and “common sense.”† † Common sense has the very curious property of being more correct retrospectively than prospectively, it seems to me that one of the principal criteria to be applied to successful projects is that its results are almost always obvious retrospectively; unfortunately, they seldom are successful prospectively. Common sense provides a kind of ultimate validation after the work after the project has completed its work; it seldom anticipates what the work is going to discover. Russel Lincoln Ackoff, The Art of Problem Solving, 1978 Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com
  • 18. ANSI/EIA–748A–2002 and Success Criteria of Earned Value Management The EIA 748A–2002 specification calls out 35 performance criteria required for compliance. These criteria are too complex for our “agile” environment. There are 10 key criteria that can be deployed here. 18/33
  • 19. 10 Criteria for Successful EVMS Define authorized work elements Identify project organizational structure Provide integrated planning, scheduling, budgeting, work authorization, and cost accumulation processes Schedule the authorized work in a sequential manner that identifies the the significant task dependencies Identify physical products and organizations Establish and maintain time–phased budget baseline Record direct costs consistently in a formal manner Periodically generate project metrics Develop revised cost estimates–at–completion based on performance to date. Incorporate authorized changes in a timely manner. 19/33
  • 20. Define Authorized Work Elements Create a Work Breakdown Structure (WBS) for all activities at the micro–schedule level The scope of the entire project must be defined in order to measure performance. This is a problem for agile methods, since scope evolves as the project evolves Schedule major iterations on 2 to 3 week boundaries Generate “macro” estimates of future work and “micro” estimates of the current iteration's work Defined project objectives, deliverables, and key milestones are based primarily on experience. 20/33
  • 21. Identify Project Organizational Structure Identify the structure of the functional organizations performing the work Define all organizational elements responsible for delivering value Identify who is doing what and what value they are delivering Assign all tasks to specific named resources Identify the major milestones and those responsible for meeting the commitments represented by these milestone 21/33
  • 22. Provide Integrated Planning, Scheduling, Budgeting, Work Authorization, and Cost Accumulation Processes Provide integration of the firms: Planning, Scheduling, Budgeting, Work Authorization Cost accumulation Project management process should be integrated with the WBS and the functional organization. 22/33
  • 23. Schedule the Authorized Work in a Sequential Manner That Identifies the the Significant Task Dependencies Describe the work sequence Identify significant dependencies required to meet the requirements Identify which tasks are impending the process of other tasks Create a “master schedule” for larger projects to connect the subordinate projects 23/33
  • 24. Identify Physical Products and Organizations All project must be able to identify and measure physical performance Define metrics which convert to “planned values” into “earned values” Project must specify: Physical Products, Deliverables, Outputs, Metrics, Milestones Technical performance indicators 24/33
  • 25. Establish & Maintain Time–Phased Budget Baseline Establish initial budgets on internal management estimates and external negotiated targets Budget for long–term efforts must be held at higher levels of the organization Time–phase budget is required to measure performance Staff ODCs 25/33
  • 26. Record Direct Cost Consistency in a Formal System “Applied Direct Costs” is the preferred method of accounting for the accrual of “value” Isolate Level of Effort costs in a separate WBS element 26/33
  • 27. Periodically Generate Project Metrics The amount of planned versus budgets earned for the work accomplished The amount of budget earned versus the actual direct costs for the same work This is the “cost variance” This differentiates EVMS from other “actual versus budget” cost analysis Weekly measures are now the “norm” Comparisons need to be detailed enough to provide intervention opportunities 27/33
  • 28. Develop Revised Cost Estimates–at–Completion (EAC) Based on Performance to Date Compare this information with the performance measure baseline to identify variances at completion 28/33
  • 29. Incorporate Authorized Changes in a Timely Manner All changes must be addressed as they effect budget and schedule Base changes on the estimated amount and assignment to functional organizations needs to be recorded as well All approved changes must be incorporated into the project baseline 29/33
  • 30. Ten Benefits of EVMS 1. It is a single management control system to provide reliable and consistent data on project performance. 2. It integrates work, schedule, and cost using a work breakdown structure. 3. The associated database of completed projects is useful for comparative analysis. 4. The cumulative cost performance index (CPI) provides an early warning signal. 5. The schedule performance index provides an early warning signal. 6. The CPI is a predictor for the final cost of the project. 7. It uses an index–based method to forecast the final cost of the project. 8. The “to-complete” performance index allows evaluation of the forecasted final cost. 9. The periodic (e.g., weekly or monthly) CPI is a benchmark. 10. The management by exception principle can reduce information overload. 30/33
  • 31. What’s Next Now that we have some tools that can be used to “manage” our efforts, what can we do with them in order for them – and us – to “earn our value?” Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com
  • 32. Deployment Plan Identify critical projects in both applications and infrastructure Baseline these projects Track the actual costs using time recording, Work Authorization and a project management system Report CV, SV, BCWP (Value) for the projects on weekly basis. Use this information to “manage” our efforts in a predictive manner. In the past we were “driving in the rearview mirror” It can be done, but it’s real sporty Let’s drive by looking out the front wind shield instead. The scenery is better, and we end up with less road kill. 32/33
  • 33. Some More Details We’ll Need Along the Way Planning, budgeting, and Analysis and management scheduling Cost variance Scheduling Schedule variance Cost account baseline Variance analysis Budgets Reporting Management reserve Undistributed budget Estimates at completion Overhead budget Indirect cost analysis Project target cost Management action Accounting Revisions and Data Direct costs Maintenance Indirect costs Authorized changes Material costs Unauthorized changes Summarization Budget reconciliation 33/33