As carbon capture and storage (CCS) moves towards large-scale commercialisation, stakeholders along the CCS chain are required to address and resolve design and operability details, from generation to storage, at a commercial scale for the first time.
As in other sectors, process simulation and modelling are key technologies for performing design calculations and analysis operations. Indeed, there is little that is new in terms of individual CCS chain components; conventional power stations, amine based CO2 capture plants, pipelines and compressors are mostly well understood.
However, there are still significant challenges in the commercial implementation of CCS. These arise principally from the fact that the whole CCS chain needs to be considered as a single system in order to make design and operation decisions that satisfactorily address the commercial imperatives and risk requirements of the various stakeholders along the chain.
The United Kingdom’s Energy Technologies Institute commissioned and co-funded a £3 million CCS System Modelling Toolkit involving E.On, EDF, Rolls-Royce, CO2DeepStore, Process Systems Enterprise and E4tech to deliver a robust, fully-integrated toolkit that can be used by CCS stakeholders across the whole CCS chain. The commercial tool arising from the project – gCCS – will be available in early 2014.
gCCS will contain a full complement of models for conventional power generation, new power generation, solvent-based carbon capture, compression, transmission and injection. In addition, it will be possible to incorporate models of other plants, such as air separation units, using commercially-available capabilities, or to create custom models that can be incorporated within the environment. The system will be able to model both steady-state and dynamic operation. It will also include costing capabilities for use in rigorous mathematical optimisation that can include both continuous and discrete decisions, providing a common basis for techno-economic decisions across the chain.
2. Webinar Program 2013-14
CCS systems integration (ROAD)
Making the business case for CCS (2Co)
Global Status of CCS: 2013 (Global CCS Institute)
North West Sturgeon Refinery Project overview (North West Redwater Partnership)
Commercial structures for CO2 networks (National Grid)
Whole-chain system modelling for CCS (gCCS)
Pipeline design and operation (ECOFYS)
Progressing onshore storage in Europe (CIUDEN)
The role of export credit agencies, commercial banks and multilateral banks in funding
CCS demonstration projects (Société Générale)
TCEP business case and contracting strategy (Summit Power)
Key social research findings (CSIRO)
ULCOS stakeholder engagement (ArcelorMittal)
Relative permeability guideline (Stanford University)
http://www.globalccsinstitute.com/get-involved/webinars
3. QUESTIONS
We will collect questions during
the presentation.
Your MC will pose these questions
to the presenter after the
presentation.
Please submit your questions
directly into the GoToWebinar
control panel.
The webinar will start shortly.
4. Alfredo Ramos Plasencia
Worked at PSE in a range of
roles, starting as a consultant in
2006 and working up to his
current role as Vice President
Strategic Business Development
CCS & Power.
Prior to this, Alfredo worked in
water services and at Aachen
University in Germany.
He graduated from Aachen
University in 2000 with a Master of
Science in Chemical Engineering.
Alfredo will provide an overview of
CCS System Modelling and
Simulation and will present some
of the capabilities of gCCS, which
is being developed by PSE.
ETI surveyed their members for requirements for CCS technology development and system modelling was identified as one of the key enabling technologies.
Steady state scenarios – Standalone power plantCCS chain with Full load power plant and 90% CO2 captureCCS chain with Full load power plant and 50% CO2 captureCCS chain with 75% load power plant and 90% CO2 captureCCS chain with 50% load power plant and 90% CO2 captureCCS chain with Full load power plant and 90% CO2 capture in summer conditionsCCS chain with Full load power plant and 90% CO2 capture in winter conditions
DS 1.1 consists of Steady state conditions (full load) maintained for five hours.Continuously reducing the power plant load from 100% to 75% (5%/min) Subsequently maintaining 75% load for 1 hour Net output of the power plant is ramped up back to 100%Steady state conditions maintained for >23 hoursDS 1.2 consists of Steady state conditions (full load) maintained for five hours.Continuously reducing the power plant load from 100% to 75% (5%/min) Steady state conditions (75% load)maintained for >42 hours
ASUblack box model, estimates air and power consumption O2 is compressed to gasifier working pressure (~ 44 bar)N2 is compressed to GT inlet pressure (~ 27 bar)GasificationGasification occurs at high temperatures (~ 1400 ºC), yielding syngas & molten ash (slag)Reaction is cooled with BFW, generating MP steamSyngas is quenched with cold syngas to decrease temperature and prevent equipment damageSyngas is cooled in a series of heat exchangers, generating HP & MP steamProduced steam is used in other process blocksSyngas ConditioningSyngas at ~275 ºC is saturated in water and heated with WGS reactor #3 outlet stream to prevent condensation in WGS reactorsAt WGS reactor #1 inlet, steam is injected to meet a steam:CO molar ratio of ~2CO and H2O are shifted to H2 and CO2 in 3 stages of WGS reactors (standard in pre-combustion capture)At the same time, COS is shifted to H2S (H2S removal in AGR processes is more efficient)WGS reaction is exothermic and syngas is cooled between stages generating HP & MP steamWGS reactor #3 outlet is cooled in several integration HE with:Syngas saturator outletNitrogen from ASU“Clean” syngas from AGRAcid gas removalSyngas is further cooled with in gas/gas heat exchangers (GGH) (with nitrogen and clean syngas streams)Water is knocked out before syngas is fed to the acid gas removal unitPhysical absorption processes (e.g. Selexol, Rectisol) are preferred since there is a high acid gas partial pressureThe physical absorption process is represented by a simplified capture plant model, where the splits desired CO2 and acid gas (H2S,COS) are specifiedAcid gas stream (H2S, CO2 and COS sent to the SRU) usually contains some CO2 which is recycled back to AGR inlet, to simplify the flowsheet, the simplified capture plant sends an acid gas stream consisting of only H2S & COSSRU model incorporates sulphur recovery unit (O2-blown Claus process) + tail gas treatment processes (Shell ClausOffgas Treating,SCOT, process). It is a black box based on E.ON knowledge and estimates O2 and power consumption and steam export flow rateGas turbineConventional gas turbine, main difference is the fuel LHV, which is up to four times less than natural gas because of the requirement for dilution with N2.