1. Year 12 IPT - Computer System Case Study
Key Dates for Completion…
1. Workplace Chosen –Week 2, Sun20th Oct
2. Questionnaire Completed / Drafted - Week 3, Tuesday 15th Oct
3. Delivered / Emailed Q to Workplace - Week 4, Tues 22ndOct
4. Returned from Workplace - Week 4, Aim for Sat 26th Oct
5. Draft Case Study – email nmiles@hillcrest.qld.edu.au for
drafting and direct feedback: Accepting up until and including
Week 5, Friday8th. Nothing After.
6. Final Case Study – submission via Ed Portal ‘Assignment
Dropbox’. Upload single word document. Week 6,Mon 4th Nov.