SlideShare una empresa de Scribd logo
1 de 24
Judith Plummer
University of Cambridge
judithplummer@farmline.com
Five Myths of
Delays in
Hydropower
Projects
Judith Plummer
University of Cambridge
Myths
 “Pre-construction delays are annoying, but it’s
construction delays you really want to avoid”
 “The more time you spend on preparation the less
the risk of expensive construction delays”
 “The costs of construction delays are fully
captured through contractual penalties and
interest during construction”
 “It does not really matter when you start because
you still get a 40 year project benefit stream”
 “Projects involving international financing
institutions get delayed in pre-construction, but
then move more smoothly in construction”
Myth 1
 “Pre-construction delays are annoying, but it’s
construction delays you really want to avoid”
Annoying to whom?
“Definitely the delay in the start of the actual construction of the project
had wide ranging delays in the reaching of many of the socio-economic
benefits to the local people. Access to school, hospital and other facilities
were delayed to that extent of the pre-construction activities being behind
schedule.” Survey response
 For many stakeholders the effects of pre-construction delay
are as serious, if not more serious, than the effects of
construction delay (including): -
 Affected families
 Government
 Environment
 Off-takers
 Consumers
Increased cost during pre-construction delay
Research on the impact of delays in
environmental licensing for
Hydropower Projects in Brazil
 Direct costs
 Indirect costs
 Unquantifiable costs
A matter for debate?
3-7% of
project cost
In survey results 59% of respondents reported that the cost of the
construction increased by more than inflation during the pre-
construction delay
Myth 1
 “Pre-construction delays are annoying, but its
construction delays you really want to avoid”
 Annoying to whom?
 For many stakeholders the effects of pre-construction
delay are as serious, if not more serious, than the effects
of construction delay
 Affected families
 Government
 Environment
 Off-takers
 Consumers
 Delayed projects suffer cost increases in excess of
inflation
 Positive spin – have collected more data in time and know more
 Negative spin – bidders add a risk premium for sluggish projects.
Myth 2
 “The more time you spend on preparation the less
the risk of expensive construction delays”
Myth 2
 “The more time you spend on preparation the less
the risk of expensive construction delays”
 Data suggests that projects which spend longer in
preparation are more prone to construction delay – not
less.
 Assertion would only be true if the additional time was
all spent on better preparation, of items which are on
the critical path
 But, this is not a call for rushed preparation, simply
that preparation time should be properly planned
and used to reduce construction risk
Myth 3
 “The costs of construction delays are fully
captured through contractual penalties and
interest during construction”
 Not true of negative impacts on stakeholders
 May not even be true of developers/contractors who
may gain reputation for delay?
Survey results – Impacts of delay
Common to Pre-construction and construction
Nature of impact
• Delay to promised local development impacts - such as access to markets (e.g.
roads and bridges)
• Delayed energy supplies - resulting in additional cost to obtain additional energy
supplies
• Delayed financial returns to Government or state project sponsor
• Delayed wider economic benefits (e.g. impact on industry or potential investors
deterred by lack of secure power supply)
• Industrial and commercial investors discouraged by lack of firm power supply
• Carbon emissions from alternate electricity supplies (typically coal or diesel)
• Delayed energy supplies - resulting in groups of the population remaining un-
served (delayed development outcomes)
• Poor communities remain un-served by electricity with implications for local
development and alleviation of poverty
Myth 3
 “The costs of construction delays are fully
captured through contractual penalties and
interest during construction”
 Not true of negative impacts on stakeholders
 May not even be true of developers/contractors who
may gain reputation for delay?
Myth 4
 “It does not really matter when you start because
you still get a 40 year project benefit stream”
 If this were the case then there would be times when it
was preferable to build a project later?
 “Real options” analysis shows that it is rarely the case
that it is better to wait for better information than to
build now with flexibility*
* Water Resources Planning under Climate Change: A “Real Options” Application to Investment Planning in the Blue Nile Marc
Jeuland, Dale Whittington – forthcoming publication
Economic analysis shows that economic returns
are lower from a later project
Bumbuna – Sierra Leone – construction delay
 Economic rate of return of project 42.2%
 With two year delay 28.5%
“But is still a very healthy rate of return”
Data From Economic Analysis report – Bumbuna Power Project
“The impact of delays in construction on
economic returns depends upon when that delay
occurs. If it occurs before construction begins (in
effect delaying all costs and all benefits) there is
no impact.”
World Bank Project appraisal report
Rampur Hydropower Project On time Delay
Construction delay
 Economic rate of return of project 14.5%
 With one year delay 12.4%
 Financial rate of return 9.3%
 With one year delay 7.7%
Pre-construction delay
 Economic rate of return of project 14.5%
 With one year delay 13.9%
 Financial rate of return 9.3%
 With one year delay 9.3%
Data From World Bank Project Appraisal Report estimates and calculations
Myth 4
 “It does not really matter when you start because
you still get a 40 year project benefit stream”
 If this were the case then there would be times when it
was preferable to build a project later?
 “Real options” analysis shows that it is rarely the case
that it is better to wait for better information than to
build now with flexibility
 Economic analysis shows that economic returns are
lower from a later project
 Standard project economic rate of return analysis
does not reflect the true impact of delay and the
scenarios on project delay should not be
considered as guidance for management of delay.
Myth 5
 “Projects involving international financing
institutions get delayed in pre-construction, but
then move more smoothly in construction”
 Survey data revealed a link between the extent of pre-
construction delay and funding source
Delay by funding source
0%
5%
10%
15%
20%
25%
30%
None Less than
1 year
1-2 years 2-3 years 3-5 years 5-10 yearsMore than
10 years
Percentageofprojects
Length of Incidence of Pre-construction Delay
IFI funding involved Private Funding
0%
5%
10%
15%
20%
25%
30%
35%
40%
None Less
than 1
year
1-2 years2-3 years3-5 years 5-10
years
More
than 10
years
Percentatgeofprojectswhereadelaywas
identified
Length of Incidence of Construction Delay
IFI funding involved Private Funding
Myth 5
 “Projects involving international financing
institutions get delayed in pre-construction, but
then move more smoothly in construction”
 Survey data revealed a link between the extent of pre-
construction delay and funding source
 But the same link existed for construction delay – which
is generally not sensitive to funding source
 Do IFIs cause delay – or do they just get involved in
riskier projects that the private sector wont fund?
But
Myths
 “Pre-construction delays are annoying, but it’s
construction delays you really want to avoid”
 “The more time you spend on preparation the less
the risk of expensive construction delays”
 “The costs of construction delays are fully
captured through contractual penalties and
interest during construction”
 “It does not really matter when you start because
you still get a 40 year project benefit stream”
 “Projects involving international financing
institutions get delayed in pre-construction, but
then move more smoothly in construction”
Thank you
Judith Plummer
University of Cambridge
judithplummer@farmline.com

Más contenido relacionado

Destacado

Civil war photographs - HST10500
Civil war photographs - HST10500Civil war photographs - HST10500
Civil war photographs - HST10500
mrectenwald
 
Copyrights, Trademarks, Patents, by Tobias Kuban and Matthias Bock
Copyrights, Trademarks, Patents, by Tobias Kuban and Matthias BockCopyrights, Trademarks, Patents, by Tobias Kuban and Matthias Bock
Copyrights, Trademarks, Patents, by Tobias Kuban and Matthias Bock
bioflux
 

Destacado (9)

Civil war photographs - HST10500
Civil war photographs - HST10500Civil war photographs - HST10500
Civil war photographs - HST10500
 
Abordaje adenopatias
Abordaje adenopatiasAbordaje adenopatias
Abordaje adenopatias
 
Cv bertille Besancon_english update
Cv  bertille Besancon_english updateCv  bertille Besancon_english update
Cv bertille Besancon_english update
 
Majo
MajoMajo
Majo
 
Présentation AG 31 mai 2016 mopa frotsi pc
Présentation AG 31 mai 2016 mopa frotsi pcPrésentation AG 31 mai 2016 mopa frotsi pc
Présentation AG 31 mai 2016 mopa frotsi pc
 
مجلة هي - العدد 257 - سبتمبر 2015
مجلة هي - العدد 257 - سبتمبر 2015مجلة هي - العدد 257 - سبتمبر 2015
مجلة هي - العدد 257 - سبتمبر 2015
 
Planilla expt. port
Planilla expt. portPlanilla expt. port
Planilla expt. port
 
Copyrights, Trademarks, Patents, by Tobias Kuban and Matthias Bock
Copyrights, Trademarks, Patents, by Tobias Kuban and Matthias BockCopyrights, Trademarks, Patents, by Tobias Kuban and Matthias Bock
Copyrights, Trademarks, Patents, by Tobias Kuban and Matthias Bock
 
McNroe SIP PRESENTATION
McNroe SIP PRESENTATIONMcNroe SIP PRESENTATION
McNroe SIP PRESENTATION
 

Similar a IHA 2013 World Congress: Judith Plummer: Special Lecture on the Impacts of Delays on Hydropower Projects

Capital and infrastructure solution brochure Single FINAL
Capital and infrastructure solution brochure Single FINALCapital and infrastructure solution brochure Single FINAL
Capital and infrastructure solution brochure Single FINAL
Christopher Matthews
 
State senate transpo hearings 11 13-13 backgroundpaper
State senate transpo hearings 11 13-13 backgroundpaperState senate transpo hearings 11 13-13 backgroundpaper
State senate transpo hearings 11 13-13 backgroundpaper
peggydrouet
 
Asim prasad
Asim prasadAsim prasad
Asim prasad
PMI2011
 

Similar a IHA 2013 World Congress: Judith Plummer: Special Lecture on the Impacts of Delays on Hydropower Projects (20)

Benefits realisation management - Kenn Dolan
Benefits realisation management - Kenn DolanBenefits realisation management - Kenn Dolan
Benefits realisation management - Kenn Dolan
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims Effectively
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
Project Finance: Construction Risk
Project Finance: Construction RiskProject Finance: Construction Risk
Project Finance: Construction Risk
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
Risk management
Risk managementRisk management
Risk management
 
52 a risk-management_approach_to_a_successful_infrastructure_project
52 a risk-management_approach_to_a_successful_infrastructure_project52 a risk-management_approach_to_a_successful_infrastructure_project
52 a risk-management_approach_to_a_successful_infrastructure_project
 
Riskanalysisin housingindustry (1)
Riskanalysisin housingindustry (1)Riskanalysisin housingindustry (1)
Riskanalysisin housingindustry (1)
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
Improving Public Sector Infrastructure Investment by Fernando Fernholz
Improving Public Sector Infrastructure Investment by Fernando FernholzImproving Public Sector Infrastructure Investment by Fernando Fernholz
Improving Public Sector Infrastructure Investment by Fernando Fernholz
 
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
Capital and infrastructure solution brochure Single FINAL
Capital and infrastructure solution brochure Single FINALCapital and infrastructure solution brochure Single FINAL
Capital and infrastructure solution brochure Single FINAL
 
Microgrid invest risk summary v08-02c
Microgrid invest risk summary v08-02cMicrogrid invest risk summary v08-02c
Microgrid invest risk summary v08-02c
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
 
b2025surveysummary (1)
b2025surveysummary (1)b2025surveysummary (1)
b2025surveysummary (1)
 
State senate transpo hearings 11 13-13 backgroundpaper
State senate transpo hearings 11 13-13 backgroundpaperState senate transpo hearings 11 13-13 backgroundpaper
State senate transpo hearings 11 13-13 backgroundpaper
 
Asim prasad
Asim prasadAsim prasad
Asim prasad
 

Más de International Hydropower Association

IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...
IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...
IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...
International Hydropower Association
 

Más de International Hydropower Association (20)

IHA 2013 World Congress: Canadian Hydropower Association: Hydropower - Canada...
IHA 2013 World Congress: Canadian Hydropower Association: Hydropower - Canada...IHA 2013 World Congress: Canadian Hydropower Association: Hydropower - Canada...
IHA 2013 World Congress: Canadian Hydropower Association: Hydropower - Canada...
 
IHA 2013 World Congress: Instituto Acende Brasil: Current initiatives and wha...
IHA 2013 World Congress: Instituto Acende Brasil: Current initiatives and wha...IHA 2013 World Congress: Instituto Acende Brasil: Current initiatives and wha...
IHA 2013 World Congress: Instituto Acende Brasil: Current initiatives and wha...
 
IHA 2013 World Congress: Nepal Hydropower Association: Hydropower Development...
IHA 2013 World Congress: Nepal Hydropower Association: Hydropower Development...IHA 2013 World Congress: Nepal Hydropower Association: Hydropower Development...
IHA 2013 World Congress: Nepal Hydropower Association: Hydropower Development...
 
IHA 2013 World Congress: Sarawak Energy: Incorporating Sustainability into Bu...
IHA 2013 World Congress: Sarawak Energy: Incorporating Sustainability into Bu...IHA 2013 World Congress: Sarawak Energy: Incorporating Sustainability into Bu...
IHA 2013 World Congress: Sarawak Energy: Incorporating Sustainability into Bu...
 
IHA 2013 World Congress: E.ON: Incorporating Sustainability into Business Pra...
IHA 2013 World Congress: E.ON: Incorporating Sustainability into Business Pra...IHA 2013 World Congress: E.ON: Incorporating Sustainability into Business Pra...
IHA 2013 World Congress: E.ON: Incorporating Sustainability into Business Pra...
 
IHA 2013 World Congress: Dr Byman Hamududu: Climate change: Four dimensions ...
 IHA 2013 World Congress: Dr Byman Hamududu: Climate change: Four dimensions ... IHA 2013 World Congress: Dr Byman Hamududu: Climate change: Four dimensions ...
IHA 2013 World Congress: Dr Byman Hamududu: Climate change: Four dimensions ...
 
IHA 2013 World Congress: IPCC: Climate change: Four dimensions for hydropower
IHA 2013 World Congress: IPCC: Climate change: Four dimensions for hydropowerIHA 2013 World Congress: IPCC: Climate change: Four dimensions for hydropower
IHA 2013 World Congress: IPCC: Climate change: Four dimensions for hydropower
 
IHA 2013 World Congress: IGA: Renewable systems: sharing experience
IHA 2013 World Congress: IGA: Renewable systems: sharing experienceIHA 2013 World Congress: IGA: Renewable systems: sharing experience
IHA 2013 World Congress: IGA: Renewable systems: sharing experience
 
IHA 2013 World Congress: Judith Plummer: Who’s investing in hydropower?
IHA 2013 World Congress: Judith Plummer: Who’s investing in hydropower?IHA 2013 World Congress: Judith Plummer: Who’s investing in hydropower?
IHA 2013 World Congress: Judith Plummer: Who’s investing in hydropower?
 
IHA 2013 World Congress: Bringing markets to the resource case study: Sarawak...
IHA 2013 World Congress: Bringing markets to the resource case study: Sarawak...IHA 2013 World Congress: Bringing markets to the resource case study: Sarawak...
IHA 2013 World Congress: Bringing markets to the resource case study: Sarawak...
 
IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...
IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...
IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...
 
IHA 2013 World Congress: ADB presentation: Case Study of Song Bung 4 Hydropow...
IHA 2013 World Congress: ADB presentation: Case Study of Song Bung 4 Hydropow...IHA 2013 World Congress: ADB presentation: Case Study of Song Bung 4 Hydropow...
IHA 2013 World Congress: ADB presentation: Case Study of Song Bung 4 Hydropow...
 
Gil Maranhão Neto, GDF SUEZ
Gil Maranhão Neto, GDF SUEZGil Maranhão Neto, GDF SUEZ
Gil Maranhão Neto, GDF SUEZ
 
Rikard Liden, World Bank
Rikard Liden, World BankRikard Liden, World Bank
Rikard Liden, World Bank
 
Cameron Ironside, IHA
Cameron Ironside, IHACameron Ironside, IHA
Cameron Ironside, IHA
 
Valdineuza do Nascimento Borges, CPPT Cuniã
Valdineuza do Nascimento Borges, CPPT CuniãValdineuza do Nascimento Borges, CPPT Cuniã
Valdineuza do Nascimento Borges, CPPT Cuniã
 
Sergio Leao, Acreditar
Sergio Leao, Acreditar Sergio Leao, Acreditar
Sergio Leao, Acreditar
 
Hon. Omar Tejada
Hon. Omar TejadaHon. Omar Tejada
Hon. Omar Tejada
 
Olivier Salignat, EDF
Olivier Salignat, EDFOlivier Salignat, EDF
Olivier Salignat, EDF
 
Mauricio Morales, ICE
Mauricio Morales, ICEMauricio Morales, ICE
Mauricio Morales, ICE
 

Último

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
Abortion pills in Kuwait Cytotec pills in Kuwait
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
lizamodels9
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
dlhescort
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
amitlee9823
 

Último (20)

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Phases of negotiation .pptx
 Phases of negotiation .pptx Phases of negotiation .pptx
Phases of negotiation .pptx
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 

IHA 2013 World Congress: Judith Plummer: Special Lecture on the Impacts of Delays on Hydropower Projects

  • 1. Judith Plummer University of Cambridge judithplummer@farmline.com
  • 2. Five Myths of Delays in Hydropower Projects Judith Plummer University of Cambridge
  • 3. Myths  “Pre-construction delays are annoying, but it’s construction delays you really want to avoid”  “The more time you spend on preparation the less the risk of expensive construction delays”  “The costs of construction delays are fully captured through contractual penalties and interest during construction”  “It does not really matter when you start because you still get a 40 year project benefit stream”  “Projects involving international financing institutions get delayed in pre-construction, but then move more smoothly in construction”
  • 4. Myth 1  “Pre-construction delays are annoying, but it’s construction delays you really want to avoid”
  • 5. Annoying to whom? “Definitely the delay in the start of the actual construction of the project had wide ranging delays in the reaching of many of the socio-economic benefits to the local people. Access to school, hospital and other facilities were delayed to that extent of the pre-construction activities being behind schedule.” Survey response  For many stakeholders the effects of pre-construction delay are as serious, if not more serious, than the effects of construction delay (including): -  Affected families  Government  Environment  Off-takers  Consumers
  • 6. Increased cost during pre-construction delay Research on the impact of delays in environmental licensing for Hydropower Projects in Brazil  Direct costs  Indirect costs  Unquantifiable costs A matter for debate? 3-7% of project cost In survey results 59% of respondents reported that the cost of the construction increased by more than inflation during the pre- construction delay
  • 7. Myth 1  “Pre-construction delays are annoying, but its construction delays you really want to avoid”  Annoying to whom?  For many stakeholders the effects of pre-construction delay are as serious, if not more serious, than the effects of construction delay  Affected families  Government  Environment  Off-takers  Consumers  Delayed projects suffer cost increases in excess of inflation  Positive spin – have collected more data in time and know more  Negative spin – bidders add a risk premium for sluggish projects.
  • 8. Myth 2  “The more time you spend on preparation the less the risk of expensive construction delays”
  • 9.
  • 10. Myth 2  “The more time you spend on preparation the less the risk of expensive construction delays”  Data suggests that projects which spend longer in preparation are more prone to construction delay – not less.  Assertion would only be true if the additional time was all spent on better preparation, of items which are on the critical path  But, this is not a call for rushed preparation, simply that preparation time should be properly planned and used to reduce construction risk
  • 11. Myth 3  “The costs of construction delays are fully captured through contractual penalties and interest during construction”  Not true of negative impacts on stakeholders  May not even be true of developers/contractors who may gain reputation for delay?
  • 12. Survey results – Impacts of delay Common to Pre-construction and construction Nature of impact • Delay to promised local development impacts - such as access to markets (e.g. roads and bridges) • Delayed energy supplies - resulting in additional cost to obtain additional energy supplies • Delayed financial returns to Government or state project sponsor • Delayed wider economic benefits (e.g. impact on industry or potential investors deterred by lack of secure power supply) • Industrial and commercial investors discouraged by lack of firm power supply • Carbon emissions from alternate electricity supplies (typically coal or diesel) • Delayed energy supplies - resulting in groups of the population remaining un- served (delayed development outcomes) • Poor communities remain un-served by electricity with implications for local development and alleviation of poverty
  • 13. Myth 3  “The costs of construction delays are fully captured through contractual penalties and interest during construction”  Not true of negative impacts on stakeholders  May not even be true of developers/contractors who may gain reputation for delay?
  • 14. Myth 4  “It does not really matter when you start because you still get a 40 year project benefit stream”  If this were the case then there would be times when it was preferable to build a project later?  “Real options” analysis shows that it is rarely the case that it is better to wait for better information than to build now with flexibility* * Water Resources Planning under Climate Change: A “Real Options” Application to Investment Planning in the Blue Nile Marc Jeuland, Dale Whittington – forthcoming publication
  • 15. Economic analysis shows that economic returns are lower from a later project Bumbuna – Sierra Leone – construction delay  Economic rate of return of project 42.2%  With two year delay 28.5% “But is still a very healthy rate of return” Data From Economic Analysis report – Bumbuna Power Project
  • 16. “The impact of delays in construction on economic returns depends upon when that delay occurs. If it occurs before construction begins (in effect delaying all costs and all benefits) there is no impact.” World Bank Project appraisal report
  • 17. Rampur Hydropower Project On time Delay Construction delay  Economic rate of return of project 14.5%  With one year delay 12.4%  Financial rate of return 9.3%  With one year delay 7.7% Pre-construction delay  Economic rate of return of project 14.5%  With one year delay 13.9%  Financial rate of return 9.3%  With one year delay 9.3% Data From World Bank Project Appraisal Report estimates and calculations
  • 18. Myth 4  “It does not really matter when you start because you still get a 40 year project benefit stream”  If this were the case then there would be times when it was preferable to build a project later?  “Real options” analysis shows that it is rarely the case that it is better to wait for better information than to build now with flexibility  Economic analysis shows that economic returns are lower from a later project  Standard project economic rate of return analysis does not reflect the true impact of delay and the scenarios on project delay should not be considered as guidance for management of delay.
  • 19. Myth 5  “Projects involving international financing institutions get delayed in pre-construction, but then move more smoothly in construction”  Survey data revealed a link between the extent of pre- construction delay and funding source
  • 20. Delay by funding source 0% 5% 10% 15% 20% 25% 30% None Less than 1 year 1-2 years 2-3 years 3-5 years 5-10 yearsMore than 10 years Percentageofprojects Length of Incidence of Pre-construction Delay IFI funding involved Private Funding 0% 5% 10% 15% 20% 25% 30% 35% 40% None Less than 1 year 1-2 years2-3 years3-5 years 5-10 years More than 10 years Percentatgeofprojectswhereadelaywas identified Length of Incidence of Construction Delay IFI funding involved Private Funding
  • 21. Myth 5  “Projects involving international financing institutions get delayed in pre-construction, but then move more smoothly in construction”  Survey data revealed a link between the extent of pre- construction delay and funding source  But the same link existed for construction delay – which is generally not sensitive to funding source  Do IFIs cause delay – or do they just get involved in riskier projects that the private sector wont fund? But
  • 22. Myths  “Pre-construction delays are annoying, but it’s construction delays you really want to avoid”  “The more time you spend on preparation the less the risk of expensive construction delays”  “The costs of construction delays are fully captured through contractual penalties and interest during construction”  “It does not really matter when you start because you still get a 40 year project benefit stream”  “Projects involving international financing institutions get delayed in pre-construction, but then move more smoothly in construction”
  • 24. Judith Plummer University of Cambridge judithplummer@farmline.com

Notas del editor

  1. So what?!take more care over time -