COMPERATIVE ANALYSIS OF THREE MAJOR TYPE OF CONTRACTS WITH
CASE STUDY
Abhijit Langhe1, Pravin Minde2
1M.E Student (Construction Management), PVPIT Engineering College, Pune, Maharashtra, India.
2Assistant Professor, Dept. of Civil Engineering, PVPIT Engineering College, Pune, Maharashtra, India.
----------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - The thirteenth FYP shows large interest in
investments in infrastructure sector by India, so there is need
for different types of contract that will satisfy the purpose.
Engineering, procurement and construction (EPC) contracts
are on the way to become the most usual form of contracting
applied by the private sector to undertake construction works
on large scale infrastructure projects like roads,
telecommunication, petroleum, real estate etc. In every
project, it is necessary to have good contract management in
place; otherwise it can have negative consequences for all
parties involved – the client, contractor, lenders, government,
etc. Here the contractor carry’s out the designs of project,
procure materials and equipment’s required as per the
specifications and delivers the project in agreed duration of
time. If contract management is not implemented and
controlled properly, it may have a negative impact on the
project as a whole. Such failures may include a delayed
schedule, cost overruns, quality, safety and more.
It was also found that the EPC contracting scheme could work
very well, especially in the cases where the contractor is in a
good position to understand all legal aspects of the contract,
including the allocation of risks.
A comparative study between PPP, Item Rate and Lump-Sum
mode of contract will enable to know the feasible mode of
contract in India. It lists certain advantages, disadvantages
and their need in contract.
Key Words: Contracts, EPC Contract, Lump-Sum
Contract, Item Rate Contract, Contract Comparison.
Construction industry is rapidly growing and therefore
requires various models of contracting. For mega
infrastructure projects a flexible and effective method is
needed. Engineering Procurement Construction (EPC)
contract is a popular type of contract for infrastructure and
power projects. EPC contractors carryout designs, procure
the material and equipment’s as per the specifications and
deliver the project in stipulated time.
Following factors areconsideredtomeasurethe executionof
project. Time, Cost, Quality, Cost-overrun, Time- overrun,
Unit cost of building, Rate of construction, Client satisfaction
EPC contracts will continue to be the predominant form of
construction contract and will be used on large scale
infrastructure projects in most jurisdiction. EPC contracts
vary on the basis of the assignment of responsibility and
related penalties.
2. LITERATURE REVIEW:-
AccordingtoAshwini Wadedwer,ShreedharPatil (December
2015). The PPPs are good projects which deliver value for
money when they are toll financed. The design and
construction risk to private partners. TheEPCcontractplays
vital role in infrastructure development.
Due to investment of private partners in PPP, risk ismore to
private sector, mainly to the lenders or financerswhichgoes
into bad loans and delay in project completion. Because of
these risk factors nowadays there is low interest from the
investors in PPP. Therefore government is moving towards
the EPC mode as it has fixed time limit with fixed cost.
3. OBJECTIVE:-
1. To determine most suitable type of contract for
construction of flyover/road.
2. To compare three different types of contracts of same
organization.
3. To identify factors causing loss or profit of project.
4. METHODOLOGY:-
Fig-1 Methodology Flow Chart
1. INTRODUCTION
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 10 | Oct 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 238
5. CASE STUDY'S:-
Case study 1:-
 Department:- Maharashtra State Road Development
Corporation Limited Mumbai.
 Name of Work:- Construction of elevated structure,
ROB and service roads of NH-4fromKm24.500toKm
25.570 in the state of Maharashtra under EPC mode.
 Type of Contract:- Engineering, Procurement and
Construction (EPC) Contract
 Length in Km:- 1.07 Km
 Completion Period:- 18 Months
 Estimated Tender Cost:- Rs. 46.1246 Crore
Case Study 2:-
 Department:- Public Works Department (PWD)
 Name of Work:- Construction of Flyover From
College of Engineering Pune to Patil Estate, Pune
(Balance Work)
 Type of Contract:- Item Rate Contract
 Length in Km:- 0.80 Km
 Completion Period:- 15 Months
 Estimated Tender Cost:- Rs.21.83 Crore
Case Study 3:-
 Department:- Pune Municipal Corporation
 Name of Work:- Construction of ROB between S.
No. 89 & 71 at Mundhawa Over Pune Solapur
Railway line on24.0 Mtr. HCMTR.
 Type of Contract:- “C” Form (Lump – sum Contract)
 Completion Period:- 24 Months
 Estimated Tender Cost:- Rs. 25.87 Crores
1. EPC Contract:- EPC contract carryoutdesignsofproject,
procure equipment’s and materials required as per the
specifications and deliver the project within the specified
period of time.
I. Types of EPC contract:
a. Single document.
b. Privately negotiated.
c. Tendered out.
d. Issued under nomination basis.
e. Multiple documents.
f. Single document.
g. Lumpsum price.
h. Fixed price.
II. Suitability:-
For mega infrastructure projects a flexible and effective
method is needed. Engineering Procurement Construction
(EPC) contract is a popular type of contract for
infrastructure and power projects. EPC contractorscarryout
designs, procure the material and equipment’s as per the
specifications and deliver the project in stipulated time.
III. Advantages:-
a. Reduced total time during the contractual process by
having just one process.
b. A seemingly “lower cost” when integrating “all” the
elements under one provider.
c. The main advantage of this service is the peace of
mind the owner gets when it hands over full
responsibility of the project to “only one contractor”, itis
much easier for the owner to manage and communicate
with one provider, which means “one neck to choke”.
d. EPC minimizes the owner’s risks.
e. EPC for mega projects is more flexible and efficient
delivery method.
IV. Disadvantages:-
a. A higher cost is assumed due to the higher risk that
comes with total responsibility, there is less
information toprepareproposalsandthereforebidders
assume more risks.
b. There is a greater disparity when comparing offers,
both economically, because each providerhasdifferent
criteria for assessing the risk.
c. Usually designs are oversizedduetolack ofinformation
available at the time when the offer is being prepared.
2. Item Rate Contract:- It is also called a schedule contract,
in this contract, the contractor undertakes the execution of
work on an item rate basis. The amount to bereceivedbythe
contractor, depends upon the quantities of various items of
work actually executed. The payment to the contractor is
made on the basis of detailed measurements of different
items of work actually done by him.
I. Suitability:-
The item rate contract is most commonlyusedforall typesof
engineering works financed bypublicorgovernmentbodies.
This type of contract is suitable for works which can be split
into various items and quantities under each item can be
estimated with accuracy.
II. Advantages:-
a. There is no need for detailed drawingsatthetimeof
allotting contract as in the case of lump sum contract. The
6. ADVANTAGES AND DISADVANTAGES OF
CONTRACTS:-
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 10 | Oct 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 239
detailed drawings can be prepared after the contract is
awarded.
b. Changes in drawings and quantities of individual
items can be made as per requirement within agreed
limits.
c. The payment to the contractor ismadeontheactual
work done by his at the agreed rates.
a. The total cost of work can only be known upon
completion. As such, the owner may incur financial
difficulty if the final cost increases substantially.
b. Additional staff is required to take detailed
measurements of work done for releasing payments to
the contractor.
I. Suitability:-
A lump sum contract is more suitable for works for which
contractors have prior construction experience. This
experience enablesthecontractorstosubmit a morerealistic
bid. This type of contract is not suitable for difficult
foundations, excavationsofuncertaincharacter,andprojects
susceptible to unpredictable hazards and variations.
a. The owner can decide whether to start or shelve the
project knowing the total lump sum price quoted by
different contractors.
b. The contractor can earn more profit by in depth
planning and effective management site.
c. Since the contractor has accepted a fixed price for the
construction, the owner is not liable for any over
expenditure. This is the most important benefit.
d. It is much simpler to get construction loan with a
Lump sum contract as it provides a high degree of
certainty as far as cost is concerned.
e. It is much easier to supervise and manage Lump sum
contracts.
III. Disadvantages:-
a. Quantifying changes is a big challenge. Suchcontracts
demand documentationand recordkeepingofchange
orders at all stages that further requires more
paperwork.
b. Lump sum contracts pose greater risk to contractor.
c. The overall constructioncompletioncouldtakelonger
than other contractual alternatives.
d. Since the contract is based on fixed price, the
contractor may start using sub-standard means and
methods and products. In such a case, the owner
should specify building materials well in advance.
e. Lump-sum contracts usually end up with higherfixed
price to cover unforeseen circumstances. Owners are
responsible for unpredicted conditions which are
beyond the control of either party.
7. DATA ANALYSIS:-
Site Dehu Road COEP Mundhawa
Type of
Contract
EPC
Contract
Item Rate
Contract
Lump-Sum
Contract
Cost
Project
amount and
scope of
work is
fixed. Extra
claim can be
done but not
easily
applicable,
as the scope
is defined
Project
amount is
given by the
client. Extra
claim can be
done as per
work
executed.
In this case
the project
amount is
fixed and
extra claim
can be as
per the
work
executed
Feasibility
Work can be
started
when the
land is
acquired
more than
90%.
Work can be
started even
if minimum
land is
acquired i.e.
25%.
Work can be
started
when more
than 50% of
land is
available to
the
contractor.
Time
Overrun
Easily time
extension is
not available
as the scope
and the
amount of
the project
is fixed.
Time
beyond the
scope of
work is
available
and can get
the time
extension
depending
on the work.
Time is
defined but
time
extension
can get
according to
valid
reasons.
Cost
Overrun
In this type
of project
cost is
Causes of
cost
overrun:
Causes of
cost
overrun:
III. Disadvantages:-
3. Lump-Sum Contract:- In this type of contract, the
contractor offers to do the whole work as shown in
drawings and described by specifications, for a total
stipulated sum of money. There are no individual rates
quoted, thus it becomes difficult to make adjustments in
the contract value if any changes are to be made in the
work later on. The schedule of different items of work is
not provided and the contractor has to completethework as
per drawings and specifications for the agreed lump sum
amount.
II. Advantages:-
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 10 | Oct 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 240
according to
tender only.
But due if
some extra
work is
carried out
i.e. utility
shifting,
escalation
additional
amount can
be obtained
from the
client.
i) Basic Cost
ii)
Escalation
due to delay
iii) Extra
Items
iv) Claims
i) Tender
Cost
ii)
Escalation
iii) Extra
Items
iv) Claims
8. SOME MAJOR EPC COMPANIES IN INDIA:-
Segment EPC Company
Construction
residential/
commercial
1. Larsen and Tourbo Ltd.
2. Shapoorji Pallonji and Co. Ltd.
3. B.G. Shirke Construction Technology
Pvt. Ltd.
4. Man Infra Construction Ltd.
5.Supreme Infrastructure India Ltd.
Infrastructur
e/general
contracting
1. Hindustan Construction Co. Ltd.
2. Gammon India
3. Simplex Infrastructure Ltd.
4. Gayatri Projects Ltd.
5. Nagarjuna Construction Ltd.
9. CONCLUSIONS:-
a. In EPC contract single contractor is appointed by the
owner for all kinds of construction works. The major
difference between lump sum and EPC isthat,inEPCthe
contractor has the responsibility of design and
construction.
b. Where as in lump sum contract the designanddrawings
are prepared by the technical team of the owner.
c. The EPC contractor hands over a working facility that’s
ready to go. A design-build contract closes out similarly
to design-bid-build contracts, with the owner and its
construction manager or designer taking an active role
in punching out the facility.
d. Design-build contracts tend to take either a traditional
design-bid-build approach to unknownslikehiddensite
conditions, or to share that risk between the owner and
the design-builder. In contrast, it’s not uncommon for
EPC contracts to shift these risks entirely to the EPC
contractor.
e. Understanding the differences between these two
seemingly quite similar design processes is a key step
when assessing which delivery system is right for your
project.
REFERENCES
1) Ashwini Wadedwer, Shreedhar Patil (December 2015),
"Comparative Study between PPP Mode of Contracts and
EPC Mode of Contracts"
2) Rahul Bali and Prof. M.R Apte (February 2014), "Risk
Management in EPC Contract - Risk Identification”
3) Benyamin Sadeghi, Mohammad Mehdi Mortaheb and
Hamed Kashani, "Identification of Recurring EPC Contract
Risks and Mitigation Strategies"
4) Phil Loots and Nick Henchie (November 2007),"Worlds
Apart: EPC and EPCM Contracts: Risk issues and allocation"
5) Abhishek Raj Singh, Dr. Sanjay Tiwari (July 2015), " EPC:
An Innovative Tool for Mega Project Construction"
6) Soroush Hejazi Kia, Ahmad Reza Tohidi (March 2015), "
Risk Allocation in Engineering Construction Contracts"
7)Christopher Marato Gofhamodimo, "Construction
Contracts"
https://www.scribd.com/document/371256964/icm1999-
03

Más contenido relacionado

La actualidad más candente

Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 AssignmentMelvin Lim
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignmentashleyyeap
 
Analysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims inAnalysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims ineSAT Publishing House
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportArissa Loh
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentHaziq1511
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkDaniel Ross
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparisonhelensuni
 
Professional practce assignment report
Professional practce assignment reportProfessional practce assignment report
Professional practce assignment reportSyafiq Zariful
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Roland_Nikles
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignmentwendyteosy
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practiceseenyeeyong
 
PP1 assignment
PP1 assignment PP1 assignment
PP1 assignment Enoch Wong
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationHarish Mahavar
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET Journal
 

La actualidad más candente (19)

Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignment
 
Analysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims inAnalysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims in
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
Newsletter TE&A
Newsletter TE&ANewsletter TE&A
Newsletter TE&A
 
Project Report
Project ReportProject Report
Project Report
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 
Professional practce assignment report
Professional practce assignment reportProfessional practce assignment report
Professional practce assignment report
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignment
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practice
 
PP1 assignment
PP1 assignment PP1 assignment
PP1 assignment
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
 

Similar a IRJET- Comperative Analysis of Three Major Type of Contracts with Case Study

“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”IOSR Journals
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsIRJET Journal
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...IRJET Journal
 
Contractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure ProjectsContractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure ProjectsAM Publications
 
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET Journal
 
Study on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction IndustryStudy on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction IndustryIRJET Journal
 
STANDARD-PROCEDURE-FOR-PRICE-ADJUSTMENT.pdf
STANDARD-PROCEDURE-FOR-PRICE-ADJUSTMENT.pdfSTANDARD-PROCEDURE-FOR-PRICE-ADJUSTMENT.pdf
STANDARD-PROCEDURE-FOR-PRICE-ADJUSTMENT.pdfMohammedBilal554495
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET Journal
 
Procurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery modelsProcurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery modelsConstruction in Focus
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET Journal
 
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...Moustafa Ismail Abu Dief
 
Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...IAEME Publication
 
Performance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projectsPerformance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projectsiaemedu
 
Transmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesTransmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesMANTHAN CHAUHAN
 
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET Journal
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET Journal
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 

Similar a IRJET- Comperative Analysis of Three Major Type of Contracts with Case Study (20)

“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction Projects
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
 
Contractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure ProjectsContractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure Projects
 
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
 
Study on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction IndustryStudy on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction Industry
 
STANDARD-PROCEDURE-FOR-PRICE-ADJUSTMENT.pdf
STANDARD-PROCEDURE-FOR-PRICE-ADJUSTMENT.pdfSTANDARD-PROCEDURE-FOR-PRICE-ADJUSTMENT.pdf
STANDARD-PROCEDURE-FOR-PRICE-ADJUSTMENT.pdf
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
 
Procurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery modelsProcurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery models
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction Project
 
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
 
Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...
 
Performance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projectsPerformance evaluation of design build (d-b) projects
Performance evaluation of design build (d-b) projects
 
Transmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesTransmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission Lines
 
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
D012522433
D012522433D012522433
D012522433
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
Matrix207
Matrix207Matrix207
Matrix207
 

Más de IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

Más de IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Último

Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 

Último (20)

Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 

IRJET- Comperative Analysis of Three Major Type of Contracts with Case Study

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 10 | Oct 2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 237 COMPERATIVE ANALYSIS OF THREE MAJOR TYPE OF CONTRACTS WITH CASE STUDY Abhijit Langhe1, Pravin Minde2 1M.E Student (Construction Management), PVPIT Engineering College, Pune, Maharashtra, India. 2Assistant Professor, Dept. of Civil Engineering, PVPIT Engineering College, Pune, Maharashtra, India. ----------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - The thirteenth FYP shows large interest in investments in infrastructure sector by India, so there is need for different types of contract that will satisfy the purpose. Engineering, procurement and construction (EPC) contracts are on the way to become the most usual form of contracting applied by the private sector to undertake construction works on large scale infrastructure projects like roads, telecommunication, petroleum, real estate etc. In every project, it is necessary to have good contract management in place; otherwise it can have negative consequences for all parties involved – the client, contractor, lenders, government, etc. Here the contractor carry’s out the designs of project, procure materials and equipment’s required as per the specifications and delivers the project in agreed duration of time. If contract management is not implemented and controlled properly, it may have a negative impact on the project as a whole. Such failures may include a delayed schedule, cost overruns, quality, safety and more. It was also found that the EPC contracting scheme could work very well, especially in the cases where the contractor is in a good position to understand all legal aspects of the contract, including the allocation of risks. A comparative study between PPP, Item Rate and Lump-Sum mode of contract will enable to know the feasible mode of contract in India. It lists certain advantages, disadvantages and their need in contract. Key Words: Contracts, EPC Contract, Lump-Sum Contract, Item Rate Contract, Contract Comparison. Construction industry is rapidly growing and therefore requires various models of contracting. For mega infrastructure projects a flexible and effective method is needed. Engineering Procurement Construction (EPC) contract is a popular type of contract for infrastructure and power projects. EPC contractors carryout designs, procure the material and equipment’s as per the specifications and deliver the project in stipulated time. Following factors areconsideredtomeasurethe executionof project. Time, Cost, Quality, Cost-overrun, Time- overrun, Unit cost of building, Rate of construction, Client satisfaction EPC contracts will continue to be the predominant form of construction contract and will be used on large scale infrastructure projects in most jurisdiction. EPC contracts vary on the basis of the assignment of responsibility and related penalties. 2. LITERATURE REVIEW:- AccordingtoAshwini Wadedwer,ShreedharPatil (December 2015). The PPPs are good projects which deliver value for money when they are toll financed. The design and construction risk to private partners. TheEPCcontractplays vital role in infrastructure development. Due to investment of private partners in PPP, risk ismore to private sector, mainly to the lenders or financerswhichgoes into bad loans and delay in project completion. Because of these risk factors nowadays there is low interest from the investors in PPP. Therefore government is moving towards the EPC mode as it has fixed time limit with fixed cost. 3. OBJECTIVE:- 1. To determine most suitable type of contract for construction of flyover/road. 2. To compare three different types of contracts of same organization. 3. To identify factors causing loss or profit of project. 4. METHODOLOGY:- Fig-1 Methodology Flow Chart 1. INTRODUCTION
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 10 | Oct 2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 238 5. CASE STUDY'S:- Case study 1:-  Department:- Maharashtra State Road Development Corporation Limited Mumbai.  Name of Work:- Construction of elevated structure, ROB and service roads of NH-4fromKm24.500toKm 25.570 in the state of Maharashtra under EPC mode.  Type of Contract:- Engineering, Procurement and Construction (EPC) Contract  Length in Km:- 1.07 Km  Completion Period:- 18 Months  Estimated Tender Cost:- Rs. 46.1246 Crore Case Study 2:-  Department:- Public Works Department (PWD)  Name of Work:- Construction of Flyover From College of Engineering Pune to Patil Estate, Pune (Balance Work)  Type of Contract:- Item Rate Contract  Length in Km:- 0.80 Km  Completion Period:- 15 Months  Estimated Tender Cost:- Rs.21.83 Crore Case Study 3:-  Department:- Pune Municipal Corporation  Name of Work:- Construction of ROB between S. No. 89 & 71 at Mundhawa Over Pune Solapur Railway line on24.0 Mtr. HCMTR.  Type of Contract:- “C” Form (Lump – sum Contract)  Completion Period:- 24 Months  Estimated Tender Cost:- Rs. 25.87 Crores 1. EPC Contract:- EPC contract carryoutdesignsofproject, procure equipment’s and materials required as per the specifications and deliver the project within the specified period of time. I. Types of EPC contract: a. Single document. b. Privately negotiated. c. Tendered out. d. Issued under nomination basis. e. Multiple documents. f. Single document. g. Lumpsum price. h. Fixed price. II. Suitability:- For mega infrastructure projects a flexible and effective method is needed. Engineering Procurement Construction (EPC) contract is a popular type of contract for infrastructure and power projects. EPC contractorscarryout designs, procure the material and equipment’s as per the specifications and deliver the project in stipulated time. III. Advantages:- a. Reduced total time during the contractual process by having just one process. b. A seemingly “lower cost” when integrating “all” the elements under one provider. c. The main advantage of this service is the peace of mind the owner gets when it hands over full responsibility of the project to “only one contractor”, itis much easier for the owner to manage and communicate with one provider, which means “one neck to choke”. d. EPC minimizes the owner’s risks. e. EPC for mega projects is more flexible and efficient delivery method. IV. Disadvantages:- a. A higher cost is assumed due to the higher risk that comes with total responsibility, there is less information toprepareproposalsandthereforebidders assume more risks. b. There is a greater disparity when comparing offers, both economically, because each providerhasdifferent criteria for assessing the risk. c. Usually designs are oversizedduetolack ofinformation available at the time when the offer is being prepared. 2. Item Rate Contract:- It is also called a schedule contract, in this contract, the contractor undertakes the execution of work on an item rate basis. The amount to bereceivedbythe contractor, depends upon the quantities of various items of work actually executed. The payment to the contractor is made on the basis of detailed measurements of different items of work actually done by him. I. Suitability:- The item rate contract is most commonlyusedforall typesof engineering works financed bypublicorgovernmentbodies. This type of contract is suitable for works which can be split into various items and quantities under each item can be estimated with accuracy. II. Advantages:- a. There is no need for detailed drawingsatthetimeof allotting contract as in the case of lump sum contract. The 6. ADVANTAGES AND DISADVANTAGES OF CONTRACTS:-
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 10 | Oct 2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 239 detailed drawings can be prepared after the contract is awarded. b. Changes in drawings and quantities of individual items can be made as per requirement within agreed limits. c. The payment to the contractor ismadeontheactual work done by his at the agreed rates. a. The total cost of work can only be known upon completion. As such, the owner may incur financial difficulty if the final cost increases substantially. b. Additional staff is required to take detailed measurements of work done for releasing payments to the contractor. I. Suitability:- A lump sum contract is more suitable for works for which contractors have prior construction experience. This experience enablesthecontractorstosubmit a morerealistic bid. This type of contract is not suitable for difficult foundations, excavationsofuncertaincharacter,andprojects susceptible to unpredictable hazards and variations. a. The owner can decide whether to start or shelve the project knowing the total lump sum price quoted by different contractors. b. The contractor can earn more profit by in depth planning and effective management site. c. Since the contractor has accepted a fixed price for the construction, the owner is not liable for any over expenditure. This is the most important benefit. d. It is much simpler to get construction loan with a Lump sum contract as it provides a high degree of certainty as far as cost is concerned. e. It is much easier to supervise and manage Lump sum contracts. III. Disadvantages:- a. Quantifying changes is a big challenge. Suchcontracts demand documentationand recordkeepingofchange orders at all stages that further requires more paperwork. b. Lump sum contracts pose greater risk to contractor. c. The overall constructioncompletioncouldtakelonger than other contractual alternatives. d. Since the contract is based on fixed price, the contractor may start using sub-standard means and methods and products. In such a case, the owner should specify building materials well in advance. e. Lump-sum contracts usually end up with higherfixed price to cover unforeseen circumstances. Owners are responsible for unpredicted conditions which are beyond the control of either party. 7. DATA ANALYSIS:- Site Dehu Road COEP Mundhawa Type of Contract EPC Contract Item Rate Contract Lump-Sum Contract Cost Project amount and scope of work is fixed. Extra claim can be done but not easily applicable, as the scope is defined Project amount is given by the client. Extra claim can be done as per work executed. In this case the project amount is fixed and extra claim can be as per the work executed Feasibility Work can be started when the land is acquired more than 90%. Work can be started even if minimum land is acquired i.e. 25%. Work can be started when more than 50% of land is available to the contractor. Time Overrun Easily time extension is not available as the scope and the amount of the project is fixed. Time beyond the scope of work is available and can get the time extension depending on the work. Time is defined but time extension can get according to valid reasons. Cost Overrun In this type of project cost is Causes of cost overrun: Causes of cost overrun: III. Disadvantages:- 3. Lump-Sum Contract:- In this type of contract, the contractor offers to do the whole work as shown in drawings and described by specifications, for a total stipulated sum of money. There are no individual rates quoted, thus it becomes difficult to make adjustments in the contract value if any changes are to be made in the work later on. The schedule of different items of work is not provided and the contractor has to completethework as per drawings and specifications for the agreed lump sum amount. II. Advantages:-
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 10 | Oct 2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 240 according to tender only. But due if some extra work is carried out i.e. utility shifting, escalation additional amount can be obtained from the client. i) Basic Cost ii) Escalation due to delay iii) Extra Items iv) Claims i) Tender Cost ii) Escalation iii) Extra Items iv) Claims 8. SOME MAJOR EPC COMPANIES IN INDIA:- Segment EPC Company Construction residential/ commercial 1. Larsen and Tourbo Ltd. 2. Shapoorji Pallonji and Co. Ltd. 3. B.G. Shirke Construction Technology Pvt. Ltd. 4. Man Infra Construction Ltd. 5.Supreme Infrastructure India Ltd. Infrastructur e/general contracting 1. Hindustan Construction Co. Ltd. 2. Gammon India 3. Simplex Infrastructure Ltd. 4. Gayatri Projects Ltd. 5. Nagarjuna Construction Ltd. 9. CONCLUSIONS:- a. In EPC contract single contractor is appointed by the owner for all kinds of construction works. The major difference between lump sum and EPC isthat,inEPCthe contractor has the responsibility of design and construction. b. Where as in lump sum contract the designanddrawings are prepared by the technical team of the owner. c. The EPC contractor hands over a working facility that’s ready to go. A design-build contract closes out similarly to design-bid-build contracts, with the owner and its construction manager or designer taking an active role in punching out the facility. d. Design-build contracts tend to take either a traditional design-bid-build approach to unknownslikehiddensite conditions, or to share that risk between the owner and the design-builder. In contrast, it’s not uncommon for EPC contracts to shift these risks entirely to the EPC contractor. e. Understanding the differences between these two seemingly quite similar design processes is a key step when assessing which delivery system is right for your project. REFERENCES 1) Ashwini Wadedwer, Shreedhar Patil (December 2015), "Comparative Study between PPP Mode of Contracts and EPC Mode of Contracts" 2) Rahul Bali and Prof. M.R Apte (February 2014), "Risk Management in EPC Contract - Risk Identification” 3) Benyamin Sadeghi, Mohammad Mehdi Mortaheb and Hamed Kashani, "Identification of Recurring EPC Contract Risks and Mitigation Strategies" 4) Phil Loots and Nick Henchie (November 2007),"Worlds Apart: EPC and EPCM Contracts: Risk issues and allocation" 5) Abhishek Raj Singh, Dr. Sanjay Tiwari (July 2015), " EPC: An Innovative Tool for Mega Project Construction" 6) Soroush Hejazi Kia, Ahmad Reza Tohidi (March 2015), " Risk Allocation in Engineering Construction Contracts" 7)Christopher Marato Gofhamodimo, "Construction Contracts" https://www.scribd.com/document/371256964/icm1999- 03