International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4319
“Factors Influencing Time and Cost Overruns
In Indian Construction Projects”
Mohammad Mujeeb Ur Rehman Bhat 1
1 M.Tech ( Construction Technology and Management) Maharaja Ranjit Singh Punjab Technical University, Bathinda,
Punjab.
---------------------------------------------------------------------***---------------------------------------------------------------------
ABSTRACT
The construction industry is an important industry at both the global level and national level. It provides huge
employment to the people and plays very significant role in country economy. Delay is one of the most
common problems in the construction industry. Time and cost overruns are a result of delays in project
execution. Project overrun is a serious economic problem in the developing countries where the project
implementation takes place in the face of many uncertainties. It wastes away financial resources, delays the
development process and also makes construction costlier. With increasing globalization and technology driven
economic growth all over the world, a scientific and systematic approach to project management becomes
imperative to ensure that project objectives are attained within the constraints of time, capital and other
resources. But with the increasing demand, the projects with time and cost overruns are also increasing. Time
and cost are the two major elements in project management, apart from quality and scope. One of the biggest
challenges in the management of construction project or to one of the project manager is to ensure that the
project is completed on time and within estimated cost.
The present study deals with analysing the factors of time and cost overrun of Indian projects. The study is well
supported by a case study and a questionnaire survey conducted for the Indian projects. According to the study
conducted, various factors are taken into account and ranked as significant and more significant factors according to
its impact onconstructionproject. The factors which play a significant role are given more preference rather than the
others according to the study. Hence, effective project planning, controlling and monitoring should be established to
enhance project performance in order to minimize or avoid time overrunandcostoverrunproblemsinIndia.Thecase
study is judged using a project management scheduling chart and is well represented into differentiable charts.
KEY WORDS – Time Overrun, Cost Overrun, Project Management, Construction Industry
1. INTRODUCTION
1.1 Time and Cost Overruns In India
One of the main objectives and policies of any public or private sectors dealing with the execution of projects is to
upgrade projects performance, through reduction of costs, completion of projects within their assigned budget and
time constraints, and improve quality. Construction industry in India is suffering from many problems which affect
time, cost and quality, these factors related to political situation and techniques used in India, these problems are
summarized as following:
• Large number of workers in comparison to the number of projects (the large number of unemployedlabourin
India);
• Borders closure and shortage of materials in markets;
• Dependency on obtaining of equipment from other countries
• Continued increase in material prices;
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4320
• Dependency on donor countries to get the fund;
• Unstable economic situation;
• Unstable political situation.
These factors above and others contributed to large proportion in making many problems in construction industry
which usually related to time and cost overruns.
Delay of project and cost overruns in India is one of most important problems at construction management field. Also
study and study in this field are few compared to worthy expected results, despite the importanceandthesignificance
of the construction sector in India. It is noted that the parties of project (owner, consultant, and contractor) don’t give
the time and cost overruns the importance at the evaluation at the end of project.
This shortage of time and cost overruns control may be as a result of:-
• Lack of knowledge and awareness about project performance.
• The distribution of delayandcostoverrunsresponsibilitiesbetweenthethree parties(contractors,consultants
and owners).
• Political conditions also serve as one of the main factor.
The problem of projects delay and cost overruns can nearly be noticed in every project at India indicating that this
problem didn't receive enough attention by both studies and responsible authorities.
1.2 Project aim
The aim of this project is to assess factors influencing time and cost overruns on construction projects in India.
1.3 Project objectives
1. To identify variables influencingconstructiontimeandcostoverrunsandtoevaluatetheirrelativeimportance.
2. Investigate the collective group perspectives on the relative significance of these factors from owner,
consultant, and contractor point view.
3. To evaluate the magnitudes of the time delay, and cost increases.
4. To evaluate the degree of agreement /disagreement regarding the ranking of these factors.
5. To conduct practical case study on a building site.
6. To formulate recommendations for improving construction performance.
1.4 Project Approach
It involves the assessment of factors influencing time and cost overruns on construction projects in India. The
objectives of the study were decided to be achieved through a two-staged approach.
First Stage
 Factors influencing time and cost overruns in construction projects in India will be first
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4321
examined and identified.
 This will be done through a relevant literature review and by conducting a pilot study that
sought advice from experienced construction practitioners.
 We will also intend to develop a questionnaire/ survey to assess the perceptions of owners,
consultants, and contractors.
Second Stage
 It is intended to carry out case study after carefully selecting and investigating them.
 These cases will give in-depth information regarding the causes of time and cost overruns at
these sites and also check the procedures and actions taken by contractors, owners and
consultants.
 Each case will be analysed separately.
 Hence we intend to illustrate the link between the data collected by questionnaire and data in case study and
also recommendations will be documented for each
1.5 Limitations and Assumptions
This study included the following limitations:
 The study included the factors influencing time and cost overruns in India only.
 Literature on delay and cost overruns in India is very limited.
2. Causes of time and cost overruns
2.1 Causes of time overruns (delay)
Time overruns (delays) can be divided into three categories:
1. Those over which neither party to the contract has any control;
2. Those over which the owner (or his/her representative) has control;
3. Those over which the contractor (or any subcontractor) has control.
The predominant factors influencing time overruns/delays are design changes, poor labour productivity, inadequate
planning and resource shortages.
2.2 Causes of cost overruns
Previous study has attempted discover reasons for the disparity between the tender sum and the final account. This
sectionidentifies the factors that influence cost overruns. Four factors were identifiedfromtheexistingstudyfindings
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4322
Morris et al (1990), Kaming et al (1997) and Chimwaso (2001). These are; design changes, inadequate planning,
unpredictable weather conditions; and fluctuations in the cost of building materials.
The factors are divided into two groups of seven critical factors and nine other factors, which are usually ignored, but
perceived to be of equal significance.
2.3 List of critical factors
1. Incomplete design at the time of tender.
2. Additional work at owner's request.
3. Changes in the owner's briefing
4. Lack of cost planning/monitoring during pre-and-post contract stages.
5. Site/poor soil conditions.
6. Adjustment of prime cost and provisional sums.
7. Re-measurement of provisional works.
8. Logistics due to site location.
9. Lack of cost reports during construction stage.
2.4 List of other factors, which are usually ignored
1. Delays in issuing information to the contractor during construction in delays.
2. Technical omissions at design stage.
3. Contractual claims, such as, extension of time with cost claims.
4. Improvements to standard drawings during construction stage.
5. Indecision by the supervising team in dealing with the contractor's queries in delays.
6. Delays in costing variations and additional works.
7. Omissions and errors in the bills of quantities.
8. Ignoring items with abnormal rates during tender evaluation, especially items with provisional quantities.
9. Some tendering manoeuvres by contractors, such as front-loading of rates.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4323
Table 1 - Variables influencing time and cost control
(Chan et al (2002), Alwi et al (2002), Assaf (2006)
Variables of delays and cost controls
 Environment restriction
 Experience of project location
 Accurate prediction of equipment production rate
 Equipment availability
 Experience of local regulation
 Weather conditions
Variables of time controls
 Build ability
 Labour productivity
 Level of planning
 Material availability
 Accuracy of materials estimate
 Accurate prediction of craftsmen production rate
 Skilled labour availability
 Locational restriction of the project
Variables of cost controls
 Inflation of material cost
 Accurate quantity take-off
 Experience of project type
Table 2 Factors affecting time and cost overrun according to different designation
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4324
Category Factor
Owner Finance and payments of completed work.
Owner interference.
Slow decision-making by owners.
Unrealistic imposed contract duration.
Contractor Subcontractors.
Site management.
Construction methods.
Improper planning.
Mistakes during construction.
Inadequate contractor experience.
Consultant Contract management.
Preparation and approval of drawings.
Quality assurance/control.
Waiting time for approval of tests and
inspections.Material Quality of material.
Shortage in material.
Labour and equipment Labour supply.
Labour productivity.
Equipment availability and failure.
Contract Change orders.
Mistakes and discrepancies in contract
documents.Contractual relationships Major disputes and negotiations.
Inappropriate overall organizational
structure linkingLack of communicationbetweentheparties.
External factors Weather condition
Regulatory changes and building Code
Problems with neighbours.
Unforeseen ground conditions
3. STUDY METHODOLOGY
3.1 Questionnaire
A questionnairewasdevelopedtoassesstheperceptionsofowners,consultants,andcontractorsduetotheimportance
index of causes and effects of delay in India construction industry. Factors influencing time and cost overruns in
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4325
construction projects in India were first examined and identified through a relevant literature review and by
conducting a pilot study that sought advice from experienced construction practitioners.
3.2 Questionnaire design
It has been assembled around of (85) factors which affect the time andcostoverrunsinengineeringprojectsinvarious
countries around the world and at intervals of time, but not all of these factors are consistent with the conditions and
circumstances surrounding the India from economic level, the type of projects, geographical region and occupation
factors which experienced the India, so it has been selected factors commensurate with 52 the nature of construction
projects and problems in the India. Modifications and new questionsthenaddedasaresultofinterviewofexperienced
construction managers to suit the local construction industry in India.
Method adopted for stage 1:- Decision Matrix
3.3 Decision Matrix
Introduction
A decision matrix is a list of values in rows and columns that allow an analyst to systematically identify, analyze, and
rate the performance of relationships between sets of values and information. Elements of a decision matrix show
decisions based on certain decision criteria. The matrix is useful for looking at large masses of decision factors and
assessing each factor’s relative significance. Decision matrix is used to describe a multi-criteria decision analysis
(MCDA) problem.
Description
A decision matrix is a chart that allows a team or individual to systematically identify, analyze, and rate thestrengthof
relationships between sets of information. The matrix is especially useful for looking at large numbers of decision
factors and assessing each factor’s relative importance.
Uses
A decision matrix is frequently used during quality planning activities to selectproduct/servicefeaturesandgoalsand
to develop process steps and weigh alternatives. For quality improvement activities, a decision matrixcanbeusefulin
selecting a project, in evaluating alternative solutions to problems, and in designing remedies.
3.4 Decision matrix/selection matrix approach for analysis-
Identify alternatives
Depending upon the team’s needs, these can be product/service features, process steps, projects, or potential
solutions. List these across the top of the matrix.
Identify decision/selection criteria
These key criteria may come from a previously prepared affinity diagram or from a brainstorming activity.Makesure
that everyone has a clear and common understanding of what the criteria mean. Also ensure that the criteria are
written so that a high score for each criterion represents a favourable result and a low score represents an
unfavourable result. List the criteria down the left side of the matrix.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4326
Assign weights
If some decision criteria are more important than others, review and agree on appropriate weights to be assigned.
Design scoring system
Before rating the alternatives, the team must agree on a scoring system. Determine the scoring range and ensure that
all team members have a common understanding of what high, medium, and low scores represent.
Rate the alternatives
For each alternative, assign a consensus rating for each decision criterion. The team may average the scores from
individual team members or may develop scores through a consensus-building activity.
Summation of scores
Multiply the score for each decision criterion by its weighting factor. Then total the scores for each alternative being
considered and analyze the results.
4. CASE STUDY
4.1 Introduction
These cases discussed in-depth information regarding the causes of time and cost overruns atconstructionprojectsin
India, also to check the procedures and actions taken by contractors, owners and consultants. Each case will be
analysed separating of others, the case will illustrate the link between the data collected by questionnaire and data in
case, recommendations will be documented for each case.
In the first stage we developed a questionnaire to assess the perceptions of owners, consultants, and contractors.
Factors influencing time and cost overruns inconstructionprojectsinIndiawerefirstexaminedandidentifiedthrough
a relevant literature review and by conducting a pilot study that sought advice from experienced construction
practitioners.
In the second stage of the project we did a case study after carefully selecting and investigating it. This case study will
give in-depth information regardingthecausesoftimeandcostoverrunsatthesitesandalsochecktheproceduresand
actions taken by contractors, owners and consultants.
The case study will be supported with the projectmanagementchartandanalysingpaposedchartalongwiththeactual
executed work and reasons for the detail.
4.2 Site details
Description
Gujarat Urban Development Authority has undertaken an extensive program of Constructionof2016DwellingUnit
under SEWS housing scheme in various T.P. schemes in the jurisdiction of GUDA Area. The Construction of
involves the major activity of Civil Work, Water supply, Sanitary, Plumbing work & Electrical Works.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4327
4.2.1 Site Information
 Construction of 2016 dwelling units under SEWS housing scheme.
 Under the observation of GUDA.
 Per flat Built up Area: - 36.75 sq. m.
 No of Units per Floor: - 8
 No of Floors: - G+3
 7km from railway station.
 Height of building from ground floor to parapet:- 12.49m
 Length of building :- 28.5m
 Breadth of Building :- 15.30m
 Built up Area :- 386.05sq m
 Cost of the Project :- Rs 83,26,80,818/-
 Total no of blocks:- 63 blocks
 The project is divided into three phases - Phase 1, Phase 2, and Phase 3.
 Currently the work in phase 1 has started which is a site of 26.68cr. Sites of phase 2 and 3 are yet to be started.
 The work which is completed till date is of 9 blocks which includes complete sub-structure.
5. RESULT AND DISCUSSION
5.1 Result of Questionnaire Survey using decision matrix
 Using the decision matrix out of 85 factors the following factors were categorized among the moderately
significant factors and very significant factors.
(Graph: 1)
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4328
Moderately Significant Factors (Greater than 50%)
1. Inappropriate type of contract used (E.g. traditional, design- and- build, etc.).
2. Slow information flow between project team members.
3. Insufficient number of staff (contractor).
4. Finding appropriate sub–contractors.
5. Low productivity and poor distribution of labour.
6. Lack of subcontractor's skills.
7. Poor site management.
8. Equipment and tool shortage on site.
9. Uncompromising attitude between parties.
10. Low harmony between technician team of contractorandconsultantwhichmayleadtocontroversiesbetween
both of them.
11. Unethical behaviours used by contractors to make high profit.
12. Dependence on an inexperienced engineer to bear the all responsibilities of the site.
13. Absence of consultant's site staff.
14. Lack of technical and managerial skills of staff which leads to delay in giving instruction.
15. Bad contract management by the consultant.
16. Lack of quality assurance / control.
17. Delays in payment and material approval.
18. Lack of problem discussions.
19. Market reputation of the consultant.
20. Contract modifications (replacement and addition of new work to the project and/or change in the
specifications).
21. Owner – initiated variation and/or interference.
22. Unrealistic contract durations imposed by owner.
23. Lack of urgency/priority on part of the owner.
24. High quality of work required.
25. Owner delay in freeing the financial payments.
26. Poor provision of information to project participants.
27. Inadequate managerial skills for all parties.
28. Lack of follow up for the project schedule and absence of continuous tracking.
29. Poor judgment in estimating time and resources
30. Slow inspection and testing procedure used in project.
31. Unclear specifications.
32. Slow drawing revision and distribution.
33. Incomplete drawings.
34. Not using systematic procedures.
35. Delays in design work / lack of design information.
36. Shortage and Delay of material delivery to site.
37. Poor material handling on site.
38. Price escalation of materials and for manpower.
39. Shortage of site workers.
40. Inappropriate overall organizational structure linking- all parties to the project.
41. Mistakes and discrepancies in contract documents.
42. Inappropriate type of contract used.
43. Poor site conditions (location, ground, etc.).
44. Poor economic conditions (currency, inflation rate, etc.).
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4329
E.S.(100%) 5 42%
V.S.(75%) 2 17%
M.S.(50%) 1 8%
S.S.(25%) 3 25%
N.S.(0%) 1 8%
E.S. (100%)
E.S. (100%)
3
3
25%
25%
V.S. (75%) 6 50%
M.S. (50%) 1 8%
S.S. (25%) 2 17%
N.S. (0%)
(0%)
0 0%
45. Design changes.
46. Lack of coordination at design phase.
47. Additional work at owner’s request.
48. Lack of cost planning/monitoring during pre and post-contract stages.
49. Improvements to standard drawings during construction stage.
50. Delay in construction, supply of raw materials and equipment by contractors.
51. Change in the scope of the project i.e. in government policies, etc.
52. Delay in preliminary handing over of project.
Very Significant Factors (Greater than 75 %)
1. Paper work – Recording and Maintenance of data
2. Cash inflow and outflow
3. Inadequate construction planning and decision making
4. Skilled labour shortage
5. Building regulations
6. Bureaucracy in Government agencies
7. Attracting skilful technicians for work
The following graphs shows the very significant factors :- (Graph 2)
 Paper work – Recording and Maintenance of data
 Cash Inflow and Outflow
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4330
E.S.(100%) 5 42%
V.S.(75%) 3 25%
M.S.(50%) 0 0%
S.S.(25%) 1 8%
N.S.(0%) 3 25%
E.S.(100%) 1 8%
V.S.(75%) 7 58%
M.S.(50%) 0 0%
S.S.(25%) 4 33%
N.S.(0%) 0 0%
E.S.(100%) 4 36%
V.S.(75%) 2 18%
M.S.(50%) 2 18%
S.S.(25%) 1 9%
N.S.(0%) 2 18%
E.S.(100%) 4 36%
V.S.(75%) 4 36%
M.S.(50%) 2 18%
S.S.(25%) 1 9%
N.S.(0%) 0 0%
 Inadequate construction planning and decision making
 Skilled labour shortage
 Building regulations
 Bureaucracy in Government agencies
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4331
E.S.(100%) 2 17%
V.S.(75%) 6 50%
M.S.(50%) 2 17%
S.S.(25%) 2 17%
N.S.(0%) 0 0%
 Attracting skilful technicians for work
5.2 Cash Flow Analysis
 The complete project is for 18 months .
 The company started with 7% of cost of project as cash in hand for the site activities
 The security deposit for the complete project is 5% of the project cost.
 We have proposed a cash flow analysis data for the company project which would give 16% profit of the
cost of project as the end of time limit for the project .
6. CONCLUSION
6.1 Conclusion and discussion
This chapter includes the conclusions and recommendations that would help in solving the problem of delay and cost
overruns at construction projects in India. The first objective of this study was to identify variables influencing
construction time and cost overruns. The second objective was to evaluate their relative importance. Investigate the
collective group perspectives on the relative significance of these factor from owner, consultant, and contractor point
view was the third objective. The fourth one was to evaluate the degree of agreement /disagreement regarding the
ranking of these factors. The fifth objective was to evaluate the magnitudes of the time delay, and cost increases. The
sixth objective was to conduct case study, and thelastonewastoformulaterecommendationstoimproveconstruction
performance.
According to the questionnairepreparedsevenfactorswhichwereanalyzedasverysignificantfactors. Thefactorsplay
and important role accordingtotheowners,consultantandcontractorpointofview.Thesefactorsareconsideredtobe
the most important factors for any Indian construction project.
Very Significant Factors (Greater than 75 %)
1. Paper work – Recording and Maintenance of data
 This factor plays an important role while analyzing the project details and its characteristics.
2. Cash inflow and outflow
 The amount of money involved in the project is the key for any work to be executed.
3. Inadequate construction planning and decision making
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4332
 The steps to be followed while the work of construction and from the first step to the completion is to in the
balanced manner between time and costing
4. Skilled labour shortage
 The type of labour determines the speed and accuracy in the work through which the work is appreciated and
even the companies reputation is judged.
5. Building Regulation
 The construction work should be into the building regulations as per the government so that there is no
problem in the future for the peoples using it.
6. Bureaucracy in Government agencies
7. Attracting skilful technicians for work
6.2 Recommendation
Using the factors which we have analyzed we have proposed the very significant and significant factors which are
considerable for the Indian construction projects.
The case study which we have done is for a building construction project of (G+3 ) floors. The estimated time for the
project is 18 months but currently due to some reasons the project has been delayed by 32 days. The reasons of the
delays are due to two main reasons. Firstly the work order which was to be issued by the government was delayed by
20 days by them and secondly the mobilization of the skilled labour took 6 days more than the project.
 The number of skilled labour can be judged primarily and the mobilization work should be started early.
 The relationship between consultant ,client and owner should be conducive for the successful completion of
project.
 The tine duration set for a project should include the days wasted on account of natural calamities, health of
labour, accidents or any unavoidable reasons which in turn can cause extension of project.
 The work executed should be upto the mark so that the bills through the government does not stop and the
rotation of work continues.
 Delay in technical as well as administrative decisions by the HOD' s of the executing agency.
 Approval of plans/designby a non-technical person(in case the HODofthe projectauthorityisanontechnical
person).
 Leaving site unattended by senior engineers.
 Off and on visits of Politicians to the sites.
 Day to day monitoring of the site.
 Details of drawing should be freezed before starting the actual work.
 External agencies should be fixed in advance.
 Brought out items should be ordered and finalized in the beginning of job.
 Possession of the complete site should be given to the external agency
 Man power and machinery to be planned properly.
 Raw materials should be well stocked before the incoming of the monsoon season.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4333
REFERENCES
 Ram Singh (2009), “Delays And Cost Overruns In Infrastructure Projects: An Enquiry IntoExtents, Causes And
Remedies”, Working Paper No. 181, Department Of Economics, Delhi School Of Economics , UniversityOfDelhi
 Dr. Chinedu Chidinma Nwachukwu And Fidelis I. Emoh (2011), “Building Construction Project Management
Success As A Critical Issue In Real Estate Development And Investment”AmericanJournalofSocial Mgmt.Sci.,
2011, 2(1): 56-75
 Khyomesh V.PatelAndChetnaM.Vyas(2011),“ConstructionMaterialsManagementOnProjectSites”,National
ConferenceOnRecentTrendsInEngineering&Technology,B.V.M.EngineeringCollege,V.V.Nagar,Gujarat,India
 Henry A. Odeyinka, Ammar Kaka And Roy Morledge (2003), An Evaluation Of Construction Cash Flow
Management Approaches In Contracting Organisations, Annual Association Of Researchers In Construction
Management (Arcom)Conference , The University Of Brighton.
 Vidalis, M.S and Najafi, T.F., 2002, Cost and Time Overruns In Highway Construction, 4th Transportation
Specially Conference of the Canadian Society for Civil-Engineering, Montreal, Quebec,CanadaJune5-8(2002).
 Ahmed,S. M. Azhar, S., Kappagantula, P., and Gollapudi, D., 2003. Delays in: A brief study of the Florida
construction industry. Proceeding of the 39th Annual Conference of the Associated Schools of Construction.
Clemson, South Carolina: Clemson University. Final report, Miami, F1 33174, USA.
 Alaghbari, M.W, Razali A. Khadir, Salim Azizah and Ernawati., 2007. The significant factors causing delay of
buildingconstructionprojectsinMalaysia.JournalofEngineering,ConstructionandArchitecturalManagement,
Vol.14, No.2, No. 8, PP. 192-206.
 Al-GahtaniK.andMohanS.,2007,Totalfloatmanagementfordelayanalysis,JournalofCostEngineering,Vol.49,No.
2, pp. 32-37.
 Morris S., 1990, Cost and time overruns in public sector projects. Economic and
Political weekly, Nov.24,1990, Vol. xxv, No.47, PP. M 154 to M 168.
 Cash flow analysis of construction projects, St. John’s, Newfoundland and Labrador /St.John’s,Terre-Neuveet
Labrador May 27-30, 2009 / 27-30 may 2009
 Hyung K. Park, Seung H. Han and Jeffrey S. Russells(2005), Cash flowforecastingmodelforgeneralcontractors
using moving weights of cost categories,
 Dr. Chinedu Chidinma ,Nwachukwu and Fidelis. I. Emoh(2011), Building construction project management
success as a critical issue inreal estate development and investment,
 Alan Twort, Gordon Rees. Civil engineering project management
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4334
 Hamidreza Afshari, Shahrzad Khosravi, Abbas Ghorbanali, Mahdi Borzabadi, Mahbod Valipour,
Identification of causes of non-excusable delays of construction projects ,2010 international conference on
e-business, management and economics IPEDR vol.3 (2011) IACSIT Press, Hong Kong.
 Jomah Mohammed Al-Najjar , factors influencing time and cost overruns on construction projects in the
gaza strip. The Islamic University of Gaza April, 2008.
 www.asce.com
 www.civilengineeringportal.com

Más contenido relacionado

La actualidad más candente

Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
eSAT Journals
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...
IAEME Publication
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurement
IAEME Publication
 

La actualidad más candente (20)

IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurement
 
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
 
IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...
IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...
IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...
 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
 
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
 
Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a review
 
Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...
Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...
Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...
 
IRJET- Identification of Critical Factors Affecting Infrastructure Projec...
IRJET-  	  Identification of Critical Factors Affecting Infrastructure Projec...IRJET-  	  Identification of Critical Factors Affecting Infrastructure Projec...
IRJET- Identification of Critical Factors Affecting Infrastructure Projec...
 

Similar a IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Projects

Similar a IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Projects (20)

IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdf
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projects
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
 
Management For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayManagement For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of Delay
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction Project
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 

Más de IRJET Journal

Más de IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Último

Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Último (20)

22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 

IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Projects

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4319 “Factors Influencing Time and Cost Overruns In Indian Construction Projects” Mohammad Mujeeb Ur Rehman Bhat 1 1 M.Tech ( Construction Technology and Management) Maharaja Ranjit Singh Punjab Technical University, Bathinda, Punjab. ---------------------------------------------------------------------***--------------------------------------------------------------------- ABSTRACT The construction industry is an important industry at both the global level and national level. It provides huge employment to the people and plays very significant role in country economy. Delay is one of the most common problems in the construction industry. Time and cost overruns are a result of delays in project execution. Project overrun is a serious economic problem in the developing countries where the project implementation takes place in the face of many uncertainties. It wastes away financial resources, delays the development process and also makes construction costlier. With increasing globalization and technology driven economic growth all over the world, a scientific and systematic approach to project management becomes imperative to ensure that project objectives are attained within the constraints of time, capital and other resources. But with the increasing demand, the projects with time and cost overruns are also increasing. Time and cost are the two major elements in project management, apart from quality and scope. One of the biggest challenges in the management of construction project or to one of the project manager is to ensure that the project is completed on time and within estimated cost. The present study deals with analysing the factors of time and cost overrun of Indian projects. The study is well supported by a case study and a questionnaire survey conducted for the Indian projects. According to the study conducted, various factors are taken into account and ranked as significant and more significant factors according to its impact onconstructionproject. The factors which play a significant role are given more preference rather than the others according to the study. Hence, effective project planning, controlling and monitoring should be established to enhance project performance in order to minimize or avoid time overrunandcostoverrunproblemsinIndia.Thecase study is judged using a project management scheduling chart and is well represented into differentiable charts. KEY WORDS – Time Overrun, Cost Overrun, Project Management, Construction Industry 1. INTRODUCTION 1.1 Time and Cost Overruns In India One of the main objectives and policies of any public or private sectors dealing with the execution of projects is to upgrade projects performance, through reduction of costs, completion of projects within their assigned budget and time constraints, and improve quality. Construction industry in India is suffering from many problems which affect time, cost and quality, these factors related to political situation and techniques used in India, these problems are summarized as following: • Large number of workers in comparison to the number of projects (the large number of unemployedlabourin India); • Borders closure and shortage of materials in markets; • Dependency on obtaining of equipment from other countries • Continued increase in material prices;
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4320 • Dependency on donor countries to get the fund; • Unstable economic situation; • Unstable political situation. These factors above and others contributed to large proportion in making many problems in construction industry which usually related to time and cost overruns. Delay of project and cost overruns in India is one of most important problems at construction management field. Also study and study in this field are few compared to worthy expected results, despite the importanceandthesignificance of the construction sector in India. It is noted that the parties of project (owner, consultant, and contractor) don’t give the time and cost overruns the importance at the evaluation at the end of project. This shortage of time and cost overruns control may be as a result of:- • Lack of knowledge and awareness about project performance. • The distribution of delayandcostoverrunsresponsibilitiesbetweenthethree parties(contractors,consultants and owners). • Political conditions also serve as one of the main factor. The problem of projects delay and cost overruns can nearly be noticed in every project at India indicating that this problem didn't receive enough attention by both studies and responsible authorities. 1.2 Project aim The aim of this project is to assess factors influencing time and cost overruns on construction projects in India. 1.3 Project objectives 1. To identify variables influencingconstructiontimeandcostoverrunsandtoevaluatetheirrelativeimportance. 2. Investigate the collective group perspectives on the relative significance of these factors from owner, consultant, and contractor point view. 3. To evaluate the magnitudes of the time delay, and cost increases. 4. To evaluate the degree of agreement /disagreement regarding the ranking of these factors. 5. To conduct practical case study on a building site. 6. To formulate recommendations for improving construction performance. 1.4 Project Approach It involves the assessment of factors influencing time and cost overruns on construction projects in India. The objectives of the study were decided to be achieved through a two-staged approach. First Stage  Factors influencing time and cost overruns in construction projects in India will be first
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4321 examined and identified.  This will be done through a relevant literature review and by conducting a pilot study that sought advice from experienced construction practitioners.  We will also intend to develop a questionnaire/ survey to assess the perceptions of owners, consultants, and contractors. Second Stage  It is intended to carry out case study after carefully selecting and investigating them.  These cases will give in-depth information regarding the causes of time and cost overruns at these sites and also check the procedures and actions taken by contractors, owners and consultants.  Each case will be analysed separately.  Hence we intend to illustrate the link between the data collected by questionnaire and data in case study and also recommendations will be documented for each 1.5 Limitations and Assumptions This study included the following limitations:  The study included the factors influencing time and cost overruns in India only.  Literature on delay and cost overruns in India is very limited. 2. Causes of time and cost overruns 2.1 Causes of time overruns (delay) Time overruns (delays) can be divided into three categories: 1. Those over which neither party to the contract has any control; 2. Those over which the owner (or his/her representative) has control; 3. Those over which the contractor (or any subcontractor) has control. The predominant factors influencing time overruns/delays are design changes, poor labour productivity, inadequate planning and resource shortages. 2.2 Causes of cost overruns Previous study has attempted discover reasons for the disparity between the tender sum and the final account. This sectionidentifies the factors that influence cost overruns. Four factors were identifiedfromtheexistingstudyfindings
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4322 Morris et al (1990), Kaming et al (1997) and Chimwaso (2001). These are; design changes, inadequate planning, unpredictable weather conditions; and fluctuations in the cost of building materials. The factors are divided into two groups of seven critical factors and nine other factors, which are usually ignored, but perceived to be of equal significance. 2.3 List of critical factors 1. Incomplete design at the time of tender. 2. Additional work at owner's request. 3. Changes in the owner's briefing 4. Lack of cost planning/monitoring during pre-and-post contract stages. 5. Site/poor soil conditions. 6. Adjustment of prime cost and provisional sums. 7. Re-measurement of provisional works. 8. Logistics due to site location. 9. Lack of cost reports during construction stage. 2.4 List of other factors, which are usually ignored 1. Delays in issuing information to the contractor during construction in delays. 2. Technical omissions at design stage. 3. Contractual claims, such as, extension of time with cost claims. 4. Improvements to standard drawings during construction stage. 5. Indecision by the supervising team in dealing with the contractor's queries in delays. 6. Delays in costing variations and additional works. 7. Omissions and errors in the bills of quantities. 8. Ignoring items with abnormal rates during tender evaluation, especially items with provisional quantities. 9. Some tendering manoeuvres by contractors, such as front-loading of rates.
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4323 Table 1 - Variables influencing time and cost control (Chan et al (2002), Alwi et al (2002), Assaf (2006) Variables of delays and cost controls  Environment restriction  Experience of project location  Accurate prediction of equipment production rate  Equipment availability  Experience of local regulation  Weather conditions Variables of time controls  Build ability  Labour productivity  Level of planning  Material availability  Accuracy of materials estimate  Accurate prediction of craftsmen production rate  Skilled labour availability  Locational restriction of the project Variables of cost controls  Inflation of material cost  Accurate quantity take-off  Experience of project type Table 2 Factors affecting time and cost overrun according to different designation
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4324 Category Factor Owner Finance and payments of completed work. Owner interference. Slow decision-making by owners. Unrealistic imposed contract duration. Contractor Subcontractors. Site management. Construction methods. Improper planning. Mistakes during construction. Inadequate contractor experience. Consultant Contract management. Preparation and approval of drawings. Quality assurance/control. Waiting time for approval of tests and inspections.Material Quality of material. Shortage in material. Labour and equipment Labour supply. Labour productivity. Equipment availability and failure. Contract Change orders. Mistakes and discrepancies in contract documents.Contractual relationships Major disputes and negotiations. Inappropriate overall organizational structure linkingLack of communicationbetweentheparties. External factors Weather condition Regulatory changes and building Code Problems with neighbours. Unforeseen ground conditions 3. STUDY METHODOLOGY 3.1 Questionnaire A questionnairewasdevelopedtoassesstheperceptionsofowners,consultants,andcontractorsduetotheimportance index of causes and effects of delay in India construction industry. Factors influencing time and cost overruns in
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4325 construction projects in India were first examined and identified through a relevant literature review and by conducting a pilot study that sought advice from experienced construction practitioners. 3.2 Questionnaire design It has been assembled around of (85) factors which affect the time andcostoverrunsinengineeringprojectsinvarious countries around the world and at intervals of time, but not all of these factors are consistent with the conditions and circumstances surrounding the India from economic level, the type of projects, geographical region and occupation factors which experienced the India, so it has been selected factors commensurate with 52 the nature of construction projects and problems in the India. Modifications and new questionsthenaddedasaresultofinterviewofexperienced construction managers to suit the local construction industry in India. Method adopted for stage 1:- Decision Matrix 3.3 Decision Matrix Introduction A decision matrix is a list of values in rows and columns that allow an analyst to systematically identify, analyze, and rate the performance of relationships between sets of values and information. Elements of a decision matrix show decisions based on certain decision criteria. The matrix is useful for looking at large masses of decision factors and assessing each factor’s relative significance. Decision matrix is used to describe a multi-criteria decision analysis (MCDA) problem. Description A decision matrix is a chart that allows a team or individual to systematically identify, analyze, and rate thestrengthof relationships between sets of information. The matrix is especially useful for looking at large numbers of decision factors and assessing each factor’s relative importance. Uses A decision matrix is frequently used during quality planning activities to selectproduct/servicefeaturesandgoalsand to develop process steps and weigh alternatives. For quality improvement activities, a decision matrixcanbeusefulin selecting a project, in evaluating alternative solutions to problems, and in designing remedies. 3.4 Decision matrix/selection matrix approach for analysis- Identify alternatives Depending upon the team’s needs, these can be product/service features, process steps, projects, or potential solutions. List these across the top of the matrix. Identify decision/selection criteria These key criteria may come from a previously prepared affinity diagram or from a brainstorming activity.Makesure that everyone has a clear and common understanding of what the criteria mean. Also ensure that the criteria are written so that a high score for each criterion represents a favourable result and a low score represents an unfavourable result. List the criteria down the left side of the matrix.
  • 8. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4326 Assign weights If some decision criteria are more important than others, review and agree on appropriate weights to be assigned. Design scoring system Before rating the alternatives, the team must agree on a scoring system. Determine the scoring range and ensure that all team members have a common understanding of what high, medium, and low scores represent. Rate the alternatives For each alternative, assign a consensus rating for each decision criterion. The team may average the scores from individual team members or may develop scores through a consensus-building activity. Summation of scores Multiply the score for each decision criterion by its weighting factor. Then total the scores for each alternative being considered and analyze the results. 4. CASE STUDY 4.1 Introduction These cases discussed in-depth information regarding the causes of time and cost overruns atconstructionprojectsin India, also to check the procedures and actions taken by contractors, owners and consultants. Each case will be analysed separating of others, the case will illustrate the link between the data collected by questionnaire and data in case, recommendations will be documented for each case. In the first stage we developed a questionnaire to assess the perceptions of owners, consultants, and contractors. Factors influencing time and cost overruns inconstructionprojectsinIndiawerefirstexaminedandidentifiedthrough a relevant literature review and by conducting a pilot study that sought advice from experienced construction practitioners. In the second stage of the project we did a case study after carefully selecting and investigating it. This case study will give in-depth information regardingthecausesoftimeandcostoverrunsatthesitesandalsochecktheproceduresand actions taken by contractors, owners and consultants. The case study will be supported with the projectmanagementchartandanalysingpaposedchartalongwiththeactual executed work and reasons for the detail. 4.2 Site details Description Gujarat Urban Development Authority has undertaken an extensive program of Constructionof2016DwellingUnit under SEWS housing scheme in various T.P. schemes in the jurisdiction of GUDA Area. The Construction of involves the major activity of Civil Work, Water supply, Sanitary, Plumbing work & Electrical Works.
  • 9. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4327 4.2.1 Site Information  Construction of 2016 dwelling units under SEWS housing scheme.  Under the observation of GUDA.  Per flat Built up Area: - 36.75 sq. m.  No of Units per Floor: - 8  No of Floors: - G+3  7km from railway station.  Height of building from ground floor to parapet:- 12.49m  Length of building :- 28.5m  Breadth of Building :- 15.30m  Built up Area :- 386.05sq m  Cost of the Project :- Rs 83,26,80,818/-  Total no of blocks:- 63 blocks  The project is divided into three phases - Phase 1, Phase 2, and Phase 3.  Currently the work in phase 1 has started which is a site of 26.68cr. Sites of phase 2 and 3 are yet to be started.  The work which is completed till date is of 9 blocks which includes complete sub-structure. 5. RESULT AND DISCUSSION 5.1 Result of Questionnaire Survey using decision matrix  Using the decision matrix out of 85 factors the following factors were categorized among the moderately significant factors and very significant factors. (Graph: 1)
  • 10. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4328 Moderately Significant Factors (Greater than 50%) 1. Inappropriate type of contract used (E.g. traditional, design- and- build, etc.). 2. Slow information flow between project team members. 3. Insufficient number of staff (contractor). 4. Finding appropriate sub–contractors. 5. Low productivity and poor distribution of labour. 6. Lack of subcontractor's skills. 7. Poor site management. 8. Equipment and tool shortage on site. 9. Uncompromising attitude between parties. 10. Low harmony between technician team of contractorandconsultantwhichmayleadtocontroversiesbetween both of them. 11. Unethical behaviours used by contractors to make high profit. 12. Dependence on an inexperienced engineer to bear the all responsibilities of the site. 13. Absence of consultant's site staff. 14. Lack of technical and managerial skills of staff which leads to delay in giving instruction. 15. Bad contract management by the consultant. 16. Lack of quality assurance / control. 17. Delays in payment and material approval. 18. Lack of problem discussions. 19. Market reputation of the consultant. 20. Contract modifications (replacement and addition of new work to the project and/or change in the specifications). 21. Owner – initiated variation and/or interference. 22. Unrealistic contract durations imposed by owner. 23. Lack of urgency/priority on part of the owner. 24. High quality of work required. 25. Owner delay in freeing the financial payments. 26. Poor provision of information to project participants. 27. Inadequate managerial skills for all parties. 28. Lack of follow up for the project schedule and absence of continuous tracking. 29. Poor judgment in estimating time and resources 30. Slow inspection and testing procedure used in project. 31. Unclear specifications. 32. Slow drawing revision and distribution. 33. Incomplete drawings. 34. Not using systematic procedures. 35. Delays in design work / lack of design information. 36. Shortage and Delay of material delivery to site. 37. Poor material handling on site. 38. Price escalation of materials and for manpower. 39. Shortage of site workers. 40. Inappropriate overall organizational structure linking- all parties to the project. 41. Mistakes and discrepancies in contract documents. 42. Inappropriate type of contract used. 43. Poor site conditions (location, ground, etc.). 44. Poor economic conditions (currency, inflation rate, etc.).
  • 11. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4329 E.S.(100%) 5 42% V.S.(75%) 2 17% M.S.(50%) 1 8% S.S.(25%) 3 25% N.S.(0%) 1 8% E.S. (100%) E.S. (100%) 3 3 25% 25% V.S. (75%) 6 50% M.S. (50%) 1 8% S.S. (25%) 2 17% N.S. (0%) (0%) 0 0% 45. Design changes. 46. Lack of coordination at design phase. 47. Additional work at owner’s request. 48. Lack of cost planning/monitoring during pre and post-contract stages. 49. Improvements to standard drawings during construction stage. 50. Delay in construction, supply of raw materials and equipment by contractors. 51. Change in the scope of the project i.e. in government policies, etc. 52. Delay in preliminary handing over of project. Very Significant Factors (Greater than 75 %) 1. Paper work – Recording and Maintenance of data 2. Cash inflow and outflow 3. Inadequate construction planning and decision making 4. Skilled labour shortage 5. Building regulations 6. Bureaucracy in Government agencies 7. Attracting skilful technicians for work The following graphs shows the very significant factors :- (Graph 2)  Paper work – Recording and Maintenance of data  Cash Inflow and Outflow
  • 12. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4330 E.S.(100%) 5 42% V.S.(75%) 3 25% M.S.(50%) 0 0% S.S.(25%) 1 8% N.S.(0%) 3 25% E.S.(100%) 1 8% V.S.(75%) 7 58% M.S.(50%) 0 0% S.S.(25%) 4 33% N.S.(0%) 0 0% E.S.(100%) 4 36% V.S.(75%) 2 18% M.S.(50%) 2 18% S.S.(25%) 1 9% N.S.(0%) 2 18% E.S.(100%) 4 36% V.S.(75%) 4 36% M.S.(50%) 2 18% S.S.(25%) 1 9% N.S.(0%) 0 0%  Inadequate construction planning and decision making  Skilled labour shortage  Building regulations  Bureaucracy in Government agencies
  • 13. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4331 E.S.(100%) 2 17% V.S.(75%) 6 50% M.S.(50%) 2 17% S.S.(25%) 2 17% N.S.(0%) 0 0%  Attracting skilful technicians for work 5.2 Cash Flow Analysis  The complete project is for 18 months .  The company started with 7% of cost of project as cash in hand for the site activities  The security deposit for the complete project is 5% of the project cost.  We have proposed a cash flow analysis data for the company project which would give 16% profit of the cost of project as the end of time limit for the project . 6. CONCLUSION 6.1 Conclusion and discussion This chapter includes the conclusions and recommendations that would help in solving the problem of delay and cost overruns at construction projects in India. The first objective of this study was to identify variables influencing construction time and cost overruns. The second objective was to evaluate their relative importance. Investigate the collective group perspectives on the relative significance of these factor from owner, consultant, and contractor point view was the third objective. The fourth one was to evaluate the degree of agreement /disagreement regarding the ranking of these factors. The fifth objective was to evaluate the magnitudes of the time delay, and cost increases. The sixth objective was to conduct case study, and thelastonewastoformulaterecommendationstoimproveconstruction performance. According to the questionnairepreparedsevenfactorswhichwereanalyzedasverysignificantfactors. Thefactorsplay and important role accordingtotheowners,consultantandcontractorpointofview.Thesefactorsareconsideredtobe the most important factors for any Indian construction project. Very Significant Factors (Greater than 75 %) 1. Paper work – Recording and Maintenance of data  This factor plays an important role while analyzing the project details and its characteristics. 2. Cash inflow and outflow  The amount of money involved in the project is the key for any work to be executed. 3. Inadequate construction planning and decision making
  • 14. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4332  The steps to be followed while the work of construction and from the first step to the completion is to in the balanced manner between time and costing 4. Skilled labour shortage  The type of labour determines the speed and accuracy in the work through which the work is appreciated and even the companies reputation is judged. 5. Building Regulation  The construction work should be into the building regulations as per the government so that there is no problem in the future for the peoples using it. 6. Bureaucracy in Government agencies 7. Attracting skilful technicians for work 6.2 Recommendation Using the factors which we have analyzed we have proposed the very significant and significant factors which are considerable for the Indian construction projects. The case study which we have done is for a building construction project of (G+3 ) floors. The estimated time for the project is 18 months but currently due to some reasons the project has been delayed by 32 days. The reasons of the delays are due to two main reasons. Firstly the work order which was to be issued by the government was delayed by 20 days by them and secondly the mobilization of the skilled labour took 6 days more than the project.  The number of skilled labour can be judged primarily and the mobilization work should be started early.  The relationship between consultant ,client and owner should be conducive for the successful completion of project.  The tine duration set for a project should include the days wasted on account of natural calamities, health of labour, accidents or any unavoidable reasons which in turn can cause extension of project.  The work executed should be upto the mark so that the bills through the government does not stop and the rotation of work continues.  Delay in technical as well as administrative decisions by the HOD' s of the executing agency.  Approval of plans/designby a non-technical person(in case the HODofthe projectauthorityisanontechnical person).  Leaving site unattended by senior engineers.  Off and on visits of Politicians to the sites.  Day to day monitoring of the site.  Details of drawing should be freezed before starting the actual work.  External agencies should be fixed in advance.  Brought out items should be ordered and finalized in the beginning of job.  Possession of the complete site should be given to the external agency  Man power and machinery to be planned properly.  Raw materials should be well stocked before the incoming of the monsoon season.
  • 15. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4333 REFERENCES  Ram Singh (2009), “Delays And Cost Overruns In Infrastructure Projects: An Enquiry IntoExtents, Causes And Remedies”, Working Paper No. 181, Department Of Economics, Delhi School Of Economics , UniversityOfDelhi  Dr. Chinedu Chidinma Nwachukwu And Fidelis I. Emoh (2011), “Building Construction Project Management Success As A Critical Issue In Real Estate Development And Investment”AmericanJournalofSocial Mgmt.Sci., 2011, 2(1): 56-75  Khyomesh V.PatelAndChetnaM.Vyas(2011),“ConstructionMaterialsManagementOnProjectSites”,National ConferenceOnRecentTrendsInEngineering&Technology,B.V.M.EngineeringCollege,V.V.Nagar,Gujarat,India  Henry A. Odeyinka, Ammar Kaka And Roy Morledge (2003), An Evaluation Of Construction Cash Flow Management Approaches In Contracting Organisations, Annual Association Of Researchers In Construction Management (Arcom)Conference , The University Of Brighton.  Vidalis, M.S and Najafi, T.F., 2002, Cost and Time Overruns In Highway Construction, 4th Transportation Specially Conference of the Canadian Society for Civil-Engineering, Montreal, Quebec,CanadaJune5-8(2002).  Ahmed,S. M. Azhar, S., Kappagantula, P., and Gollapudi, D., 2003. Delays in: A brief study of the Florida construction industry. Proceeding of the 39th Annual Conference of the Associated Schools of Construction. Clemson, South Carolina: Clemson University. Final report, Miami, F1 33174, USA.  Alaghbari, M.W, Razali A. Khadir, Salim Azizah and Ernawati., 2007. The significant factors causing delay of buildingconstructionprojectsinMalaysia.JournalofEngineering,ConstructionandArchitecturalManagement, Vol.14, No.2, No. 8, PP. 192-206.  Al-GahtaniK.andMohanS.,2007,Totalfloatmanagementfordelayanalysis,JournalofCostEngineering,Vol.49,No. 2, pp. 32-37.  Morris S., 1990, Cost and time overruns in public sector projects. Economic and Political weekly, Nov.24,1990, Vol. xxv, No.47, PP. M 154 to M 168.  Cash flow analysis of construction projects, St. John’s, Newfoundland and Labrador /St.John’s,Terre-Neuveet Labrador May 27-30, 2009 / 27-30 may 2009  Hyung K. Park, Seung H. Han and Jeffrey S. Russells(2005), Cash flowforecastingmodelforgeneralcontractors using moving weights of cost categories,  Dr. Chinedu Chidinma ,Nwachukwu and Fidelis. I. Emoh(2011), Building construction project management success as a critical issue inreal estate development and investment,  Alan Twort, Gordon Rees. Civil engineering project management
  • 16. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4334  Hamidreza Afshari, Shahrzad Khosravi, Abbas Ghorbanali, Mahdi Borzabadi, Mahbod Valipour, Identification of causes of non-excusable delays of construction projects ,2010 international conference on e-business, management and economics IPEDR vol.3 (2011) IACSIT Press, Hong Kong.  Jomah Mohammed Al-Najjar , factors influencing time and cost overruns on construction projects in the gaza strip. The Islamic University of Gaza April, 2008.  www.asce.com  www.civilengineeringportal.com