WORK BREAKDOWN STRUCTURE
SOFTWARE PROJECT MANAGEMENT (SPM)




Work Breakdown Structure of Insurance Survey Portal (ISP)



                    Submitted To:


                    Madam Aasma Abid



                     Submitted By:


                    Abdul-Rehman Aslam
                           (9998)

                      Yasir Mehmood
                           (9994)
Introduction
The Work Breakdown Structure presented here represents all the work required to complete
this project. It helps to easily communicate the work and processes involved to execute the
project. The Project Manager and project team use the WBS to develop the project schedule,
resource requirements and costs




Outline View


1. Insurance Survey Portal

  1.1 Initiation
    1.1.1 Evaluation & Recommendations

    1.1.2 Develop Project Charter

    1.1.3 Deliverable: Submit Project Charter

    1.1.4 Project Sponsor Reviews Project Charter

    1.1.5 Project Charter Signed/Approved

  1.2 Planning
    1.2.1 Create Preliminary Scope Statement

    1.2.2 Determine Project Team

    1.2.3 Project Team Kickoff Meeting

    1.2.4 Develop Project Plan

    1.2.5 Submit Project Plan

    1.2.6 Milestone: Project Plan Approval
1.3 Execution
   1.3.1 Project Kickoff Meeting

   1.3.2 Verify & Validate User Requirements

   1.3.3 Design System

   1.3.4 Procure Hardware/Software

   1.3.5 Install Development System

   1.3.6 Testing Phase

   1.3.7 Install Live System

   1.3.8 User Training

   1.3.9 Go Live

  1.4 Control
   1.4.1 Project Management

   1.4.2 Project Status Meetings

   1.4.3 Risk Management

   1.4.4 Update Project Management Plan

  1.5 Closeout
   1.5.1 Audit Procurement

   1.5.2 Document Lessons Learned

   1.5.3 Update Files/Records

   1.5.4 Gain Formal Acceptance

   1.5.5 Archive Files/Documents
Tabular View


Level 1              Level 2          Level 3
1 Insurance Survey   1.1 Initiation   1.1.1 Evaluation & Recommendations
  Portal                              1.1.2 Develop Project Charter
                                      1.1.3 Deliverable: Submit Project Charter
                                      1.1.4 Project Sponsor Reviews Project Charter
                                      1.1.5 Project Charter Signed/Approved
                     1.2 Planning     1.2.1 Create Preliminary Scope Statement
                                      1.2.2 Determine Project Team
                                      1.2.3 Project Team Kickoff Meeting
                                      1.2.4 Develop Project Plan
                                      1.2.5 Submit Project Plan
                                      1.2.6 Milestone: Project Plan Approval
                     1.3 Execution    1.3.1 Project Kickoff Meeting
                                      1.3.2 Verify & Validate User Requirements
                                      1.3.3 Design System
                                      1.3.4 Procure Hardware/Software
                                      1.3.5 Install Development System
                                      1.3.6 Testing Phase
                                      1.3.7 Install Live System
                                      1.3.8 User Training
                                      1.3.9 Go Live
                     1.4 Control      1.4.1 Project Management
                                      1.4.2 Project Status Meetings
                                      1.4.3 Risk Management
                                      1.4.4 Update Project Management Plan
                     1.5 Closeout     1.5.1 Audit Procurement
                                      1.5.2 Document Lessons Learned
                                      1.5.3 Update Files/Records
                                      1.5.4 Gain Formal Acceptance
                                      1.5.5 Archive Files/Documents
Tree Structure View

Más contenido relacionado

La actualidad más candente

Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Agus Suhanto
 
Top 7 WBS Mistakes Project Managers Make
Top 7 WBS Mistakes Project Managers MakeTop 7 WBS Mistakes Project Managers Make
Top 7 WBS Mistakes Project Managers Makejoshnankivel
 
Project integration management ch 4
Project integration management ch 4Project integration management ch 4
Project integration management ch 4Sammer Qader
 
Project time management
Project time managementProject time management
Project time managementJivan Nepali
 
Project Management Process Groups And Knowledge Areas
Project Management Process Groups And Knowledge AreasProject Management Process Groups And Knowledge Areas
Project Management Process Groups And Knowledge Areasguestfe6ad
 
Why Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and SolutionsWhy Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and SolutionsMichael Krigsman
 
05 project scope management
05  project scope management05  project scope management
05 project scope managementAla Ibrahim
 
Project Management - Foundation
Project Management - FoundationProject Management - Foundation
Project Management - FoundationShabbeer Zafar
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process GroupsBhuWan Khadka
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementMohamed Loey
 
1.3 Schwalbe Ch3(1).ppt
1.3 Schwalbe Ch3(1).ppt1.3 Schwalbe Ch3(1).ppt
1.3 Schwalbe Ch3(1).pptAddayKhan
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycleSAJID ALI RUK
 

La actualidad más candente (20)

Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
 
Top 7 WBS Mistakes Project Managers Make
Top 7 WBS Mistakes Project Managers MakeTop 7 WBS Mistakes Project Managers Make
Top 7 WBS Mistakes Project Managers Make
 
Project integration management ch 4
Project integration management ch 4Project integration management ch 4
Project integration management ch 4
 
Project quality management
Project quality managementProject quality management
Project quality management
 
Project time management
Project time managementProject time management
Project time management
 
Project Management Process Groups And Knowledge Areas
Project Management Process Groups And Knowledge AreasProject Management Process Groups And Knowledge Areas
Project Management Process Groups And Knowledge Areas
 
Project scope management 1
Project scope management 1Project scope management 1
Project scope management 1
 
Project Communications Management
Project Communications ManagementProject Communications Management
Project Communications Management
 
Project Management Tools
Project Management ToolsProject Management Tools
Project Management Tools
 
1. introduction
1. introduction1. introduction
1. introduction
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
Why Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and SolutionsWhy Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and Solutions
 
05 project scope management
05  project scope management05  project scope management
05 project scope management
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
Project Management - Foundation
Project Management - FoundationProject Management - Foundation
Project Management - Foundation
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process Groups
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
 
1.3 Schwalbe Ch3(1).ppt
1.3 Schwalbe Ch3(1).ppt1.3 Schwalbe Ch3(1).ppt
1.3 Schwalbe Ch3(1).ppt
 
Project Management for Public Works Professionals
Project Management for Public Works ProfessionalsProject Management for Public Works Professionals
Project Management for Public Works Professionals
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 

Destacado

Work Breakdown Structure ( WBS) : For a Project Management Process
Work Breakdown Structure ( WBS) : For a Project Management ProcessWork Breakdown Structure ( WBS) : For a Project Management Process
Work Breakdown Structure ( WBS) : For a Project Management ProcessDhawal Thakkar PMP
 
Plan 06 perencanaan manajemen proyek2
Plan 06 perencanaan manajemen proyek2Plan 06 perencanaan manajemen proyek2
Plan 06 perencanaan manajemen proyek2Anggunara Thea
 
El aguila de wilmar ivan G L
El aguila de wilmar ivan G LEl aguila de wilmar ivan G L
El aguila de wilmar ivan G Lwilmar gonzalez
 
E 12 bsp1779_pankajkumarvisualcv
E 12 bsp1779_pankajkumarvisualcvE 12 bsp1779_pankajkumarvisualcv
E 12 bsp1779_pankajkumarvisualcvPankaj Kumar
 
Tugas plkj
Tugas plkjTugas plkj
Tugas plkjhanif003
 
Presentazione Tweetaliano Erasmus/EILC
Presentazione Tweetaliano Erasmus/EILCPresentazione Tweetaliano Erasmus/EILC
Presentazione Tweetaliano Erasmus/EILCg0bb1
 
Hindi kavita laal tamatar
Hindi kavita  laal tamatarHindi kavita  laal tamatar
Hindi kavita laal tamatarRakhi Sharma
 
SMX Melbourne 2012 - Auditing PPC Campaigns - Leigh Hanney
SMX Melbourne 2012 - Auditing PPC Campaigns - Leigh HanneySMX Melbourne 2012 - Auditing PPC Campaigns - Leigh Hanney
SMX Melbourne 2012 - Auditing PPC Campaigns - Leigh HanneyLeigh Hanney
 
ดนตรีสากล
ดนตรีสากลดนตรีสากล
ดนตรีสากลKan Directioner
 

Destacado (20)

Work Breakdown Structure ( WBS) : For a Project Management Process
Work Breakdown Structure ( WBS) : For a Project Management ProcessWork Breakdown Structure ( WBS) : For a Project Management Process
Work Breakdown Structure ( WBS) : For a Project Management Process
 
Pm Student Ho
Pm Student HoPm Student Ho
Pm Student Ho
 
Plan 06 perencanaan manajemen proyek2
Plan 06 perencanaan manajemen proyek2Plan 06 perencanaan manajemen proyek2
Plan 06 perencanaan manajemen proyek2
 
WBS PROJECT
WBS PROJECTWBS PROJECT
WBS PROJECT
 
Ravi tiwari
Ravi tiwariRavi tiwari
Ravi tiwari
 
Ihm2
Ihm2Ihm2
Ihm2
 
El aguila de wilmar ivan G L
El aguila de wilmar ivan G LEl aguila de wilmar ivan G L
El aguila de wilmar ivan G L
 
Sec Presentation
Sec  PresentationSec  Presentation
Sec Presentation
 
Реализация мероприятий развития государственных программ города Москвы в 2013...
Реализация мероприятий развития государственных программ города Москвы в 2013...Реализация мероприятий развития государственных программ города Москвы в 2013...
Реализация мероприятий развития государственных программ города Москвы в 2013...
 
E 12 bsp1779_pankajkumarvisualcv
E 12 bsp1779_pankajkumarvisualcvE 12 bsp1779_pankajkumarvisualcv
E 12 bsp1779_pankajkumarvisualcv
 
Стимулирование органов местного самоуправления в Москве по итогам первого пол...
Стимулирование органов местного самоуправления в Москве по итогам первого пол...Стимулирование органов местного самоуправления в Москве по итогам первого пол...
Стимулирование органов местного самоуправления в Москве по итогам первого пол...
 
Tugas plkj
Tugas plkjTugas plkj
Tugas plkj
 
T pack presentation
T pack presentationT pack presentation
T pack presentation
 
Presentazione Tweetaliano Erasmus/EILC
Presentazione Tweetaliano Erasmus/EILCPresentazione Tweetaliano Erasmus/EILC
Presentazione Tweetaliano Erasmus/EILC
 
Spm report
Spm reportSpm report
Spm report
 
Radhin 4+
Radhin 4+Radhin 4+
Radhin 4+
 
Hindi kavita laal tamatar
Hindi kavita  laal tamatarHindi kavita  laal tamatar
Hindi kavita laal tamatar
 
SMX Melbourne 2012 - Auditing PPC Campaigns - Leigh Hanney
SMX Melbourne 2012 - Auditing PPC Campaigns - Leigh HanneySMX Melbourne 2012 - Auditing PPC Campaigns - Leigh Hanney
SMX Melbourne 2012 - Auditing PPC Campaigns - Leigh Hanney
 
Kumpulan 1
Kumpulan 1Kumpulan 1
Kumpulan 1
 
ดนตรีสากล
ดนตรีสากลดนตรีสากล
ดนตรีสากล
 

Similar a Work BreakDown Structure

Work Breakdown Structure Template(1).docx
Work Breakdown Structure Template(1).docxWork Breakdown Structure Template(1).docx
Work Breakdown Structure Template(1).docxShahid Farooq, PMP
 
Implementation-Plan_X_Corp
Implementation-Plan_X_CorpImplementation-Plan_X_Corp
Implementation-Plan_X_CorpJared Bourne
 
Iso12207:2008 standard
Iso12207:2008 standardIso12207:2008 standard
Iso12207:2008 standardMaria Akther
 
Work Breakdown Structure (WBS) TemplateThis Project WB.docx
Work Breakdown Structure (WBS) TemplateThis Project WB.docxWork Breakdown Structure (WBS) TemplateThis Project WB.docx
Work Breakdown Structure (WBS) TemplateThis Project WB.docxambersalomon88660
 
Project Work Breakdown Structure
Project Work Breakdown StructureProject Work Breakdown Structure
Project Work Breakdown StructureDemand Metric
 
Project mgmt life cycle origination
Project mgmt life cycle originationProject mgmt life cycle origination
Project mgmt life cycle originationMujtaba Masood
 
Software proposal sample_project_1-_web_site_development_by_zx_7_of_november_...
Software proposal sample_project_1-_web_site_development_by_zx_7_of_november_...Software proposal sample_project_1-_web_site_development_by_zx_7_of_november_...
Software proposal sample_project_1-_web_site_development_by_zx_7_of_november_...Oleg Zhuravlev
 
MSF Process model
MSF Process modelMSF Process model
MSF Process modelunruliness
 
Project Scope Management Chapter 05.pptx
Project Scope Management Chapter 05.pptxProject Scope Management Chapter 05.pptx
Project Scope Management Chapter 05.pptxKareemBullard1
 
project managment - wang jing yuan (Eric Wang)
project managment - wang jing yuan (Eric Wang)project managment - wang jing yuan (Eric Wang)
project managment - wang jing yuan (Eric Wang)Eric Wang
 
Software proposal sample_project_2-_mobile_application_development_by_swpropo...
Software proposal sample_project_2-_mobile_application_development_by_swpropo...Software proposal sample_project_2-_mobile_application_development_by_swpropo...
Software proposal sample_project_2-_mobile_application_development_by_swpropo...Oleg Zhuravlev
 

Similar a Work BreakDown Structure (20)

Work Breakdown Structure Template(1).docx
Work Breakdown Structure Template(1).docxWork Breakdown Structure Template(1).docx
Work Breakdown Structure Template(1).docx
 
Implementation-Plan_X_Corp
Implementation-Plan_X_CorpImplementation-Plan_X_Corp
Implementation-Plan_X_Corp
 
Iso12207:2008 standard
Iso12207:2008 standardIso12207:2008 standard
Iso12207:2008 standard
 
Work Breakdown Structure (WBS) TemplateThis Project WB.docx
Work Breakdown Structure (WBS) TemplateThis Project WB.docxWork Breakdown Structure (WBS) TemplateThis Project WB.docx
Work Breakdown Structure (WBS) TemplateThis Project WB.docx
 
2nd meeting
2nd meeting2nd meeting
2nd meeting
 
Project Work Breakdown Structure
Project Work Breakdown StructureProject Work Breakdown Structure
Project Work Breakdown Structure
 
PgM ITTOs
PgM ITTOsPgM ITTOs
PgM ITTOs
 
Pmt 01
Pmt 01Pmt 01
Pmt 01
 
Training Report
Training ReportTraining Report
Training Report
 
Iss 05
Iss 05Iss 05
Iss 05
 
Project mgmt life cycle origination
Project mgmt life cycle originationProject mgmt life cycle origination
Project mgmt life cycle origination
 
Software proposal sample_project_1-_web_site_development_by_zx_7_of_november_...
Software proposal sample_project_1-_web_site_development_by_zx_7_of_november_...Software proposal sample_project_1-_web_site_development_by_zx_7_of_november_...
Software proposal sample_project_1-_web_site_development_by_zx_7_of_november_...
 
MSF Process model
MSF Process modelMSF Process model
MSF Process model
 
Archive Documents
Archive DocumentsArchive Documents
Archive Documents
 
Maximo project approach using prince2
Maximo project approach using prince2Maximo project approach using prince2
Maximo project approach using prince2
 
Project Scope Management Chapter 05.pptx
Project Scope Management Chapter 05.pptxProject Scope Management Chapter 05.pptx
Project Scope Management Chapter 05.pptx
 
project managment - wang jing yuan (Eric Wang)
project managment - wang jing yuan (Eric Wang)project managment - wang jing yuan (Eric Wang)
project managment - wang jing yuan (Eric Wang)
 
Peer Review
Peer ReviewPeer Review
Peer Review
 
Trn 04
Trn 04Trn 04
Trn 04
 
Software proposal sample_project_2-_mobile_application_development_by_swpropo...
Software proposal sample_project_2-_mobile_application_development_by_swpropo...Software proposal sample_project_2-_mobile_application_development_by_swpropo...
Software proposal sample_project_2-_mobile_application_development_by_swpropo...
 

Más de Abdul Aslam

Challenges of cloud final
Challenges of cloud finalChallenges of cloud final
Challenges of cloud finalAbdul Aslam
 
Star ,Snow and Fact-Constullation Schemas??
Star ,Snow and  Fact-Constullation Schemas??Star ,Snow and  Fact-Constullation Schemas??
Star ,Snow and Fact-Constullation Schemas??Abdul Aslam
 
Job analysis of a reporter
Job analysis of a reporterJob analysis of a reporter
Job analysis of a reporterAbdul Aslam
 
Project Progress Report
Project Progress ReportProject Progress Report
Project Progress ReportAbdul Aslam
 
Components of a Data-Warehouse
Components of a Data-WarehouseComponents of a Data-Warehouse
Components of a Data-WarehouseAbdul Aslam
 
Difference between ER-Modeling and Dimensional Modeling
Difference between ER-Modeling and Dimensional ModelingDifference between ER-Modeling and Dimensional Modeling
Difference between ER-Modeling and Dimensional ModelingAbdul Aslam
 
Transaction Processing System
Transaction Processing SystemTransaction Processing System
Transaction Processing SystemAbdul Aslam
 
Final Year Project (ISP),Project Demo
Final Year Project (ISP),Project DemoFinal Year Project (ISP),Project Demo
Final Year Project (ISP),Project DemoAbdul Aslam
 
Distributed Operating System,Network OS and Middle-ware.??
Distributed Operating System,Network OS and Middle-ware.??Distributed Operating System,Network OS and Middle-ware.??
Distributed Operating System,Network OS and Middle-ware.??Abdul Aslam
 
Software Testing Tool Report
Software Testing Tool ReportSoftware Testing Tool Report
Software Testing Tool ReportAbdul Aslam
 
Cloud Computing
 Cloud Computing Cloud Computing
Cloud ComputingAbdul Aslam
 
Erd For Gift Shop
Erd For Gift ShopErd For Gift Shop
Erd For Gift ShopAbdul Aslam
 

Más de Abdul Aslam (12)

Challenges of cloud final
Challenges of cloud finalChallenges of cloud final
Challenges of cloud final
 
Star ,Snow and Fact-Constullation Schemas??
Star ,Snow and  Fact-Constullation Schemas??Star ,Snow and  Fact-Constullation Schemas??
Star ,Snow and Fact-Constullation Schemas??
 
Job analysis of a reporter
Job analysis of a reporterJob analysis of a reporter
Job analysis of a reporter
 
Project Progress Report
Project Progress ReportProject Progress Report
Project Progress Report
 
Components of a Data-Warehouse
Components of a Data-WarehouseComponents of a Data-Warehouse
Components of a Data-Warehouse
 
Difference between ER-Modeling and Dimensional Modeling
Difference between ER-Modeling and Dimensional ModelingDifference between ER-Modeling and Dimensional Modeling
Difference between ER-Modeling and Dimensional Modeling
 
Transaction Processing System
Transaction Processing SystemTransaction Processing System
Transaction Processing System
 
Final Year Project (ISP),Project Demo
Final Year Project (ISP),Project DemoFinal Year Project (ISP),Project Demo
Final Year Project (ISP),Project Demo
 
Distributed Operating System,Network OS and Middle-ware.??
Distributed Operating System,Network OS and Middle-ware.??Distributed Operating System,Network OS and Middle-ware.??
Distributed Operating System,Network OS and Middle-ware.??
 
Software Testing Tool Report
Software Testing Tool ReportSoftware Testing Tool Report
Software Testing Tool Report
 
Cloud Computing
 Cloud Computing Cloud Computing
Cloud Computing
 
Erd For Gift Shop
Erd For Gift ShopErd For Gift Shop
Erd For Gift Shop
 

Último

Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxDr. Sarita Anand
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17Celine George
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxJisc
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxPooja Bhuva
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSCeline George
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfDr Vijay Vishwakarma
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...pradhanghanshyam7136
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxPooja Bhuva
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jisc
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxEsquimalt MFRC
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsKarakKing
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentationcamerronhm
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.MaryamAhmad92
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxCeline George
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and ModificationsMJDuyan
 

Último (20)

Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 

Work BreakDown Structure

  • 2. SOFTWARE PROJECT MANAGEMENT (SPM) Work Breakdown Structure of Insurance Survey Portal (ISP) Submitted To: Madam Aasma Abid Submitted By: Abdul-Rehman Aslam (9998) Yasir Mehmood (9994)
  • 3. Introduction The Work Breakdown Structure presented here represents all the work required to complete this project. It helps to easily communicate the work and processes involved to execute the project. The Project Manager and project team use the WBS to develop the project schedule, resource requirements and costs Outline View 1. Insurance Survey Portal 1.1 Initiation 1.1.1 Evaluation & Recommendations 1.1.2 Develop Project Charter 1.1.3 Deliverable: Submit Project Charter 1.1.4 Project Sponsor Reviews Project Charter 1.1.5 Project Charter Signed/Approved 1.2 Planning 1.2.1 Create Preliminary Scope Statement 1.2.2 Determine Project Team 1.2.3 Project Team Kickoff Meeting 1.2.4 Develop Project Plan 1.2.5 Submit Project Plan 1.2.6 Milestone: Project Plan Approval
  • 4. 1.3 Execution 1.3.1 Project Kickoff Meeting 1.3.2 Verify & Validate User Requirements 1.3.3 Design System 1.3.4 Procure Hardware/Software 1.3.5 Install Development System 1.3.6 Testing Phase 1.3.7 Install Live System 1.3.8 User Training 1.3.9 Go Live 1.4 Control 1.4.1 Project Management 1.4.2 Project Status Meetings 1.4.3 Risk Management 1.4.4 Update Project Management Plan 1.5 Closeout 1.5.1 Audit Procurement 1.5.2 Document Lessons Learned 1.5.3 Update Files/Records 1.5.4 Gain Formal Acceptance 1.5.5 Archive Files/Documents
  • 5. Tabular View Level 1 Level 2 Level 3 1 Insurance Survey 1.1 Initiation 1.1.1 Evaluation & Recommendations Portal 1.1.2 Develop Project Charter 1.1.3 Deliverable: Submit Project Charter 1.1.4 Project Sponsor Reviews Project Charter 1.1.5 Project Charter Signed/Approved 1.2 Planning 1.2.1 Create Preliminary Scope Statement 1.2.2 Determine Project Team 1.2.3 Project Team Kickoff Meeting 1.2.4 Develop Project Plan 1.2.5 Submit Project Plan 1.2.6 Milestone: Project Plan Approval 1.3 Execution 1.3.1 Project Kickoff Meeting 1.3.2 Verify & Validate User Requirements 1.3.3 Design System 1.3.4 Procure Hardware/Software 1.3.5 Install Development System 1.3.6 Testing Phase 1.3.7 Install Live System 1.3.8 User Training 1.3.9 Go Live 1.4 Control 1.4.1 Project Management 1.4.2 Project Status Meetings 1.4.3 Risk Management 1.4.4 Update Project Management Plan 1.5 Closeout 1.5.1 Audit Procurement 1.5.2 Document Lessons Learned 1.5.3 Update Files/Records 1.5.4 Gain Formal Acceptance 1.5.5 Archive Files/Documents