This document summarizes a study on safety hazard identification in the UK construction industry. It presents a procedure to calculate hazard identification indices (HII) for construction method statements. The study found maximum HII values of 0.899 or 89.9% for a nuclear project. Low HII values indicate knowledge, process, and procedure barriers that can be addressed by an IT tool called Total-Safety that helps standardize hazard identification and risk assessment methods. Total-Safety uses a task-based approach and database to improve information sharing across projects.
2. Outline
Introduction
Hazard and Accident Causation
Procedure for establishing hazard
identification levels
Analysis of Results Obtained
Barrier to improve hazard identifications
System for Hazard Identification
Improvement
3. Introduction
Hazard identification is fundamental to construction safety
management; unidentified hazards present the most
unmanageable hazards.
Maximum hazard identification levels were found to be 0.899
89.9% for a construction project within the nuclear industry
the reasons for low hazard identification levels indicates key
barriers. This leads to the presentation of an Information
Technology IT tool for construction project safety management
Total-Safety and, in particular, a module within Total-Safety
designed to help construction personnel develop method
statements with improved levels of hazard identification.
4. Hazard and Accident
Causation
This paper presents an investigation of safety hazard identifi-
cation within the U.K. construction industry. Starting with a
discussion of an accident causation model, within the context of
how hazards lead to accidents, it indicates that managing
hazardous events is a fundamental aspect of construction safety
management. Within the construction industry, risk assessment
is the practical means by which hazardous events are managed.
However, unidentified hazards negate the risk assessment
process; risks cannot be assessed and control measures
cannot be developed
The paper presents a procedure that indicates the level of
hazard identification within method statements via calculation of
minimum and maximum hazard identification indices. A “method
statement” is a carefully
5. Overview of Hazards and
Accident Causation
Hazards effect
Fatal accident
Severity=max
Accident
Severity>0
Precaution Control Measure
(Limit hazard movement)
Preventive control measure]
(limit hazard entry)
Hazard
6. Hazard and Accident
Causation(Identified Hazard)
Precaution Control Measure (Limit hazard movement)
By reducing its probability of occurrence
Preventive control measure (limit
hazard entry)
By reducing its severity
Consideration of hazards in terms of their probability of occurrence
and severity of consequence provides the general rationale
for performing all safety risk assessments, which are undertaken
as follows:
1.Estimate the probability of a hazard’s occurrence
2. Evaluate the risk associated with the hazard based upon the
frequency and severity estimations
3. Respond to the hazard by implementing suitable control
measures.
7. Hazard and Accident Causation
(Unidentified Hazard)
If Hazard is identified it will be covered by the first assumption
but if it is not identified it will have
1.Complete freedom of entry into the triangle, will have an
uncontrolled probability of occurrence
2. Complete freedom of movement within the triangle, the hazard
will have an uncontrolled severity if it does occur.
8. Hazard identification in U.k
construction
Investigation into hazard identification levels have been initially
targeted on three different industry sectors :UK rail, nuclear, and
general construction .
9. Procedure for establishing
hazard identification levels
Procedure was into five steps
1.Step one (Data collective)
Method statement were collected from the construction projects
and then categorized to concrete work, steel work, earth work,
and brick work
To make bench marking for the above information two main
sources were used
1.Construction Industry Publication
2. Information held by the contractor operating on both
projects, such as project risk logs, the safety section of the
company intranet, and other safety related data held on the
individual projects.
10. Cont..
Step two :Method statement preanalysis
Step three:Eastablishing Hazard scoring system
1. The hazard is identified and assessed—score of “1.0;”
2.The hazard is identified but not assessed—score of “0.5;”
3.The hazard is not identified or assessed—score of “0.0.”
11. Cont..
Step four: Determination of the reasonably practicable risk
Step five: Determination of hazard identification level
HII = H1/H0
where H0 represents the total number of relevant hazards in a
method statement and H1 represents the combined identification
and assessment status of those hazards. Therefore if the total
number of potential hazards in a construction method were x and
if all had been both identified and assessed thus obtaining a score
of “1” per hazard then H0=H1=x and HII=1, the best possible
rating.
12. Cont..
HIImin took account of hazards that were explicitly
included in the method statement; this value
represents the lower limit for the level of hazard
identification in a
method statement. HIImax took account of those
same hazards plus hazards that were relevant but
not explicitly included
14. Analysis of Results Obtained
1.Qualatative as shown in the table
2.Quantative: levels for each project were compared to a
“control” project in which a perfect level of hazard identification
was achieved, i.e., for this control project all HIImin and HIImax
values were set to 1.000. The hypothesized mean differences
between HIImin for the control project and Projects A, B, and C
were 0.252, b0.079, and 0.338, respectively. Values for the
corresponding HIImax were 0.209, 0.065, and 0.259. it available
to any individual. This is perhaps the most important
15. Barrier to improve hazard
identifications
1. Knowledge and information barriers:
• Lack of information sharing across projects;
• Lack of resources on smaller projects, e.g., industry publications,
full-time safety department, etc.;
• Subjective nature of hazard identification and risk assessment;
and
• Reliance upon tacit knowledge.
2. Process and procedures barriers:
• Lack of standardized approach; and
• Undefined structure for tasks and hazards.
16. System for Hazard
Identification Improvement
Based on the hypothesis that barriers exist to improve these
levels the work was continued to develop a new system of
hazard and risk management, Total-Safety.
18. Overview of Total Safety
Data base management
Method statement
Method of statement development models
1.Construction methods
The construction method is a discrete list of tasks that describe the
work outlined in the scope of the method statement.
2.Task Based Risk Assessment
A risk assessment is nothing more than a careful examination
of what, in your work, could cause harm to people,
so that you can weigh up whether you have taken enough
19. Conclusion
Triangle of accident causation
Procedure for establishing hazard identification levels
Barrier to improve hazard identifications
Overview of Total Safety