Detailed Engineering Design Phase
Engineering Design Integrity Workflow
Introduction
Detailed Design Engineering Design
Integrity Workflow (EDIW)
EDIW is AMEC’s best practice guidance to Engineering Managers and supporting
personnel for the delivery of technical integrity. It is an ‘aide-memoir’ that highlights
the key deliverables and activities throughout the lifecycle of a typical Detailed Design
project.
Detailed Design is broken into seven phases:
1 Scope Definition and Engineering Execution Strategy
2 Commencement of Detailed Design
3 Initial Design Development and Hazard Identification
4 Initial Design Review & Audit
5 Approval for Design (AFD)
6 Approval for Construction (AFC)
7 Design Close-Out
The workflow shown in the EDIW Road Map illustrates the execution sequence on a generic
Detail Design Project. The vertical columns show activities that can be undertaken concurrently
whilst the sequential flow of work is across the Road Map. As the deliverables and activities in each
phase are completed, work can transition into the next phase.
Situations will arise when work will need to be be done out of sequence, typically to meet a
demanding project schedule. Use of the EDIW allows the risks of out-of-sequence working to be
identified and the necessary mitigation strategies to be put in place.
AMEC’s corporate governance and assurance of Engineering will measure compliance with the
EDIW workflow and ensure out-of-phase working is being identified and managed. This document
contains a copy of the Detail Design EDIW Workflow Road Map and includes detailed descriptions of
the activities, the key engineering disciplines and supporting documentation.
1
Phase 1
Scope Definition and Engineering Execution Strategy
Preparation for commencement of detail design. To evaluate FEED deliverables to ensure
engineering is sufficiently mature for detail design to progress in a controlled and minimal
change environment. To confirm Engineering Execution Plan.
2
Activities / Deliverables Description
Key
Discipline
Supporting Documentation
1
Engineering
Execution Strategy
Review / confirm Engineering Execution Strategy, e.g.
execution locations, workshare, disciplines required,
specialist support, etc.
Project
Manager
and Project
Engineering
Manager
Tender documentation, Project Execution Plan
(PEP)
2
Feed / BoD
Validation
Confirm maturity of Front End Engineering Design. Identify
any areas of concern and ensure these are captured on the
Technical Risk Register.
Project
Engineering
Manager
3
Project Baseline
Standards
Establish which codes, standards and specifications are to be
utilised, eg. Corporate, project, client, and confirm procedure.
Include in Engineering Execution Plan and / or Discipline Job
Design Specifications.
Project
Engineering
Manager
Engineering Baseline Standards, Document No.
OAG-X160-190-GDL-012 (previously
AOD-92-043 )
4
Engineering Audit
Schedule
Create formal schedule to identify when technical integrity
audits, design reviews, HAZIDS, HAZOPS, etc are to be carried
out. Align to Level 3 Engineering Plan and include in
Engineering Execution Plan.
Project
Engineering
Manager
Technical Safety Events Schedule
(Lead Technical Safety Engineer)
5
Engineering
Execution Plan &
Engineering
Organisation Chart
Create Engineering Execution Plan complete with key
supporting documents / information.
Project
Engineering
Manager
6
Integrated
Engineering
Systems
Agree engineering design tools to be used and confirm
that system hardware, software and support is available.
Include issues such as PDMS or PDS, Cats and Specs, survey
methods, dimensional control techniques, etc. Document and
record in the Engineering Execution Plan and discipline job
design specifications.
Engineering
Systems
and All
Disciplines
Engineering Systems Project Start-up Manual,
Document No. OAGX160-170-MAN-002
7 QRA & FRA Strategy
Establish status of project Quantitative Risk Assessment
(QRA), Fire Risk Assessment (FRA) and Emergency Escape &
Rescue Assessment (EERA) information and confirm
methadology for timely delivery into engineering design
process. Agree accountability for delivery, eg. Client, 3rd
party, AMEC, and record in Engineering Execution Plan.
Technical
Safety
Hazard Management Philosophy, OAG-X160-
190-GDL-009 (previously AOD-97-001):
Hazard & Risk Management, OAG-X160-190-
PRO-024
8
Discipline Job
Design Specification
Define the key project specific design parameters and
operational constraints that are applicable to the appropriate
discipline for the detailed design of the project. To identify key
individuals, roles and responsibilities, design tools, key codes
and standards, etc.
All Disciplines
9
Level 3
Engineering Plan
Agree work breakdown structure, develop CTRs and create
level 3 integrated engineering plan covering all disciplines. To
be included in Engineering Execution Plan.
All Disciplines
10
Confirm CE
Compliance Strategy
Review and confirm strategy for CE Compliance . Ensure
discipline Lead Engineers are aware of their responsibilities
and appropriate resources / measures are in place.
Project
Engineering
Manager
Corporate CE Compliance Strategy OAG-
X160-190-MAN-001; Project Compliance with
Pressure Equipment Regulations OAG-X160-
050-PRO-001; Pressure Equipment
Regulations Guidelines AOD-97-047; ATEX
Guidelines, OAG-X160-190-GDL-003; Machinery
Directive Guidelines, O&G-ENG-REP-29-001;
Electromatic Compatibility Regulations
Guidelines, OAG-X160-190-GDL-003; MC, The
Electrical Equipment (Safety) Regulations
Guideleines, OAG-X160-190-GDL-003.
11
Technical Risk
Register
Create formal Technical Risk Register identifying all possible
risks asscociated with the engineering design.
Techncal Safety
Activities / Deliverables Description
Key
Discipline
Supporting Documentation
1
Performance
Standards &
Verification Scheme
Confirm safety critical systems / elements and set
appropriate performance standards. i.e. functionality,
reliability and survivability. Develop scheme to allow the
independent competent body (ICB) to verify the design
against the performance standards.
Technical
Safety
Hazard Management Philosophy, OAG-X160-
190-GDL-009 (previously AOD-97-001); Hazard
& Risk Management, OAG-X160-190-PRO-024;
Design Verification Activities (under DCR),
OAG-X160-190-PRO-028; Platform Safety Case.
2
Document
Distribution Matrix
Create formal document distribution matrix to ensure all
disciplines & departments receive all necessary design
information in a timely manner.
Project
Engineering
Manager
3
Structural Integrity
Interface
Ensure structural integrity interfaces are identified & visible
to Project, e.g. AMEC / Client focal points, Technical
Authorities, Independent Verification Bodies, etc.
Structural
4
Material Selection
Report
Report defining the requirements and specifications of
necessary material.
Metallurgy
AMEC Corporate Material Engineering
Specifications.
5
Hazard Management
Plan
Create Hazard Management Plan identifying all key hazards,
technical safety activities and the approach to managing
Major Accident Hazards (MAH) in the design.
Technical
Safety
Hazard & Risk Management, OAG-X160-190-
PRO-024; Management of Functional Safety
Guideline OAG-X160-190-GDL-004
6 Piping Specifications
Develop / confirm baseline piping specifications, utilising
AMEC Corporate specifications where possible.
Piping AMEC Corporate Piping Specifications.
7 PDMS Calalogues
Ensure PDMS catalogues are populated & available for all
affected disciplines, utilising AMEC Corporate data, i.e. CPC,
where possible.
Engineering
Systems,
supported by
Piping,
Electrical,
Instruments,
Structural &
HVAC
8 CMSS Philosophy
Develop Control Monitoring and Safety Systems (CMSS)
Philosophy covering key instrumentation and control systems
e.g. Process Control System (PCS), Emergency Shutdown
System (ESD) and Fire and Gas (F&G).
Instruments
Phase 2
Commencement of Detail Design
To formally kick off the Engineering Design Process in accordance with the project execution plan
and to ensure that key engineering strategies / philosophies are in place.
3
4
Phase 3
Initial Design Development and Hazard Identification
To develop initial design deliverables to Inter Discipline Review (IDC) stage and identify key hazards.
Activities / Deliverables Description
Key
Discipline
Supporting Documentation
1 HAZID
Perform hazard identification studies, as identified on
Engineering Audit Schedule / Technical Safety Events
Schedule.
Technical
Safety
Project Hazard Identification (HAZID) AOD-92-
018; Engineering & Design Reviews, OAG-X160-
190-PRO-013.
2 ENVID
Formal assessment of environmental aspects associated
with a modification or a change, and to propose
prevention or mitigating measures.
Technical
Safety
Environmental Impact Identification (ENVID)
OAG-X160-190-PRO-121; Engineering & Design
Reviews, OAG-X160-190-PRO-013.
3 PFD IDC
Issue Process Flow Diagrams (PFD’s) on formal
Inter-Discipline Review (IDC).
Process
4
Shutdown & Blowdown
Philosophy
Explain the measures to prevent and control blowdown
and how this will be achieved.
Process
5 P&ID’s IDC
Issue Piping & Instrumentation Diagrams (P&ID’s) on
formal Inter-Discipline Review (IDC).
Process
6 C&E IDC
Issue Cause & Effects for formal Inter-Discipline
Review (IDC).
Process and
Instruments
7 Plot Plans / Layouts IDC
Issue equipment Plot Plans / Layouts on formal
inter-Discipline Review (IDC).
Piping and
Layouts
8
Hazardous Area
Layouts IDC
Issue Hazardous Area Layouts for formal
Inter-Discipline Review (IDC).
Technical
Safety
9 Equipment List
Create master project equipment list identifying all
major items of tagged equipment, e.g. vessels, pumps,
motors, generators, hydrocycolnes, chemical injection
packages, electrical switchgear, control panels, etc.
Mechanical
10
Mechanical Handling
Strategy
Develop Mechanical Handling Strategy including general
approach / constraints, platform crane limits, installation
philosophy, operation and maintenance, etc.
Mechanical
and Structural
11
Particular Material
Appraisals (PMA)
Where required, i.e. where Corporate PMA’s or EAM’s
are not suitable, develop new PMA’s and obtain approval
from Notified Bodies (NoBo’s).
PED Focal
Point
12
Fire Risk Assessment
(FRA)
Determine Fire & Explosion scenarios and identifies
requirements for prevention, control and mitigation
measures.
Technical
Safety
13
Emergency Escape &
Resecue Assesment
(EERA)
Identify requirements for emergency escape & rescue,
e.g. lifeboats, escape routes, plant layout, etc
Technical
Safety
14 Dropped Object Study
Identify and assess the potential risks to drilling,
production, process equipment, and manned areas from
dropped or swinging objects. Where the consequence
of a dropped object is considered significant, to propose
prevention or mitigating measures.
Technical
Safety
15 Blast Design Philosophy
Develop philosophy that assesses potential explosion
hazards and identifies appropriate blast loadings to be
applied to the engineering design process, eg. Vessels,
pipe supports, structural steel, etc.
Technical
Safety
16 PFP / AFP Philosophy
Develop philosophy that identifies requirements for
Passive Fire Protection (PFP) and/or Active Fire
Protection (AFP).
Technical
Safety
17 HIPPS Review
Initial review to establish requirements for a High
Integrity Pressure Protection System.
Instruments
Management of Functional Safety,
OAG-X160-190-GDL-004
5
Phase 4
Initial Design Review and Audit
To confirm that the initial design development is robust.
Activities / Deliverables Description
Key
Discipline
Supporting Documentation
1 Hazardous Area Review
Formal Engineering discipline review of hazardous area
layouts to confirm requirements for the correct selection
and location of equipment.
Technical
Safety
Hazard and Risk Management Procedure
OAG-X160-190-PRO-024; Engineering &
Design reviews, OAG-X160-190-PRO-013
2
P&ID Review and / or
‘Initial Hazop’
Formal Engineering discipline review of P&ID's to
confirm design basis.
Process,
Piping,
Technical
Safety,
Instruments
Formal Hazop, OAG-X160-190-PRO-017;
Engineering & Design Reviews, OAG-X160-190-
PRO-013
3
Plot Plans / Layout / 3-D
Model Review
Formal Engineering review of Plot Plans / Layouts. The
review shall ensure that the layout design complies with
the required technical, safety, operability and
maintainability standards. Makes sure the layout is cost
effective, ensures the constructability of the work and
agrees the layout basis on which the detailed design can
proceed.
Piping and
Layouts,
Structural,
Mechanical,
Electrical,
Technical
Safety, Process
Engineering & Design Reviews,
OAG-X160-190-PRO-013
4 C&E Review
Formal review of Cause & Effects diagrams to confirm
design basis and alignment with Hazard Management
Plan.
Instruments,
Process,
Technical
Safety
Hazard and Risk Management Procedure
OAG-X160-190-PRO-024; Engineering &
Design reviews, OAG-X160-190-PRO-013;
Management of Functional Safety Guideline
OAG-X160-190-GDL-004
5 Technical Audit
Obtain confirmation, by sampling of project
documentation, that the engineering of the project is to
the required standard and free from errors.
Independent
(Corporate
Engineering)
Technical Audit Procedure
OAG-X160-190-PRO-022
6
Phase 5
Design Approval
To ‘Freeze’ the Process design, and develop dependent design & procurement activities.
Activities / Deliverables Description
Key
Discipline
Supporting Documentation
1
PUWER
Assessments
Conduct initial PUWER assessment typically by review of
PDMS model and/or vendor / equipment supplier information
received to date.
Technical
Safety,
Mechanical
Engineering & Design Reviews,
OAG-X160-190-PRO-013
2 HAZOP
Hazard and Operability Studies, a systematic multi-discipline
study based on the applications of guidewords to identify
causes of potential hazards and operability constraints in a
facility.
Process,
Technical
Safety
Dependent on Project updated P&ID’s and
C&E’s may be prepared from commented IDC’s
from Phase 3 Formal HAZOP, OAG-X160-190-
PRO-017 (previously AOD-92-022); Engineering
& Design Reviews, OAG-X160-190-PRO-013
- Note: additional HAZOP’s may be required,
i.e. earlier or later in the project. PEM to
consult with Process & Technical Safety Lead
Engineers.
3 SHE Audit (AFD)
SHE Audit ensures that the design obligations under The
Health and Safety At Work Act 1974 and project health, safety
and environmental performance standards are being or have
been met during the engineering and design processes.
Technical
Safety
SHE Audit Procedure OAG-X160-190-PRO-023;
Engineering & Design Reviews, OAG-X160-190-
PRO-013
4
Environmental
Report
Issue final report to document & confirm that the design has
considered all applicable environmental aspects &
demonstrates that design controls have been included to
minimise / control the environmental impact.
Technical
Safety
Engineering & Design Reviews, OAG-X160-190-
PRO-013
5
Constructability
Review
Conduct formal Constructability Reviews to ensure safe and
efficient installation of plant & equipment.
Affected
disciplines +
Construction /
Implementa-
tion Group
Engineering & Design Reviews,
OAG-X160-190-PRO-014
6 P&ID AFD
Issue Approved For Design (AFD) Process and
Instrumentation Diagrams.
Process
7 C&E AFD Issue Approved For Design (AFD) Cause & Effects. Instruments
8
Process Data Sheets
AFD
Issue Approved For Design (AFD) Process Data Sheets. Process
9
HP / LP Interface
Listing
Identify all HP / LP interfaces on formal register and ensure
that all have been addressed satisfactorily via HAZOP’s and /
or individual reviews.
Process
10 Holds Register Develop register to record & manage post AFD design holds.
Engineering
Manager
11 SIL Assessments
Conduct assessment to determine target Safety Integrity
Level (SIL). Note: Where the target SIL is 3, then it is likely
that a High Integrity Pressure Protection System (HIPPS) will
be required. If the value is found to be 1 or 2, then a HIPPS
will not be required.
Instruments
Management of Functional Safety,
OAG-X160-190-GDL-004
12 HIPPS Study
Conduct study to formally identify the performance
requirements of the High Integrity Pressure Protection
System (HIPPS) and demonstrate that it is robust. Should
include dynamic study for a range of transient conditions.
Process
Management of Functional Safety,
OAG-X160-190-GDL-005
13
HIPPS Reliability
Study
Conduct study to formally demonstrate that the High Integrity
Pressure Protection System (HIPPS) complies with the
reliability & availability criteria for the Project, e.g. as
stipulated in the performance standards.
Instruments
Management of Functional Safety,
OAG-X160-190-GDL-004
14
SIL Achievement
Report
Conduct independent assessment to formally record that the
target Safety Integrity Levels (SIL’s have been achieved) Must
be completed prior to introduction of Hydrocarbons.
Independent
Competent
Person (ICP)
Management of Functional Safety, OAG-X160-
190-GDL-004
15 Flow Assurance
Conduct flow assurance studies to demonstrate the process
design under a range of flow conditions, i.e. start-up to 100%.
Process
16
Verification of
Vendor Information
& Certification -
Design Completion
Verify, primarily through review of vendor documentation,
that their design & manufacture of fabricated packages, etc is
robust and contains sufficient information to facilitate
completion of affected AMEC discipline design.
Affected
disciplines
17
PFEER
Compliance Report
Issue final report as documented confirmation that the design
meets the requirements of the Prevention of Fire and
Explosion, and Emergency Response (PFEER) Regulations
Technical
Safety
AMEC (LSE: AMEC) is a focused supplier of high-value consultancy, engineering and project management services to the world’s natural resources, nuclear, clean energy, water and environmen-
tal sectors. With annual revenues of over £2.5 billion, AMEC designs, delivers and maintains strategic and complex assets for its customers. The company employs some 22,000 people in around
40 countries worldwide.
For further information please see amec.com
Activities / Deliverables Description
Key
Discipline
Supporting Documentation
1 SHE Audit AFC
Conduct SHE Audit at AFC stage in accordance with
Harmonised Procedure.
Technical
Safety
SHE Audit Procedure OAG-X160-190-PRO-023
2
IEC 61511
Compliance Report
Final report to formally demostrate that the Safety
Instrumented Systems comply with the requirements of
IEC 61511.
Instruments
Management of Functional Safety, OAG-X160-
190-GDL-004
3 PFD’s AFC
Issue Approved For Construction (AFC) Process Flow
Diagrams.
Process
4
Operational Safety
Case Development
Commence operational Safety Case development.
Technical
Safety
5 P&ID’s AFC
Issue Approved For Construction (AFC) Process and
Instrumentation Diagrams.
Process
6
Quantative Risk
Assessment (QRA)
Complete QRA activities to confirm that the design is robust
and complies with legislative requirements.
Technical
Safety
7 C&E AFC Issue Approved For Construction (AFC) Cause & Effects. Instruments
8
Operating
Procedures Review
/ Operational HAZOP
Ensure operating procedures are verified line by line against
the facilities provided on the P&ID’s.
Process,
Technical
Safety
Formal HAZOP, OAG-X160-190-PRO-017
(previously AOD-92-022); Engineering & Design
Reviews, OAG-X160-190-PRO-013
9
Fabrication
Drawings AFC
Issue Approved For Construction (AFC) Piping Isometrics,
Structural Steelwork drgs, etc.
Affected
Disciplines
10
Verification of
Vendor Information
& Certification -
Installation,
Operation &
Maintenance
Verify, primarily through review of vendor documentation,
that their design & manufacture of fabricated packages, etc is
robust and contains sufficient information to facilitate safe
installation, operation & maintenance.
Affected
Disciplines
11
EC Design
Examination
Certificates
Where AMEC are deemed to be the manufacturer of the piping
systems, then under the PED/PER, AMEC have to apply to the
Notified Body (NoBo) for an EC Design Examination
Certificate (Cat IV assemblies only).
PER Focal
point
Project Compliance with the Pressure
Equipment Directive, Document
No. OAG-X160-190-GDL-007.
12
Declaration of
Conformity
Where AMEC are deemed to be the manufacturer of the piping
systems, then under the PED/PER, AMEC have to create a
Declaration of Conformity, signed by the Project Manager.
Project
Manager
Project Compliance with the Pressure
Equipment Directive, Document
No. OAG-X160-190-GDL-007.
Phase 6
Approval for Construction (AFC)
To ensure that sufficient design information & certification is available to facilitate
safe installation, operation & maintenance.
Activities / Deliverables Description
Key
Discipline
Supporting Documentation
1
Safety Case
Acceptance (HSE)
Submit Safety Case to HSE & close out all queries /
correspondance prior to next stage of operations.
Technical
Safety
2
Certifying Authority
(CA) / Independent
Verification Bodies
(IVB) Acceptance
Close out all outstanding technical queries and obtain final
Letter of Acceptance.
Technical
Safety
3
Complete
Project As-Built
Documentation
Complete as-builts of design drawings and deliverables in
accordance with Project / Client requirements.
Affected
Disciplines
As Built Drawings and Documentation,
AOD-92-021
Phase 7
Design Close-Out
To ensure all final design deliverables are completed and that client and statutory obligations are
satisfactorily resolved.

Más contenido relacionado

La actualidad más candente

oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02
Mario Fonseca
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
PMI Chennai Chapter
 
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
Philippe Porta
 

La actualidad más candente (20)

oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02
 
Basic engineering_Checklist
Basic engineering_ChecklistBasic engineering_Checklist
Basic engineering_Checklist
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
Project Schedule - Level IV Schedule
Project Schedule - Level IV ScheduleProject Schedule - Level IV Schedule
Project Schedule - Level IV Schedule
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
 
Piping Design Course in Hyderabad
Piping Design Course in HyderabadPiping Design Course in Hyderabad
Piping Design Course in Hyderabad
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 
Engineering Services Capabilities
Engineering Services CapabilitiesEngineering Services Capabilities
Engineering Services Capabilities
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
 
Practical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex ProjectsPractical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex Projects
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draft
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
Epc overview
Epc  overviewEpc  overview
Epc overview
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Pid.pdf
Pid.pdfPid.pdf
Pid.pdf
 
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
 
Pr 1159 - commissioning and start-up procedure
Pr 1159 - commissioning and start-up procedurePr 1159 - commissioning and start-up procedure
Pr 1159 - commissioning and start-up procedure
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Scope of work
Scope of workScope of work
Scope of work
 

Destacado

Measuring posit hange_final
Measuring posit hange_finalMeasuring posit hange_final
Measuring posit hange_final
Franco Taday
 
Fwb Electrical Deliverables Interdisciplinary Interfaces
Fwb Electrical Deliverables   Interdisciplinary InterfacesFwb Electrical Deliverables   Interdisciplinary Interfaces
Fwb Electrical Deliverables Interdisciplinary Interfaces
biiswashruta
 
Shaft Alignment Trainer [SAT] presentation
Shaft Alignment Trainer [SAT] presentationShaft Alignment Trainer [SAT] presentation
Shaft Alignment Trainer [SAT] presentation
Spectra Quest Inc
 
Engineering drawings
Engineering drawingsEngineering drawings
Engineering drawings
Gary Trowles
 
Introduction to electrical engineering
Introduction to electrical engineeringIntroduction to electrical engineering
Introduction to electrical engineering
Rajneesh Budania
 
Value Engineering And Value Analysis
Value Engineering And Value AnalysisValue Engineering And Value Analysis
Value Engineering And Value Analysis
thombremahesh
 

Destacado (10)

Measuring posit hange_final
Measuring posit hange_finalMeasuring posit hange_final
Measuring posit hange_final
 
Fwb Electrical Deliverables Interdisciplinary Interfaces
Fwb Electrical Deliverables   Interdisciplinary InterfacesFwb Electrical Deliverables   Interdisciplinary Interfaces
Fwb Electrical Deliverables Interdisciplinary Interfaces
 
Design Checklist Civil & Structural
Design Checklist Civil & StructuralDesign Checklist Civil & Structural
Design Checklist Civil & Structural
 
Shaft Alignment Tolerances
Shaft Alignment TolerancesShaft Alignment Tolerances
Shaft Alignment Tolerances
 
188757055 1-alignment
188757055 1-alignment188757055 1-alignment
188757055 1-alignment
 
Prealignment
PrealignmentPrealignment
Prealignment
 
Shaft Alignment Trainer [SAT] presentation
Shaft Alignment Trainer [SAT] presentationShaft Alignment Trainer [SAT] presentation
Shaft Alignment Trainer [SAT] presentation
 
Engineering drawings
Engineering drawingsEngineering drawings
Engineering drawings
 
Introduction to electrical engineering
Introduction to electrical engineeringIntroduction to electrical engineering
Introduction to electrical engineering
 
Value Engineering And Value Analysis
Value Engineering And Value AnalysisValue Engineering And Value Analysis
Value Engineering And Value Analysis
 

Similar a Detailed engineering-design-phase

INDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTINDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORT
Nur Ain Samsudin
 
ADEPP & Other Software
ADEPP & Other SoftwareADEPP & Other Software
ADEPP & Other Software
Fabienne Salimi
 
Resume - Jeff Mason 09282015
Resume - Jeff Mason 09282015Resume - Jeff Mason 09282015
Resume - Jeff Mason 09282015
Jeff Mason
 

Similar a Detailed engineering-design-phase (20)

Genisision – Sales – 012 – Capability Statement Expanded
Genisision – Sales – 012 – Capability Statement ExpandedGenisision – Sales – 012 – Capability Statement Expanded
Genisision – Sales – 012 – Capability Statement Expanded
 
Architecture presentation 8
Architecture presentation 8Architecture presentation 8
Architecture presentation 8
 
Ray-Goodfellow.ppt
Ray-Goodfellow.pptRay-Goodfellow.ppt
Ray-Goodfellow.ppt
 
INDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTINDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORT
 
Dlw resume july 2016
Dlw  resume july 2016Dlw  resume july 2016
Dlw resume july 2016
 
Dlw resume march 2016 p
Dlw  resume march 2016 pDlw  resume march 2016 p
Dlw resume march 2016 p
 
L012627682
L012627682L012627682
L012627682
 
L012627682
L012627682L012627682
L012627682
 
A Review on Design Process of Orthopedic Implants
A Review on Design Process of Orthopedic ImplantsA Review on Design Process of Orthopedic Implants
A Review on Design Process of Orthopedic Implants
 
CV
CVCV
CV
 
ADEPP & Other Software
ADEPP & Other SoftwareADEPP & Other Software
ADEPP & Other Software
 
Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template
 
Resume - Jeff Mason 09282015
Resume - Jeff Mason 09282015Resume - Jeff Mason 09282015
Resume - Jeff Mason 09282015
 
SPEC Process Engineering&Construction
SPEC Process Engineering&ConstructionSPEC Process Engineering&Construction
SPEC Process Engineering&Construction
 
Front End Engineering Design (FEED) Project Control Training
Front End Engineering Design (FEED) Project Control TrainingFront End Engineering Design (FEED) Project Control Training
Front End Engineering Design (FEED) Project Control Training
 
Safety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxSafety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptx
 
Safety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxSafety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptx
 
Oberoi Hotel
Oberoi HotelOberoi Hotel
Oberoi Hotel
 
Ali Raza CV(Final)
Ali Raza CV(Final)Ali Raza CV(Final)
Ali Raza CV(Final)
 
Senior Mechanical Engineer CV
Senior Mechanical Engineer CVSenior Mechanical Engineer CV
Senior Mechanical Engineer CV
 

Más de raghunathan janarthanan

Más de raghunathan janarthanan (20)

Epc areas of activity
Epc areas of activityEpc areas of activity
Epc areas of activity
 
Smart communities
Smart communitiesSmart communities
Smart communities
 
Piping presentation part ii 2
Piping presentation part ii 2Piping presentation part ii 2
Piping presentation part ii 2
 
3rd generation modularization by flour
3rd generation modularization   by flour3rd generation modularization   by flour
3rd generation modularization by flour
 
global recruitment services (GPS) A division of saipem
global recruitment services (GPS) A division of saipemglobal recruitment services (GPS) A division of saipem
global recruitment services (GPS) A division of saipem
 
Aveva pdms (1)
Aveva pdms (1)Aveva pdms (1)
Aveva pdms (1)
 
Pdms overview
Pdms overviewPdms overview
Pdms overview
 
Nick amott
Nick amottNick amott
Nick amott
 
Global support position in oil & gas
Global support position in oil & gasGlobal support position in oil & gas
Global support position in oil & gas
 
New role in piping linked with planning
New role in piping linked with planningNew role in piping linked with planning
New role in piping linked with planning
 
Innovative system implementation
Innovative system implementation Innovative system implementation
Innovative system implementation
 
Piping design engineering module
Piping design engineering modulePiping design engineering module
Piping design engineering module
 
Jr consulting services
Jr consulting services Jr consulting services
Jr consulting services
 
India development projects
India   development projectsIndia   development projects
India development projects
 
Country development projects
Country development projectsCountry development projects
Country development projects
 
Natural food corner
Natural food cornerNatural food corner
Natural food corner
 
New ventures
New venturesNew ventures
New ventures
 
Saving money
Saving moneySaving money
Saving money
 
Scheduling or routing technology
Scheduling or routing technologyScheduling or routing technology
Scheduling or routing technology
 
Finland successful school reform
Finland successful school reformFinland successful school reform
Finland successful school reform
 

Último

unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
Abortion pills in Kuwait Cytotec pills in Kuwait
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
lizamodels9
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
lizamodels9
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
dollysharma2066
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
dlhescort
 
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
amitlee9823
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Anamikakaur10
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
amitlee9823
 

Último (20)

unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 

Detailed engineering-design-phase

  • 1. Detailed Engineering Design Phase Engineering Design Integrity Workflow
  • 2. Introduction Detailed Design Engineering Design Integrity Workflow (EDIW) EDIW is AMEC’s best practice guidance to Engineering Managers and supporting personnel for the delivery of technical integrity. It is an ‘aide-memoir’ that highlights the key deliverables and activities throughout the lifecycle of a typical Detailed Design project. Detailed Design is broken into seven phases: 1 Scope Definition and Engineering Execution Strategy 2 Commencement of Detailed Design 3 Initial Design Development and Hazard Identification 4 Initial Design Review & Audit 5 Approval for Design (AFD) 6 Approval for Construction (AFC) 7 Design Close-Out The workflow shown in the EDIW Road Map illustrates the execution sequence on a generic Detail Design Project. The vertical columns show activities that can be undertaken concurrently whilst the sequential flow of work is across the Road Map. As the deliverables and activities in each phase are completed, work can transition into the next phase. Situations will arise when work will need to be be done out of sequence, typically to meet a demanding project schedule. Use of the EDIW allows the risks of out-of-sequence working to be identified and the necessary mitigation strategies to be put in place. AMEC’s corporate governance and assurance of Engineering will measure compliance with the EDIW workflow and ensure out-of-phase working is being identified and managed. This document contains a copy of the Detail Design EDIW Workflow Road Map and includes detailed descriptions of the activities, the key engineering disciplines and supporting documentation. 1
  • 3. Phase 1 Scope Definition and Engineering Execution Strategy Preparation for commencement of detail design. To evaluate FEED deliverables to ensure engineering is sufficiently mature for detail design to progress in a controlled and minimal change environment. To confirm Engineering Execution Plan. 2 Activities / Deliverables Description Key Discipline Supporting Documentation 1 Engineering Execution Strategy Review / confirm Engineering Execution Strategy, e.g. execution locations, workshare, disciplines required, specialist support, etc. Project Manager and Project Engineering Manager Tender documentation, Project Execution Plan (PEP) 2 Feed / BoD Validation Confirm maturity of Front End Engineering Design. Identify any areas of concern and ensure these are captured on the Technical Risk Register. Project Engineering Manager 3 Project Baseline Standards Establish which codes, standards and specifications are to be utilised, eg. Corporate, project, client, and confirm procedure. Include in Engineering Execution Plan and / or Discipline Job Design Specifications. Project Engineering Manager Engineering Baseline Standards, Document No. OAG-X160-190-GDL-012 (previously AOD-92-043 ) 4 Engineering Audit Schedule Create formal schedule to identify when technical integrity audits, design reviews, HAZIDS, HAZOPS, etc are to be carried out. Align to Level 3 Engineering Plan and include in Engineering Execution Plan. Project Engineering Manager Technical Safety Events Schedule (Lead Technical Safety Engineer) 5 Engineering Execution Plan & Engineering Organisation Chart Create Engineering Execution Plan complete with key supporting documents / information. Project Engineering Manager 6 Integrated Engineering Systems Agree engineering design tools to be used and confirm that system hardware, software and support is available. Include issues such as PDMS or PDS, Cats and Specs, survey methods, dimensional control techniques, etc. Document and record in the Engineering Execution Plan and discipline job design specifications. Engineering Systems and All Disciplines Engineering Systems Project Start-up Manual, Document No. OAGX160-170-MAN-002 7 QRA & FRA Strategy Establish status of project Quantitative Risk Assessment (QRA), Fire Risk Assessment (FRA) and Emergency Escape & Rescue Assessment (EERA) information and confirm methadology for timely delivery into engineering design process. Agree accountability for delivery, eg. Client, 3rd party, AMEC, and record in Engineering Execution Plan. Technical Safety Hazard Management Philosophy, OAG-X160- 190-GDL-009 (previously AOD-97-001): Hazard & Risk Management, OAG-X160-190- PRO-024 8 Discipline Job Design Specification Define the key project specific design parameters and operational constraints that are applicable to the appropriate discipline for the detailed design of the project. To identify key individuals, roles and responsibilities, design tools, key codes and standards, etc. All Disciplines 9 Level 3 Engineering Plan Agree work breakdown structure, develop CTRs and create level 3 integrated engineering plan covering all disciplines. To be included in Engineering Execution Plan. All Disciplines 10 Confirm CE Compliance Strategy Review and confirm strategy for CE Compliance . Ensure discipline Lead Engineers are aware of their responsibilities and appropriate resources / measures are in place. Project Engineering Manager Corporate CE Compliance Strategy OAG- X160-190-MAN-001; Project Compliance with Pressure Equipment Regulations OAG-X160- 050-PRO-001; Pressure Equipment Regulations Guidelines AOD-97-047; ATEX Guidelines, OAG-X160-190-GDL-003; Machinery Directive Guidelines, O&G-ENG-REP-29-001; Electromatic Compatibility Regulations Guidelines, OAG-X160-190-GDL-003; MC, The Electrical Equipment (Safety) Regulations Guideleines, OAG-X160-190-GDL-003. 11 Technical Risk Register Create formal Technical Risk Register identifying all possible risks asscociated with the engineering design. Techncal Safety
  • 4. Activities / Deliverables Description Key Discipline Supporting Documentation 1 Performance Standards & Verification Scheme Confirm safety critical systems / elements and set appropriate performance standards. i.e. functionality, reliability and survivability. Develop scheme to allow the independent competent body (ICB) to verify the design against the performance standards. Technical Safety Hazard Management Philosophy, OAG-X160- 190-GDL-009 (previously AOD-97-001); Hazard & Risk Management, OAG-X160-190-PRO-024; Design Verification Activities (under DCR), OAG-X160-190-PRO-028; Platform Safety Case. 2 Document Distribution Matrix Create formal document distribution matrix to ensure all disciplines & departments receive all necessary design information in a timely manner. Project Engineering Manager 3 Structural Integrity Interface Ensure structural integrity interfaces are identified & visible to Project, e.g. AMEC / Client focal points, Technical Authorities, Independent Verification Bodies, etc. Structural 4 Material Selection Report Report defining the requirements and specifications of necessary material. Metallurgy AMEC Corporate Material Engineering Specifications. 5 Hazard Management Plan Create Hazard Management Plan identifying all key hazards, technical safety activities and the approach to managing Major Accident Hazards (MAH) in the design. Technical Safety Hazard & Risk Management, OAG-X160-190- PRO-024; Management of Functional Safety Guideline OAG-X160-190-GDL-004 6 Piping Specifications Develop / confirm baseline piping specifications, utilising AMEC Corporate specifications where possible. Piping AMEC Corporate Piping Specifications. 7 PDMS Calalogues Ensure PDMS catalogues are populated & available for all affected disciplines, utilising AMEC Corporate data, i.e. CPC, where possible. Engineering Systems, supported by Piping, Electrical, Instruments, Structural & HVAC 8 CMSS Philosophy Develop Control Monitoring and Safety Systems (CMSS) Philosophy covering key instrumentation and control systems e.g. Process Control System (PCS), Emergency Shutdown System (ESD) and Fire and Gas (F&G). Instruments Phase 2 Commencement of Detail Design To formally kick off the Engineering Design Process in accordance with the project execution plan and to ensure that key engineering strategies / philosophies are in place. 3
  • 5. 4 Phase 3 Initial Design Development and Hazard Identification To develop initial design deliverables to Inter Discipline Review (IDC) stage and identify key hazards. Activities / Deliverables Description Key Discipline Supporting Documentation 1 HAZID Perform hazard identification studies, as identified on Engineering Audit Schedule / Technical Safety Events Schedule. Technical Safety Project Hazard Identification (HAZID) AOD-92- 018; Engineering & Design Reviews, OAG-X160- 190-PRO-013. 2 ENVID Formal assessment of environmental aspects associated with a modification or a change, and to propose prevention or mitigating measures. Technical Safety Environmental Impact Identification (ENVID) OAG-X160-190-PRO-121; Engineering & Design Reviews, OAG-X160-190-PRO-013. 3 PFD IDC Issue Process Flow Diagrams (PFD’s) on formal Inter-Discipline Review (IDC). Process 4 Shutdown & Blowdown Philosophy Explain the measures to prevent and control blowdown and how this will be achieved. Process 5 P&ID’s IDC Issue Piping & Instrumentation Diagrams (P&ID’s) on formal Inter-Discipline Review (IDC). Process 6 C&E IDC Issue Cause & Effects for formal Inter-Discipline Review (IDC). Process and Instruments 7 Plot Plans / Layouts IDC Issue equipment Plot Plans / Layouts on formal inter-Discipline Review (IDC). Piping and Layouts 8 Hazardous Area Layouts IDC Issue Hazardous Area Layouts for formal Inter-Discipline Review (IDC). Technical Safety 9 Equipment List Create master project equipment list identifying all major items of tagged equipment, e.g. vessels, pumps, motors, generators, hydrocycolnes, chemical injection packages, electrical switchgear, control panels, etc. Mechanical 10 Mechanical Handling Strategy Develop Mechanical Handling Strategy including general approach / constraints, platform crane limits, installation philosophy, operation and maintenance, etc. Mechanical and Structural 11 Particular Material Appraisals (PMA) Where required, i.e. where Corporate PMA’s or EAM’s are not suitable, develop new PMA’s and obtain approval from Notified Bodies (NoBo’s). PED Focal Point 12 Fire Risk Assessment (FRA) Determine Fire & Explosion scenarios and identifies requirements for prevention, control and mitigation measures. Technical Safety 13 Emergency Escape & Resecue Assesment (EERA) Identify requirements for emergency escape & rescue, e.g. lifeboats, escape routes, plant layout, etc Technical Safety 14 Dropped Object Study Identify and assess the potential risks to drilling, production, process equipment, and manned areas from dropped or swinging objects. Where the consequence of a dropped object is considered significant, to propose prevention or mitigating measures. Technical Safety 15 Blast Design Philosophy Develop philosophy that assesses potential explosion hazards and identifies appropriate blast loadings to be applied to the engineering design process, eg. Vessels, pipe supports, structural steel, etc. Technical Safety 16 PFP / AFP Philosophy Develop philosophy that identifies requirements for Passive Fire Protection (PFP) and/or Active Fire Protection (AFP). Technical Safety 17 HIPPS Review Initial review to establish requirements for a High Integrity Pressure Protection System. Instruments Management of Functional Safety, OAG-X160-190-GDL-004
  • 6. 5 Phase 4 Initial Design Review and Audit To confirm that the initial design development is robust. Activities / Deliverables Description Key Discipline Supporting Documentation 1 Hazardous Area Review Formal Engineering discipline review of hazardous area layouts to confirm requirements for the correct selection and location of equipment. Technical Safety Hazard and Risk Management Procedure OAG-X160-190-PRO-024; Engineering & Design reviews, OAG-X160-190-PRO-013 2 P&ID Review and / or ‘Initial Hazop’ Formal Engineering discipline review of P&ID's to confirm design basis. Process, Piping, Technical Safety, Instruments Formal Hazop, OAG-X160-190-PRO-017; Engineering & Design Reviews, OAG-X160-190- PRO-013 3 Plot Plans / Layout / 3-D Model Review Formal Engineering review of Plot Plans / Layouts. The review shall ensure that the layout design complies with the required technical, safety, operability and maintainability standards. Makes sure the layout is cost effective, ensures the constructability of the work and agrees the layout basis on which the detailed design can proceed. Piping and Layouts, Structural, Mechanical, Electrical, Technical Safety, Process Engineering & Design Reviews, OAG-X160-190-PRO-013 4 C&E Review Formal review of Cause & Effects diagrams to confirm design basis and alignment with Hazard Management Plan. Instruments, Process, Technical Safety Hazard and Risk Management Procedure OAG-X160-190-PRO-024; Engineering & Design reviews, OAG-X160-190-PRO-013; Management of Functional Safety Guideline OAG-X160-190-GDL-004 5 Technical Audit Obtain confirmation, by sampling of project documentation, that the engineering of the project is to the required standard and free from errors. Independent (Corporate Engineering) Technical Audit Procedure OAG-X160-190-PRO-022
  • 7. 6 Phase 5 Design Approval To ‘Freeze’ the Process design, and develop dependent design & procurement activities. Activities / Deliverables Description Key Discipline Supporting Documentation 1 PUWER Assessments Conduct initial PUWER assessment typically by review of PDMS model and/or vendor / equipment supplier information received to date. Technical Safety, Mechanical Engineering & Design Reviews, OAG-X160-190-PRO-013 2 HAZOP Hazard and Operability Studies, a systematic multi-discipline study based on the applications of guidewords to identify causes of potential hazards and operability constraints in a facility. Process, Technical Safety Dependent on Project updated P&ID’s and C&E’s may be prepared from commented IDC’s from Phase 3 Formal HAZOP, OAG-X160-190- PRO-017 (previously AOD-92-022); Engineering & Design Reviews, OAG-X160-190-PRO-013 - Note: additional HAZOP’s may be required, i.e. earlier or later in the project. PEM to consult with Process & Technical Safety Lead Engineers. 3 SHE Audit (AFD) SHE Audit ensures that the design obligations under The Health and Safety At Work Act 1974 and project health, safety and environmental performance standards are being or have been met during the engineering and design processes. Technical Safety SHE Audit Procedure OAG-X160-190-PRO-023; Engineering & Design Reviews, OAG-X160-190- PRO-013 4 Environmental Report Issue final report to document & confirm that the design has considered all applicable environmental aspects & demonstrates that design controls have been included to minimise / control the environmental impact. Technical Safety Engineering & Design Reviews, OAG-X160-190- PRO-013 5 Constructability Review Conduct formal Constructability Reviews to ensure safe and efficient installation of plant & equipment. Affected disciplines + Construction / Implementa- tion Group Engineering & Design Reviews, OAG-X160-190-PRO-014 6 P&ID AFD Issue Approved For Design (AFD) Process and Instrumentation Diagrams. Process 7 C&E AFD Issue Approved For Design (AFD) Cause & Effects. Instruments 8 Process Data Sheets AFD Issue Approved For Design (AFD) Process Data Sheets. Process 9 HP / LP Interface Listing Identify all HP / LP interfaces on formal register and ensure that all have been addressed satisfactorily via HAZOP’s and / or individual reviews. Process 10 Holds Register Develop register to record & manage post AFD design holds. Engineering Manager 11 SIL Assessments Conduct assessment to determine target Safety Integrity Level (SIL). Note: Where the target SIL is 3, then it is likely that a High Integrity Pressure Protection System (HIPPS) will be required. If the value is found to be 1 or 2, then a HIPPS will not be required. Instruments Management of Functional Safety, OAG-X160-190-GDL-004 12 HIPPS Study Conduct study to formally identify the performance requirements of the High Integrity Pressure Protection System (HIPPS) and demonstrate that it is robust. Should include dynamic study for a range of transient conditions. Process Management of Functional Safety, OAG-X160-190-GDL-005 13 HIPPS Reliability Study Conduct study to formally demonstrate that the High Integrity Pressure Protection System (HIPPS) complies with the reliability & availability criteria for the Project, e.g. as stipulated in the performance standards. Instruments Management of Functional Safety, OAG-X160-190-GDL-004 14 SIL Achievement Report Conduct independent assessment to formally record that the target Safety Integrity Levels (SIL’s have been achieved) Must be completed prior to introduction of Hydrocarbons. Independent Competent Person (ICP) Management of Functional Safety, OAG-X160- 190-GDL-004 15 Flow Assurance Conduct flow assurance studies to demonstrate the process design under a range of flow conditions, i.e. start-up to 100%. Process 16 Verification of Vendor Information & Certification - Design Completion Verify, primarily through review of vendor documentation, that their design & manufacture of fabricated packages, etc is robust and contains sufficient information to facilitate completion of affected AMEC discipline design. Affected disciplines 17 PFEER Compliance Report Issue final report as documented confirmation that the design meets the requirements of the Prevention of Fire and Explosion, and Emergency Response (PFEER) Regulations Technical Safety
  • 8. AMEC (LSE: AMEC) is a focused supplier of high-value consultancy, engineering and project management services to the world’s natural resources, nuclear, clean energy, water and environmen- tal sectors. With annual revenues of over £2.5 billion, AMEC designs, delivers and maintains strategic and complex assets for its customers. The company employs some 22,000 people in around 40 countries worldwide. For further information please see amec.com Activities / Deliverables Description Key Discipline Supporting Documentation 1 SHE Audit AFC Conduct SHE Audit at AFC stage in accordance with Harmonised Procedure. Technical Safety SHE Audit Procedure OAG-X160-190-PRO-023 2 IEC 61511 Compliance Report Final report to formally demostrate that the Safety Instrumented Systems comply with the requirements of IEC 61511. Instruments Management of Functional Safety, OAG-X160- 190-GDL-004 3 PFD’s AFC Issue Approved For Construction (AFC) Process Flow Diagrams. Process 4 Operational Safety Case Development Commence operational Safety Case development. Technical Safety 5 P&ID’s AFC Issue Approved For Construction (AFC) Process and Instrumentation Diagrams. Process 6 Quantative Risk Assessment (QRA) Complete QRA activities to confirm that the design is robust and complies with legislative requirements. Technical Safety 7 C&E AFC Issue Approved For Construction (AFC) Cause & Effects. Instruments 8 Operating Procedures Review / Operational HAZOP Ensure operating procedures are verified line by line against the facilities provided on the P&ID’s. Process, Technical Safety Formal HAZOP, OAG-X160-190-PRO-017 (previously AOD-92-022); Engineering & Design Reviews, OAG-X160-190-PRO-013 9 Fabrication Drawings AFC Issue Approved For Construction (AFC) Piping Isometrics, Structural Steelwork drgs, etc. Affected Disciplines 10 Verification of Vendor Information & Certification - Installation, Operation & Maintenance Verify, primarily through review of vendor documentation, that their design & manufacture of fabricated packages, etc is robust and contains sufficient information to facilitate safe installation, operation & maintenance. Affected Disciplines 11 EC Design Examination Certificates Where AMEC are deemed to be the manufacturer of the piping systems, then under the PED/PER, AMEC have to apply to the Notified Body (NoBo) for an EC Design Examination Certificate (Cat IV assemblies only). PER Focal point Project Compliance with the Pressure Equipment Directive, Document No. OAG-X160-190-GDL-007. 12 Declaration of Conformity Where AMEC are deemed to be the manufacturer of the piping systems, then under the PED/PER, AMEC have to create a Declaration of Conformity, signed by the Project Manager. Project Manager Project Compliance with the Pressure Equipment Directive, Document No. OAG-X160-190-GDL-007. Phase 6 Approval for Construction (AFC) To ensure that sufficient design information & certification is available to facilitate safe installation, operation & maintenance. Activities / Deliverables Description Key Discipline Supporting Documentation 1 Safety Case Acceptance (HSE) Submit Safety Case to HSE & close out all queries / correspondance prior to next stage of operations. Technical Safety 2 Certifying Authority (CA) / Independent Verification Bodies (IVB) Acceptance Close out all outstanding technical queries and obtain final Letter of Acceptance. Technical Safety 3 Complete Project As-Built Documentation Complete as-builts of design drawings and deliverables in accordance with Project / Client requirements. Affected Disciplines As Built Drawings and Documentation, AOD-92-021 Phase 7 Design Close-Out To ensure all final design deliverables are completed and that client and statutory obligations are satisfactorily resolved.